Professional Documents
Culture Documents
Dieter Katz
March 2006
NZ TREASURY Financing Major Infrastructure Projects: Public Private
P OLICY PERSPECTIVES Partnerships (PPPs)
PAPER 06/02
ISSN 1176-9513
• There are other ways of obtaining private sector finance without having
to enter into a PPP;
The paper concludes that PPPs are worthwhile only if all three of the
following conditions are met:
Summary.......................................................................................................ii
Introduction .................................................................................................. 1
What is a PPP?............................................................................................ 2
Conclusion ................................................................................................... 9
References................................................................................................. 10
Introduction
This paper concerns itself with infrastructure concession agreements,
under which a government agency awards a long-term contract to a private
PPPs are said to bring party to design, build and operate a facility that provides services either to
projects forward and offer the public or back to the government agency. Typical examples from
better value for money. overseas would include toll roads, prisons, stadiums, water treatment
plants and military training facilities.
While few public private partnerships of this kind (PPPs1) have been
undertaken in New Zealand, they have been popular in a number of
countries for advancing the construction of large public infrastructure
projects. They are said to offer “the potential to bring forward projects and
free up public funds for other projects”2 and “offer the potential for
government agencies to achieve better value for money through value
drivers such as improved risk sharing, innovation, better asset utilisation
and the adoption of commercial production and management practices”.3
PPPs are very complex and this paper cannot do justice to all the issues
they give rise to.4 Moreover, PPPs have been and continue to be
controversial. Attention is drawn to the disclaimer on page i which is
particularly pertinent in the case of this paper.
1
Sometimes also known as private finance initiatives (PFI).
2
The Independent, 11 December 2002.
3
Senator Nick Minchin, Australian Minister of Finance and Administration, June 2002.
4
A fuller treatment can be found, for example, in Webb and Pulle (2002), Osborne (2000),
Fiscal Affairs Department (2004), de Bettignies and Ross (2004) and in a recent
publication by the Office of the Auditor General (2006).
• The contract is typically for 20-30 years, or a substantial part of the life of
the facility;
• At the end of the contract, control of the facility is usually returned to the
government or a local authority.
Conventional Private
PPP Sector Procurement
Public Treasury Public
Agency (financier) Agency
Financier Consortium
• The Corrections Act 2004 prohibits the Crown from entering into any
contract for the management of any prison.
• Section 130 of the Local Government Act 2002 prohibits PPPs for water
and wastewater services.
There are some instances There have been very few New Zealand PPPs of the kind described above,
of delivery of public services but one example is described in the appendix. There have been no
by the private sector substantial PPPs entered into by a central government agency.
(conventional private sector
New Zealand no longer has a Ministry of Works. Design and construction
procurement), but these are is almost always contracted out to the private sector. While operation and
not widespread either. maintenance is often carried out by the public sector, this is certainly not
always the case. For example, Transit New Zealand (the public agency
responsible for building and maintaining state highways) contracts out all
maintenance of state highways, as well as design and construction.
Another example is the Auckland Central Remand prison, the operation of
which was contracted out in 2000.5
5
The management contract was not renewed in 2005 as a result of the Corrections Act
2004.
Public sector assessments often suffer from an optimism bias. (While the
same is also true for many private sector projects, it is probably difficult to
…better whole-of-life project establish empirically whether, or the extent to which, public6 sector projects
suffer more from optimism bias than private sector projects) . Under a PPP
evaluation,
the private sector has arguably a stronger incentive than a government
agency to be realistic about the prospects of a project. This is because of
the considerable financial investment the consortium has put at risk. One
would expect the private sector not to submit a tender if the business case
does not stack up.
It seems clear that there are stronger incentives to correctly identify the
whole of life costs of construction and operation, and the likely revenue
stream, under a PPP, if project risk is transferred to the private sector.
…stronger incentives to The extent to which better optimization will result depends on a number of
innovate and minimize factors:
whole-of-life costs,
• The state of knowledge about construction methods and long-term
maintenance and operational requirements. Where a public agency
undertakes many similar projects, such as Transit NZ, there may be less
scope for innovation and optimisation than in the case of more
specialised projects that are done on a one-off basis, e.g. a city council
contracting for a water treatment plant.
• The extent of scope given to the PPP consortium to vary designs and
innovate. The scope is greater when the public agency specifies its
requirements in terms of service levels. The less it can do so, i.e. the
more it specifies the contract in input terms or in terms of physical or
engineering specifications, the less scope there is for the private sector
to achieve whole-of-life efficiencies beyond those already obtained by
the public agency in developing its contract specifications. For example,
the public agency may find it difficult to define a motorway project in a
6
This author is not aware of any credible studies on this point.
In sum, the scope for private sector innovation and whole-of-life optimization
(relative to conventional procurement) is another advantage of transferring risk
to the private sector. But sometimes it will be not very significant.
Access to additional capital: The government does not have to provide capital
in the case of PPPs. This can be an advantage where the government has a
poor credit rating and is not able to raise finance, and where financial markets
cannot readily distinguish between general government borrowing and
government borrowing for a specific revenue-earning infrastructure project.
This is not at present an issue in New Zealand.
In any case, where the infrastructure relies for its revenue on a public
agency paying a user fee (e.g. prisons), then it is likely that the PPP
financier will face no better credit rating for this project than the
government, and is not, therefore, likely to have better access to capital,
even if the government has a poor credit rating.
