DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
LIST OF CONTENTS
Item Content
A GENERAL CONDITIONS AND REQUIREMENTS Page No
A.1 Introduction 2
A.2 References 2
A.3 Document requirements 2
A.4 Document levels 2
A.5 Software License 2
A.6 Calibration Records 3
A.7 Final Inspection 3
A.8 Form of delivery 3
B SCOPE OF DOCUMENT SUPPLY
B.1 General Equipment (if specified) 4
B.2 Electric Generators and Motors 5
We reserve all rights in this document and in the information
2 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
A.2 References
2006/95/EC Low Voltage Directive (LVD)
We reserve all rights in this document and in the information
contained therein. Reproduction, use or disclosure to third
3 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
If the file containing the manufacturing, test records and certificates documentation is too big to be sent by e-
contained therein. Reproduction, use or disclosure to third
mail, an e-mail to Siemens shall be sent with information stating that a CD with all the manufacturing , test report
Parties without express authority is strictly forbidden.
4 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
B.1 GENERAL EQUIPMENT (if equipment not specified in the following tables)
Table of documentation ID number of documentation Documents to be included
Product class A
Serial produced standard equipment that is certified to any code or 1CS35115-0011
standard, such as GOST, UL, CSA, NEMA, ASME, etc.
Product class B 1CS35115-0012
Serial equipment with no hazardous categorisation and that is not
covered by any other requirement in this document.
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used + +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Declaration of Conformity with other foreign regulation if required in the Purchase Order Technical
Specifications.
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. +
3. Design verification or validation
We reserve all rights in this document and in the information
• If the design requires to be certified by a recognised independent organisation the design review + +
contained therein. Reproduction, use or disclosure to third
• ATEX (or IEC Ex) Type Test Certificate (where applicable) shall be supplied as attachments to an
installation verification scheme.
© Siemens Industrial Turbomachinery AB
4. Layout drawing
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed +
equipment. The drawing shall give main dimensions, pipe supports and allowable forces.
5. List of Material and Equipment
All pressure retaining or load bearing material, rotating parts or filler metal, shall be listed with the +
following stated:
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc.to EN 10204-3.1. +
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information: +
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Construction data report for piping, including ISO drawings + +
• Record of dimensional check, for all inter connecting points
• Heat treatment reports
• NDE reports (RT, MT, UT etc.)
• Pressure test report
• Surface treatment report (progress log with final DFT)
9. Functional and/or routine test reports
• Performance and/or run test of rotating equipment. + +
• Functional and/or installation test report for electrical equipment, valves, instruments etc.
A 087 0474-B 00-03 MS Word 97
5 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
4. Layout drawing
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed
© Siemens Industrial Turbomachinery AB
equipment. The drawing shall give main dimensions, pipe supports and allowable forces.
5. List of Material and Equipment
All pressure retaining or load bearing material, rotating parts, filler metal or other material that is attached to + + +
a pressure vessel, shall be listed with the following stated:
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc. to EN 10204-3.1 + + +
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information:
• Welder ID-stamp on work
• Welding procedures and welder qualifications
8. NDE, heat treatment and test reports.
• Surface treatment report (progress log with final DFT) + + +
9. Functional and/or routine test reports
• Type test and routine test reports. + + + + +
• Test reports according to IEC 60034 and additional requirements in the Inspection and Test Plan.
10. Calibration reports
The instrument calibration records shall also be delivered in paper format, attached to the equipment. + + + + +
A 087 0474-B 00-03 MS Word 97
6 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
Air Blast Coolers acc. to MD 2006/42/EC and PED 97/23/EC article 3.3 1CS35115-0031
Air Blast Coolers acc. to MD 2006/42/EC and PED 97/23/EC 1CS35115-0032
Air Blast Coolers acc. to API661 and ASME VIII, incl U-stamp 1CS35115-0033
Air Blast Coolers acc. to API661 and ASME VIII, excl U-stamp 1CS35115-0034
Air Blast Coolers with other foreign certification 1CS35115-0035
Electrical installation and instruments see Table B.13.
