You are on page 1of 8

Powering Ontario for the next half-century: Refurbishing Darlington

By Colin Hunt, Publisher and Editor, Nuclear Canada Yearbook

Introduction and Overview be understated. Since first production of However, after 25 years of electricity
In 2016, Ontario Power Generation (OPG) electricity in 1990 Darlington has produced generation, the reactors and their associated
will commence construction for a project approximately 560 TWh of electricity. This systems must be refurbished for continued
of utmost importance to the future of amount of electricity is equivalent to about operation. So starting in 2016 with Unit 2,
the province of Ontario: the comprehen- one year’s total annual consumption of the reactors will be removed from service
sive refurbishment of the four CANDU electricity in Canada, or about four and a in sequence for an outage of approxi-
nuclear reactors at it’s Darlington Nuclear half years of electricity consumption in the mately three years each. When complete,
Generating Station. Over the course of province of Ontario. Each year, Darlington Darlington will continue electricity
the subsequent ten years, thousands of typically produces about 25 to 29 TWh, production for another thirty years
OPG and contract personnel will carry or about 18-20 per cent of Ontario’s total
out a series of complex tasks to replace annual electricity demand. The total overnight capital cost of the
or renovate thousands of systems and refurbishment project is expected to be less
components throughout the station for With 934 MW each, the four Darlington than $10 billion. It should be noted that
each of its four reactors. reactors are the largest CANDU reactors the refurbishment of Darlington is not the
in the world. Unit 2 entered service in first nuclear station to have units renovated.
The importance of Darlington NGS to 1990, Unit 1 in 1992, and Units 3 and 4 Bruce Power has just completed its refurbish-
the economic health of Ontario cannot in 1993. ment of Bruce Units 1 and 2. Point Lepreau

3 x 3 array floor mockup with bellows (intend to remove and reuse). (Photo courtesy of OPG)
in New Brunswick also completed refur- dedicated to the project. The second
bishment and returned to service in 2012. was the need to build dedicated training
Lessons learned from these refurbishments facilities to train contract skilled trades
have been built into OPG’s project planning. workers in techniques for working success-
fully in the confines of a nuclear power
Renovation of Darlington also builds upon station, in particular the reactor vault. The
OPG’s own past experience specifically lessons and successes from Pickering 3’s
with the refurbishments of Pickering Units successful retubing have been incorporated
1 and 4 and the early retubing projects in every CANDU refurbishment project
of Pickering Units 1-4 from 1985-1992. ever since.
The pioneer learning experiences at the
Pickering station are central to the success As a result, there can be confidence that the
of the current refurbishment project of project will achieve its goals, both financial
Darlington. What was shown at Pickering and technical, because it builds upon more
was the importance of a dedicated project than 30 years of experience with similar
team and workforce in major project projects that have come before it. Unit 2 close up low pressure turbine.
(Photo courtesy of OPG)
refurbishment work. The first two Pickering
units used only station personnel in the Project Scope
1980s for their retubing, and their return to The first steps in the Darlington refurbish-
conditions being discovered in plant
service was greatly delayed as a result. ment began six years ago. It started with
equipment resulting in possible project
inspections of the current state of the
delays and increased costs. Also essential is
However, Pickering 3 retubing completed station and its equipment, and planning for
the agreement of the CNSC on the scope
in 1992 pioneered two key concepts in the outages and the associated work plans.
of the work. And early involvement and
major nuclear plant renovation work. The It also included early inclusion of some of
contracting with supplier companies ensures
first was the need to hire skilled trades its private sector partners in the project,
that services, equipment and expertise
from outside the regular station personnel along with securing the needed approvals
will be available as required by the project
process from the Canadian Nuclear Safety
timelines to avoid delays.
Commission (CNSC) including an envi-
ronmental assessment.
The First Steps
OPG has already completed a large number
As a result of its preliminary inspections,
of necessary first steps in its refurbishment
analysis and planning, OPG announced
project. It has completed the construc-
in February 2010 its intentions to proceed
tion of the large training facility, the
with the refurbishment of Darlington.
Darlington Energy Complex or DEC. This
is the principal hub of the refurbishment
At this time, some of the remaining steps in
project. It includes a full scale replica of a
refining the project scope include:
Darlington reactor and other mockups. It
• Completing detailed inspections on
includes a testing facility for the specialized
plant conditions;
tools required for retubing the reactors.
• Confirming the regulatory scope of the
The purpose of these facilities is to ensure
refurbishments
that all skilled trades workers contracted
• Awarding all major contracts with
for the project will have familiarity with
private sector partners.
working conditions, procedures and tooling
before entering the station. The DEC
The result of this will be a fully defined
includes warehousing space for materials
project scope, cost and schedule for
and components required for the project.
execution. Past experience has shown
The DEC is also the new home of the
that the success of refurbishment projects
Darlington Information Centre.
Lower pressure turbine blades under-
is directly dependent on the extent and
going inspection during routine mainte- accuracy of all of these factors. Detailed
nance outage. (Photo courtesy of OPG) Training on the mockup is critical. All
inspections, for example, minimize or
activity within the reactor vault in retubing
eliminate the possibility of unexpected
will be first done by direct hands-on
DNGS mockup lattice tube inside view. (Photo courtesy of OPG)

