Application to commission an installation


Application to alter an existing installation
Application to decommission an installation
Please return the completed application to creos Luxembourg S.A., L-2084 Luxembourg or by e-mail to: meteringgasLP@creos.net.
If you need help Tel: (+352) 2624-2624/ 7h30- 17hOO or info@creos.net
It is recommended that you complete this application form with your fitter. The ALUGAZ form ''Notifiaction de travaux sur une installation de gaz'' duly
completed by your fitter must be attached to this application as part of commissioning of a new installation or when altering an installation.
Please use block capitals

Application User of the grid Holder of the connection


(person paying for the work) (if different from the application) (if different from the applicant)
(consumer/tenant) (owner)
Name- First name Arthur
Surname Vazovsky
Commercial register
No- Street 15 Park Drai Eechelen
Pstcode/Town, City 1499 Luxembourg
E-mail
Mobile phone/fixes line phone
Date
Signature

Fitter Name/Company name

Address of the gas installatin

No of the building 15 Street/Economic activity area Park Drai Eechelen


Floor 1 Flat ---
Postcode 1499 Town/City Luxembourg
Please choose one of the following three options

Commissioning of a new installation


If your house/building is not yet connected to the natural gas grid, please firs submit to Creos your application for a new connection using the form

Total capacity requested 140 kW Please note that according the liberalisation of the
customer must enter into a gas supply contract with
Nominal pressure requested 10 mbar people commissioning the gas installation. This supply
steps with the grid operator to allow the supply of gas. A
Charges for meter installation complete list of suppliers can be found on the end
customer does not choose a supplier a default
Installation of a cat. 1 gas meter 175.50 € ≤200kW accordance with Article 4 of the law of 1 August 20 the
natural gas market, as amended.
Installation of a cat. 2 gas meter 285.50€ <200kW -≤600kW

The present appliaction is deemed to be an order for the installation of a meter in accordance with the tariff coresponding to the total power of the installation as in the tabels

Payments

Payment period Value Costs Addition information


01/01/19-01/02/19 91 € 4.00 Addition information
01/02/19-01/03/19 18 € 1.20
01/03/19-01/04/19 45 € 2.05
TOTAL € 12.59

Important Information
1 Please indicate the total capacity (power) of all devices connected to the gas installation.
2 In general for an installation connected to the low-pressure grid, the nominal pressure is equal the 20 mbar (standard)
3 The number is indicated on the gas meter. You can also enter the POD number you finde on your supplier's bill.