Page No.

Reference Comments Response

1 Traffic Volume • Different figures for traffic volume of opening • Comment is accepted and correction has
year have been indicated on page 3 and 8 been made accordingly.
which is 322 and 329 respectively. Please,
use a single correct figure for traffic volume.
Similarly include the correct project length
since same has been inconsistently
indicated as 121.2km and 121.8km.

8 Projected Road • In your report, it has been stated that.... • Comment is accepted and correction has
Traffic Considering AADT and the design classes been made accordingly.
listed under the category of Link Road which
is from DC2-DC7, the project road falls
under the category of Design Class DC5.
But, according to ERA 2013 Geometric
Design manual, category of Link Road is
from DC3-DC7. Hence, please correct.

9 Geometric Design • According to ERA Geometric Design manual


Standard 2013, the geometric design is influenced by
numerous factors and controlled by specific
design criteria as follows;

o Traffic volume expected to use the o Addressed in Section 1.5. Detailed


road analysis is shown in the Feasibility
Study Report.
o Composition of traffic

o The design vehicle o Addressed in Section 2.3

o Design speed o Addressed in Section 2.5

o Terrain type o Addressed in Table 1.3


Page No. Reference Comments Response

o Road side population and land use o Addressed in Sections 1.4 and 1.5 by
way of indication of locations of
Towns and estimation of Non-
motorized traffic which subsequently
has impact on the design of road
cross-section in the detailed design.

o Pavement type o The design standards to be adopted


during design are addressed in
Section 3. However the detailed
design will be presented in the
Engineering Report.

o Soil type and climate o General aspect of the climate of the


region is addressed in Table 1.2.
However the detailed aspects of
these issues will be presented in the
Material and Site Investigation
Report as well as Engineering
Report.

o Construction technology o This issue will be addressed in the


Tender Documents.

o Functional classification of the road o Addressed in Section 2.2.2.

o Safety o This issues will be addressed in the


course of the detailed design
o Economy and environmental
consideration

• Hence, we would like to advise you to • It is believed that most of the above issues
incorporate all the stated factors in you have been addressed in the report as shown
Page No. Reference Comments Response

report. above. However some of the issues will be

1 Structural Design • The design drawings of the culverts show • Culverts section drawings are prepared
of Kombolcha reduced width excluding the walkway from based on highway design cross section; it
bypass Road the carrageway incorporates all required width of the
Project • It has been indicated that, there is carriageway.
discrepancy in grade of concrete detail • The design of Box culvert and wing wall is
shown on the box culvert section drawing done for concrete grade of C-30. It is typing
(cylindrical strength of 20MPa (Grade 25) error and please correct the General Note of
and the box culvert wing walls (cylindrical Box Culvert wing wall design drawing as
strength of 24MPa (Grade 30). Grade of Concrete from C-25 to C-30.
• There is also a discrepancy in the grade of • The Rebar grade description of Box Culvert
reinforcement detail shown on the box is similar with the wing wall. Similarly it is
culvert section drawing (yield strength of typing error and please correct the General
300MPa (<20mm dia.) and 400MPa note of Wing wall design drawing as yield
(>=20mm dia.) and the box culvert wing wall strength of 300MPa (<20mm dia.) and
(yield strength of 500MPa). 400MPa (>=20mm dia.)