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used + + + + +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Manufacturers Data Report (e.g. ASME Form U-1)
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. + + + + +
3. Design verification or validation
• If the design requires to be certified by a recognised independent organisation the design review + + + + +
We reserve all rights in this document and in the information
contained therein. Reproduction, use or disclosure to third
ATEX (or IEC Ex) Type Test Certificate (where applicable) shall be supplied as attachments to an
installation verification scheme.
4. Layout drawing
© Siemens Industrial Turbomachinery AB
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed + + + + +
equipment. The drawing shall give main dimensions and allowable forces.
5. List of Material and Equipment
All pressure retaining or load bearing material, rotating parts, filler metal or other material that is attached to + + + +
a pressure vessel, shall be listed with the following stated:
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc. to EN 10204-3.1. + +
Structural steel may be supplied with a Test Report acc. to EN 10204-2.2.
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information: + +
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Record of dimensional check, for all inter connecting points + + + + +
• Heat treatment reports
• NDE reports (RT, MT, UT etc.)
• Pressure test report
• Surface treatment report (progress log with final DFT)
9. Functional and/or routine test reports
• Performance and/or run test of rotating equipment. + + + + +
• Flushing or cleanness report.
• Siemens quality report from final inspection if specified in Purchase Order Delivery Specification
A 087 0474-B 00-03 MS Word 97
7 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
Heat Exchangers and Pressure Vessels acc. to PED 97/37/EC article 3.3 1CS35115-0041
Heat Exchangers and Pressure Vessels and piping acc. to PED 97/37/EC or 1CS35115-0042
ASME VIII incl U-stamp
Heat Exchangers and Pressure Vessels acc. to ASME VIII excl. U-stamp 1CS35115-0043
Heat Exchangers and Pressure Vessels with other foreign certification. 1CS35115-0044
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used + + + +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Manufacturers Data Report (e.g. ASME Form U-1)
• Declaration of Conformity with other foreign regulation if required in the Purchase Order Technical
Specifications.
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. + + + +
We reserve all rights in this document and in the information
contained therein. Reproduction, use or disclosure to third
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed + + + +
equipment. The drawing shall give main dimensions, wall thickness and allowable forces.
5. List of Material and Equipment
All pressure retaining or load bearing material, rotating parts, filler metal or other material that is attached to + + +
a pressure vessel, shall be listed with the following stated:
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc. to EN 10204-3.1 + +
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information: + +
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Record of dimensional check, for all inter connecting points + + + +
• Heat treatment reports
• NDE reports (RT, MT, UT etc.)
• Pressure test report
• Surface treatment report (progress log with final DFT)
9. Functional and/or routine test reports
• Siemens quality report from final inspection if specified in Purchase Order Delivery Specification. + + + +
• Cleanliness check where applicable
10. Calibration reports
A 087 0474-B 00-03 MS Word 97
The instrument calibration records shall also be delivered in paper format, attached to the equipment.
8 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
• If the design requires to be certified by a recognised independent organisation the design review + + +
Parties without express authority is strictly forbidden.
Drawing that is needed for identification of material and installed equipment. The drawing shall give main + + + +
dimensions and allowable forces.
5. List of Material and Equipment
All load bearing material and filler metal, shall be listed with the following stated: +
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc.to EN 10204-3.1. +
Structural steel may be supplied with a Test Report acc. to EN 10204-2.1.
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information: +
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Record of dimensional check, for all inter connecting points + + + +
• Heat treatment reports
• NDE reports (RT, MT, UT etc.) (e.g PT or MT on lifting lugs)
• Surface treatment report (progress log with final DFT)
• Load test report of Lifting Equipment
9. Functional and/or routine test reports
• Trial assembly report, if required. + + + +
• Type test and routine test reports for motors, generators, switchgears and transformers etc.
• Functional and/or installation test report for electrical equipment, valves, instruments etc.
10. Calibration reports
The instrument calibration records shall also be delivered in paper format, attached to the equipment.
A 087 0474-B 00-03 MS Word 97
9 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
4. Layout drawing
Parties without express authority is strictly forbidden.
