REPORT
FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED
STATIONS (VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD
METRO STATION) INCLUDING CIVIL, ARCHITECTURAL
FINISHES, WATER SUPPLY, SANITARY INSTALLATION
DRAINAGE, EXTERNAL DEVELOPMENT, FIRE FIGHTING, FINE
DETECTION, E&M WORKS AND PEB STRUCTURES ON PRIORITY
SECTION OF CORRIDOR-1, PHASE-1 OF AGRA METRO AT AGRA,
UTTAR PRADESH, INDIA. (BH-4, 5 & 7).
SUBMITTED TO
PROJECT NO - 1876
JAN.-2020
BY
INTERIM REPORT ON
GEOTECHNICAL INVESTIGATION
FOR
AT LOCATION FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED
STATIONS (VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD METRO
STATION) INCLUDING CIVIL, ARCHITECTURAL FINISHES, WATER
SUPPLY, SANITARY INSTALLATION DRAINAGE, EXTERNAL
DEVELOPMENT, FIRE FIGHTING, FINE DETECTION, E&M WORKS
AND PEB STRUCTURES ON PRIORITY SECTION OF CORRIDOR-1,
PHASE-1 OF AGRA METRO AT AGRA, UTTAR PRADESH, INDIA.
CONTENTS
SL. No. CHAPTER PAGE NO.
1
INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED STATIONS
(VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD METRO STATION)
INCLUDING CIVIL, ARCHITECTURAL FINISHES, WATER SUPPLY, SANITARY
INSTALLATION DRAINAGE, EXTERNAL DEVELOPMENT, FIRE FIGHTING,
FINE DETECTION, E&M WORKS AND PEB STRUCTURES ON PRIORITY
SECTION OF CORRIDOR-1, PHASE-1 OF AGRA METRO AT AGRA, UTTAR
PRADESH, INDIA.
The study of bore logs/results of laboratory and other field tests as above from ground
level reveal that:-
1.1 At the location of borehole BH – 4 P-B/1 (P2/30).
The sub-soil strata: -
From existing ground surface to 1.00m consists filled up Soil.
From depths 1.00 to 2.50 m consists of Yellowish Sandy Silt of Non Plasticity with
Gravels (ML), having SPT field ‘N’ value is 9 showing loose dense compactness of the
strata.
From depths 2.50 to 5.50 m consists of Brownish Clayey Silt of Medium Plasticity
with Gravels (CI), having SPT field ‘N’ values ranging from 13 to 20 showing stiff to
very stiff consistency of the strata.
From depths 5.50 to 8.50 m consists of Grayish Sandy Silt of Non Plasticity with
Gravels (ML), having SPT field ‘N’ values ranging from 27 to 33 showing medium
dense to dense compactness of the strata.
From depths 8.50 to 17.50 m consists of Grayish Clayey Silt of Medium Plasticity with
Gravels (CI), having SPT field ‘N’ values ranging from 34 to 43 showing hard
consistency of the strata.
From depths 17.50 to 22.00 m consists of Grayish Silty Sand with Gravels (SM),
having SPT field ‘N’ values ranging from 46 to 53 showing dense to very dense
compactness of the strata.
From depths 22.00 to 32.50 m consists of Brownish Sandy Silt of Low Plasticity with
Gravels (ML-CL), having SPT field ‘N’ values ranging from 57 to 82 showing hard
consistency of the strata.
From depths 32.50 to 40.00 m consists of Brownish Clayey Silt of Medium Plasticity
(CI), having SPT field ‘N’ values ranging from 78 to 116 showing hard consistency of
the strata.
From depths 40.00 to 43.00 m consists of Brownish Sandy Silt of Non Plasticity (ML),
having SPT field ‘N’ values ranging from 97 to 101 showing very hard dense
compactness of the strata.
From depths 43.00 to 50.45 m consists of Brownish Clayey Silt of Low Plasticity (CL),
having SPT field ‘N’ values ranging from 95 to 111 showing hard consistency of the
strata.
The depth wise observed SPT values & details of rock cores of subsoil strata are given
in Soil Profile of respective bore holes.
1.2 At the location of borehole BH – 5 (P-3/14).
The sub-soil strata: -
2
INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED STATIONS
(VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD METRO STATION)
INCLUDING CIVIL, ARCHITECTURAL FINISHES, WATER SUPPLY, SANITARY
INSTALLATION DRAINAGE, EXTERNAL DEVELOPMENT, FIRE FIGHTING,
FINE DETECTION, E&M WORKS AND PEB STRUCTURES ON PRIORITY
SECTION OF CORRIDOR-1, PHASE-1 OF AGRA METRO AT AGRA, UTTAR
PRADESH, INDIA.
3
INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED STATIONS
(VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD METRO STATION)
INCLUDING CIVIL, ARCHITECTURAL FINISHES, WATER SUPPLY, SANITARY
INSTALLATION DRAINAGE, EXTERNAL DEVELOPMENT, FIRE FIGHTING,
FINE DETECTION, E&M WORKS AND PEB STRUCTURES ON PRIORITY
SECTION OF CORRIDOR-1, PHASE-1 OF AGRA METRO AT AGRA, UTTAR
PRADESH, INDIA.
From depths 16.00 to 19.00 m consists of Brownish Clayey Silt of Low Plasticity with
Gravel (CL), having SPT field ‘N’ values ranging from 45 to 48 showing hard
consistency of the strata.
From depths 19.00 to 22.00 m consists of Greyish Silty Sand (SM), having SPT field
‘N’ values ranging from 50 to 57 showing dense to very dense compactness of the
strata.
From depths 22.00 to 28.00 m consists of Grayish Sandy Silt of Non Plasticity with
Gravels (ML), having SPT field ‘N’ values ranging from 53 to 104 showing very dense
to hard compactness of the strata.
From depths 28.00 to 32.50 m consists of Brownish Silty Sand of Low Plasticity with
Gravels (ML-CL), having SPT field ‘N’ values ranging from 97 to 103 showing hard
consistency of the strata.
From depths 32.50 to 48.00 m consists of Brownish Clayey Silt of Medium Plasticity
with Gravels (CI), having SPT field ‘N’ values ranging from 91 to 109 showing very
hard consistency of the strata.
From depths 48.00 to 50.45 m consists of Brownish Silty Sand of Low Plasticity (ML-
CL), having SPT field ‘N’ values ranging from 105 to 125 showing very hard
consistency of the strata.
The depth wise observed SPT values & details of rock cores of subsoil strata are given
in Soil Profile of respective bore holes.
As per IS:1893, Part-I, 2016, In soil deposits consisting of submerged loose sands and
soils falling under classification SP with standard penetration N-values less than 15 in
seismic Zones III, IV, V and less than 10 in seismic Zone II, the vibration caused by
earthquake may cause liquefaction or excessive total and differential settlements. Such
sites should preferably be avoided while locating new settlements or important projects.
Otherwise, this aspect of the problem needs to be investigated and appropriate methods
of compaction or stabilization adopted to achieve suitable N-values as indicated in Note
3 under Table 1. i.e.
For Seismic Zone, III, IV &V, Corrected N value should be > 15 for 0.0 – 5.0 m depth.
Corrected N value should be > 25 for 5.0 – 10.0 m depth
For 5.0 -10.0 m depth, the corrected N value should be interpolated from above.
Alternatively, deep pile foundation may be provided and taken to depths well into the
layer which is not likely to liquefy.
Marine clays and other sensitive clays are also known to liquefy due to collapse of soil
structure and will need special treatment according to site condition.
4
INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED STATIONS
(VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD METRO STATION)
INCLUDING CIVIL, ARCHITECTURAL FINISHES, WATER SUPPLY, SANITARY
INSTALLATION DRAINAGE, EXTERNAL DEVELOPMENT, FIRE FIGHTING,
FINE DETECTION, E&M WORKS AND PEB STRUCTURES ON PRIORITY
SECTION OF CORRIDOR-1, PHASE-1 OF AGRA METRO AT AGRA, UTTAR
PRADESH, INDIA.
In present case, the site falls in earthquake zone – III and the subsoil encountered is
mostly of classification ML, SM, CL & CI with Intermediate layers of ML-CL.
The ground water level was encountered at 30.15m to 31.05m depth in boreholes and
considered 20.0m depth for analysis.
Liquefaction analysis as per IS: 1893, Part-I, 2016 is attached herewith.
Viewing the type of subsoil strata encountered, corrected N values and ground water
condition at site, in light of the susceptibility of liquefaction as specified in IS: 1893,
Part-I, 2016, it may be concluded that the subsoil strata encountered at site shall liquefy
at the location during earthquake.
3.0 RECOMMENDATIONS:
Depending on the field and laboratory observations of subsoil strata, test results and the
type of structures proposed at site, the most feasible soil-foundation system is
recommended as normal bored cast in situ R.C.C. piles foundations of 1.2m diameter at
different depths with cut-off level of 2.30m depth below existing Ground level.
Type of Foundation: Bored Cast in situ RCC Pile
The safe load carrying capacities of these piles are given in following table:-
Bore Dia of Cut-off Length of Safe load carrying capacity, ( T )
Holes No piles, level piles below
(mm) below cut-off, In comp. In uplift In lateral
EGL, (m) (m)
BH –4 2.30 34.00 380.00 270.0 45.0
(P-B/1/ 1200
P/2-30) 2.30 38.00 600.00 320.0 45.0
5
INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR
CONSTRUCTION OF ELEVATED VIADUCT AND 3 NOS. ELEVATED STATIONS
(VIZ. TAJ EAST GATE, BASAI & FATEHABAD ROAD METRO STATION)
INCLUDING CIVIL, ARCHITECTURAL FINISHES, WATER SUPPLY, SANITARY
INSTALLATION DRAINAGE, EXTERNAL DEVELOPMENT, FIRE FIGHTING,
FINE DETECTION, E&M WORKS AND PEB STRUCTURES ON PRIORITY
SECTION OF CORRIDOR-1, PHASE-1 OF AGRA METRO AT AGRA, UTTAR
PRADESH, INDIA.
