Professional Documents
Culture Documents
BY
JUNE, 2016
ii
CERTIFICATION
_____________________ ______________________
PROF. P. O, PHIL-EZE PROF. P.A.O ODJUGO
(Supervisor) (External Examiner)
____________________________________
PROF. P.O, PHIL-EZE
(Head, Department of Geography)
_________________________________________________
REV.FR.PROF.HILARY ACHUNIKE
(Dean, Faculty of the Social Science)
iii
TABLE OF CONTENTS
Title Page i
Certification ii
Table of Contents iii
Dedication v
Acknowledgement vi
List of Tables vii
List of Figures ix
List of Acronyms x
Abstract xi
CHAPTER ONE: INTRODUCTION
1.0 Background of the Study 1
1.1 Statement of research the problem 5
1.2 Aim and Objectives of the Research 7
1.3 The Study Area 8
1.4 Literature Review 15
1.5 Research Methodology 27
1.6 Plan of the Project 33
CHAPTER TWO: THE ORIGIN AND CURRENT PRACTICE OF EIA IN
KOGI STATE
2.1.0 Origin of EIA in Kogi State 34
2.1.1 Kogi State Administrative and Legal Framework of EIA 34
2.1.2 Legal Framework 36
2.1.3 Current Practice of EIA in Kogi State 38
2.1.4 EIA Process and Procedural Framework 40
2.1.5 Analysis of the Awareness of EIA in Kogi State 42
2.1.6 Summary of the Current Practice of EIA in Kogi State 58
CHAPTER THREE: IDENTIFICATION OF EIA COMPLIANCE LEVEL
IN KOGI STATE
3.1 Identification of the level of compliance with EIA 59
3.2 Response from Questionnaires on the level of compliance 59
3.3 Facts from publication and existing EIA Documents 76
iv
DEDICATION
ACKNOWLEDGEMENT
I thank God most high for his love, protection and provision for me to finish this work. I
am grateful to my supervisor, Professor P.O.PHIL-EZE, for his tireless attention and sacrifice to
see the work come to completion. I thank all the lecturers of this honourable Department for their
I thank all my friends in and outside the Department for standing with me to see that the
work succeeds. Finally, I thank my dear wife RUTH, A. TIMOTHY, all the members of
SHAIBU’s family and my children for their prayers and support throughout the period of this
programme. May God bless all those who contributed to the success of this work.
vii
LIST OF TABLE
LIST OF FIGURES
Fig. 1: Nigeria showing Kogi State 9
Fig. 2: Kogi State showing the Study Area 10
Fig. 3: Kogi State showing the six Local Governments with major
Industries 28
Fig. 4: Level of awareness of EIA in Kogi State 57
Fig. 5: Factors affecting the level of compliance 75
Fig. 6: Analysis of the variations in the level of agreement by respondents
on EIA 105
x
LIST OF ACRONYMS
1. CBA Cost Benefit Analysis
2. CEP Committee on Environmental Protection
3. CEQ Council on Environmental Quality
4. EEC European Economic Community
5. EIA Environmental Impact Assessment.
6. EIS Environmental Impact Statement
7. EMP Environmental Management Plan
8. FEPA Federal Environmental Protection Agency.
9. FME Federal Ministry of Environment
10. GIS Geographic Information System.
11. IEE Initial Environmental Examination
12. KOSEPA Kogi State Environmental Protection Agency
13. LGA Local government Areas.
14. NESREA National Environmental Standards and Regulations
Enforcement Agency.
15. NGO Non governmental Organisation
16. NKJ New King James Version.
17.NNPC Nigerian National Petroleum Corporation
18. PCA Principal Component Analysis.
19. SEAP State Environmental Action Plan
20. UN United Nations
21. UNEP United Nation Environmental Programmes
22.USA United State of America
23.WHO World Health Organisation.
xi
ABSTRACT
This study analysed the level to which development projects in Kogi State comply with
environmental impact assessment policy. To achieve its aim, the study examines the current
practice of EIA in Kogi State, identifies the level of compliance of development project with EIA,
analysed the reasons for the level of compliance, and suggest strategies for effective
implementation of EIA in Kogi State. Field work was conducted between April 24th and
September 26th, 2012. During the field work, we observrd that major development projects and
industries were found to concentrate more in six local government areas of the state. These local
governments are Ajaokuta, Ankpa Dekina, Kabba/Bunu, Lokoja and Ofu which later become the
study area. Structured questionnaires were used to collect data from the public, staff of the
regulating agencies and staff of companies and project proponents. The three categories of
respondents have seperate questionnaire. Oral interview was conducted across the state to generate
handy information. Existing EIA reports were analysed to ascertain their worth. Statistical
packages for social sciences (SPSS) version 19 was used to analyse the data. The programme
extracted the rated values for each of the variables and transform them to Mean which was further
used in the analysis of variance, correlation and Principal Component Analysis.The results indicate
low level of awareness of EIA and low level of compliance with EIA in the state. The PCA result
identifies four major components responsible for the low level of compliance with EIA in the
state. These includes, Poor concern for EIA provisions, Poor stakeholders engagement in EIA
process, cost of EIA permit and lack of accessibility to qualified EIA consultants. Other reasons
discovered to impede EIA compliance in the state include multiple EIA regulators, inadequate
baseline data, lack of enforcement policy and others. The study recommends that awareness
campaign on EIA should be given priority in the state. The state edict and the national guidelines
should be in harmony and there should be an agency vested with the responsibility of enforcing
EIA policy in the state.
