Professional Documents
Culture Documents
4189340223C
DEIF A/S
Application notes
CONTENTS
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 2 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
This paper gives guidelines to installation of the DEIF Multi-line 2 generator control and protection
units. It is, however, not a complete installation instruction. Therefore, even if terminal numbers are
shown in the drawings, the drawings are to be used as guidance only.
Installing and operating the Multi-line 2 products implies work with dangerous currents and voltages,
and therefore it should be done by qualified personal only.
DEIF takes no responsibility for operation or installation of the generator set. If there is any doubt
about how to install or operate the system on which the Multi-line 2 products are measuring, the
company responsible for installation or operation must be contacted.
2 General description
2.1 Introduction
The DEIF Multi-line 2 units for protection and control of diesel generators and turbine generators,
can be combined to achieve systems with highly different characteristics.
In the following, a number of applications using the DEIF Multi-line 2 products is shown. The reader
should notice that application is a dynamic piece of work, therefore in the future this handbook will
be upgraded from time to time with new applications. Also note that AC connections are not shown,
in order to make the diagrams easier to understand. For AC connections please refer to the manual
for the Multi-line 2 unit in question.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 3 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
This first release of this application handbook will not contain any applications regarding the
Generator Protection Unit, but concentrate on applications based on the combined control and
protection units.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 4 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
3 Protection of generators
All Multi-line 2 units contain generator protection functions. The no. of available functions are
dependent on the unit type and the chosen options. Please refer to the relevant data sheets for
Multi-line 2 products.
Multi-line 2 can control speed governors / AVR’s using relay or analogue outputs
If the prime mover is provided with an electronic speed governor the analogue governor control
output may be chosen. Manual control is still possible via binary inputs on the Multi-line 2, or an
"electronic potentiometer" (EPN-110DN or EP-Q96) is applied to manual/automatic remote control
of the diesel engine. The 2 relay outputs from the Multi-line 2 can then control the electronic speed
governor through the EPN-110DN or EP-Q96.
Isochronous mode
The term "Isochronous" refers to load independent frequency control, i.e. the frequency is kept
constant at 50/60Hz at 0...100% load.
Do not be confused, the speed droop setting on the governor is still necessary to make sure the
Multi-line 2 unit is able to do its job - load sharing and frequency control.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 5 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
The diagram shows the necessary connections to carry out speed control using relay outputs.
M U LT I-LIN E 2
LO W ER
S PEED 60
S PEED
LO W ER 59
PILO T
M OT O R
R A IS E
58
S PEED S PEED
R A IS E 57
S U PPLY FO R
PILO T M OT O R
The diagram shows the necessary connections to carry out voltage control using relay outputs.
V OLT A G E 64 LOW ER
LOW ER V OLT A G E
63
62 RA IS E
V OLT A G E V OLT A G E
RA IS E 61
C OMMON
S UPPLY FOR
A V R V OLT A G E
C ONT ROL
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 6 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
The diagram shows the output only. To connect to a specific governor, please refer to the note
“Interfacing DEIF equipment to governors and AVR’s”, doc. ref. no. 4189340149.
MU LT I-LINE 2
OUT PUT 66 + /- 2 0 mA
FOR S PEED
67 0
G OV ERNOR
The diagram shows the output only. To connect to a specific AVR, please refer to the note
“Interfacing DEIF equipment to governors and AVR’s”, doc. ref. no. 4189340149.
MULT I-LINE 2
OUT PUT 70 + /- 2 0 mA
FOR A V R
71 0
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 7 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
The Multi-line 2 can be configured to carry out the following standard running modes:
- Fixed frequency control (standalone single generator) with internal or external frequency
set point.
- Fixed power control (base load in island applications, power control in parallel with mains
applications) with internal or external power set point.
- Droop running control (controlled speed drop at increasing generator power production)
with internal or external base frequency setting)
- Active load sharing control with internal or external frequency set point.
If the voltage / var (reactive power) / power factor control option is chosen, the following available
running modes are added:
- Fixed voltage control (standalone single generator) with internal or external voltage set
point.
- Fixed var control (base var load in island applications, var production control in parallel
with mains applications) with internal of external reactive power set point.
- Fixed power factor control (parallel with mains) with internal or external power factor set
point.
- Reactive load sharing control with internal or external voltage set point.
The selection is carried out using the binary inputs “mode 1 – mode 6”, terminals 48 to 53 (input)
and terminal 56 (common). An input is activated by applying +24 VDC to the input and 0 VDC to
common.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 8 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
MULT I-LINE 2
+ 2 4 V DC
There are 2 analogue inputs available, both of which are +/- 10 VDC inputs, non-galvanically
separated:
Analogue input (term 40(signal) and 41 (gnd)) +/- 10 VDC equals frequency/power.
