Total capacity requested 140 kW Please note that according the liberalisation of the
customer must enter into a gas supply contract with
Nominal pressure requested 10 mbar people commissioning the gas installation. This supply
steps with the grid operator to allow the supply of gas. A
Charges for meter installation complete list of suppliers can be found on the end
customer does not choose a supplier a default
Installation of a cat. 1 gas meter 175.50 € ≤200kW accordance with Article 4 of the law of 1 August 20 the
natural gas market, as amended.
Installation of a cat. 2 gas meter 285.50€ <200kW -≤600kW
The present appliaction is deemed to be an order for the installation of a meter in accordance with the tariff coresponding to the total power of the installation as in the tabels
Payments
Important Information
1 Please indicate the total capacity (power) of all devices connected to the gas installation.
2 In general for an installation connected to the low-pressure grid, the nominal pressure is equal the 20 mbar (standard)
3 The number is indicated on the gas meter. You can also enter the POD number you finde on your supplier's bill.