1
CHAPTER ONE
INTRODUCTION
Kogi State was created in 1991. As a new state, succesive governments have continued to
clamore for development projects to boost the economy of the state. To this end, the Kogi State
Beside industrial activities, other economic activities like hunting, grazing, lumbering,
mining, fishing and farming are fast growing in the state. All these economic activities and the
quest for accelerated infrasturactural development leave negative effects on the environment of
the state such as accelerated soil erosion, deforestation, flooding, and soil degradation.
In most cases, the exploration of natural resouces are done with little regard to
consequences owing to high level of poverty and deprivation in the state which compelled people
to undermine the productivity of land in their quest for food, fuel and shelter. However, this
unregulated economic acivities only promote poverty and worsen environmental degradation.
In the past, many development plans like cost-benefit analysis (CBA), environmental audit,
feasibility study, and environmental action plan have been developed for the state, but all these
strategies did not consider environmental cost, public opinion and social and environmental impact
environmental management become indispensable. Adeniyi, (1998) defines EIA as “a tool for
development planning which states the effects of a proposed project on the environment, predicts
2
the likely impact in magnitude, extent and significance and find ways to reduce unacceptable
impacts and provides the developers the pros and cons of alternatives, including the option not to
Federal Ministry of Environment, (FME, 2002) defines EIA as a study to identify, predict,
evaluate, and communicate information about the impact of a proposed project on the environment
and to detail out the necessary mitigation measures prior to project approval and implementation.
The main objectives of EIA is to identify and predict the impact of polices and activities
on the environment so that there is an opportunity for interested parties to decide whether those
Nigeria in 1995 summarised the steps to be taken in EIA preparation to include the following;
Project proposal, Initial Environmental Examination (IEE), screening, scoping, EIA study, EIA
According to Nwafor, (2006), EIA was institutionalized in the United States (USA) as a
requirement of the country’s National Environmental Policy Act of 1969. The EIA legislation has
created a situation in the USA in which decisions on major developmental activities can only be
Following the adoption of EIA in the USA, several industrialized countries of the World
made EIA compulsory for approval of development projects (Alo, 1999). For example, Canada
adopted EIA in 1973 with Australia closely following in 1974. Many countries in both developed
and developing economy have come to appreciate and adopt EIA as a tool for sustainable
development.
3
necessary tool for environmental management through their policy on the environment. For
example, the European Economic Community (EEC) in July, 1985 adopted a directive making
environmental assessment mandatory for certain categories of projects prior to their consideration.
The United Nations (UN) since 1972 established a specialized Agency on the environment known
as United Nations Environment Programmes (UNEP) with a deep consideration for EIA. The
World Bank had since 1991 adopted mandatory EIA procedures for funding development projects
(Alo, 1999). The World Health Organization (WHO) has also advocated the need to assess the
opportunities for development as well as the adverse impact upon human health of such
Prior to the promulgation of the EIA decree in 1992, the Nigerian government had made
several attempts at ensuring a sustainable environment. This led to the creation of a regulatory
body known as the Federal Environmental Protection Agency (FEPA) in 1988. The agency was
charged with the overall responsibility of protecting and developing the Nigerian environment. In
furtherance of the objectives of the agency, a national policy on the environment was developed
as the main working document for the preservation and protection of the Nigerian environment.
States and local councils were encouraged to establish their own environmental regulatory bodies
for the purpose of maintaining good environmental quality based on the perculiarity of the terrain.
(Echefu, et al 2007)
created in 1999 but, without an appropriate enabling law on enforcement issues. This situation
however created a vacuum in the effective enforcement of environmental laws and regulations in
the country until 2007 when the National Environmental Standards and Regulations Enforcement
4
Agency (NESREA) act was created, (Echefu et al 2007). The NESREA act empowers the agency
to be responsible for enforcing all environmental laws, guidelines, policies, standards and
To this end, EIA has been adopted in Nigeria as a powerful tool for sustainable
development. Hence the promulgation of the EIA Decree No. 86, of 1992 and its subsequent
amendment in 2004 has made it mandatory for EIA to be fully applied to development projects in
the private and public sectors of the economy right from the planning stage. Some of these
virgin land, estate development requiring the acquisition of land of five hectares and above, large
The objectives of EIA in Nigeria are contained in Decree No. 30, of 2004. Section 13 and
the schedule to the Decree contains a list of mandatory study activities relating to nineteen (19)
For effective implementation of the EIA Decree, one EIA procedural guideline and five
departmental guidelines in the major sectors of the economy have been published to assist project
proponents and stakeholders in conducting EIA. Based on the EIA Decree No. 86 of 1992, the 36
states of Nigeria are to adopt EIA in their environmental management policy. Hence, Kogi State
established a legal framework through which EIA can be implemented. The policy framework at
the state level identifies the need for an agency to formulate environmental policy and manage all
the aspect of the environment. In this regard, Kogi State Environmental Protection Agency
(KOSEPA), was established through Edict No. 3 of 1995. The Edict empowers the Agency to
exercise both advisory and executive role on environmental matters in the state. The Edict also
5
gives absolute authority to the Agency to seal off premises where activities leading to
environmental degradation are carried out. More importantly, the Edict adopts EIA for
development projects. Section 30, subsection (2) of the Edict states that “Every person who intends
to carry out such physical development such as manufacturing or industrial activities in any
premises within the state shall prior to the commencement of such activities submit to the Agency
an Environmental Impact Assessment report and obtain a certification from the Agency”.