Analogue input (term 42 (signal) and 41 (gnd)) +/- 10 VDC equals voltage/var/power factor.
If the “external set point” mode is chosen (see paragraph 5.2 / 5.3) the use of the 2 analogue inputs
are determined by the running mode selection as follows:
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 9 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
Mode inputs 4 (term. 51) to 6 (term 53) (voltage/var/power factor control option F):
The examples for island operation are for 1…n generators running together or separated by
a bus bar tie breaker.
After start of DG1 the Multi-line 2 is activated (“Start sync./contr.” input is activated). The Multi-line 2
will control the speed governor towards the set slip frequency (set via display setting). When the
generator frequency is inside the accept band the Multi-line 2 will calculate the "correct sync. pulse
transmit" according to the breaker closing time and the actual slip frequency.
After closing of generator circuit breaker, the Multi-line 2 unit will connect itself to the common PS
line (common power control) and the common QS line (common reactive power share line), this is
done by internal relay contacts. When only one DG is connected to the busbar, the Multi-line 2 will
control the frequency according to the set point.
After DG2 is started and connected to the busbar the two Multi-line 2’s will control the generators to
share the load equally in percentages of the active load, according to the size of the generators.
If the showed contact "DE-LOAD" is activated, the Multi-line 2 will disconnect itself from the PS/QS
line, and then control the generator towards zero power, and open the breaker when 5% load
(factory setting, programmable) is reached.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 10 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
Fig. 7, application for synchronisation, normal power / reactive power load sharing of two or more DGs.
Note: If var sharing option is not included, only terminals 37 and 38 needs to be connected.
The control outputs for speed governor and AVR (Voltage control / var sharing option) can be
relay or analogue outputs. See “Speed Governor / AVR connections”.
6.3 Load sharing with tie breaker bus bar separation and synchronisation.
This application utilises the DEIF HAS-111DG synchronisation check unit for synchronising the bus
tie breaker. The HAS-111DG will, via the ∆f output, control the frequency of the “A” side generators
during synchronisation.
The ∆f output is -5…0…+5 VDC output. 0 VDC is equal to correct frequency, -5 VDC equals 2.5 Hz
too slow and +5 VDC equals 2.5 Hz too fast, compared to the correct synchronisation frequency.
Note that the ∆f output terminals and the Multi-line 2 input terminals are “twisted”. This is due to the
fact that the HAS-111DG ∆f output indicates the actual deviation and the Multi-line 2 inputs are set
point inputs. So, if the frequency is too low (HAS-111DG output gives a negative value), the input
value on the Multi-line 2 units must go positive.
To carry out this task, the “A” side Multi-line 2 units must be set to external frequency control during
bus tie breaker (TB) synchronisation. This is achieved by activating the “mode 3” input on the “A”
side Multi-line 2 units.
The scaling of the frequency input is fixed to –10…0…+10 VDC input equal to –5…selected base
frequency…+5 Hz.
The relay C1 is used to start and hold the synchronisation. When the TB closes, the hold will be
cancelled.
Note also that 2 aux. contacts on the TB is used to open/close the power and reactive power load
sharing lines between the “A” and the “B” sides.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 11 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
Fig. 8, load sharing with tie breaker bus bar separation and synchronisation.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 12 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
7 Shaft generator
This application is for shaft generator (SG) where no frequency / power control is possible, i.e. the
SG frequency is determined by the main engine speed. As a consequence of this, the SG is not
permitted to run parallel with the diesel generators (DG’s) for a longer period of time. A certain
parallel running time is allowed (normally 1 min.) for “bump less” load transfer rom / to the shaft
generator.
The application uses a Multi-line 2 unit for each generator, incl. the SG. The SG unit is carrying out
protection, synchronising and load transfer from the SG to the diesel generators.
The analogue speed control output on the SG Multi-line 2 unit is used to control the DG units via
the control input on these. As the speed control output is a +/- 20 mA output, a 500 Ω resistor is
used to convert this to +/- 10 VDC which matches the input range.
When the “SYNC SG” is pushed, the relay C1 will activate and stay activated until the shaft
generator breaker (SGB) closes. This will de-activate C1.
The C1 activates:
- “Start sync./contr.” (term. 25) input on the SG unit. As long as the SGB is open,
synchronisation will take place.
- Connection of the analogue speed control signal from the SG unit (term. 66(+) and 67) to
the analogue f/P input (term. 40(+) and 41). Note that the connection is “twisted”. This is to
achieve a “decrease signal” to the DG units when the SG unit requires an “increase signal”
to the SG.
- “Mode 3” (term 50) input on the DG units. This will cause the analogue input for frequency
/ power to be used as set point.
