Professional Documents
Culture Documents
allows the WBS to logically sum the lower-level elements that support the
measuring of cost, schedule, and technical analysis in an EVM system. It
also allows a program manager to more precisely identify which
components are causing cost or schedule overruns and to more
effectively mitigate the root cause of the overruns. Moreover, when
appropriately integrated with systems engineering, cost estimating, EVM,
and risk management, a WBS provides the basis to allow program
managers to have a better view into a program’s status, facilitating
continual improvement.
Case study 8 highlights problems that can occur when this best practice
is not followed.
GAO, Plutonium Disposition Program: DOE Needs to Analyze the Root Causes of Cost
Increases and Develop Better Cost Estimates, GAO-14-231 (Washington, D.C.: February
13, 2014).
14When following the product-oriented best practice, there should not be WBS elements
for various functional activities like design engineering, logistics, risk, or quality, because
these efforts should be embedded in each activity.
The WBS should be used as the outline for the schedule, using the levels
WBS and Scheduling of indenture down to the work package level. Because the WBS defines
the work in lower levels of detail, its framework provides the starting point
for defining all activities that will be used to develop the program
schedule.
The lowest level of the WBS is the work package. Within the work
packages, the activities are defined and scheduled. When developing the
program schedule, the WBS may be copied into the scheduling software.
From there, the lower-level work packages and subsequent activities and
tasks are defined.
By breaking the work into smaller and more manageable work elements,
WBS and EVM a WBS can be used to integrate the scheduled activities and costs for
accomplishing each work package at the lowest level of the WBS. This is
essential for developing the resource-loaded schedule that forms the
foundation for the EVM performance measurement baseline. Thus, a
WBS is an essential part of EVM cost, schedule, and technical monitoring
because it provides a consistent framework from which to measure
progress. This framework can be used to monitor and control costs based
on the original baseline and to track where and why there are differences.
In this way, the WBS serves as the common framework for analyzing the
original cost estimate and the final cost outcome.
The WBS also provides a common thread between EVM and the
schedule that allows for further understanding of program cost and
schedule variances. When the work is broken down into small pieces,
progress can be linked to the schedule for better assessments of cost,
technical, schedule, and performance issues. The WBS also enhances
program control by tying the contractual work scope to the schedule.
16GAO, Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G
(Washington, D.C.: December 2015).
The WBS is valuable for identifying and monitoring risks. During the cost
WBS and Risk estimating phase, the WBS is used to flag elements likely to encounter
Management risks, allowing for better contingency planning. During program execution,
the WBS may also be used to monitor risks using the EVM system.
The WBS can help identify activities in the schedule that are at risk
because resources are lacking or because too many activities are
planned in parallel. In addition, risk items can be mapped to activities in
the schedule and the results can be examined through a schedule risk
analysis. 17
Establishing a WBS as soon as possible for the program’s life cycle that
WBS Benefits details the WBS for each phase provides many program benefits:
17More information on best practices for schedule risk analysis can be found in GAO,
Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G
(Washington, D.C.: December 2015).
The U.S. Census Bureau planned to significantly change the methods and technology it
used to count the population with the 2020 Decennial Census, such as offering an option
for households to respond to the survey via the Internet. This involved developing and
acquiring IT systems and infrastructure to support the collection and processing of Internet
response data.
GAO was asked to review the Bureau’s efforts to deliver an Internet response option for the
2020 census. Among other objectives, GAO was asked to assess the reliability of
estimated costs and savings for Internet response. To do this, GAO reviewed Bureau
studies, cost estimates, project plans, schedules, and other documentation.
GAO concluded that the Internet response option cost estimate was not comprehensive.
The Internet response option cost estimate included costs from 2010 to 2020 and provided
a subset of assumptions for researching, testing, and deploying an Internet response
option. While the estimate was structured around these high-level cost elements, these
elements were not defined, and therefore it was not clear whether all costs associated with
the Internet response option were included. Bureau officials stated that the estimate was
not developed based on a work breakdown structure with defined elements because the
2020 Census program was not mature enough to have such a structure at the time the
initial estimate was developed. They stated that the estimate would be updated to reflect
the program’s work breakdown structure once the preliminary design decision was made.
However, a work breakdown structure should have been initially set up when the program
was established and successively updated with more detail over time as more information
became known about the program.
GAO recommended that to ensure that the Bureau was better positioned to deliver an
Internet response option for the 2020 Decennial Census, the Secretary of Commerce
should direct the Under Secretary for Economic Affairs to direct the Director of the Census
Bureau to ensure that the estimated costs associated with the Internet response option
were updated to reflect significant changes in the program and to fully meet the
characteristics of a reliable cost estimate. The Department of Commerce agreed with our
recommendation and took steps to implement it. In August 2017, the Census Bureau
finalized its Census Enterprise Data Collection and Processing (CEDCAP) Cost Analysis
Requirements Description (CARD), which included a basis for estimating the costs
associated with the Internet response option. Subsequently, in December 2017, the Bureau
finalized its updated 2020 Decennial life cycle cost estimate that included the CEDCAP
CARD as an input to the estimate. GAO’s April 2018 analysis of the updated cost estimate
found that the Bureau had made significant improvements in its cost estimation process
across the four characteristics of a reliable estimate. As a result, the Bureau was better
positioned to deliver an Internet response option for the 2020 Decennial Census.
Survey of Step 4
Process Tasks • Define a work breakdown structure (WBS) that is standardized and
product-oriented.
• Ensure the cost estimate WBS matches the schedule and earned
value management WBS, if applicable.
• Describe each WBS element in a WBS dictionary.
• Update the WBS as the program becomes better defined to reflect
changes as they occur.
• The WBS clearly outlines the end product and major work of the
program.
• In addition to hardware and software elements, the WBS contains
program management and other common elements to ensure that all
work is covered.
• The WBS contains at least 3 levels of indenture and the sum of the
children elements equal their parent elements.
• The cost estimate WBS matches the schedule WBS, as well as the
earned value management WBS if applicable.
• The WBS is standardized so that cost data can be collected and used
for estimating future programs.
• The WBS is updated as the program becomes better defined and to
reflect changes as they occur.
A WBS dictionary exists that defines what is included in each element
and how it relates to others in the hierarchy.
Likely Effects If Criteria • Without a WBS, the program lacks a framework to develop a schedule
Are Not Fully Met and cost plan that can easily track technical accomplishments—in
terms of resources spent in relation to the plan as well as completion
of activities and tasks.
• If a cost estimate does not specifically break out common costs, such
as government furnished equipment (GFE) costs, or does not include