Professional Documents
Culture Documents
Project Management
WHAT IS A PROJECT?
Definition
• Subsidiary processes
• Procurement planning
Implementation/Execution Phase
• Transfer documents
• Release resources
• Evaluation
• Lessons learned
What is Project Management ?
• Excavation
• Concreting
• Brickwork
• Bar/Gantt Chart
• Line-of-Balance
• Linear Programming
• Network Analysis
Bar/Gantt Chart
P
S
Examples :
1) Land(P) must be purchased before road, building(S)
can start.
2) Supper(S) starts when the cooking is complete (P).
3) Concrete(S) pouring starts after the forms are built(P).
Three Main Relationships-Gantt Charts
• Start to Start (SS) – SS tasks can't start until a
preceding task starts. However, they can start later.
S
Examples:
1) As soon as you put the batter in the oven (P) you can
start making the icing (S).
2) Mixing of chemicals(S) cannot start until air quality testing
starts(P).
3) You can’t start up the machine(S) until the pollution
testing starts(P).
Three Main Relationships-Gantt Charts
• Finish to Finish (FF) – FF tasks can't end before a
preceding task ends. However, they can end later.
Examples :
1)Electrical work cannot finish until dry walling is
complete.”
2)“Design work cannot finish until environmental studies
are complete”
3) Paint Interior of the house and setup furniture.
• The following table shows the tasks, dependencies, and
estimated times a project manager might input to a basic
GANTT chart for a software development project.
Project Start Date : 2nd February 2021
a b c e g
1 2 3 4 6 8
d
h
f
5 7
The AON network
Start a b c f Stop
d e
Classification of Projects
• Projects can be classified on the basis of
• Duration
• Quantum of Investment
• Ownership
• Risk Involved
Classification of Projects
Duration
• Greenfield project
• Brownfield project
• Divestment project
• Expansion Project
• Diversification Project
Classification of Projects
• Expansion project : There is an increase in the capacity of
existing plant.
• It is of two types
• Forward Integration
• Backward Integration
Classification of Projects
• Forward Integration Project: Downstream expansion is
called forward integration.
• The product of the existing product becomes raw material
for the proposed project, i.e. a steel industry moves for
manufacturing steel pipes.
• Backward Integration Project: Upstream expansion is
called backward integration.
• The raw material needed for the existing industry is
proposed to be manufactured by a new project, i.e. a steel
pipe industry plans to manufacture its raw material, steel
itself.
Classification of Projects
• Diversification Project: Financial Synergy may be
obtained by combining two firms:
• One with better financial resources but poor technical
capabilities and another firm with strong technical
capabilities but poor financial resources.
• Concentric diversification Project
• Conglomerate diversification Project