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed + + + +
equipment. The drawing shall give main dimensions, pipe supports and allowable forces.
© Siemens Industrial Turbomachinery AB
10 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
1. Declaration of conformity
• Declaration of Conformity with applicable Purchase Order Delivery Specification, including a + +
specification of used standards.
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. + +
3. Design verification or validation
If the design requires to be certified by a recognised independent organisation the design review certificate
or type approval certificate shall be supplied.
4. Layout drawing
We reserve all rights in this document and in the information
contained therein. Reproduction, use or disclosure to third
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed + +
equipment. The drawing shall give main dimensions, pipe supports and allowable forces.
Parties without express authority is strictly forbidden.
11 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
• ATEX (or IEC Ex) Type Test Certificate (where applicable) shall be supplied as attachments to an
Parties without express authority is strictly forbidden.
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed
equipment. The drawing shall give main dimensions, pipe supports and allowable forces.
5. List of Material and Equipment
Load bearing material and the filler metal used for welding of it, shall be listed with the following stated:
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc. to EN 10204-3.1.
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information:
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Record of dimensional check, for all inter connecting points +
• NDE reports (PT, MT, UT etc.) for load bearing equipment, structural steel and lifting lugs
• Load test report for any type of lifting equipment
• Surface treatment report (progress log with final DFT)
9. Functional and/or routine test reports
• Performance and/or run test of rotating equipment. + + + +
• Type test and routine test reports for motors, generators, switchgears and transformers etc.
• Functional and/or installation test report for electrical equipment, valves, instruments etc.
10. Calibration reports
The instrument calibration records shall also be delivered in paper format, attached to the equipment.
A 087 0474-B 00-03 MS Word 97
12 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
Gas and Fire Detection Equipment installed in Gas Turbine Unit. 1CS35115-0091
Fire Extinguisher Container Unit. 1CS35115-0092
Fire Extinguisher Equipment installed in Gas Turbine Unit. 1CS35115-0093
Electrical installation and instruments see Table B.13.
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used + + +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Declaration of Conformity with other foreign regulation if required in the Purchase Order Delivery
Specifications.
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. + +
3. Design verification or validation
• If the design requires to be certified by a recognised independent organisation the design review + + +
We reserve all rights in this document and in the information
• ATEX (or IEC Ex) Type Test Certificate (where applicable) shall be supplied as attachments to an
Parties without express authority is strictly forbidden.
Drawing of a functional unit, piping that is needed for identification of material and installed equipment. + +
The drawing shall give main dimensions, pipe supports and allowable forces, if applicable.
5. List of Material and Equipment
All pressure retaining or load bearing material and filler metal, shall be listed with the following stated: + +
• Part designation or part number
• Dimension and Material Code
• Material Certificate number and charge/heat number
6. Material identification and test certificates
Inspection Certificates acc.to EN 10204-3.1. +
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information:
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• NDE reports (RT, MT, UT etc.) + +
• Pressure test report
• Surface treatment report (progress log with final DFT)
9. Functional and/or routine test reports
• Functional and/or installation test report for electrical equipment, valves, instruments etc. + + +
• Siemens quality report from final inspection if specified in Purchase Order Delivery Specification
10. Calibration reports
The instrument calibration records shall also be delivered in paper format, attached to the equipment. + +
A 087 0474-B 00-03 MS Word 97
13 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
If the design requires to be certified by a recognised independent organisation the design review certificate +
Parties without express authority is strictly forbidden.
Drawing of a unit that is needed for identification of material and installed equipment.
5. List of Material and Equipment
Electrical equipment and instruments, shall be listed with the following stated: + + + +
• Part designation or part number
• Instrument individual number
6. Material identification and test certificates
Inspection Certificates acc. to EN 10204-3.1.
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information:
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Surface treatment report if painted for outdoor installation. (progress log with final DFT) +
9. Functional and/or routine test reports
• Functional and/or installation test report for electrical equipment, valves, instruments etc. + + + +
10. Calibration reports
The instrument calibration records shall also be delivered in paper format, attached to the equipment.
