Professional Documents
Culture Documents
09
System Rev: 00 Date:22.02.09
JOHN ENERGY
DOC NO.- IMS/OPR/SP-04/033 Page 1 of 5
LIMITED
1.0 Purpose
The purpose of this procedure is to establish a safe Material handling using Cranes and other lifting
machines.
2.0 Scope
The scope of this procedure covers all Rig installation, Work shop & Site of John Energy Ltd.
3.0 Responsibility
a) The Tool Pusher / Assistant Driller/ Rigger is responsible to follow this procedure while Heavy
Material handling and lifting activity.
b) Crane / lifting equipment operator to follow the procedure
c) HSE Engineer/officer is responsible for implementing this procedure at Site/Workshop.
4.0 Procedure:
a) Planning:
b) Safe Slinging:
Following care should be taken in respect to Slings.
• Where the Crane/Lifting Machine Operator cannot CLEARLY see the Load, (from Pick up,
Travel, to Placing Down), a SECOND Person SHALL act as a "Banksman", (The Banksman
is to be formally Trained), Using Recognised "Hand Signals", (clearly understood by Both
Persons).
NO PERSON SHALL Stand near, or Walk below, any Suspended Load. TAG LINES are
mandatory to Control the Load. Loads SHALL NOT be Lifted or Swung across other
personnel.
Sufficient "Wire Rope", "Clips" and "Saddles" SHALL be Used, Maintained & correctly
Orientated, at all times.
1/8 to 7/16 2
1/2 to 5/8 3
3/4 to 7/8 4
1 5
1 1/8 6
1 1/4 to 1 3/8 7
1 1/2 to 2 ¼ 8
c) Cranes:
Following care should be taken about the Crane being used.
• Ensure that no Crain shall be used unless it has a current test certificate
• Observe safe load for lift radius.
• Cranes shall only be operated by Competent Appointed Operators
• No person shall stand/ride on load during the Lifting, swinging, Traveling or Lowering
Operations.
• Jerking/snatching during Lifting or Lowering Load to be avoided. Swinging of load or rapid
traversing to be avoided
• Load shall not be left suspended, whilst the Operator is away from his controls, or the machine
is shut down.
• Ensure crane operator and signalman adopts and understands signals adopted.
• Crane is jacked on firm Foundation and wooden logs.
• Crane operator should ensure that, no obstructions are there for movement of load.
• Crane operator should sound audible warning before lifting load.
• Visually check all wire rope for deterioration, damage and proper lubrication.
• Check weight indicator and load cells for proper operation, where applicable.
• Check all control mechanisms for excessive wear of components and contamination by
lubricants or other foreign matter.
• Visually check for cracked or corroded members in crane boom and structure.
• Check belts and chains for proper adjustment (tension) and alignment.
Material handling to be started once all the above checks are completed and found satisfactory.
-------x--------