The above values should be confirmed through Initial pile load tests as per IS: 2911
(Part-IV) in the field before adopting these values for design purposes.
Frictional angles are restricted to 32o in the pile capacity calculations.
Bulk density are restricted to 1.00 t/m3 below water table.
Recommended pile capacities are without deducting the self-weight of piles.
Permissible lateral deflection equal to 1% of pile diameter.
It should be ensured that the bottom of the pile bore is cleaned properly before casting
the pile. This is important because the soil particles tend to settle down at the bottom of
the pile bore, which can cause reduction in pile capacities.
Sufficient initial and routine static pile load tests should be done to ensure that the safe
load on the piles exceeds the design loads. The number of routine pile load tests may be
increased if significant variations are observed. High Strain Dynamic pile load tests
may also be done on selected piles for higher reliability.
It is also recommended that pile integrity tests (PIT) be carried out on all working piles
installed on site, in order to assess the quality of the pile construction. The PIT results
may be used as a guideline to select the appropriate piles for routine load tests.
The site falls in earthquake zone –III as per IS: 1893, 2016 and the structure shall be
designed accordingly.
4.0 CLOSURE
We appreciate the opportunity given to us to submit this report. This presented report is
based on observations and tests on samples collected from the boreholes as decided by
the client. In case any difference is noticed in the field subsoil strata and reported
subsoil strata during excavation please contact us before proceeding with further
construction.
For SAI GEOTECHNICAL ENGINEERS PVT. LTD.
6
BOREHOLE NO. : 4 SHEET NO : 7
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.0 m Location No. :- P-B/1(P2/30) DATE STARTED : 20/12/2020
Co-ordinates: E: 207662.711 N: 3007355.476 DATE COMPLETED : 25/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
DEPTH OF SAMPLE BELOW
DESCRIPTION OF SOIL
NATURE OF SAMPLING
PENETRATION (CM)
(%)
SPECIFIC GRAVITY
REPRESENTATION
DEPTH IN METERS
Angle of friction
NO. OF BLOWS
TYPE OF TEST
REFERENCE
Cohesion, C,
eo Cc
SYMBOLIC
(Degrees)
(kg/sqcm)
L.W.L (M)
GRAVEL
SAND
CLAY
( MM)
SILT
100.00 0.0 DS 0.00 1 0.00 - 1.00 Filled Up
99.00 1.0 SPT 1.00 1 1.00 - 1.45 9 30 9 13 Yellowish Sandy Silt of 8.0 34.0 55.0 3.0
Non Plasticity with
Gravels
98.50 1.5 UDS 1.50 1 1.50 - 1.90 (ML) N P - 1.65 1.53 7.95 - 2.66 DST 0.04 26
97.50 2.5 SPT 2.50 2 2.50 - 2.95 13 30 13 13 4.0 5.0 68.0 23.0
Brownish Clayey Silt of
Medium Plasticity with
96.00 4.0 SPT 4.00 3 4.00 - 4.45 20 30 20 20
Gravels
(CI)
95.50 4.5 UDS 4.50 2 4.50 - 4.90 41.55 25.63 15.92 1.73 1.57 9.97 25.68 2.71 UUT 1.25 6 0.726 0.223
94.50 5.5 SPT 5.50 4 5.50 - 5.95 27 30 27 27 3.0 39.0 56.0 2.0
Grayish Sandy Silt of
Non Plasticity with
93.00 7.0 SPT 7.00 5 7.00 - 7.45 33 30 33 33
Gravels
(ML)
92.50 7.5 UDS 7.50 3 7.50 - 7.90 N P - 1.75 1.60 9.58 - 2.65 DST 0.00 27
30.15
91.50 8.5 SPT 8.50 6 8.50 - 8.95 37 30 37 37 7.0 10.0 58.0 25.0
150
89.50 10.5 UDS 10.50 4 10.50 - 10.90 41.51 27.14 14.37 1.84 1.63 12.85 27.81 2.68 UUT 1.47 5 0.644 0.219
84.00 16.0 SPT 16.00 11 16.00 - 16.45 43 30 43 43 0.0 4.0 75.0 21.0
83.50 16.5 UDS 16.50 6 16.50 - 16.90 44.86 27.24 17.62 1.90 1.65 14.86
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
BOREHOLE NO. : 4 SHEET NO : 8
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.000 m Location No. :- P-B/1(P2/30) DATE STARTED : 20/12/2020
Co-ordinates: E: 207662.711 N: 3007355.476 DATE COMPLETED : 25/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
SYMBOLIC REPRESENTATION
SHEAR STRENGTH CONSOLIDATION
CHARACTERISTICS PARAMETERS
DEPTH IN METERS BELOW
PENETRATION (CM)
SPECIFIC GRAVITY
DEPTH IN METERS
(%)
(%)
TYPE OF TEST
REFERENCE
eo Cc
Cohesion, C,
(kg/sqcm)
GRAVEL
L.W.L
SAND
( MM)
CLAY
SILT
81.00 19.0 SPT 19.00 13 19.00 - 19.45 51 30 51 29 5.0 45.0 50.0 0.0
79.50 20.5 SPT 20.50 14 20.50 - 20.95 53 30 53 29 7.0 51.0 42.0 0.0
78.00 22.0 SPT 22.00 15 22.00 - 22.45 57 30 57 57 6.0 27.0 60.0 7.0
77.50 22.5 UDS 22.50 8 22.50 - 22.90 29.98 23.91 6.07 1.91 1.67 14.37
76.50 23.5 SPT 23.50 16 23.50 - 23.95 59 30 59 59 3.0 26.0 65.0 6.0
74.50 25.5 UDS 25.50 9 25.50 - 25.90 28.02 21.46 6.56 1.95 1.68 16.03 - 2.66 UUT 0.68 10 0.583 0.124
30.15
150
71.50 28.5 UDS 28.50 10 28.50 - 28.90 28.12 22.01 6.11 1.96 1.70 15.01
70.50 29.5 SPT 29.50 20 29.50 - 29.95 77 30 77 77 11.0 24.0 57.0 8.0
68.50 31.5 UDS 31.50 11 31.50 - 31.90 26.9 20.1 6.81 2.02 1.71 18.26 9.05
67.50 32.5 SPT 32.50 22 32.50 - 32.95 78 30 78 78 2.0 16.0 69.0 13.0
Brownish Clayey Silt of
Medium Plasticity
(CI)
66.00 34.0 SPT 34.00 23 34.00 - 34.45 84 30 84 84
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
BOREHOLE NO. : 4 SHEET NO : 9
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.000 m Location No. :- P-B/1(P2/30) DATE STARTED : 20/12/2020
Co-ordinates: E: 207662.711 N: 3007355.476 DATE COMPLETED : 25/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
SYMBOLIC REPRESENTATION
SPT TEST RESULTS GRAIN SIZE ANALYSIS
CHARACTERISTICS PARAMETERS
DEPTH OF SAMPLE BELOW
DEPTH IN METERS BELOW
PENETRATION (CM)
SPECIFIC GRAVITY
DEPTH IN METERS
(%)
(%)
(%)
NO. OF BLOWS
TYPE OF TEST
eo Cc
REFERENCE
Cohesion, C,
(kg/sqcm)
GRAVEL
SAND
( MM)
CLAY
SILT
65.50 34.5 UDS 34.50 12 34.50 - 34.90 43.05 25.61 17.44 2.03 1.71 18.54
64.50 35.5 SPT 35.50 24 35.50 - 35.95 105 30 105 105 0.0 15.0 62.0 23.0
62.50 37.5 UDS 37.50 13 37.50 - 37.90 42.15 25.80 16.35 SLIPPED 25.50 2.72 UUT* 1.55 5
61.50 38.5 SPT 38.50 26 38.50 - 38.95 89 30 89 89 0.0 19.0 60.0 21.0 .
