Professional Documents
Culture Documents
----Appellant
Versus
----Respondent
Advocates who appeared in this case:-
Judgment
//Reportable//
28/02/2018
company. While the appellant had 26% share in that company, the
of ‘Go’ and ‘No Go’ and declared the Parsa Kente and Kanta Basan
Mine Closure Plan. The said guidelines required, inter alia, the
dated 27.11.2013.
coal, under the price adjustment clause of the CMDA, the Sole
the Force Majeure events were treated as admitted and the delay
in the commencement date for the supply of coal was not the
provided. With regard to the second claim, the Sole Arbitrator inter
alia held that the respondent was entitled to Rs.78 crores towards
fixed costs and the losses incurred due to the failure of the
Account since the stage of closing any mine or part of it had not
from the running bills of the respondent for coal supplied on that
count were unjust, premature and contrary to the CMDA. The third
this appeal.
the appellant and Mr. Dushyant Dave, Senior Counsel for the
respondent.
ordinary prudence could have arrived at. It was contended that the
commence delivery of Coal within forty two months from the date
within forty two months from the date of allotment of coal blocks.
4.5.2 of the CMDA further provided that in the event the Company
Mr. Gopal Subramanium, argued that the CMDA did not even
resort to the terms of the CMDA itself. It was submitted that the
could have begun before the said date as well. This is clear equally
from the expression “...the Company shall use its best efforts to
commence delivery of Coal within forty two (42) Months from the
each operating year provided that the first escalation was to occur
means the financial year and includes the period from the
date were operative, the first Operating Year would have been
Operating Year was and ought to have been taken by the Sole
(10 of 64) [CMA-3785/2017]
the first price escalation would have been from financial year
would only occur as per the contract terms only in the financial
emphasis on the point that the appellant in the present case was
clauses of the CMDA over the one adopted by the Sole Arbitrator,
but the relevant clauses of the CMDA only allowed for one possible
and thus in conflict with the public policy of India. Mr. Gopal
Natural Gas Corporation Ltd. Vs. Saw Pipes Ltd. - (2003) 5 SCC
and the Commercial Court also failed to appreciate that the parties
Force Majeure and only that date and not any other, was relevant
contended that the claimant on the one hand could not take the
of the CMDA for benefiting from the price adjustment clause. The
Kadambolithaya & Others – AIR 1965 SC 241, and New Bihar Biri
Leaves Co. & Ors. Vs. State of Bihar & Ors., (1981) 1 SCC 537 and
terms of the contract and admitted facts on record that it was 25-
3-2013 and then allowing the claimant’s claim for price adjustment
for damages based on fixed costs, the Sole Arbitrator in Para 21-
23 of the Award held that since the appellant failed to off-take the
the Act of 1872. The claim for damages on account of fixed cost
with which the respondent had entered into a Coal Mining Services
the purported loss incurred by the AMPL, with whom the appellant
obligations were/ are strictly limited within the CMDA dated 16-7-
sub contractor was not one. The appellant in its legal capacity
They could not have relied upon CW1/72, which was a mere
from the CMDA dated 16.7.2008 was pointed out to the Sole
made out under Section 73 of the Indian Contract Act, 1872. Mr.
2015 and the judgment of the court below are in the facts of the
RVUNL would open and maintain ‘Escrow Account’ with the CCO in
the condition and agreed that the amount deposited into the
Escrow account.
(15 of 64) [CMA-3785/2017]
Court in Oil and Natural Gas Corporation Ltd. Vs. Western Geco
has over the long run financial ramification of about Rs.955 crore
public which would bear the costs through higher tariffs if the
Arbitrator and the order of Commercial Court could have only been
Dushyant Dave submitted that the Sole Arbitrator acting within his
31(3) of the Act of 1996 have been assigned for the said
SCC 142, Mr. Dushyant Dave submitted that the court’s jurisdiction
over the award under Section 37 of the Act is not appellate though
SAIL Vs. Gupta Brother Steel Tubes Limited – (2009) 10 SCC 63,
1996.
the Apex Court and the award passed was restored holding that
the terms of the contract. It was submitted that the Sole Arbitrator
CMDA to hold that the application for the price adjustment clause
the parties to the CMDA. This Court cannot exercise its power of
Inc. Vs. Burn Standard Co. Ltd. - (2006) 11 SCC 181 and National
pay the contract price per MT to the company duly adjusted as per
3.2.1 of the CMDA whereunder the company was to carry out all
Thermal Power Stations. All expenses incurred for all the works
all clearances, reports and licenses for the term of the agreement
and all charges incurred for arranging mining data, geological data
delivery / supply of coal to the appellant was thus the last part/
for contract price for discharge of all the obligations, services and
under Clause 5.4. The contract price under Clause 5.1.2 was total
delivery price per metric tonne of coal at the delivery point not
(19 of 64) [CMA-3785/2017]
5.3, but the price being charged and paid under the contract was
not simply related to mere delivery of coal, though the contract for
5.2.2 of CMDA provides that for the first Operating Year, the basic
which was to remain frozen during the first year. The basic price of
price adjustment, on the quoted rate after the first year was to be
2013 as even though actual delivery of coal did not take place, the
performed.