As a result of this development, EIA has been adopted in Kogi state. However, the quality
of environmental impact assessment carried out and the level of compliance with EIA procedural
guidlines have to be examined to see whether EIA in the state is in consonance with the Federal
Kogi State as a newly created state is striving for development. Successive governments in
the state over the years have clamoured for development strategies which include calling on foreign
Most of the development projects undertaken however, have little or no regard for
environmental consequences. Consequently, negative impacts are often left on the environment of
any area where development projects have been undertaken. To aviod this urgly trend, EIA was
Nigeria promulgated EIA Decree No. 86 in 1992 and for proper implementation of the
Decree, a procedural guideline was prepared. The guideline is to assist project proponents in
This procedural guideline, has a list of mandatory study activities in five sectors of the
economy to assist the project proponents in the preparation of EIA. These activities include
Agriculture/Agro-Allied, Fisheries, Forestry, and Industry; Water supply, Transport, Mining and
quarrying. Others include Land Reclamation, Dams and Irrigation, Petroleum and Petrochemicals.
Infrastructure Installation and Ports, Housing, Railway, Electric power Generation, Plantation,
Further to the publication of the procedural guideline, there are five sectorial guidelines
prepared by the then Federal Environmental Protection Agency to guide project proponents in the
preparation of EIA in the major sectors of the economy. Despite the legal and adminstrative
framework of EIA methodologies at the national level, Some States in Nigeria are yet to adopt an
EIA that strictly adhere to the procedural guidelines set up by the Federal government on the
preparation of EIA. In most of these states, there exist a strong conflict between the Federal
Government policy and state policy on EIA. There are also many bodies regulating EIA with
overlapping responsibilities and as such EIA methodologies seem to have been down played and
Some states in Nigeria, had a review of their EIA system in order to accommodate the
Federal Government guidelines. Lagos state and Ondo state are good examples in this regard. The
Federal Ministry of Environment in 2010 also had a review of the EIA methodologies to
However, in Kogi State, given the rapid rate of development projects, and the dual nature
of EIA regulating bodies, as well as the desire for a sustainable development in the State, there is
need for an evaluation of the methods adopted in the preparation of EIA in the state. To achieve
this, this study has been designed to evaluate the compliance of development projects in Kogi State
7
with EIA procedural guidelines. Each step enumerated in the guideline which include project
proposal, initaial Environmental Examination, EIA screening, EIA scoping, EIA Review (public
participation), Decision making, Environmetal monitoring and Auditing shall be examined to see
whether they are fully complied with by Kogi State EIA process.
This study is therefore designed to evaluate the methodological approach to EIA in Kogi State
in order to ascertain the compliance of development projects with EIA provisions and suggest
ways through which proper implementation of EIA can be achieved to ensure sustainable
environmental management.
The aim of this project is to analyse the level to which development projects in Kogi State
Objectives
in Kogi state.
8
1.3.1 Location
Kogi State was created on 27th August, 1991 during the national state creation exercise. It
has a land mass of about 30,354.7 km square and a total population of 3, 278, 048 people, Aikoye.
(2008). The present day Kogi State was known as Kabba province during the colonial era with
Lokoja as the provincial Headquarters. The state is divided into three geographical areas popularly
known as senatorial districts. These are Kogi West and Kogi central, carved out of the old Kwara
State and Kogi east, carved out of the old Benue State.
The state lies between latitudes 60 35” and 80 36” North of the equator and longitudes 50
30” and 70 50” East of the prime meridian. The state shares boundary with Kwara State to the west,
Ondo and Ekiti states to the South west, Anambra and Enugu States to the south East, Benue and
Nassarawa to the North East, and the Federal Capital Territory and Niger State to the North West
and North respectively. The state is centrally located of all the states in Nigeria and possesses the
1.3.2 Size
Kogi State covers a total land area of 29, 833km2. It is divided into three senatorial districts
of Kogi West, Kogi Central and Kogi East. At creation, there were sixteen (16) Local Government
Areas with ten (10) carved out of the old Kwara and six (6) carved out of the old Benue State.
During the December 1996 state and local government creation exercise, the number of local
government areas in the state increased to twenty-one (21). These Local Government Areas are:
Adavi, Ajaokuta, Ankpa, Bassa, Dekina, Ibaji, Idah, Ijumu, Igala-Mela, Kabba/Bunu, Kogi,
Lokoja, Mopa-moro, Ofu, Ogori-mangogo, Okehi, Okene, Olamaboro, Omala, Yagba East and
Yagba west.
9
1.3.3 Geology
The geology of Kogi State has a complex characteristic due to variations in their mode of
formation. There are basement complex rocks, meta-sedimentary and other sedimentary
formations and alluvium. Around the western part of River Niger in the state exists atypical granitic
or mi-granitic rocks, (Adejoke, 1999). Older granites of Pre-Cambian age are found around
Lokoja, Isanlu, Mopa and Egbe. Hard rocks of granite and other basement complex rocks are found
around Itakpe and Agbaja. The geology of the eastern part of the state shows a remarkable
difference. A large part of Ankpa, Ofu, Igala-mela and Olamaboro are made up of sedimentary
11
rocks, World Bank, (1998). On the other hands, Bassa and Kogi and Omala depict a type of shale
outcrops with high alluvial deposit owing to their location in the flood plain of rivers Niger and
Benue.