60.00 40.0 SPT 40.00 27 40.00 40.45 97 30 97 25 3.0 20.0 74.0 3.0
150
(ML)
57.00 43.0 SPT 43.00 29 43.00 43.45 95 30 95 55 4.0 33.0 50.0 13.0
56.50 43.5 UDS 43.50 15 43.50 43.90 33.51 23.18 10.33 SLIPPED
54.00 46.0 SPT 46.00 31 46.00 46.45 108 30 108 61 Brownish Clayey Silt of 0.0 29.0 57.0 14.0
Low Plasticity
53.50 46.5 UDS 46.50 16 46.50 46.90 (CL) SLIPPED 14.50 2.69 UUT* 1.18 8
52.50 47.5 SPT 47.50 32 47.50 47.95 110 30 110 62 33.01 23.51 9.50
50.00 50.0 SPT 50.00 33 50.00 50.45 111 30 111 63 2.0 24.0 62.0 12.0
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
SHEET NO : 10
N - VALUE
12
15
18
21
DEPTH IN M
24
OBSERVED
27 CORRECTED
30
33
36
39
42
45
48
51
54
BOREHOLE NO. : 5 SHEET NO : 11
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.0 m Location No. :- P-3/14 DATE STARTED : 23/12/2020
Co-ordinates: E: 208120.541 N: 3007365.687 DATE COMPLETED : 29/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
DEPTH OF SAMPLE BELOW
DESCRIPTION OF SOIL
NATURE OF SAMPLING
PENETRATION (CM)
(%)
SPECIFIC GRAVITY
REPRESENTATION
DEPTH IN METERS
Angle of friction
NO. OF BLOWS
TYPE OF TEST
REFERENCE
Cohesion, C,
eo Cc
SYMBOLIC
(Degrees)
(kg/sqcm)
L.W.L (M)
GRAVEL
SAND
CLAY
( MM)
SILT
100.00 0.0 DS 0.00 1 0.00 - 1.00 Filled Up
99.00 1.0 SPT 1.00 1 1.00 - 1.45 6 30 6 8 Brownish Sandy Silt of 0.0 28.0 69.0 3.0
Non Plasticity
98.50 1.5 UDS 1.50 1 1.50 - 1.90 (ML) N P - 1.60 1.51 6.06 - 2.66 DST 0.05 26
97.50 2.5 SPT 2.50 2 2.50 - 2.95 18 30 18 18 0.0 4.0 74.0 22.0
95.50 4.5 UDS 4.50 2 4.50 - 4.90 Brownish Clayey Silt of 42.51 26.15 16.36 1.72 1.57 9.67 25.46 2.71 UUT 1.24 6 0.726 0.218
Medium Plasticity
94.50 5.5 SPT 5.50 4 5.50 - 5.95 31 30 31 31 (CI) 0.0 3.0 74.0 23.0
92.50 7.5 UDS 7.50 3 7.50 - 7.90 43.21 25.06 18.15 1.75 1.61 8.49
31.05
91.50 8.5 SPT 8.50 6 8.50 - 8.95 44 30 44 38 0.0 45.0 53.0 2.0
150
89.50 10.5 UDS 10.50 4 10.50 - 10.90 Grayish Sandy Silt of N P - 1.82 1.64 11.05 - 2.66 DST 0.00 28
Non Plasticity
88.50 11.5 SPT 11.50 8 11.50 - 11.95 52 30 52 39 (ML) 0.0 41.0 56.0 3.0
85.50 14.5 SPT 14.50 10 14.50 - 14.95 54 30 54 54 9.0 19.0 60.0 12.0
Brownish Clayey Silt of
Low Plasticity with
84.00 16.0 SPT 16.00 11 16.00 - 16.45 58 30 58 58
Gravel
(CL)
83.50 16.5 UDS 16.50 6 16.50 - 16.90 15.0 22.0 49.0 14.0 34.71 24.58 10.13 1.89 1.65 14.25 12.05 2.68 UUT 1.05 8 0.624 0.227
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
BOREHOLE NO. : 5 SHEET NO : 12
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.000 m Location No. :- P-3/14 DATE STARTED : 23/12/2020
Co-ordinates: E: 208120.541 N: 3007365.687 DATE COMPLETED : 29/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
SYMBOLIC REPRESENTATION
SHEAR STRENGTH CONSOLIDATION
CHARACTERISTICS PARAMETERS
DEPTH IN METERS BELOW
PENETRATION (CM)
SPECIFIC GRAVITY
DEPTH IN METERS
(%)
(%)
TYPE OF TEST
REFERENCE
eo Cc
Cohesion, C,
(kg/sqcm)
GRAVEL
L.W.L
SAND
( MM)
CLAY
SILT
81.00 19.0 SPT 19.00 13 19.00 - 19.45 67 30 67 39
80.50 19.5 UDS 19.50 7 19.50 - 19.90 N P - 1.89 1.64 15.29 - 2.65 DST 0.00 28
79.50 20.5 SPT 20.50 14 20.50 - 20.95 71 30 71 40 Grayish Sandy Silt of 3.0 30.0 65.0 2.0
Non Plasticity with
Gravels
78.00 22.0 SPT 22.00 15 22.00 - 22.45 76 30 76 41 (ML)
76.50 23.5 SPT 23.50 16 23.50 - 23.95 67 30 67 34 4.0 25.0 68.0 3.0
75.00 25.0 SPT 25.00 17 25.00 - 25.45 61 30 61 61 5.0 19.0 61.0 15.0
74.50 25.5 UDS 25.50 9 25.50 - 25.90 34.29 23.85 10.44 1.94 1.68 15.53 15.40 2.68 UUT 1.21 8 0.595 0.219
31.05
150
71.50 28.5 UDS 28.50 10 28.50 - 28.90 33.54 23.52 10.02 1.99 1.70 16.98
70.50 29.5 SPT 29.50 20 29.50 - 29.95 74 30 74 74 2.0 15.0 70.0 13.0
68.50 31.5 UDS 31.50 11 31.50 - 31.90 42.05 25.94 16.11 SLIPPED
Brownish Clayey Silt of
Medium Plasticity
(CI)
67.50 32.5 SPT 32.50 22 32.50 - 32.95 71 30 71 71 4.0 16.0 59.0 21.0
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
BOREHOLE NO. : 5 SHEET NO : 13
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.000 m Location No. :- P-3/14 DATE STARTED : 23/12/2020
Co-ordinates: E: 208120.541 N: 3007365.687 DATE COMPLETED : 29/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
SYMBOLIC REPRESENTATION
SPT TEST RESULTS GRAIN SIZE ANALYSIS
CHARACTERISTICS PARAMETERS
DEPTH OF SAMPLE BELOW
DEPTH IN METERS BELOW
PENETRATION (CM)
SPECIFIC GRAVITY
DEPTH IN METERS
(%)
(%)
(%)
NO. OF BLOWS
TYPE OF TEST
eo Cc
REFERENCE
Cohesion, C,
(kg/sqcm)
GRAVEL
SAND
( MM)
CLAY
SILT
65.50 34.5 UDS 34.50 12 34.50 - 34.90 41.45 25.65 15.80 2.02 1.69 19.31
64.50 35.5 SPT 35.50 24 35.50 - 35.95 89 30 89 89 11.0 23.0 42.0 24.0
62.50 37.5 UDS 37.50 13 37.50 - 37.90 45.04 27.45 17.59 2.04 1.70 20.02 28.05 2.72 UUT 1.72 5.0 0.600 0.230
61.50 38.5 SPT 38.50 26 38.50 - 38.95 103 30 103 103 3.0 19.0 52.0 26.0
150
58.50 41.5 SPT 41.50 28 41.50 41.95 105 30 105 105 4.0 14.0 59.0 23.0
54.00 46.0 SPT 46.00 31 46.00 46.45 103 30 103 103 5.0 17.0 56.0 22.0
50.00 50.0 SPT 50.00 33 50.00 50.45 103 30 103 103 3.0 14.0 62.0 21.0
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
SHEET NO : 14
N - VALUE
0 20 40 60 80 100 120
0
12
15
18
21
DEPTH IN M
24
OBSERVED
27 CORRECTED
30
33
36
39
42
45
48
51
54
BOREHOLE NO. : 7 SHEET NO : 15
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.0 m Location No. :- P-4/5 DATE STARTED : 29/12/2020
Co-ordinates: E: N: DATE COMPLETED : 04/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
DEPTH OF SAMPLE BELOW
DESCRIPTION OF SOIL
NATURE OF SAMPLING
PENETRATION (CM)
(%)
SPECIFIC GRAVITY
REPRESENTATION
DEPTH IN METERS
Angle of friction
NO. OF BLOWS
TYPE OF TEST
REFERENCE
Cohesion, C,
eo Cc
SYMBOLIC
(Degrees)
(kg/sqcm)
L.W.L (M)
GRAVEL
SAND
CLAY
( MM)
SILT
100.00 0.0 DS 0.00 1 0.00 - 1.00 Filled Up
99.00 1.0 SPT 1.00 1 1.00 - 1.45 8 30 8 11 Yellowish Sandy Silt of 0.0 34.0 63.0 3.0
Non Plasticity
98.50 1.5 UDS 1.50 1 1.50 - 1.90 (ML) N P - 1.64 1.53 7.09 - 2.65 DST 0.02 26
97.50 2.5 SPT 2.50 2 2.50 - 2.95 19 30 19 23 3.0 51.0 46.0 0.0
95.50 4.5 UDS 4.50 2 4.50 - 4.90 N P - 1.73 1.58 9.45 - 2.64 DST 0.00 30
94.50 5.5 SPT 5.50 4 5.50 - 5.95 31 30 31 31 5.0 13.0 80.0 2.0
91.50 8.5 SPT 8.50 6 8.50 - 8.95 43 30 43 37 0.0 10.0 86.0 4.0
150
90.00 10.0 SPT 10.00 7 10.00 - 10.45 50 30 50 40 0.0 52.0 48.0 0.0
89.50 10.5 UDS 10.50 4 10.50 - 10.90 N P - 1.79 1.61 11.05 - 2.63 DST 0.00 30
88.50 11.5 SPT 11.50 8 11.50 - 11.95 46 30 46 35 0.0 51.0 49.0 0.0
Greyish Silty Sand
(SM)
87.00 13.0 SPT 13.00 9 13.00 - 13.45 52 30 52 37
85.50 14.5 SPT 14.50 10 14.50 - 14.95 57 30 57 39 0.0 53.0 47.0 0.0
84.00 16.0 SPT 16.00 11 16.00 - 16.45 48 30 48 48 4.0 18.0 65.0 13.0
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
BOREHOLE NO. : 7 SHEET NO : 16
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.000 m Location No. :- P-4/5 DATE STARTED : 29/12/2020
Co-ordinates: E: N: DATE COMPLETED : 04/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
DEPTH OF SAMPLE BELOW
DESCRIPTION OF SOIL
NATURE OF SAMPLING
PENETRATION (CM)
SPECIFIC GRAVITY
REPRESENTATION
DEPTH IN METERS
(%)
TYPE OF TEST
Angle of friction
REFERENCE
Cohesion, C,
eo Cc
SYMBOLIC
(Degrees)
(kg/sqcm)
GRAVEL
L.W.L
( MM)
SAND
CLAY
SILT
81.00 19.0 SPT 19.00 13 19.00 - 19.45 50 30 50 29 0.0 72.0 28.0 0.0
79.50 20.5 SPT 20.50 14 20.50 - 20.95 57 30 57 32 0.0 52.0 48.0 0.0
78.00 22.0 SPT 22.00 15 22.00 - 22.45 53 30 53 28 10.0 21.0 68.0 1.0
77.50 22.5 UDS 22.50 8 22.50 - 22.90 N P - 1.98 1.69 16.97 - 2.65 DST 0.00 28
76.50 23.5 SPT 23.50 16 23.50 - 23.95 59 30 59 30 Grayish Sandy Silt of 18.0 13.0 66.0 3.0
Non Plasticity with
Gravels
75.00 25.0 SPT 25.00 17 25.00 - 25.45 101 30 101 50 (ML)
150
73.50 26.5 SPT 26.50 18 26.50 - 26.95 104 30 104 49 27.0 29.0 43.0 1.0
72.00 28.0 SPT 28.00 19 28.00 - 28.45 97 30 97 97 17.0 18.0 59.0 6.0
71.50 28.5 UDS 28.50 10 28.50 - 28.90 28.24 22.15 6.09 2.01 1.71 17.80 8.90 2.66 UUT 0.72 10 0.556 0.126
Brownish Silty Sand of
Low Plasticity With
70.50 29.5 SPT 29.50 20 29.50 - 29.95 102 30 102 102
Gravels
(ML-CL)
69.00 31.0 SPT 31.00 21 31.00 - 31.45 103 30 103 59 6.0 21 65 8.0
68.50 31.5 UDS 31.50 11 31.50 - 31.90 27.84 21.51 6.33 SLIPPED
67.50 32.5 SPT 32.50 22 32.50 - 32.95 101 30 101 101 0.0 9.0 69.0 22.0
Brownish Clayey Silt of
Medium Plasticity
(CI)
66.00 34.0 SPT 34.00 23 34.00 - 34.45 91 30 91 91
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
BOREHOLE NO. : 7 SHEET NO : 17
PROJECT : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station) including Civil, Architectural Finishes, Water Suply, Senitary
Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
REDUCED LEVEL OF B/HOLE : 100.000 m Location No. :- P-4/5 DATE STARTED : 29/12/2020
Co-ordinates: E: N: DATE COMPLETED : 04/12/2020
FIELD TEST RESULTS LABORATORY TEST RESULTS
SAMPLE REFERENCE NO. SHEAR STRENGTH CONSOLIDATION
DESCRIPTION OF SOIL
NATURE OF SAMPLING
CHARACTERISTICS PARAMETERS
MOISTURE CONTENT
N, VALUE ( Corrected )
N, VALUE ( Recorded )
BELOW REFERENCE
PENETRATION (CM)
DEPTH OF SAMPLE
SPECIFIC GRAVITY
REPRESENTATION
DEPTH IN METERS
DEPTH IN METERS
(%)
(%)
(%)
NO. OF BLOWS
Angle of friction
TYPE OF TEST
Cohesion, C,
eo Cc
SYMBOLIC
WITH I.S.