price index. The proviso thereto simply stipulates that the effect of
commenced the work under the CMDA in the year 2008 and
the appellant. Yet all along during the period preceeding actual
(21 of 64) [CMA-3785/2017]
submitted that Clause 7.3 of the CMDA deals with the effect of
that neither of the parties shall be liable for any claim for any loss,
carry out terms of the agreement to the extent such failure has
Majeure situation vide its letter dated 13.11.2011. That being the
(22 of 64) [CMA-3785/2017]
nor have they been so awarded. What the Sole Arbitrator has
the fact that in the meantime the wholesale price index and
consumer price index may have steeply gone up. The converse of
deflation, though very unlikely, may also have occurred with its
signed both the claimant and the respondent were fully conscious
the year 2011-2012 even though, apart from the actual supply of
started on 20.05.2011 and the supplies were made till the year
would have been liable to supply coal in the year 2024 at the rate
(24 of 64) [CMA-3785/2017]
as would follow from the payment of basic price of coal at the rate
Investment Co. Ltd. Vs. Eagle Star Life Assurance Co. Ltd. - WLR
1020.
04.01.2014 and 26.04.2014 about the said idle fixed costs and the
obtained permission from the Ministry of Coal for utilizing the coal
apply for rakes to the Indian Railways. The said exercise was
part could not have sold the ready coal to third parties as such
sales were prohibited under the applicable law i.e. Clause 4.5.4 of
appellant's inability to lift mined coal ready for dispatch as per its
and was within the sole domain of the Sole Arbitrator. That finding
term of the CMDA. It was submitted that in the facts obtaining the
owner allotted coal blocks for the purposes of mines closure plan.
The appellant being the mine owner was therefore obliged to open
the said account as per Clause 3.3 (d) of the CMDA. The Sole
award which has been not interfered with by the court below for
Ltd. Vs. State of Assam – (2016) 9 SCC 519. Reference was also
made to the judgment of the Apex Court in Oil & Natural Gas
Company Ltd. Vs. Saw Pipes Ltd. - (2003) 5 SCC 705 wherein it
electricity to the general public. The said report, apart from being
the first time before this Court, more so after rejection of the
precedents.
respondent into four parts. The first pertained to when the price
company claimed and was entitled to, the third to Escrow Account
railway siding. While the first three of these four have been
under:-
Definitions:-
“Basic Price” shall mean the basic price paid for the
Coal which shall be calculated in accordance with Clause
5.2.
Main Clauses:-
Wherein:
Quoted price is for the coal for which 1.29 times ‘F’
grade raw coal will be consumed. Further for achieving
30% Ash (ADB), the yield of 77.5% has been considered
as per beneficiation contract. This criteria has been
adopted while working out ceiling price.
(i) xxxxxxx
(ii) xxxxxxx
(iii) xxxxxx
(iv) xxxxxx
(v) The occurrence of an event of force majeure shall
not relieve either party from its obligations to make any
payment hereunder for performance rendered prior to
the occurrence of force majeure or for partial
performance hereunder during periods of force majeure.
(vi) xxxxxxx
(vii) If a force majeure event continues for a prolonged
period of 30 (thirty) days and as a result of such force
majeure RVUNL is not able to take delivery of the coal,
the company may dispose of coal in accordance with
clause 4.5.4.
(i) xxxxxxx
(ii) xxxxxxx
no event for evaluating the legality and validity of the award dated
the award dated 27-5-2015 one way or the other within the scope
The appellant's argument is that the claimant could not avail the
matters affecting the value of money and the necessity for its
equalisation.
Coal to the Delivery, Points, and the Joint Venture Agreement, the
RVUNL shall pay the Contract Price per MT to the Company duly
Clause 4.5.1 of the CMDA indicates that the delivery of Coal shall
(42) months from the date of allotment of the Coal Blocks (25-6-
and admittedly the coal supply under the CMDA only then started.
has been heavily relied by both the learned Sole Arbitrator and the
the price adjustment clause. This Clause inter alia provides that
part. We are however of the view that clause 1.2.9 of the CMDA
reasons set out above and hold that the commencement date
stipulates that the basic price as set out in Clause 5.2.2 shall be
The proviso aforesaid thus makes it amply clear that the first
escalation in the basic price of coal was to occur only after the
by the appellant.