Off-balance sheet financing: When people say that PPPs will give access to
more capital, i.e. will bring forward projects and free up public funds for
… and access to additional
other projects, they usually mean that PPPs are a way of financing projects
capital without affecting the without breaching the government’s self-imposed borrowing limit. This
gross debt target, appears to have been the motivation for PPPs in the UK and in Australia, at
least in the early days.
The New Zealand Government must maintain prudent levels of total debt.8
To manage total debt at prudent levels the Government focuses on
ensuring SOEs have debt structures that achieve best commercial practice
and has a self-imposed borrowing limit in the form of a gross sovereign-
issued debt target. 9 PPPs could provide the opportunity to raise funds
beyond what would be normally possible under the gross sovereign-issued
debt target.
7
See also the discussion below on performance enforcement.
8
Section 26G of the Public Finance Act.
9
Budget Policy Statement 2005.
This is more difficult in the case of infrastructure that does not earn revenue
from third parties, such as prisons, and roads financed from “shadow
tolls”.10 In such situations the Crown typically bears the demand risk.
While accounting rules are in a state of flux on this point,11 it appears that
where the demand risk is not transferred, financial liabilities arising from
obligations under a PPP contract would need to be recorded on the
Crown’s balance sheet irrespective of who raised the capital.12
Note, if the Crown finances a project that would have been viable as an
… but this can also be unsubsidised PPP, the debt would be matched on its balance sheet by a
achieved in other ways than corresponding asset, namely the value of the income stream accruing to
the infrastructure (e.g. a toll road). The net worth of the Crown is not
by entering into a PPP.
immediately affected, although the set of financial risks faced by the Crown
does change. The higher gross debt does not, therefore, reflect a higher
economic burden on tax payers. In any case, the higher debt gradually
reduces back to zero over the life of the asset. In such cases, there may
be a case for treating the debt in the same way as SOE debt structures,
and there may be ways of managing public perceptions of increased debt
by, for example, reporting investments in income-earning assets separately
from other assets.
The example of SOEs illustrates the point that there are other ways of
managing concerns about the effect on gross debt than by entering into a
PPP. These should be considered alongside any proposal to enter into a
PPP, if the motivation for the PPP is to finance income-earning
infrastructure without putting pressure on the government’s gross debt
target (i.e. off-balance sheet).
In the case where a public agency is the user (such as a schools PPP), this
‘advantage’ is a double-edged sword: a contractual obligation to provide the
money for maintenance comes at the cost of reduced budget flexibility, yet
limited deferment of maintenance need not always harm an asset unduly.
10
Under a shadow toll, the number of vehicles using a road is counted, and the toll is paid
by the government.
11
See Office of the Auditor-General (2006) and Davies P and Eustice K (2005).
12
Davies P and Eustice K (2005).
13
See BEC and Sir Michael Latham, Constructing the team, reproduced in Dr Eamonn
Butler & Allan Stewart MP, Seize the Initiative, Adam Smith Institute, 1996, quoted in
Grahame Allen (2001), p.34.
14
Australian Council for Infrastructure Development, Australia at a Crossroads
Public/Private partnerships or Perish?, quoted in Webb and Pulle (2002).
Both kinds of risk are often reduced by including in the contract loss sharing
or profit sharing provisions. But such provisions reduce the extent of risk
transfer, and therefore the advantages of PPPs.16
15
There is an extensive literature on the choice between entering into explicit contracts and
coordinating activities via a command relationship. This is loosely known as the “theory
of the firm”. See, for example, O. Williamson (1980).
16
Ehrhardt D and Erwin T (2004)
But, aside from the problems with the public sector comparator, these
studies suffer from the fact that few PPPs are more than one third through
their lives.
Conclusion
There is little reliable empirical evidence about the costs and benefits of
PPPs. This paper has therefore made a qualitative assessment.
A PPP may be a good way It concludes that the more complete transfer of risk that is possible under a
of procuring services only if PPP, results in better project evaluation and stronger incentives to innovate
three conditions are met: and minimize whole of life costs. But these advantages must be balanced
Project outcomes can be against the large contract negotiation costs, the inflexibilities of a long-term
contract and the reduced competitive pressures on performance after the
specified in service level
contract has been entered into (compared with a situation where the
terms, performance can be contract is re-tendered periodically over the life of the infrastructure).
measured objectively and
performance objectives are The decision whether to proceed with a PPP rather than with a
durable. conventional procurement process turns principally on the following three
questions:
3. Are the public agency’s desired outcomes likely to be durable, given the
length of the contract?
17
HM Treasury (2003)
Quay Park Arena Management has agreed to build, own, operate and
maintain the Arena for 40 years, when ownership of the building and the
operating systems will be transferred to the Council. Construction is
currently in progress.
As the arena was not commercially viable, the Council provided a subsidy
by way of a contribution of $68.2 million towards the capital cost of $80
million.
Quay Park Arena Management has put up the remaining $11 million. It will
be entitled to revenue from ticket sales and venue rentals. The agreement
provides for the Council to receive royalties, which will in part be used to
fund community events at the Arena. However, there is no guarantee that
royalties will be received.
The main reason for choosing a PPP approach was that the Council does
not understand and has no experience in operating a major events venue.
Under the agreement, the private sector partner, which has the experience
and skills to run this type of business, is responsible for operations and
carries the operational risk.