(Degrees)
(kg/sqcm)
GRAVEL
/ L.W.L
LEVEL
SAND
( MM)
CLAY
SILT
(%)
65.50 34.5 UDS 34.50 12 34.50 - 34.90 34.16 24.59 9.57 SLIPPED
64.50 35.5 SPT 35.50 24 35.50 - 35.95 99 30 99 99 0.0 11.0 65.0 24.0
62.50 37.5 UDS 37.50 13 37.50 - 37.90 32.14 22.59 9.55 SLIPPED 27.05 2.72 UUT* 1.69 5.0
150
(CI)
59.50 40.5 UDS 40.50 14 40.50 40.90 33.81 24.58 9.23 SLIPPED
58.50 41.5 SPT 41.50 28 41.50 41.95 109 30 109 109 9.0 21.0 59.0 11.0
54.00 46.0 SPT 46.00 31 46.00 46.45 89 30 89 89 5.0 17.0 56.0 22.0
52.00 48.0 SPT 48.00 32 48.00 48.45 105 30 105 60 Brownish Silty Sand of 16.0 23.0 53.0 8.0
Low Plasticity
50.00 50.0 SPT 50.00 33 50.00 50.45 125 30 125 70 (ML-CL)
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST
* = REMOULDED SAMPLE
BORE LOG CHART AND DATA SHEET
SHEET NO : 18
N - VALUE
12
15
18
21
DEPTH IN M
24
OBSERVED
27 CORRECTED
30
33
36
39
42
45
48
51
54
19
20
21
22
23
24
25
26
27
28
29
30
COMPUTATION OF LIQUEFACTION POTENTIAL AS PER IS 1893 (PART 1) :2016
Type of Sampler [with liner (1) / without liner (0)] : 0 Depth of water table cosidered for analysis = 20.00 m
2
UNIT WEIGHT OF SOIL
SAMPLER CORRECTION, CS
MID. DEPTH OF LAYER (M)
LIQUEFACTION, P (T / M )
2
2
FINES CONTENT (FC)
(%)
( T/M )
SILT CONTENT ( %)
DEPTH OF SPT (M)
REMARK
(CRR)7.5
ALPHA
(MSF)
BETA
(%)
EFFECTIVE
EFFECTIVE
FROM
BULK
BULK
TO
1.00 2.50 1.15 9 1.65 1.65 1.65 1.65 1.75 55 03 1.24 1.24 0.25 0.99 0.12 6.8 0.75 1.20 1.05 1.70 10.9 91.0 5.00 1.20 18 0.191 1.44 0.275 0.34 2.83 NO LIQUEFAC-TION
2.50 4.00 2.65 13 1.65 1.65 1.65 1.65 3.25 68 23 2.84 2.84 1.85 0.98 0.28 9.8 0.75 1.20 1.05 1.59 14.7 91.0 5.00 1.20 22 0.242 1.44 0.348 0.99 3.54 NO LIQUEFAC-TION
4.00 5.50 4.15 20 1.73 1.73 1.73 1.73 4.75 68 23 5.37 5.37 4.33 0.97 0.54 15.0 0.85 1.20 1.05 1.35 21.7 58.0 5.00 1.20 31 - - - - - NO LIQUEFAC-TION
5.50 7.00 5.65 27 1.73 1.73 1.73 1.73 6.25 56 02 7.97 7.97 6.93 0.96 0.79 20.3 0.85 1.20 1.05 1.16 25.2 58.0 5.00 1.20 35 - - - - - NO LIQUEFAC-TION
7.00 8.50 7.15 33 1.75 1.75 1.75 1.75 7.75 56 02 10.58 10.58 9.53 0.94 1.03 24.8 0.95 1.20 1.05 1.02 30.3 83.0 5.00 1.20 41 - - - - - NO LIQUEFAC-TION
8.50 10.00 8.65 37 1.75 1.75 1.75 1.75 9.25 58 25 13.20 13.20 12.15 0.92 1.26 27.8 0.95 1.20 1.05 0.91 30.3 83.0 5.00 1.20 41 - - - - - NO LIQUEFAC-TION
10.00 11.50 10.15 40 1.84 1.84 1.84 1.84 10.75 58 25 15.90 15.90 14.79 0.89 1.47 30.0 1.00 1.20 1.05 0.82 31.0 83.0 5.00 1.20 42 - - - - - NO LIQUEFAC-TION
11.50 13.00 11.65 34 1.84 1.84 1.84 1.84 12.25 58 25 18.66 18.66 17.55 0.85 1.65 25.5 1.00 1.20 1.05 0.74 23.8 94.0 5.00 1.20 33 - - - - - NO LIQUEFAC-TION
13.00 14.50 13.15 36 1.89 1.89 1.89 1.89 13.75 70 24 21.45 21.45 20.32 0.80 1.78 27.0 1.00 1.20 1.05 0.68 23.1 94.0 5.00 1.20 32 - - - - - NO LIQUEFAC-TION
14.50 16.00 14.65 39 1.89 1.89 1.89 1.89 15.25 70 24 24.29 24.29 23.15 0.75 1.89 29.3 1.00 1.20 1.05 0.63 23.3 96.0 5.00 1.20 32 - - - - - NO LIQUEFAC-TION
16.00 17.50 16.15 43 1.90 1.90 1.90 1.90 16.75 75 21 25.53 25.53 24.39 0.70 1.86 32.3 1.00 1.20 1.05 0.60 24.4 55.0 5.00 1.20 34 - - - - - NO LIQUEFAC-TION
17.50 19.00 17.65 46 1.90 1.90 1.90 1.90 18.25 55 00 25.91 25.91 24.77 0.66 1.78 34.5 1.00 1.20 1.05 0.60 26.1 50.0 5.00 1.20 36 - - - - - NO LIQUEFAC-TION
19.00 20.50 19.15 51 1.90 1.90 1.90 1.57 19.75 50 00 26.16 25.91 25.02 0.62 1.69 38.3 1.00 1.20 1.05 0.59 28.5 42.0 5.00 1.20 39 - - - - - NO LIQUEFAC-TION
20.50 22.00 20.65 53 1.90 1.90 1.90 0.90 21.25 42 00 26.42 25.17 25.28 0.59 1.62 39.8 1.00 1.20 1.05 0.59 29.6 67.0 5.00 1.20 40 - - - - - NO LIQUEFAC-TION
22.00 23.50 22.15 57 1.91 1.91 1.91 0.91 22.75 60 07 26.65 23.90 25.50 0.57 1.58 42.8 1.00 1.20 1.05 0.59 31.8 71.0 5.00 1.20 43 - - - - - NO LIQUEFAC-TION
23.50 25.00 23.65 59 1.91 1.91 1.91 0.91 24.25 65 06 26.89 22.64 25.74 0.55 1.54 44.3 1.00 1.20 1.05 0.58 32.4 71.0 5.00 1.20 43 - - - - - NO LIQUEFAC-TION
25.00 26.50 25.15 62 1.95 1.95 1.95 0.95 25.75 65 06 27.02 21.27 25.85 0.53 1.49 46.5 1.00 1.20 1.05 0.58 34.0 64.0 5.00 1.20 45 - - - - - NO LIQUEFAC-TION
26.50 28.00 26.65 66 1.95 1.95 1.95 0.95 27.25 58 06 27.19 19.94 26.02 0.52 1.47 49.5 1.00 1.20 1.05 0.58 36.2 64.0 5.00 1.20 48 - - - - - NO LIQUEFAC-TION
28.00 29.50 28.15 71 1.96 1.96 1.96 0.96 28.75 58 06 27.29 18.54 26.11 0.51 1.45 53.3 1.00 1.20 1.05 0.58 39.0 65.0 5.00 1.20 51 - - - - - NO LIQUEFAC-TION
29.50 31.00 29.65 77 1.96 1.39 1.96 0.96 30.25 57 08 27.39 17.14 26.13 0.50 1.42 57.8 1.00 1.20 1.05 0.58 42.2 65.0 5.00 1.20 55 - - - - - NO LIQUEFAC-TION
31.00 32.50 31.15 82 2.02 1.02 2.02 1.02 31.75 57 08 27.53 15.78 25.31 0.49 1.40 61.5 1.00 1.20 1.05 0.59 45.7 65.0 5.00 1.20 59 - - - - - NO LIQUEFAC-TION
32.50 34.00 32.65 78 2.02 1.02 2.02 1.02 33.25 57 08 27.71 14.46 23.99 0.48 1.38 58.5 1.00 1.20 1.05 0.61 45.0 15.0 2.50 1.05 49 - - - - - NO LIQUEFAC-TION
31
COMPUTATION OF LIQUEFACTION POTENTIAL AS PER IS 1893 (PART 1) :2016
Type of Sampler [with liner (1) / without liner (0)] : 0 Depth of water table cosidered for analysis = 20.00 m
2
UNIT WEIGHT OF SOIL
SAMPLER CORRECTION, CS
MID. DEPTH OF LAYER (M)
LIQUEFACTION, P (T / M )
2
2
FINES CONTENT (FC)
(%)
( T/M )
SILT CONTENT ( %)
DEPTH OF SPT (M)
REMARK
(CRR)7.5
ALPHA
(MSF)
BETA
(%)
EFFECTIVE
EFFECTIVE
FROM
BULK
BULK
TO
1.00 2.50 1.15 6 1.60 1.60 1.60 1.60 1.75 69 03 1.20 1.20 0.24 0.99 0.12 4.5 0.75 1.20 1.05 1.70 7.2 96.0 5.00 1.20 13 0.140 1.44 0.202 0.24 2.00 NO LIQUEFAC-TION
2.50 4.00 2.65 18 1.60 1.60 1.60 1.60 3.25 74 22 2.80 2.80 1.84 0.98 0.28 13.5 0.75 1.20 1.05 1.59 20.3 96.0 5.00 1.20 29 0.410 1.44 0.590 1.65 5.89 NO LIQUEFAC-TION
4.00 5.50 4.15 28 1.72 1.72 1.72 1.72 4.75 74 22 5.29 5.29 4.26 0.97 0.53 21.0 0.85 1.20 1.05 1.35 30.4 97.0 5.00 1.20 41 - - - - - NO LIQUEFAC-TION
