Professional Documents
Culture Documents
Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each
week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-
hand inventory would be negative without it. Customer orders (committed) are as follows:
3 48 50 -2 + 70 = 68
4 68 50 18 18
5 18 50 -32 + 70 = 38
6 38 50 -12 + 70 = 58
7 58 50 8 8
8 8 50 -42 + 70 = 28
PROBLEM 22
Determine the available-to-promise (ATP)
quantities for each period for Problem 21.
PERIOD
10 1 2 3 4 5 6 7 8
Forecast 50 50 50 50 50 50 50 50
Customer orders
52 35 20 12
(commited)
Projected on-hand
28 48 68 18 38 58 8 28
inventory
MPS 70 70 70 70 70 70
Available-to-
promise inventory 28 35 38 70 70 70
(uncommitted)