had been ten years, the price adjustment clause could not be
the price index and consumer price index in the meantime had
and work continued till 2014 and thereafter the supply disrupted/
would the respondent still be liable to supply the coal at the rate of
that the price adjustment clause in the CMDA provides that once it
Resultantly the first escalation in the basic price of coal under the
right in contending that the appellant is not seeking that this court
The Supreme Court in ONGC Vs. Saw Pipes Ltd., supra, held
that the court will set aside an arbitral award under Section 34(2)
the aforesaid report the Apex Court formulated the question for its
dispute in accordance with the terms of the contract and also take
Gas Corporation Ltd. Vs. Saw Paipes Ltd., supra, held that an
Section 34 (2) of the Act. In Para 14 of the said report, it was held
as under:-
Sharma and Co., dealt with a case where there was an agreement
which was that the rates quoted by the contractor shall hold good
Haryana to Delhi. It was held by the Supreme Court that there was
bringing aggregate stone only from ‘Nooh’. In view of the fact that
Sole Arbitrator was an error on the face of the record and was also
whether the award was against the specific terms of contract and
Apex Court in para 42.3 of the report observed that third subhead
thereof. The Apex Court however held that where the Arbitrator
The Apex Court in Rajasthan State Mines & Minerals Ltd. Vs.
albeit in a case arising out of the Arbitration Act, 1940, held that
“It is settled law that the arbitrator is the creature of the contract
“the rates wherever fixed are binding during the currency of the
judgment of the High Court, which had modified the award in part
while awarding rate of Rs.210 per cubic metre for the work
the relevant aspects in awarding higher rate for that work than the
proceeds on the assumption that the sale of goods can fetch price
only when they are actually sold and supplied. When there is no
months inter alia for force majure reason. Not fixed in stone, date
can be visualised for the purpose of Clause 5.2.2 read with Clause
Zero Year.
gathered from the words used in the agreement. If the words are
the words actually used therein that the parties had agreed on a
the contract unless they are such that one may suspect that they
do not convey the intention correctly. If the words are clear, there
Larson and Toubro Limited Vs. Mohan Lal Harbans Lal Bhayana –
and that “as the contract between appellant and respondent deals
to be rejected. The Sole Arbitrator and the court below have acted
to claim No.1 are vitiated with patent illegality and hence are
this head and the appellant has been required to pay an amount of
vis scheduled quantity for lack of its readiness. As per the finding
finding recorded by the Sole Arbitrator, the appellant had not even
per the delivery schedule and 60 days beyond. The delay thus was
damages on that count does not disclose the basis on which the
petition where it was pleaded that since the claimant had a back to
2009 for the extraction of coal, the ultimate liability to bear costs
per the delivery schedule under CMDA fell upon the claimant of
coal received by the respondent was only 9.19 lakh MT, leaving
respondent claimant for the loss a third party, AMPL, in its contract
read thus:-
claimant under the CMDA which was before him for the losses its
all, while the certificate is for Rs.77.39 crore, and not Rs.78 crore,
the Sole Arbitrator has rounded it off (which he could not in law
do) not to Rs.77 crore, reckoning for .39 but to Rs.78 crores.
Ltd. Vs. Workmen and Others – (1971) 2 SCC 617, held that when
the provisions of the Code of Civil Procedure and the Evidence Act
are not applicable in view of Section 19(1) of the Act of 1996. But
present case, the Sole Arbitrator has not at all discussed the
and has not discussed and analysed the method and manner of
Contract Act.
or loss under Section 73 of the Contract Act is a sine qua non for
Section 74 of the Contract Act, it was held that proof of loss is not
its jurisdiction. For the reasons set out hereinabove, the award on
1940, the Court, after setting aside the award, also had the power
award to the arbitrator with the direction that he must assign the
influenced by his earlier award, which had already been set aside
The Apex Court then held that the limited discretion available
Act. This for the reason that consequent to disposal of the main
the court was wider, the 1996 Act made provision for the
supervisory role of courts, for the review of the arbitral award with
and can only quash the award leaving the parties free to begin the
here limited only to the award on claim No.2 regarding Fixed Costs
The third claim, which the learned Sole Arbitrator has allowed
and the court below refused to set aside under its impugned order
it would open and maintain the Escrow Account with the CCO
the Escrow Account from the immediate next payment of the coal
bills towards the dispatches of the coal. The respondent thus was
CMDA also clearly makes the respondent company liable for all
costs in the mining of coal activity. The costs towards mine closure
any mining or any part of it had not yet arrived, the deduction
(58 of 64) [CMA-3785/2017]
arbitrary and also as premature, held the Sole Arbitrator and liable
Account may be released every five years in line with the periodic
any mine and/or part thereof had not arrived and therefore the
clearly states that all expenses incurred for the Works shall be
both the Sole Arbitrator and the court below overlooked clinching
under:-
constitute the “fundamental policy of Indian law” and held that the
decision in ONGC Ltd. v. Saw Pipes Ltd., supra, does not elaborate
that aspect. Even so, the expression must include all such
The Apex Court in ONGC Ltd. v. Saw Pipes Ltd., supra, held
policy of law in India’ for testing the validity of arbitral award are
well stated. They are that the Arbitrator must have a judicial
the Sole Arbitrator not only suffers for one, from patent illegality,
which goes to the root of the matter. The Sole Arbitrator in arriving
wholly within his jurisdiction and does not warrant interference for
costs is unsustainable not only for the reason that it was passed
the Act of 1996 for reasons which having been fully made out and
1996.
award dated 27-5-2015 of the Sole Arbitrator and the order dated
are liable to be set aside. They are so and would stand set aside.
//Jaiman//