5.50 7.00 5.65 31 1.72 1.72 1.72 1.72 6.25 74 23 7.87 7.87 6.84 0.96 0.78 23.3 0.85 1.20 1.05 1.17 29.2 97.0 5.00 1.20 40 - - - - - NO LIQUEFAC-TION
7.00 8.50 7.15 38 1.75 1.75 1.75 1.75 7.75 74 23 10.47 10.47 9.42 0.94 1.02 28.5 0.95 1.20 1.05 1.03 35.1 55.0 5.00 1.20 47 - - - - - NO LIQUEFAC-TION
8.50 10.00 8.65 44 1.75 1.75 1.75 1.75 9.25 53 02 13.10 13.10 12.05 0.92 1.25 33.0 0.95 1.20 1.05 0.91 35.9 55.0 5.00 1.20 48 - - - - - NO LIQUEFAC-TION
10.00 11.50 10.15 47 1.82 1.82 1.82 1.82 10.75 53 02 15.78 15.78 14.68 0.89 1.46 35.3 1.00 1.20 1.05 0.82 36.5 59.0 5.00 1.20 48 - - - - - NO LIQUEFAC-TION
11.50 13.00 11.65 52 1.82 1.82 1.82 1.82 12.25 56 03 18.51 18.51 17.41 0.85 1.64 39.0 1.00 1.20 1.05 0.75 36.9 59.0 5.00 1.20 49 - - - - - NO LIQUEFAC-TION
13.00 14.50 13.15 59 1.82 1.82 1.82 1.82 13.75 56 03 21.24 21.24 20.14 0.80 1.77 44.3 1.00 1.20 1.05 0.68 38.0 72.0 5.00 1.20 50 - - - - - NO LIQUEFAC-TION
14.50 16.00 14.65 54 1.82 1.82 1.82 1.82 15.25 60 12 23.97 23.97 22.87 0.75 1.87 40.5 1.00 1.20 1.05 0.63 32.1 63.0 5.00 1.20 43 - - - - - NO LIQUEFAC-TION
16.00 17.50 16.15 58 1.89 1.89 1.89 1.89 16.75 49 14 25.15 25.15 24.01 0.70 1.83 43.5 1.00 1.20 1.05 0.61 33.4 58.0 5.00 1.20 45 - - - - - NO LIQUEFAC-TION
17.50 19.00 17.65 64 1.89 1.89 1.89 1.89 18.25 55 03 25.58 25.58 24.45 0.66 1.76 48.0 1.00 1.20 1.05 0.60 36.3 58.0 5.00 1.20 48 - - - - - NO LIQUEFAC-TION
19.00 20.50 19.15 67 1.89 1.89 1.89 1.56 19.75 55 03 25.84 25.59 24.70 0.62 1.67 50.3 1.00 1.20 1.05 0.60 38.0 67.0 5.00 1.20 50 - - - - - NO LIQUEFAC-TION
20.50 22.00 20.65 71 1.89 1.89 1.89 0.89 21.25 65 02 26.09 24.84 24.96 0.59 1.60 53.3 1.00 1.20 1.05 0.60 40.3 67.0 5.00 1.20 53 - - - - - NO LIQUEFAC-TION
22.00 23.50 22.15 76 1.89 1.89 1.89 0.89 22.75 65 02 26.30 23.55 25.17 0.57 1.56 57.0 1.00 1.20 1.05 0.59 42.4 71.0 5.00 1.20 55 - - - - - NO LIQUEFAC-TION
23.50 25.00 23.65 67 1.89 1.89 1.89 0.89 24.25 68 03 26.51 22.26 25.38 0.55 1.52 50.3 1.00 1.20 1.05 0.59 37.4 76.0 5.00 1.20 49 - - - - - NO LIQUEFAC-TION
25.00 26.50 25.15 61 1.94 1.94 1.94 0.94 25.75 61 15 26.66 20.91 25.49 0.53 1.47 45.8 1.00 1.20 1.05 0.59 34.0 76.0 5.00 1.20 45 - - - - - NO LIQUEFAC-TION
26.50 28.00 26.65 65 1.94 1.94 1.94 0.94 27.25 61 15 26.84 19.59 25.67 0.52 1.45 48.8 1.00 1.20 1.05 0.58 35.7 86.0 5.00 1.20 47 - - - - - NO LIQUEFAC-TION
28.00 29.50 28.15 68 1.99 1.99 1.99 0.99 28.75 73 13 27.05 18.30 25.86 0.51 1.43 51.0 1.00 1.20 1.05 0.58 37.3 83.0 5.00 1.20 49 - - - - - NO LIQUEFAC-TION
29.50 31.00 29.65 74 1.99 1.99 1.99 0.99 30.25 70 13 27.31 17.06 26.11 0.50 1.42 55.5 1.00 1.20 1.05 0.58 40.6 87.0 5.00 1.20 53 - - - - - NO LIQUEFAC-TION
31.00 32.50 31.15 64 1.99 1.02 1.99 0.99 31.75 65 22 27.46 15.71 26.12 0.49 1.40 48.0 1.00 1.20 1.05 0.58 35.1 80.0 5.00 1.20 47 - - - - - NO LIQUEFAC-TION
32.50 34.00 32.65 71 1.99 0.99 1.99 0.99 33.25 59 21 27.61 14.36 24.81 0.48 1.38 53.3 1.00 1.20 1.05 0.60 40.3 15.0 2.50 1.05 44 - - - - - NO LIQUEFAC-TION
32
COMPUTATION OF LIQUEFACTION POTENTIAL AS PER IS 1893 (PART 1) :2016
Type of Sampler [with liner (1) / without liner (0)] : 0 Depth of water table cosidered for analysis = 20.00 m
2
UNIT WEIGHT OF SOIL
SAMPLER CORRECTION, CS
MID. DEPTH OF LAYER (M)
LIQUEFACTION, P (T / M )
2
2
FINES CONTENT (FC)
(%)
( T/M )
SILT CONTENT ( %)
DEPTH OF SPT (M)
REMARK
(CRR)7.5
ALPHA
(MSF)
BETA
(%)
EFFECTIVE
EFFECTIVE
FROM
BULK
BULK
TO
1.00 2.50 1.15 8 1.64 1.64 1.64 1.64 1.75 63 03 1.23 1.23 0.25 0.99 0.12 6.0 0.75 1.20 1.05 1.70 9.6 46.0 5.00 1.20 16 0.170 1.44 0.245 0.30 2.50 NO LIQUEFAC-TION
2.50 4.00 2.65 19 1.64 1.64 1.64 1.64 3.25 46 00 2.83 2.83 1.85 0.98 0.28 14.3 0.75 1.20 1.05 1.59 21.5 46.0 5.00 1.20 30 - - - - - NO LIQUEFAC-TION
4.00 5.50 4.15 27 1.73 1.73 1.73 1.73 4.75 46 00 5.36 5.36 4.32 0.97 0.54 20.3 0.85 1.20 1.05 1.35 29.4 82.0 5.00 1.20 40 - - - - - NO LIQUEFAC-TION
5.50 7.00 5.65 31 1.73 1.73 1.73 1.73 6.25 80 02 7.95 7.95 6.91 0.96 0.79 23.3 0.85 1.20 1.05 1.16 28.9 82.0 5.00 1.20 39 - - - - - NO LIQUEFAC-TION
7.00 8.50 7.15 37 1.75 1.75 1.75 1.75 7.75 80 02 10.56 10.56 9.51 0.94 1.03 27.8 0.95 1.20 1.05 1.02 33.9 90.0 5.00 1.20 45 - - - - - NO LIQUEFAC-TION
8.50 10.00 8.65 43 1.75 1.75 1.75 1.75 9.25 86 04 13.19 13.19 12.14 0.92 1.26 32.3 0.95 1.20 1.05 0.91 35.2 48.0 5.00 1.20 47 - - - - - NO LIQUEFAC-TION
10.00 11.50 10.15 50 1.79 1.79 1.79 1.79 10.75 48 00 15.84 15.84 14.77 0.89 1.47 37.5 1.00 1.20 1.05 0.82 38.7 49.0 5.00 1.20 51 - - - - - NO LIQUEFAC-TION
11.50 13.00 11.65 46 1.79 1.79 1.79 1.79 12.25 49 00 18.53 18.53 17.45 0.85 1.64 34.5 1.00 1.20 1.05 0.75 32.6 49.0 5.00 1.20 44 - - - - - NO LIQUEFAC-TION
13.00 14.50 13.15 52 1.82 1.82 1.82 1.82 13.75 49 00 21.24 21.24 20.14 0.80 1.77 39.0 1.00 1.20 1.05 0.68 33.4 47.0 5.00 1.20 45 - - - - - NO LIQUEFAC-TION
14.50 16.00 14.65 57 1.82 1.82 1.82 1.82 15.25 47 00 23.97 23.97 22.87 0.75 1.87 42.8 1.00 1.20 1.05 0.63 34.0 78.0 5.00 1.20 45 - - - - - NO LIQUEFAC-TION
16.00 17.50 16.15 48 1.86 1.86 1.86 1.86 16.75 65 13 25.13 25.13 24.01 0.70 1.83 36.0 1.00 1.20 1.05 0.61 27.7 74.0 5.00 1.20 38 - - - - - NO LIQUEFAC-TION
17.50 19.00 17.65 45 1.86 1.86 1.86 1.86 18.25 60 14 25.46 25.46 24.34 0.66 1.75 33.8 1.00 1.20 1.05 0.61 26.0 28.0 4.56 1.14 34 - - - - - NO LIQUEFAC-TION
19.00 20.50 19.15 50 1.94 1.94 1.94 1.61 19.75 28 00 25.71 25.46 24.55 0.62 1.66 37.5 1.00 1.20 1.05 0.60 28.4 48.0 5.00 1.20 39 - - - - - NO LIQUEFAC-TION
20.50 22.00 20.65 57 1.94 1.94 1.94 0.94 21.25 48 00 26.03 24.78 24.86 0.59 1.60 42.8 1.00 1.20 1.05 0.60 32.4 69.0 5.00 1.20 43 - - - - - NO LIQUEFAC-TION
22.00 23.50 22.15 53 1.98 1.98 1.98 0.98 22.75 68 01 26.34 23.59 25.15 0.57 1.56 39.8 1.00 1.20 1.05 0.59 29.6 69.0 5.00 1.20 40 - - - - - NO LIQUEFAC-TION
