To, Le Chocola
Ajman | UAE
Mr.Obaid
Phone Number: +971 508060009
• Insulation details.
• Refrigeration unit details.
• Price details.
• Payment and Commercial Terms.
We trust you will find our offer in line with your requirements. However, for further
clarification, please do not hesitate to contact us.
Thanking you and assuring you of our best services at all times.
Warm Regards,
Al Raihan Aluminum & Glass works
INSULATION DETAILS:
Wall and Ceiling panels: Wall and Ceiling panels of the cold room will be
constructed using fabricated sandwich panels formed by expanding polyurethane
within 0.5mm thick white polyester coated galvanized steel sheet. In order to
obtain homogeneous and continuous adhesion between polyurethane and steel
sheets, the panels are effected in press. Panel long sides are joined by means of
molded and tongue and groove. Adjacent sides are drawn and locked together with
special cam lock fasteners, which are formed in place during production. In this
way continuous and homogeneous insulation is obtained together with a double
vapor barrier created by two panels, joints sealed by low temperature flexible
sealant.
Dimension :8480 x 5570 x 26100 mm
Material :Rigid injected CFC free polyurethane foam.
Thickness (Wall & Ceilings) :100 mm
Cladding :Polyurethane panel cladded on both sides with 0.5mm thick white polyester coated GI sheet.
Flooring :Not in Scope
Doors :1 no. Sliding Door with Rails, Rollers Size: 900 x 19000mm
Floor Heater :Floor heater with standby system sensor and control will be provided for the freezer floor
Door accessories :Pressure port, polar strip curtains will be provided for the door.
ELECTRICAL ACCESSORIES:
Control Panel Board - Weatherproof IP 54 enclosure
Indication Lamps - 220 V lamps for compressor, heater & evaporator motor
Earth Leakage Circuit - 300 MA tripping rate for each motors
Contactor - For compressor, evaporator motor & heaters
Time delay switches - 0 to 5 minutes adjustable time delay switch for restarting
Digital Control - Automatic defrosting, temperature display & automatic temperature controller
Overload protection - for compressor, evaporator /condensing motors
Thermal protection - 0° centigrade thermal protection for heaters
Compressor protection - Thermal HP / LP / OP protection
Timer - 24 Hrs. defrosting timer
Control wiring - With Color Code
Lights - Necessary lighting with double fluorescent vapor proof corrosion resistant lights will be
provided.
PRICE DETAILS:
Our best possible price for the above said complete job of supply, erection and commission of
cold room will be Aed.
NOTE: Any additional works other than mentioned in the quotation including the below
mentioned shall be under the responsibility of the client.
1) Leveled floor for erection of cold room
2) Main power supply via separate isolator to our control panel
3) Temporary power supply to our erection team
4) Approvals from local and municipal authorities
5) Any other items which is not specifically included in this offer.
6) Stands and grill door for the condensing units
PAYMENT AND COMMERCIAL TERMS:
Guarantee : One year warrantee from the date of completion.
Completion time : 3 week from the date of receipt of confirmed order with advance payment.