1.3.4 Climate
Kogi State has a tropical rainy climate with a wet and a dry season. The state experience
long period of rainy season between seven (7) and eight (8) months, (March to October) while the
dry season lasts for about four (4) months (November-February). The wet season can be further
classified into two, long wet season occurring from April to July and a short wet season occurring
from September to October. The dry season have the same characteristic. There is a short dry
season occurring in August popularly known as “August break”, and a long dry season occurring
between November and March. A cool, dry and dusty air popularly known as “harmattan” always
marks the beginning of the dry season. This condition normally prevails till late January when hot,
dry and sunny weather prevails to usher in the rainy season. The annual rainfall total for the state
is about 1, 200mm. The mean monthly temperature is between 260C in December and 300C in
1.3.5 Relief
The state is found within the Niger/Benue river trough with a “Y” shape at the confluence
in Lokoja. The evolution of the trough is complex and bewildering. Adejoke (1999) opined that,
this major depression was formed about 150 – 200 million years ago. The Benue opening, he said
was formed through the development of major faults which separated highlands viz the Jos Plateau
The relief of the State is generally rugged and undulating. The land rises from about 300
metres along the Niger Benue confluence, to the heights of 600 metres above sea level in the
12
uplands. Agbaja Plateau, which ranges from 335 to 366 metres above sea level, and the much
higher Okoro Agbo hills at Ogidi in Ijumu LGA are some of the predominant landforms in the
state. The terrains particularly around the rivers are made up of hills, plateaux and inselbergs with
elongated ridges. However, the topography is steeped with gentle slopes along the numerous
valleys existing in the state. Examples of such elevation in the state include mount Patti, (420m),
1.3.6 Drainage
Kogi State is drained by the major rivers in Nigeria, river Niger and river Benue. In the
eastern part, river Benue cut through Omala local government and Bassa while river Niger drains
Kogi and Lokoja local government. The Benue river is navigable as far as Garua in the rainy
season, but up to Makurdi in Benue state in the dry season (World Bank, 1998). After the
confluence at lokoja, the river passes through Ajaokuta local government and Idah local
Other smaller rivers exist in the state, especially in the eastern part. Examples of such rivers
are Omala river, Ofu river, Olamaboro river, Nachalo river, Okura, Ubele and Adawo e t c.
Osomera falls at kilometre four on Okene/Ajaokuta road, Ofejiji falls in Okura Olafia, Egeneja
warm spring in Bassa Local Government Area and Adankolo river are other drainage features
1.3.7 Soil
Generally, soils in Kogi State can be grouped into low and high productive soils. High
productive soils are usually the alluvial type formed around the riverine areas.This type of soil is
restricted to the flood plain of rivers Niger and Benue, paticularlly, in the following local
13
government Areas. Omala, Kabba/bunu, Yagba East and Yagba west, Ajaokuta, Kogi and Lokoja.
This hydromorphic soil contain a mixture of coarse alluvial deposits (Word Bank 1998).
The low productive soil (laterite) dominates the remaining local government areas of the state.
This type of soil is characterised by large grains and loose particles with high proportion of sand.
The soil is poor in nutrients and highly permeable which makes it easily eroded.
1.3.8 Vegetation
Generally, the vegetation of the state is the Guinea Savanna type of vegetation in Nigeria.
However, variations exist in the structure and physiognomy of the vegetation from one part of the
state to another. For example, Dekina, Ofu, Ankpa, Olamaboro, Idah and Bassa Local Government
Areas have rich deciduous and occasional stunted trees including Iroko, (Melicia excelsa),
mahogany (Khaya ivorensis), akee apple (Blighia sapida), mango tree (Mangifera indica), custard
apple (Annona senegalensis), bush mango (Irvingia gabonensis), and other towering trees. Other
LGAs are in the guinea savanna or parkland savanna belt with tall grasses and scattered trees.
These are green in the rainy season with fresh leaves and tall grasses, but the land is open
during the dry season, showing shed trees and the remains of burnt grasses. The trees which grow
in cluster grow up to about 10 metres tall, interspersed with grasses which grow up to about three
metres.
These trees include locust bean (Parkia biglobosa), shear butter (Vitellaria paradoxam),
beans spp (Argemone mexicana), cashew (Anacadium occidentalis), and the isoberlinia trees. The
different types of vegetation are, however, not in their natural luxuriant state owing to the careless
human use of the forest and the resultant derived deciduous and savanna vegetations.
14
1.3.9 Population
The 2006 population census put the population of the state at 3, 278.487 with an average
density of 109.9, persons/km2. In 1991, the population of the state was 2, 144, 756 with a density
of 72.9 persons/km2. This statistics reveal a rapid increase in the population of the state. Highest
population densities are recorded in Okene, Ankpa, Idah, and Adavi local government areas of the
state. A comparison between the 1991 and 2006 census results revealed a percentage change of
about 52.65, (NPC, 2006). A breakdown of the state population according to LGAs is shown in
Table 1.
1.3.10 Industrialization
The economy of the state is largely dominated by primary activities like fishing, trading,
and agriculture. However, large scale manufacturing industries like the Iron and Steel industry at
Ajaokuta, the Iron ore mining at Itakpe, the cement Factory at Obajana,the Goldsfield coal minning
at Okobo, Ankpa,the West African Ceramics at Oguro are fast developing. Similarly, many new
industries like the dehydrated lime project at Itobe, the Organic fertilizer industry at Anyigba,
Sugar refinery at Ibaji, Cement factory at Ekinrin-Ade and the proposed Petroleum refinery at
Itobe and others are likely to commence operation soon in the state. All these industries have both
Besides, other economic activities like large scale farming, petroleum filling stations,
Estate development, satelite network and many others are fast growing in the state.