23.50 25.00 23.65 59 1.98 1.98 1.98 0.98 24.25 66 03 26.69 22.44 25.50 0.55 1.53 44.3 1.00 1.20 1.05 0.59 32.9 69.0 5.00 1.20 44 - - - - - NO LIQUEFAC-TION
25.00 26.50 25.15 101 1.98 1.98 1.98 0.98 25.75 66 03 26.97 21.22 25.78 0.53 1.49 75.8 1.00 1.20 1.05 0.58 55.4 44.0 5.00 1.20 71 - - - - - NO LIQUEFAC-TION
26.50 28.00 26.65 104 1.98 1.98 1.98 0.98 27.25 43 01 27.26 20.01 26.07 0.52 1.47 78.0 1.00 1.20 1.05 0.58 57.0 65.0 5.00 1.20 73 - - - - - NO LIQUEFAC-TION
28.00 29.50 28.15 97 2.01 2.01 2.01 1.01 28.75 59 06 27.52 18.77 26.31 0.51 1.46 72.8 1.00 1.20 1.05 0.57 52.3 65.0 5.00 1.20 67 - - - - - NO LIQUEFAC-TION
29.50 31.00 29.65 102 2.01 1.81 2.01 1.01 30.25 59 06 27.80 17.55 26.57 0.50 1.45 76.5 1.00 1.20 1.05 0.57 54.9 73.0 5.00 1.20 70 - - - - - NO LIQUEFAC-TION
31.00 32.50 31.15 103 2.01 1.01 2.01 1.01 31.75 65 08 28.03 16.28 26.37 0.49 1.43 77.3 1.00 1.20 1.05 0.57 55.5 91.0 5.00 1.20 71 - - - - - NO LIQUEFAC-TION
32.50 34.00 32.65 101 2.01 1.01 2.01 1.01 33.25 69 22 28.25 15.00 25.10 0.48 1.41 75.8 1.00 1.20 1.05 0.59 56.3 15.0 2.50 1.05 61 - - - - - NO LIQUEFAC-TION
33
SAI GEOTECHNICAL ENGINEERS PRIVATE LIMITED
Project : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station)
including Civil, Architectural Finishes, Water Suply, Senitary Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB
structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
Assume EGL is equal to ground level at boreholes
Existing ground level at Borehole-4 = 100.000 m
Ground level at borehole = 100.000 m
Type of pile = Bored Pile Reference. IS 2911 (Part 1/Section 2): 2010
Dia of pile = 1.200 m Piles in granular soils
Area of pile (Ap) = 1.131 m
2
Qu = Ap (1/2 DgNg + PDNq) + SKi PDi tandi Asi
Perimeter of pile = 3.770 m
Reference borehole, BH = BH-04/P-B/1(P2/30) Piles in cohesive soils
Vertical load on pile P = 50 t Qu = Ap Nc Cp + Sai ci Asi
where
2
Unit weight of water gw = 1.00 t/m3 Ap - cross-sectional area of the pile tip, in m ;
Maximum overburden pressure, 15D = 15 D x density
2
D - diameter of pile shaft, in m;
15D = 18 m = 32.28 t/m Nq - bearing capacity factors depending upon the angle of internal friction, φ at pile tip.
Depth of Cut off level from EGL = 2.30 m taken from fig. 1 of annex-B of reference [9]
Free Length of the pile L1 = 0.00 m Ng - bearing capacity factors depending upon the angle of internal friction, φ at pile tip.
taken from general shear failure according to IS 6403
2
Length of pile below cut-off level Le = 38.0 m PD - effective overburden pressure at pile tip, in t/m ;
∑nni=1 - summation for layers 1 to n in which pile is installed and which contribute to positive
Ultimate capacity of pile Qu = 1534.4 t Ki - coefficient of earth pressure applicable for the ith layer;
Factor of safety FOS = 2.5 Pdi - effective overburden pressure for the ith layer, in t/m 2
Safe capacity of pile Qsafe = 613.75 t δi - angle of wall friction between pile and soil for the ith layer; and
Recommended Vertical pile capacity Q safe = 600.00 t Asi - surface area of pile shaft in the ith layer in m 2.
Pile founding level = 59.700 m Nc - bearing capacity factor, considered as 9;
αi - adhesion factor for the ith layer depending on the consistency of soil;
From to thickness depth cohesion friction d g' PD Nc Nq for Nq Ng CNc PD Nq 0.5 g D Ng Qeb PDi Asi Ki Qsfi (sand) Qsfi (clay) Qsfi Qsf Qu Qsafe
(m) (m) (m) (m) ci (t/m2) f (deg) (deg) (t/m3) (t/m2) (Meyor)Ng (t/m2) (t/m2) (t/m2) (t) (t/m2) (m2) (t) (t) (t) (t) (t) (t)
2.30 5.30 3.00 3.0 12.5 0 0 1.65 4.95 9 1.00 0.00 0.00 112.5 0.0 0.00 127 2.48 11.31 1.0 0.00 42.41 42.41 42.41 169.65
5.30 8.50 3.20 6.2 0.0 27 27 1.73 10.49 9 13.20 13.00 14.47 0.0 136.3 15.02 171 7.72 12.06 1.0 47.44 0.00 47.44 89.85 261.01 104.40
8.50 11.00 2.50 8.7 14.7 0 0 1.75 14.86 9 1.00 0.00 0.00 132.3 0.0 0.00 150 12.67 9.42 1.0 0.00 69.27 69.27 159.12 308.8 123.50
11.00 14.00 3.00 11.7 14.7 0 0 1.84 20.38 9 1.00 0.00 0.00 132.3 0.0 0.00 150 17.62 11.31 1.0 0.00 83.13 83.13 242.25 391.9 156.75
14.00 17.00 3.00 14.7 14.7 0 0 1.89 26.05 9 1.00 0.00 0.00 132.3 0.0 0.00 150 23.22 11.31 1.0 0.00 83.13 83.13 325.38 475.0 190.00
17.00 20.00 3.00 17.7 0.0 31 31 1.90 31.75 9 20.63 24.00 25.99 0.0 762.0 29.63 895 28.90 11.31 1.0 196.40 0.00 196.40 521.78 1417.1 566.85
20.00 22.00 2.00 19.7 0.0 31 31 1.00 32.28 11 20.63 24.00 25.99 0.0 774.7 15.60 894 32.75 7.54 1.0 148.37 0.00 148.37 670.15 1564.0 625.59
22.00 25.00 3.00 22.7 6.8 0 0 1.00 32.28 9 1.00 0.00 0.00 61.2 0.0 0.00 69 35.25 11.31 1.0 0.00 23.07 23.07 693.22 762.4 304.98
25.00 28.00 3.00 25.7 6.8 0 0 1.00 32.28 9 1.00 0.00 0.00 61.2 0.0 0.00 69 38.25 11.31 1.0 0.00 23.07 23.07 716.29 785.5 314.20
28.00 30.00 2.00 27.7 6.8 0 0 1.00 32.28 9 1.00 0.00 0.00 61.2 0.0 0.00 69 40.75 7.54 1.0 0.00 15.38 15.38 731.68 800.9 320.36
30.00 32.30 2.30 30.0 6.8 0 0 1.00 32.28 9 1.00 0.00 0.00 61.20 0 0.00 69 42.90 8.67 1.0 0.00 17.69 17.69 749.36 818.6 327.43
32.30 34.30 2.00 32.0 15.5 0 0 1.00 32.28 9 1.00 0.00 0.00 139.50 0 0.00 158 45.05 7.54 1.0 0.00 35.06 35.06 784.42 942.2 376.88
34.30 36.30 2.00 34.0 15.5 0 0 1.00 32.28 9 1.00 0.00 0.00 139.50 0 0.00 158 47.05 7.54 1.0 0.00 35.06 35.06 819.48 977.3 390.90
36.30 39.30 3.00 37.0 15.5 0 0 1.00 32.28 9 1.00 0.00 0.00 139.50 0 0.00 158 49.55 11.31 1.0 0.00 52.59 52.59 872.07 1029.8 411.94
39.30 40.30 1.00 38.0 0.0 28 28 1.00 32.28 9 14.72 15.00 16.72 0.00 484 10.03 559 51.55 3.77 1.0 103.33 0.00 103.33 975.41 1534.4 613.75
40.30 42.30 2.00 40.0 0.0 28 28 1.00 32.28 9 14.72 15.00 16.72 0.00 484 10.03 559 53.05 7.54 1.0 212.68 0.00 212.68 1188.09 1747.1 698.82
42.30 45.30 3.00 43.0 11.8 0 0 1.00 32.28 9 1.00 0.00 0.00 106.20 0 0.00 120 55.55 11.31 1.0 0.00 40.04 40.04 1228.13 1348.2 539.29
34
SAI GEOTECHNICAL ENGINEERS PVT. LTD.