* HIGS High Integrated Generator Switchgear
UMD Uninterrupted Motor Drive
A 087 0474-B 00-03 MS Word 97
14 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
B.11 ENCLOSURES FOR TURBINE, FOR DRIVEN EQUIPMENT, CONTROL ROOM AND BATTERY ROOM.
Table of documentation ID number of documentation Documents to be included
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Declaration of Conformity with other foreign regulation if required in the Purchase Order Technical
Specifications.
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. + + + +
3. Design verification or validation
If the design requires to be certified by a recognised independent organisation the design review certificate + + +
We reserve all rights in this document and in the information
4. Layout drawing
Parties without express authority is strictly forbidden.
Drawing of the assembly that is needed for identification of material and installed equipment. The drawing + + +
shall give main dimensions and allowable loads.
© Siemens Industrial Turbomachinery AB
15 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
B.12 FLEXIBLE COUPLINGS, GEAR UNIT, DRIVEN PROCESS PUMP AND GAS COMPRESSOR.
Table of documentation ID number of documentation Documents to be included
Drawing of a functional unit, vessel or piping that is needed for identification of material and installed
equipment. The drawing shall give main dimensions, pipe supports and allowable forces.
5. List of Material and Equipment
Load bearing material, rotating parts, electrical equipment and instruments, shall be listed with the + + +
following stated:
• Part designation or part number
• Material Code
• Material Certificate number and charge/heat number
• Instrument individual number
6. Material identification and test certificates
• Inspection Certificates acc. to EN 10204-3.1. + + +
7. Weld Plan or Weld Map with WPS and qualifications
A weld plan or a weld map that is signed off in production, with not less than the following information: + +
• Welder ID-stamp on work
• Welding procedures and welder qualifications
• Filler metal charge/heat number
8. NDE, heat treatment and test reports
• Record of dimensional check, for all inter connecting points + + + +
• Heat treatment reports
• NDE reports (RT, MT, UT etc.)
• Surface treatment report (progress log with final DFT)
9. Functional and/or routine test reports
• Performance and/or run test of rotating equipment. + + + +
10. Calibration reports
• The instrument calibration records shall also be delivered in paper format, attached to the equipment. + + +
A 087 0474-B 00-03 MS Word 97
16 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
Electrical installation of safety circuit equipment in safe area application (not 1) 1CS35115-0131
Electrical installation of electrical equipment in safe area application (LVD) 1CS35115-0132
Electrical installation of electrical equipment in hazardous area application (Ex) 1CS35115-0133
Instrumentation equipment in safe area application (LVD) 1CS35115-0134
Instrumentation in hazardous area application (Ex) 1CS35115-0135
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used + + + + +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Declaration of Conformity with other foreign regulation if required in the Purchase Order Delivery
Specifications..
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards. + + + + +
3. Design verification or validation
• + + +
We reserve all rights in this document and in the information
If the design requires to be certified by a recognised independent organisation the design review
contained therein. Reproduction, use or disclosure to third
ATEX (or IEC Ex) Type Test Certificate (where applicable) shall be supplied as attachments to an
installation verification scheme.
4. Layout drawing
© Siemens Industrial Turbomachinery AB
17 (17)
Respons. dept Date Reg.
DELIVERY SPECIFICATION GPLQ 2003-09-10
Manufacturing and Test Records Prepared
Peter Mannewald
This document is issued in Pulse.
Valves 1CS35115-0141
Strainers and Orifice Nozzles 1CS35115-0142
Pumps 1CS35115-0143
Flowmeters 1CS35115-0144
Valve actuator 1CS35115-01445
1. Declaration of conformity
• EC Declaration of Conformity with applicable EC Directives, including a specification of used + + + + +
standards, to be supplied for single equipment and assemblies including installed equipment.
• Declaration of Conformity with other foreign regulation if required in the Purchase Order Delivery
Specifications.
2. Inspection and Test Plan
The Inspection and Test Plan shall refer to the used procedures and/or standards.
3. Design verification or validation
• If the design requires to be certified by a recognised independent organisation the design review + + + +
We reserve all rights in this document and in the information
contained therein. Reproduction, use or disclosure to third