Man’s activities (Development Projects) have both negative and positive impact on the
environment. Man can not abandon his development projects because of its negative impact on the
environment. On the other hand, the environment remains the only platform for development
projects. It is therefore important for man to balance his quest for development with environmental
UNEP (1980a), World Bank, (1995), Nwafor, (2006), and Anago (2008), define sustainable
development as the ability of the present generation to meet its needs without compromising the
potentials of the future generation to meet theirs. In other words, “The right to development must
be fulfilled so as to equitably meet developmental and environmental needs of the present and
According to Nwafor, (2006) the concept of sustainable development and its practical
implementation had been increasingly considered by policy makers to be one of the most crucial
tools for achieving a balance between economic, social and environmental objectives.
Sustainability is not a wholly new idea. “….according to the Bible (Deuteronomy Chapter
22 Vs 6 – 7), the Israelites were commanded that “if a Birds nest happens to be before you along
the way, in any tree, or on the ground, with young ones or eggs with the mother sitting on the
young or on the eggs, you shall not take the mother with the young; you shall surely let the mother
go, and take the young for yourself, that it may be well with you and that you may prolong your
The ideal value behind the commandment is that, as the Israelites satisfy their own needs,
they should remember that the future generation should not be deprived. Given the importance of
sustainable development, Nwafor, (2006) states that, the generic procedure of environmental
impact assessment has therefore, evolved into an environmental management and assessment tool
Environmental monitoring, Environmental auditing, feasibility studies etc has been adopted for
sustainable development but these did not take environmental cost, public opinion, social and
realistic approach that is technically well suited and well established with the potential to make
critical contributions to sound decision making processes and to equitable and sustainable
development. However, there are huge differences between the EIA system of the developed
the developed countries of the world differs in so many ways from those of the developing
countries. Apart from having its origin in the USA, Nwafor, (2006), notes that, the method of
approach and its appreciation differ significantly from those of the developing countries.
By the 1970s, the environmental movement that began in the 1960s had build up public
awareness about the interactions between the environment and development. As a result of this
public awareness, elected public office holders strive to keep their manifestos by tackling
environmental problems. It was in response to such awareness that President Richard Nixon in
May, 1969 established a president’s Council on Environmental Quality (CEQ) with himself as
Chairman, to implement environmental policy decision, (Nwafor, 2006). The driving force in
environmental policy as well as EIA in the USA as in other developed countries of the world is
their public awareness on the interaction between environment and development. This explains
why the adoption of EIA in developed countries followed very closely. For example, after the
Stockholm conference in 1972, Canada adopted EIA in 1973, Australia in 1974, Western Germany
in 1975 and France in 1976. The approval of European Economic Community (EEC) Directive on
EIA in 1985, made mandatory the enactment of EIA legislation in many European countries. It
should be noted that the UK prior to this directive have a high-developed town and country
planning system in which certain features of EIA were incorporated. The Netherlands adopted EIA
Given the awareness of the interaction between development and environment, and the
negative consequences of industrialization on the global economy, EIA in developed countries has
come to appreciate sub-regional cooperation and trans-boundary EIA. In the light of this, the
United Nations Economic Commission for Europe through its convention on Environmental
18
Impact Assessment in trans-boundary context seeks to encourage the development of bilateral and
Despite the awareness, there are enormous variation between the situation in central and
eastern Europe. According to Donnelly, et al. (1998), some countries here have implemented the
European directive on EIA in readiness for accession to the European Union. Similarly in Latin
America and South Eastern Asia, many countries have developed EIA systems of varying
EIA in developing countries had been challenged by the prevailing socio – economic
circumstances. Alo, (1999) notes that “The paucity of adoption strategies in the developing
planning within the poor GNPs of such nation”. EIA has been adopted in many developing
countries of the world. Colombia in South America was the first to adopt EIA legislation in 1974,
(Alo, 1999). Thailand, Philippines, Rwanda, Botswana, Kenya, Nigeria, Tanzania, Peru, Sri-
Lanka, Argentina, Zimbabwe and others have adopted EIA legislation. (Kerdeman, 2009).
foreign investments which are flowing into developing countries, are based on the exploitation of
the limited natural resources such as mineral, wildlife/forestry, marine resources and others. The
government in most developing countries, do not only canvass foreign investment, but also do
everything to attract them. According to Tundu, (1999), the promotion of private foreign
investment has created fears that putting investors to rigorous and public scrutiny of their projects
on environmental grounds may scare them away, thus depriving the economy of this badly needed
foreign direct investment. Similarly, Kerdeman, (2009) notes that EIA in many developing
19
countries, are often not users – friendly, and are inaccessible, scarcely propose feasible
alternatives, fail to designate major impact as “significant” or offer dubious justification for
selection of the final action. Despite the often already – weak status of many EIAs, many project
The driving force for development projects in most developing countries is the desire for
job creation and eradication of poverty. For these reasons, most government embarked on
development projects without due regard for consequences. The proposal for the construction of
Kafin Zaki dam on the Kumadugu-Yobe basin in North Eastern Nigeria, by the Federal
Government and the Bauchi state government was to create more employment for the people and
boost their economic well being. According to the then governor of Bauchi state, Alhaji Isah
Yuguda, “It is estimated that the project would produce one million tonnes of sugarcane annually,
generate ethanol for fuel and provide over one million new jobs in agro-allied industries such as
rice mills, vegetable oil mills, and cotton ginneries as well as dairy and poultry products' industries.