Lateral load analysis as per IS 2911
Pile parameters
Diameter of pile, D = 1.20 m
Characteristic strength of concrete (fck) M35 = 35 N/mm2
Elastic modulus of pile material, E 5000 * (fck)^0.5 = 29580 N/mm2
= 29580399 kN/m2
Moment of inertia of pile material, I PI* D^4 / 64 = 0.1017876 m4
EI = 3010918 kNm2
Stiffness factor & Depth of fixity
For soil having constant modulus
Stiffness factor T = (EI/hh)1/5
(From table 3. of reference [9])
Coefficient of subgrade reaction for pile, hh = 1.688 x 103 kN/m3
= 1688 kN/m3
T = 4.470
Free standing length of pile L1 = 0.00 m
L1/T = 0.00 m
As per fig.4 of annexure c of reference [9]
For fixed head pile Lf/T = 2.2 m
Depth of fixity Lf = 9.83 m
Distance of pile from pile cap botttom to length of fixity L = L1 +Lf
L = 9.83 m
3
Deflection at pile head (fixed head condition) y = Q (L1+Lf) /12EI
Permisssible deflection at Cutoff level x = 1% of pile diameter
= 0.012 m
For the allowable deflection at pile cap bottom, the lateral force is = Q
Q = y12EI/((L1+Lf)3)
Q = 456.03 kN
Lateral pile capacity Q = 456.0 kN
or say 45.60 tons
35
SAI GEOTECHNICAL ENGINEERS PRIVATE LIMITED
Project : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station)
including Civil, Architectural Finishes, Water Suply, Senitary Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB
structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
Assume EGL is equal to ground level at boreholes
Existing ground level at Borehole-5 = 100.000 m
Ground level at borehole = 100.000 m
Type of pile = Bored Pile Reference. IS 2911 (Part 1/Section 2): 2010
Dia of pile = 1.200 m Piles in granular soils
Area of pile (Ap) = 1.131 m
2
Qu = Ap (1/2 DgNg + PDNq) + SKi PDi tandi Asi
Perimeter of pile = 3.770 m
Reference borehole, BH = BH-05/P-3/14 Piles in cohesive soils
Vertical load on pile P = 50 t Qu = Ap Nc Cp + Sai ci Asi
where
2
Unit weight of water gw = 1.00 t/m3 Ap - cross-sectional area of the pile tip, in m ;
Maximum overburden pressure, 15D = 15 D x density
2
D - diameter of pile shaft, in m;
15D = 18 m = 31.36 t/m Nq - bearing capacity factors depending upon the angle of internal friction, φ at pile tip.
Depth of Cut off level from EGL = 2.30 m taken from fig. 1 of annex-B of reference [9]
Free Length of the pile L1 = 0.00 m Ng - bearing capacity factors depending upon the angle of internal friction, φ at pile tip.
taken from general shear failure according to IS 6403
2
Length of pile below cut-off level Le = 34.0 m PD - effective overburden pressure at pile tip, in t/m ;
∑nni=1 - summation for layers 1 to n in which pile is installed and which contribute to positive
Ultimate capacity of pile Qu = 1208.7 t Ki - coefficient of earth pressure applicable for the ith layer;
Factor of safety FOS = 2.5 Pdi - effective overburden pressure for the ith layer, in t/m 2
Safe capacity of pile Qsafe = 483.49 t δi - angle of wall friction between pile and soil for the ith layer; and
Recommended Vertical pile capacity Q safe = 450.00 t Asi - surface area of pile shaft in the ith layer in m 2.
Pile founding level = 63.700 m Nc - bearing capacity factor, considered as 9;
αi - adhesion factor for the ith layer depending on the consistency of soil;
From to thickness depth cohesion friction d g' PD Nc Nq for Nq Ng CNc PD Nq 0.5 g D Ng Qeb PDi Asi Ki Qsfi (sand) Qsfi (clay) Qsfi Qsf Qu Qsafe
(m) (m) (m) (m) ci (t/m2) f (deg) (deg) (t/m3) (t/m2) (Meyor)Ng (t/m2) (t/m2) (t/m2) (t) (t/m2) (m2) (t) (t) (t) (t) (t) (t)
2.30 5.30 3.00 3.0 12.4 0 0 1.60 4.80 9 1.00 0.00 0.00 111.6 0.0 0.00 126 2.40 11.31 1.0 0.00 42.07 42.07 42.07 168.29
5.30 8.30 3.00 6.0 12.4 0 0 1.72 9.96 9 1.00 0.00 0.00 111.6 0.0 0.00 126 7.38 11.31 1.0 0.00 70.12 70.12 112.19 238.41 95.36
8.30 11.30 3.00 9.0 0.0 28 28 1.75 15.21 9 14.72 15.00 16.72 0.0 228.2 17.55 278 12.59 11.31 1.0 75.68 0.00 75.68 187.87 465.8 186.30
11.30 14.30 3.00 12.0 0.0 28 28 1.82 20.67 9 14.72 15.00 16.72 0.0 310.1 18.25 371 17.94 11.31 1.0 107.88 0.00 107.88 295.75 667.1 266.82
14.30 17.30 3.00 15.0 10.5 0 0 1.82 26.13 9 1.00 0.00 0.00 94.5 0.0 0.00 107 23.40 11.31 1.0 0.00 59.38 59.38 355.13 462.0 184.80
17.30 20.00 2.70 17.7 0.0 28 28 1.89 31.23 9 14.72 15.00 16.72 0.0 468.5 18.96 551 28.68 10.18 1.0 155.23 0.00 155.23 510.36 1061.7 424.66
20.00 23.30 3.30 21.0 0.0 28 28 1.00 31.36 11 14.72 15.00 16.72 0.0 470.3 10.03 543 32.88 12.44 1.0 217.52 0.00 217.52 727.87 1271.2 508.46
23.30 25.00 1.70 22.7 0.0 28 28 1.00 31.36 9 14.72 15.00 16.72 0 470.3 10.03 543 35.38 6.41 1.0 120.57 0.00 120.57 848.45 1391.7 556.69
25.00 28.00 3.00 25.7 12.1 0 0 1.00 31.36 9 1.00 0.00 0.00 108.9 0.0 0.00 123 37.73 11.31 1.0 0.00 41.05 41.05 889.50 1012.7 405.07
28.00 31.00 3.00 28.7 12.1 0 0 1.00 31.36 9 1.00 0.00 0.00 108.9 0.0 0.00 123 40.73 11.31 1.0 0.00 41.05 41.05 930.56 1053.7 421.49
31.00 34.00 3.00 31.7 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 43.73 11.31 1.0 0.00 58.36 58.36 988.91 1164.0 465.60
34.00 36.30 2.30 34.0 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 46.38 8.67 1.0 0.00 44.74 44.74 1033.66 1208.7 483.49
36.30 39.30 3.00 37.0 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 49.03 11.31 1.0 0.00 58.36 58.36 1092.01 1267.1 506.84
39.30 42.30 3.00 40.0 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 52.03 11.31 1.0 0.00 58.36 58.36 1150.37 1325.4 530.18
42.30 45.30 3.00 43.0 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 55.03 11.31 1.0 0.00 58.36 58.36 1208.73 1383.8 553.52
45.30 48.00 2.70 45.7 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 57.88 10.18 1.0 0.00 52.52 52.52 1261.25 1436.3 574.53
48.00 50.00 2.00 47.7 17.2 0 0 1.00 31.36 9 1.00 0.00 0.00 154.80 0 0.00 175 60.23 7.54 1.0 0.00 38.91 38.91 1300.16 1475.2 590.09
36
SAI GEOTECHNICAL ENGINEERS PVT. LTD.