As “mode 1” (term. 48) and “mode 2” (term. 49) are active on the DG units, The diesel generators
are running in “load sharing” mode (provided the “start sync./contr.” input on the DG units is
activated).
When the SGB closes, The C1 relay signal de-activates. At the same time the “mode 2” inputs on
the DG units are removed. This forces the diesel generators to run in “fixed power” mode.
When the “DE-LOAD SG” is pushed, the relay C2 will activate and stay activated until the SGB is
opened.
The C2 activates:
- “Start sync./contr.” (term. 25) and “de-load” (term. 45) input on the SG unit. As long as the
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 13 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
As “mode 1” (term. 48) is active on the DG units, The diesel generators are running in “fixed power”
mode (provided the “start sync./contr.” input on the DG units is activated).
When the SGB opens, The C2 relay signal de-activates. At the same time the “mode 2” inputs on
the DG units are set (by opening of SGB). This forces the diesel generators to run in “load sharing”
mode.
To avoid re-synchronisation of the SGB, the “start sync./contr.” input on the SG unit must be
removed.
When the “DE-LOAD DG’s” is pushed, the relay C3 is activated. This will activate the “de-load”
input (term. 45) on the DG units. When both generator breakers are open, C3 will de-activate.
As “mode 1” (term. 48) is active on the DG units, The diesel generators are running in “fixed power”
mode (provided the “start sync./contr.” input on the DG units is activated).
NOTE: As long as the “DE-LOAD” inputs is active, a re-synchronisation will not take place after
opening of the generator breaker.
To avoid re-synchronisation, the “start sync./contr.” input must be removed from the DG
units after opening of GB’s.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 14 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
Fig. 9, Shaft generator synchronisation and subsequent load transfer to / from diesel generators
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 15 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
Seen from a control point of view, a mains network is very similar to a shaft generator. It is a power
supply unit running a fixed frequency and voltage, of which we do not have any control.
Due to the nature of mains parallel running the voltage control option must be used,
otherwise var (cos ϕ) control is not possible, and generator over currents may occur.
To control speed / power and voltage / reactive power of the Diesel Generators (DG’s) the Mains
Breaker (MB) Multi-line 2 unit analogue speed (term. 66-67) and voltage (term. 70-71) outputs are
used. The terminals 67 and 71 are interconnected. This is possible due to the fact that the outputs
are individually galvanic separated.
The 2 500 Ω resistors across the outputs converts the +/- 20 mA output into +/- 10 VDC, which is
the correct value for the DG units inputs.
When the “SYNC / CONTR MB START” pushbutton is pressed, the relay C1 will activate.
This will:
- Activate the MB unit
- Connect the MB unit analogue outputs to the DG units analogue set point inputs
- Set the DG units set point selection in “external” (activating “mode 3” and “mode 6” (term.
50 and 53)).
During synchronisation (MB open) the DG’s are running in “load / var sharing” modes.
When the MB closes, this is changed to “fixed load / var” modes” (the MB aux. contacts disconnect
the “mode 2 and 5”).
The system is now running parallel with mains. The MB unit is using internal set points for power
and cos ϕ to control the diesel generator plant, meaning the power consumption from the mains is
controlled to a fixed value. If external set points for power / cos ϕ are needed, activation of “mode 3
and 6” (term. 50 and 53) are needed. In this case, power can be controlled with a 0…10 VDC signal
on terminals 40(+)-41 and cos ϕ can be controlled with a 0…10 VDC signal on terminals 42(+)-41.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 16 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
To transfer load to the DG’s, the pusbutton “DE-LOAD MB” is pushed. This will activate relay C2
which will stay activated until the MB is opened.
C2 activates the “de-load” (term 45) input on the MB unit. This activates the ramp down function of
the MB unit, which will attempt to ramp the mains power consumption to 0. As the outputs from the
MB unit to the DG units inputs are “twisted” a “de-crease” signal from the MB units will bee seen as
an “increase” signal by the DG units, i.e. the DG’s will pick up power.
When the mains power reaches 5% load, the mains breaker will be opened.
To transfer load to mains, the “DE-LOAD DG’s” pushbutton is pushed. This will activate relay C3
which will stay activated until both generator breakers are opened.
When the DG’s reaches 5% load, the generator breaker will be opened.
NOTE: When C3 de-activates, the “START SYNC / CONTR” must be de-activated to prevent
re-synchronisation of the generator.
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 17 of 18
APPLICATION NOTES
Multi-line 2 4189340223C
Fig. 10, mains breaker synchronisation, load transfer to / from mains, peak lopping
Errors and changes excepted
DEIF A/S • Tel: +45 9614 9614 • Fax: +45 9614 9615 • E-mail: deif@deif.com Page 18 of 18