Therefore, its impact in boosting food production and increasing export earnings is set to be felt
across the north-eastern region, the most improverished geo-political zone in the country and an
area where crop failure due to drought has increased unemployment and poverty to all-time high,”
In pursuant to this goal, the governor undermined the negative consequence of the project and was
bent on its completion. However, controversy over the construction of the dam had engaged
politicians from all divides within the areas that benefit from the Rivers Jama’are and Yobe. Bauchi
State Governor, Isa Yuguda, made several frantic efforts at actualising the dream of constructing
the dam which has the potential of boosting economic activities in parts of the state. His move has
also met stiff resistance from Senator Lawan and Governor Ibrahim Geidam of Yobe State.
(Abubakar,2010).
20
In contrast to the provision of the EIA acts, the Secretary to the Government of the
Federation (SGF), in 2010, Alhaji Mahmud Yayale Ahmed, in support of the dam project made a
categorical statement that the present administration will ensure the completion of the dam before
the end of its tenure. Yayale was reported to have made the promise to the people of Bauchi State
when he led a Federal Government delegation to condole with the state over the death of their
To settle the controversy over the construction of the Kafin Zaki dam in contrast to
Yayale’s position, President Goodluck Jonathan told a delegation of Bauchi State government who
visited the Presidential Villa that he would have to study the report of the EIA before taking a final
decision on whether or not to go ahead with the Kafin-Zaki dam project, (Abubakar, 2010). It is
pertinent to notes that, the President’s referrence to EIA report was to free himself from the danger
The priority of EIA processes in developing countries is not sustainable development rather
it has become a source of revenue to the government and decision makers. For example, Kerdeman,
(2009) opines that Nigeria is one of the greatest violators of EIA regulations due to poor
participation, corruption, and /or down playing of EIA”. She went further to say that with poor
participation, weak civil society, corruption among others, EIA best practices have by and large
been downplayed, ignored and abandoned. Mass poverty, she said, was identified as a factor
The promotion of foreign investment in India has created a weak EIA system in the country.
Kerdeman (2009), notes that even at a functional level, where projects require public consultation
for EIA, there is hardly any evidence that project ever get rejected.In Zimbabwe, the EIA legal
framework does not make provision for public participation. The obligation to do the EIA is on
21
the developer and the environmental management Agency. Developers who are politically
connected have been known to get EIA License without doing any meaningful EIA (Kerdeman,
2009). In Tanzania, according to Tundu, (1999), there are cases of development projects approved
by the government against public opinion. The Rufiji Delta prawn farming remains a reference
point. In most developing countries, the close relationship between leaders and corrupt
businessmen has led political leaders to take decisions which do not consider national interest but
EIA in developing countries is therefore faced with serious challenges and in most cases
has been altered. However, the situation in different countries within the continent varies
considerably. According to Wood, (2003),within Africa, while the South Africa EIA system has
Ghana, as yet EIA is unimportant in Somalia. It was noted that the most conspicuous difference
relates to the fact that the first EIAs to be carried out in developing countries were usually
a widespread indigenous demand for a better environmental protection (Wood, 2003). There are
many examples of EIA being undertaken in developing countries, by no means all as a result of
donor agency pressure (Wood, 2003).These include EIAs in Brazil, Chile, China, Columbia,
Egypt, Ghana, India, Indonesia, Malaysia, Pakistan, the Phillipines, South Africa and many others
(Wood, 2003).
In most states of Nigeria, there are many regulatory bodies for EIA with overlapping
responsibilities.Wood (2003), notes that “EIA functions better when there are specific legal
requirements for its application, where an environmental impact statement is prepared, and where
authorities are accountable for taking its result into consideration in decision–making.With many
22
regulatory bodies, duties are often neglected. Duruigbo, (2002) states that despite the establishment
of the Federal Ministry of Environment in Nigeria, Nigerian laws vests regulatory powers over the
petroleum industry with the Nigerian National Petroleum Corporation (NNPC). This according to
him means that the NNPC is both a developer in partinership with foreign companies and a
The legal basis of EIA systems in most developing countries may be weak and non
mandatory. Besides, in most developing countries, the regulatory bodies are lacking both in status
and efficiency. According to Wood (2003), the organisations responsible for implementing EIA
provision in developing countries are frequently new, lacking in status and political clout and
working in a culture where an absence of information sharing considerably reduces their influence.
He emphsised that it is clearly desirable to put in place not only the legal requirement for EIA but,
sufficient institutional and personnel capacity and resources to implement them effectively.
The compliance of EIA in most developing countries is not satisfactory and often neglects
some impacts. Wood (2003), notes that it is not uncommon for certain impacts to be neglected in
some developing countries EIA report .He sited the example of India EIA regulations, where
Landscape and visual impacts are not included. Similarly,in Nigeria it is the responsibility of the
Federal Ministry of Environment to oversee the conduct of an EIA process by a proponent and the
issuance of an environmental impact certification. while on the other hand, it is the statutory
statements (EIS) are complied. The agency had sealed three tele-communication base stations
belonging to MTN, ZAIN and STARCOMMS in Ilorin, Kwara state in 2013 over non-compliance
with EIA and audit report of the Federal Ministry of Environment (Shittu, 2013). However, there
23
are several telecommunication base stations in many other places across the state with the same
error that have not been sealed by the agency. Similarly, the Federal Ministry of Environment was
found to have given provisionary approval for projects before the completion of EIA.