Lateral load analysis as per IS 2911
Pile parameters
Diameter of pile, D = 1.20 m
Characteristic strength of concrete (fck) M35 = 35 N/mm2
Elastic modulus of pile material, E 5000 * (fck)^0.5 = 29580 N/mm2
= 29580399 kN/m2
Moment of inertia of pile material, I PI* D^4 / 64 = 0.1017876 m4
EI = 3010918 kNm2
Stiffness factor & Depth of fixity
For soil having constant modulus
Stiffness factor T = (EI/hh)1/5
(From table 3. of reference [9])
Coefficient of subgrade reaction for pile, hh = 1.688 x 103 kN/m3
= 1688 kN/m3
T = 4.470
Free standing length of pile L1 = 0.00 m
L1/T = 0.00 m
As per fig.4 of annexure c of reference [9]
For fixed head pile Lf/T = 2.2 m
Depth of fixity Lf = 9.83 m
Distance of pile from pile cap botttom to length of fixity L = L1 +Lf
L = 9.83 m
3
Deflection at pile head (fixed head condition) y = Q (L1+Lf) /12EI
Permisssible deflection at Cutoff level x = 1% of pile diameter
= 0.012 m
For the allowable deflection at pile cap bottom, the lateral force is = Q
Q = y12EI/((L1+Lf)3)
Q = 456.03 kN
Lateral pile capacity Q = 456.0 kN
or say 45.60 tons
37
SAI GEOTECHNICAL ENGINEERS PRIVATE LIMITED
Project : Geotechnical Investigation work for Construction of elevated viaduct and 3 nos. elevated stations (viz, Taj East Gate, Basai & Fatehabad Road Metro Station)
including Civil, Architectural Finishes, Water Suply, Senitary Installation, Drainage, Extrnal Development, Fine Fighting, Fire Detection, E&M works and PEB
structures on Priority Section of Corridor-1, Phase-1 of Agra Metro at Agra, Uttar Pradesh, India.
Assume EGL is equal to ground level at boreholes
Existing ground level at Borehole-7 = 100.000 m
Ground level at borehole = 100.000 m
Type of pile = Bored Pile Reference. IS 2911 (Part 1/Section 2): 2010
Dia of pile = 1.200 m Piles in granular soils
Area of pile (Ap) = 1.131 m
2
Qu = Ap (1/2 DgNg + PDNq) + SKi PDi tandi Asi
Perimeter of pile = 3.770 m
Reference borehole, BH = BH-07/P-4/5 Piles in cohesive soils
Vertical load on pile P = 50 t Qu = Ap Nc Cp + Sai ci Asi
where
2
Unit weight of water gw = 1.00 t/m3 Ap - cross-sectional area of the pile tip, in m ;
Maximum overburden pressure, 15D = 15 D x density
2
D - diameter of pile shaft, in m;
15D = 18 m = 32.01 t/m Nq - bearing capacity factors depending upon the angle of internal friction, φ at pile tip.
Depth of Cut off level from EGL = 2.30 m taken from fig. 1 of annex-B of reference [9]
Free Length of the pile L1 = 0.00 m Ng - bearing capacity factors depending upon the angle of internal friction, φ at pile tip.
taken from general shear failure according to IS 6403
2
Length of pile below cut-off level Le = 34.0 m PD - effective overburden pressure at pile tip, in t/m ;
∑nni=1 - summation for layers 1 to n in which pile is installed and which contribute to positive
Ultimate capacity of pile Qu = 1339.8 t Ki - coefficient of earth pressure applicable for the ith layer;
Factor of safety FOS = 2.5 Pdi - effective overburden pressure for the ith layer, in t/m 2
Safe capacity of pile Qsafe = 535.93 t δi - angle of wall friction between pile and soil for the ith layer; and
Recommended Vertical pile capacity Q safe = 520.00 t Asi - surface area of pile shaft in the ith layer in m 2.
Pile founding level = 63.700 m Nc - bearing capacity factor, considered as 9;
αi - adhesion factor for the ith layer depending on the consistency of soil;
From to thickness depth cohesion friction d g' PD Nc Nq for Nq Ng CNc PD Nq 0.5 g D Ng Qeb PDi Asi Ki Qsfi (sand) Qsfi (clay) Qsfi Qsf Qu Qsafe
(m) (m) (m) (m) ci (t/m2) f (deg) (deg) (t/m3) (t/m2) (Meyor)Ng (t/m2) (t/m2) (t/m2) (t) (t/m2) (m2) (t) (t) (t) (t) (t) (t)
2.30 5.30 3.00 3.0 0.0 30 30 1.64 4.92 9 18.40 20.00 22.40 0.0 98.4 22.04 136 2.46 11.31 1.0 16.06 0.00 16.06 16.06 152.28
5.30 8.00 2.70 5.7 0.0 28 28 1.73 9.59 9 14.72 15.00 16.72 0.0 143.9 17.35 182 7.26 10.18 1.0 39.27 0.00 39.27 55.33 237.66 95.07
8.00 10.00 2.00 7.7 0.0 28 28 1.75 13.09 9 14.72 15.00 16.72 0.0 196.4 17.55 242 11.34 7.54 1.0 45.47 0.00 45.47 100.80 342.7 137.09
10.00 13.00 3.00 10.7 0.0 30 30 1.79 18.46 9 18.40 20.00 22.40 0.0 369.2 24.06 445 15.78 11.31 1.0 103.01 0.00 103.01 203.81 648.6 259.44
13.00 16.00 3.00 13.7 0.0 30 30 1.82 23.92 9 18.40 20.00 22.40 0.0 478.4 24.46 569 21.19 11.31 1.0 138.37 0.00 138.37 342.18 910.9 364.37
16.00 19.00 3.00 16.7 10.5 0 0 1.94 29.74 9 1.00 0.00 0.00 94.5 0.0 0.00 107 26.83 11.31 1.0 0.00 59.38 59.38 401.56 508.4 203.37
19.00 22.00 3.00 19.7 0.0 31 31 1.32 32.01 11 20.63 24.00 25.99 0.0 768.2 20.59 892 31.72 11.31 1.0 215.56 0.00 215.56 617.12 1509.3 603.70
22.00 25.00 3.00 22.7 0.0 28 28 1.00 32.01 9 14.72 15.00 16.72 0 480.2 10.03 554 35.20 11.31 1.0 211.68 0.00 211.68 828.80 1383.2 553.27
25.00 28.00 3.00 25.7 0.0 28 28 1.00 32.01 9 14.72 15.00 16.72 0 480.2 10.03 554 38.20 11.31 1.0 229.72 0.00 229.72 1058.52 1612.9 645.16
28.00 31.00 3.00 28.7 7.2 0 0 1.00 32.01 9 1.00 0.00 0.00 64.8 0.0 0.00 73 41.20 11.31 1.0 0.00 24.43 24.43 1082.95 1156.2 462.49
31.00 32.50 1.50 30.2 7.2 0 0 1.00 32.01 9 1.00 0.00 0.00 64.80 0 0.00 73 43.45 5.65 1.0 0.00 12.21 12.21 1095.16 1168.5 467.38
32.50 34.50 2.00 32.2 16.9 0 0 1.00 32.01 9 1.00 0.00 0.00 152.10 0 0.00 172 45.20 7.54 1.0 0.00 38.23 38.23 1133.39 1305.4 522.16
34.50 36.30 1.80 34.0 16.9 0 0 1.00 32.01 9 1.00 0.00 0.00 152.10 0 0.00 172 47.10 6.79 1.0 0.00 34.40 34.40 1167.79 1339.8 535.93
36.30 39.30 3.00 37.0 16.9 0 0 1.00 32.01 9 1.00 0.00 0.00 152.10 0 0.00 172 49.50 11.31 1.0 0.00 57.34 57.34 1225.14 1397.2 558.86
39.30 42.30 3.00 40.0 16.9 0 0 1.00 32.01 9 1.00 0.00 0.00 152.10 0 0.00 172 52.50 11.31 1.0 0.00 57.34 57.34 1282.48 1454.5 581.80
42.30 45.30 3.00 43.0 16.9 0 0 1.00 32.01 9 1.00 0.00 0.00 152.10 0 0.00 172 55.50 11.31 1.0 0.00 57.34 57.34 1339.82 1511.8 604.73
45.30 48.30 3.00 46.0 16.9 0 0 1.00 32.01 9 1.00 0.00 0.00 152.10 0 0.00 172 58.50 11.31 1.0 0.00 57.34 57.34 1397.16 1569.2 627.67
38
SAI GEOTECHNICAL ENGINEERS PVT. LTD.
Lateral load analysis as per IS 2911
Pile parameters
Diameter of pile, D = 1.20 m
Characteristic strength of concrete (fck) M35 = 35 N/mm2
Elastic modulus of pile material, E 5000 * (fck)^0.5 = 29580 N/mm2
= 29580399 kN/m2
Moment of inertia of pile material, I PI* D^4 / 64 = 0.1017876 m4
EI = 3010918 kNm2
Stiffness factor & Depth of fixity
For soil having constant modulus
Stiffness factor T = (EI/hh)1/5
(From table 3. of reference [9])
Coefficient of subgrade reaction for pile, hh = 1.832 x 103 kN/m3
= 1832 kN/m3
T = 4.397
Free standing length of pile L1 = 0.00 m
L1/T = 0.00 m
As per fig.4 of annexure c of reference [9]
For fixed head pile Lf/T = 2.2 m
Depth of fixity Lf = 9.67 m
Distance of pile from pile cap botttom to length of fixity L = L1 +Lf
L = 9.67 m
3
Deflection at pile head (fixed head condition) y = Q (L1+Lf) /12EI
Permisssible deflection at Cutoff level x = 1% of pile diameter
= 0.012 m
For the allowable deflection at pile cap bottom, the lateral force is = Q
Q = y12EI/((L1+Lf)3)
Q = 478.99 kN
Lateral pile capacity Q = 478.0 kN
or say 47.80 tons
39