NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 28 October 2016

(New Activities are in Blue text – existing/ongoing activities in Black Text)

ZONE 4 MARINE CONSTRUCTION – Richard Malberg


Key Activity this week Key Activity next week
 Continue Revetment works in vicinity of Construction jetty continuing  Continue Revetment works in vicinity of Construction jetty continuing
 Maintenance dredging works by JGCS in Harbour Basin  Maintenance dredging works by JGCS in Harbour Basin to continue
recommenced after rough seas conditions  Water tests of temporary waste water treatment facility for
 Temporary waste water treatment facility for dewatering of Crude Oil dewatering of Crude Oil Pipeline to commence operation & hold
Pipe made ready for start-up discharge for approval by authorities.
 Closing Punch B items  Closing B Punch items
 Remedial work on concrete slab on grade at Solids Berth delayed by  Continue remedial work on concrete slab on grade at the Solids Berth
wet weather  System Mechanical Completion of the last section of the Revetment
 Walk around of revetment works in the vicinity of the Construction in vicinity of the construction jetty.
Jetty

Area of Concern Action to Area of Concern

a. NSRP plans to commence Maintenance Dredging in January 2017. A a. NSRP is progressing an Invitation to Bid for dredging services to
delay in timely completion of the maintenance dredging may be an complete maintenance dredging in the outer harbour & access
impediment the port opening. channel. PQ of bidders to be determined in next week.

562510469.docx Page 1 of 3
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 28 October 2016
(New Activities are in Blue text – existing/ongoing activities in Black Text)

CONSTRUCTION - Richard Malberg/Le Van Loi


Key Activity this week Key Activity next week
 Hydro-testing, pipe flushing & blowing, and piping reinstatements  Hydro-testing, pipe flushing & blowing, and piping reinstatements
 Loop Checks in Process & Utility areas  Loop Checks in Process & Utility areas
 Punch listing & killing on completed systems in Utility & Process  Punch listing & killing on completed systems in Utility & Process Areas
Areas  Aqua milling continuing in interconnecting pipe-rack and Utility units
 Aqua milling in interconnecting pipe rack & in B100  Continue blowdown of closed loop cooling water system
 Continued blowdown of closed loop cooling water system
Area of Concern Action to Area of Concern
a. The current rate of progress of the post-hydro testing activities of a. JGCS has added direct labour and supervision to perform post-hydro
flushing and reinstatement are too slow to achieve M42 Project test activities. Letter issued to JGCS to seek an explanation of the
Mechanical Completion in Process units. recovery plan for above ground piping and readiness for final walk
b. The number of final walk arounds to complete is an increasing arounds in the Process systems.
challenge over M40 to M42. Punch A killing will be a priority and the b. IPMT are focused on the final walk arounds required for Non-Process
Punch B killing on process area utility systems is likely to become an Systems and in Utility Areas, as few Process system walk arounds are
impediment to System RFSU of utility systems in Process Areas. being implemented. IPMT and OPT resource review to be progressed
c. The resource level of electrical, instrumentation and controls in early November to ensure there are adequate responsible persons
inspection personnel is inadequate to support the loop checks, identified for walk arounds within every Utility and Process unit.
function checks, reinstatements, and final walk arounds. c. IPMT resources are being supplemented by OPT resources. IPMT and
d. Quality of work in the Hydrogen Manufacturing Unit is unsatisfactory OPT are seeking to identify suitable people to provide support.
and further rework is identified. Improved coordination of work d. JGC has added technical supervision resources and direct labour. is
sequence and progressive inspections is required. coordinating actions with GS. Further action will follow if collaboration is
e. SSP04 remediation, reconditioning of panels and panel replacement ineffective.

562510469.docx Page 2 of 3
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 28 October 2016
(New Activities are in Blue text – existing/ongoing activities in Black Text)

f. Refinery fire water readiness for start-up e. Reconditioning activities on panels are being monitored on site.
f. JGCS requested to give priority to system completion and service tests.