Inadequate coverage of EIA sytems in most developing countries can be attributed to poor
scoping of impacts. George, (2000a) notes that,where scoping does take place, it is often directed
towards meeting developing countries pollution control requirements, rather than addressing the
full range of potential environmental impacts from a proposed development. Though there is a
specific procedural and sectoral guidelines in Nigeria, only few EIAs are prepared in relation to
them. These are often neglected because most EIA consultants operate independently rather than
using inter-disciplinary teams. World Bank, (1997a) and George, (2000b) notes that few EIAs in
The quality of EIA reports in developing countries and particularly in Nigeria is another
major challenge facing EIA implementation and practice. Ahmad and Wood, (2000) notes that
very few EIA reports have been made available to the public even for training purposes in Egypt.
Similarly, in Kogi, EIA reports are inaccessible to the public. Even during and after the public
display period, many lack access to EIA reports for which they are highly interested. Even when
the reports are on display, in most developing countries, the reports are often very complex and
difficult to comprehend.
Kakonge (2006), notes that “The EIA process loses much of its value if reports are difficult
to comprehend or are not produced in time for those who can understand them to give their
comments.This according to him has been the case in the Niger Delta and it has created mistrust
and suspicion. Duruigbo, (2002), states that community leaders in the Niger Delta still insist that
it is possible for companies to obtain permit and commence oil production without conducting an
24
environmental impact study. He further stated that, vague language and obsolete provisions
weaken the legal framework existing in Nigeria and that, lack of enforcement compounds
faillings. For example ,the section 30, subsection(2) of the EIA Edict in Kogi State, states that
every person who intends to carry out physical development such as manufacturing or industrial
activities in any premises within the state shall prior to the commencement of such activities submit
to KOSEPA an environmental impact assessment report and obtain a certification from the
Agency. Any person who fails to comply with this provision shall be guilty of an offence. This
Besides vague language, in most developing countries, experts are foreign and the few
indigenuos experts are poorly renumerated (Kakonge, 2006). In Nigeria, few EIA indigenous
consultants exist and most state lack one. It is important to note that most consultants in Nigeria
do not apply a multidisciplinary approach to EIA preparation. Wood, (2003), notes that, in many
developing countries EIA reports are written in English, rather than in the native language, and
seldom make concessions to the few lay readers ability to review them. This problem is more
compounded in places like Kogi State where all the industries are located in the rural areas where
only few people understand English language. Kakonge, (2006) states that, most countries in sub-
Saharan Africa have adopted EIA requirements laid out by other countries (especially in the three-
tier categorisation of projects by their likely impact). While it may not be bad to draw on the
in Africa today where there are weaknesses or an absence of environmental quality standards.
African countries should perhaps consider establishing their own environmental quality norms and
by several authors including Clark, (1999) is that “There is a lack of trained human resources and
of financial resources that often lead to the preparation of inadequate and irrelevant EIA reports
in developing countries. George (2000b) notes that environmental conditions in tropical or sub-
tropical areas render many of the environmental assumptions, models, and standards derived in
temperate zones inappropriate. FME, (2010) notes that “Baseline socio-economic and
environmental data are grossly inadequate for effective EIA preparation. Ngeri, (2010) states that
inadequate capacity for the interpretation of environmental impacts and the knowledge of current
global trends on new technology clouds EIA preparation in developing countries and Nigeria in
particular. She further states that the EIA acts in Nigeria is not in tune with the current global
trends since it was last reviewed in 2004, considering the dynamism of environmental issues.
The public in most developing countries are yet to catch the awareness of the importance
of EIA in sustainable development. Kakonge, (2006) opines that the public showed a lack of
appreciation of the role of EIA in development and had insufficient information about proposed
development projects. He said the developer in most cases did not consult the local communities
directly and the public had limited opportunities to play a role in determining the EIA terms of
reference.
For effective public participation in EIA system, Kakonge, (2006) opines that the EIA
process calls for an effective public awareness campaign aimed at empowering people to make
rational and appropriate choices and decisions about development projects that affect them.
On the issue of capacity and personnel development for EIA preparation, in some
developing countries like Ghana, Tunisia and South Africa, institutions and non governmental
organisations (NGO) provide training for EIA development. Damtie and Bayou, (2008) note that
26
in Ghana and Tunisia some tertiarry institutitons provide training on EIA which is run as part of
various environment-related courses. They argued that unless institutions which are designated to
participate in EIA are staffed by capable personnel, the EIA system will be weak and unable to
accomplish the desired goal. The case in Kogi State and most developing countries is rather
pathetic because personnel that make up the EIA regulatory bodies lack expertise and are often
appointed by politicains.
It is clear from the literature that EIA in most Developing Countries have been studied and
reviewed. Kerdman, (2009), examines the challenges of EIA in Tanzania, India and many African
countries, Wood, (2003) looks at the methods and practice of EIA in Developing Countries and
observed enormous challenges; most countries in Africa had a review of their EIA system to meet
up with current Global best practice. The Nigerian EIA system was also reviewed in 2010 to
overcome some of the prevailing challenges like inadequate base-line data, indaquate personnel
capacity for EIA development. During the review, some states like Adamawa, Taraba, Ondo, Ekiti
and Abuja complained seriously on the existence of many regulatory bodies with overlapping
responsibilities in their state which has resulted in low level of compliance with EIA in those states,
(FME, 2010).