Darlington. (Photo courtesy of OPG)


training in the DEC. The facility is an additional dry storage warehouse is being The calandria tubes are separated from the
designed to accommodate all of the training built to store previously removed spent fuel pressure tubes by an annulus gas, carbon
requirements of workers that will be removed from the reactors. dioxide, and a series of springs called garter
contracted to carry out the refurbishment springs, to maintain separation between the
work in the years ahead. Retubing the Darlington two tubes.
Reactors
OPG is also making other large changes to Replacing the pressure and calandria tubes All of these components, pressure tubes,
the plant site. These include: of the Darlington reactors is a critical calandria tubes and feeder tubes, must
• Changes to plant services infrastructure timeline in plant refurbishment. Each be replaced in the retubing operation.
• Changes to electrical power distribution reactor consists of 480 fuel channels, each Also to be replaced are the end fittings,
• A new boiler house for steam heating, and containing a pressure tube, which is inside including the shield plugs, and the internal
• Changes to roads and site access. a calandria tube. The pressure tubes contain components such as the garter springs.
13 CANDU fuel bundles each. At each
In addition, OPG is constructing new end of each pressure tube are the feeder Space can be limited within the reactor
facilities to store reactor system heavy tubes. These transport heavy water coolant vault, and the tooling must be designed
water during the reactor outages. It is also from the reactor calandria to and from the for and to accommodate the restrictions
building a storage facility to accept reactor steam generators. in space within it. All of the work must be
components after volume reduction. Finally, done at the reactor face in protective suits

Unit 3 low pressure turbine open for inspection during routine maintenance outage. (Photo courtesy of OPG)
Mockup reactor face with fuel channel assemblies and lower feeder pipes. (Photo courtesy of OPG)

or remotely using automated tools. Thus, After inspection, and due to continuous inspection capabilities in renewed
the importance of the DEC for hands-on maintenance during planned outages, it operation after refurbishment is
training becomes vital to prepare workers was determined that the steam generators complete.
for conditions at the reactor face, both at Darlington would not need replacement
in working with the tools and with the and are fit for service for another 30 years. With respect to the turbine/generator,
experience of working in protective suits. In part this was because of newer, more a component condition assessment
corrosion-resistant material than found concluded that no replacement of the major
Steam Generators and in the steam generators of older reactors. components, such as generator rotors,
Turbine/Generators It is also in part due to improvements in turbine spindles and cylinders was required.
Each Darlington reactor has four steam maintenance cleaning of the tube sheets The refurbishment work here will primarily
generators. Receiving coolant from and plant chemistry made over the past consist of:
the reactor or primary side, the steam two decades. • Inspection, repair and replacement of
generators produce steam at 265 degrees turbine components and auxiliaries;
C under saturation conditions to the Renovation work to the steam generators • Inspection, repair and replacement of
secondary side. This steam is in turn will include: generator components and auxiliaries
transported to the high and low pressure • Water lancing to remove tube sheet (including replacement/rewind of two
turbines, cooled and condensed, and deposits; generator stators);
returned to the inlet secondary side of the • Primary side cleaning to remove • Inspection, repair and replacement of
steam generators. magnetite accumulation; and moisture separator reheater internals and
• Installation of access ports to improve auxiliaries; and
Floor mock-up 6 x 9 array with fuel channel tubes, end fittings and lower feeder pipes. (Photo courtesy of OPG)
• Complete replacement of the analog • Confirming the regulatory scope of the • Babcock and Wilcox Canada Ltd.
turbine control systems and excitation project with the CNSC; • Black & McDonald
control with digital systems (including • Awarding all major contracting arrange- • Candu Energy Inc.
hydraulic components). ments with contractors and suppliers to • E.S. Fox Ltd.
ensure availability; • GE Hitachi Nuclear Energy Canada
The original steam generators were built • Completing the detailed engineering; and • SNC Lavalin Nuclear Inc.
by Babcock & Wilcox, while the turbine/ • Establishing in detail the critical path of • Worley Parsons
generator sets were built by BBC (Brown the entire outage including replacing the
Boveri) now Alstom. fuel channels and feeder tubes. In 2015, OPG will complete and release
the detailed cost estimates for execution
The Path Forward At this time, OPG has completed of the refurbishment outages. It will also
Some work remains to be done to prepare contracting arrangements with a number release the detailed project schedule and
Darlington for commencement of refur- of large companies based in Ontario for its timelines.
bishment and the first reactor outage. These various parts of the refurbishment project.
tasks include: These companies include: Closing Notes
• Completing detailed plant inspections • Aecon Construction Group Inc. The scope of work to be done in the
to confirm plant conditions and refine • Alstom Power & Transport Canada Inc. Darlington refurbishment project
the scope of the project; • AMEC NSS means that it will be one of the largest

CV inspection – vented sheild plug. (Photo courtesy of OPG)


3 x 6 array floor mockup with some end fittings installed. (Photo courtesy of OPG)

construction projects in Canada for more One of the great advantages that nuclear It is also not subject to the great variations
than a decade. Normally, OPG has about energy has provided Ontario over these in output, either hour by hour or day by
2,600 people working at the site. Carrying years has been both the low cost and the day, which is experienced by renewable
out the refurbishment work will require at price stability of its electricity supply. sources such as wind or solar generation.
peak up to an additional 2,000 workers, Unlike fossil fuels, the cost of electricity
primarily in skilled trades. The impact on from nuclear power does not vary signifi- By committing to the full refurbishment
employment in the demand for skilled cantly over time, as the bulk of the cost of of the Darlington NGS, OPG is helping
trades workers will therefore be significant. nuclear-generated electricity comes largely to ensure that reliable nuclear power
from capital construction costs and ongoing will remain the cornerstone of Ontario’s
For more than 30 years, nuclear power maintenance and operating costs, all of electricity system well into the second half
has been the backbone of the electricity which are generally constant over time. of the 21st century.
system in the province of Ontario. At this Because fuel is such a small portion of the
time, it accounts for well over half of all the total lifetime operating cost, nuclear power
electricity generated in the province. Of is not affected by the considerable variations
that, nearly one-third is produced by the in fuel costs to which fossil fuel sources
Darlington CANDU reactors. are subject.

C ANADIAN NUCLEAR SOCIETY ANNUAL INDUSTRY REVIEW AND BUYER’S GUIDE 2014 21

You might also like