In Kogi State, however, the reason(s) for low level of compliance with EIA despite the
state legal framework is yet to be studied. It is on this premise that this study is designed to access
the methods and principles adopted in EIA practice in Kogi State and to suggest ways of improving
The research methodology adopted was basically survey design. The data for this research
work were collected from primary and secondary sources. The primary data were obtained through
interviews conducted using structured questionnaire and field observations. Some of the
information collected include, the number of Federal Development projects in the state, State
development projects and private companies operating in the state. The list of projects that were
established between 1995-2012 which have EIA report in the state and those without it. Other
information like the number and status of the Consultant firm that prepares EIA reports, the
duration for the preparation of the report, the cost of the report and the cost of obtaining an EIA
licence and others. Places like the Federal Ministry of Environment, KOSEPA, the ten companies
with registered EIA system in the state and the state Ministry of Environment and Physical
Planning were visited for the interview. The fieldwork was conducted between April 24th and
September 26th, 2012. For proper administration of the questionnaire, three research assistants
were employed.
Kogi State has twenty one Loca Glovernment Areas as shown in Figure 2. For the purpose
of this research, six local government areas were randomly selected for the interview.These six
Local Government Areas were selected after the preliminary study of EIA in Kogi State. The
preliminary study revealed that the industries that have EIA reports are located in six Local
Government Areas in Kogi State as shown in Figure 3. One hundred and ten copies of the
questionnaire were administered to the public in each of the six Local Government Areas .
28
The questionnaire was reviewed by three research experts from the University of Nigeria
Nsukka who eliminated and reclassified some of the questions. They include Professor I. A. Madu,
Dr. M.C. Obeta, and Dr. T. C. Nzeadibe, all from Department of Geography, University of Nigeria,
Nsukka. The questionnaire was further subjected to pre-test interview to establish the degree of
The study applied a quantitative approach using data collected from questionnaire survey.
There was seperate questionnaire for the regulating agencies in the state and government staff,
29
another one was for project proponents and companies staff and the other one for the public or the
society where the projects are located. In all, three different questionnaires were administered for
The questionnaire for the public was administered in the six local government areas where
there are major industries in the state. These Local Government Areas include Ajaokuta, Ankpa,
Dekina, Kabba/bunu, Lokoja, and Ofu. One hundred and ten copies of questionniares were
administered in each of these Local Government Areas. Each local government area was divided
into districts. The administration of the questionniares was done to reflect the number of districts
in each local government area. The target was that at least one hundred copies will be recovered
from each of the Local Government Area. However, only five hundred and ninety eight copies
were recovered from the six Local Government Areas. Some were not filled and others were not
returned.
The questionniare for the regulating agencies in the state were administered in all the
offices that have regulatory power on EIA in Kogi State.These agencies include, Local government
health department, Area town planning office, Local Government works Department, State
Ministry of Environment and physical planning, Federal Ministry of Environment field office,
State Ministry of works, Kogi State Environmental protection Agency (KOSEPA), Urban and
Regional planning and Kogi State Town Planning office. The administration of questionniares in
these nine(9) offices were done based on the staff strenght of each of the agency. A minimum of
four copies and a maximum of eigth copies were administered. In all, seventy two copies were
The questionniare for the project proponents and company staff were administered to the
major industries located in the six Local Government Areas of the state. The administration was
30
carried out in the following areas. Cement factory at ALO ITOBE, Limestone quarry at ALO
ITOBE, Borehole water project at KABBA, Etisalat Network base station project at KABBA,
Biotic fertilizer company at OJUWO AGBEJI, OFFEJIJI waterfalls, Zuma 828 coal mining at
OKOBO in Ankpa, MTN network Base station at INYOLOGWU Ankpa, West African Ceramics
at Ajaokuta, ZHONG YANG Recycling projet at Ajaokuta. Dangote Cement factory at Obajana,
Limestone quarry at Obajana. Housing Estate at Lokoja. For all the state owned projects, the
relevant agencies in control like the state Ministry of works, State Ministry of Commerce and
Industry, State Water Board, Urban and Regional Planning Board were interviewed. In all, two
copies of the questionniare each were administered for both private and public projects in the
selected areas. In summary, for Type I questionnaire (Public) six hundred and sixty (660) copies
were administered, for Type II questionnaire (Regulators) seventy-two (72) copies were
administered and for Type III questionnaire (Project proponents) thirty-four (34) copies were
administered. A total of seven hundred and sixty-six copies were administered in all.
Interview was carried out on the origin, current practice and the level of compliance with
EIA in the state in the following estabilishment. RUWASA (Rural water sanitation agency),
KOSEPA (Kogi State Environmental Protection Agency), Kogi State Ministry of Environment
and Physical planning, Kogi State Town Planning Head office and Area offices, Kogi State Urban
and Regional Planning Board, Kogi State Ministry of Works and the village Heads of Okobo,
Obajana and the district Heads of Enjema district in Ankpa local government area council.
Secondary data used for this study were obtained from published articles, library, journals,
Newspapers, EIA draft and final copies found with key institutions responsible for the
31
implementation of EIA like the Federal Ministry of Environment, KOSEPA, Kogi State Ministry
of Environment and Physical Planning and other relevant agences. Some of the existing EIA
reports in the state were examined and reviewed to see their level of compliance with the
guidelines. Textbooks and magazines, Decree and government gazette and the Internet were as
The data generated from both primary and secondary sources were subjected to statistical
analysis like mean, frequency and correlation.These statistical techniques were used to determine
the frequency of a particular variable as a challenge to EIA delivery in Kogi State based on the
result from the questionnaire. The Federal Government procedural guidelines on the preparation
of EIA and the decree 30 of 2004 on EIA was used to study the relationship that exist between the
two EIA policy. Each items in the procedural guideline like public participation, terms of reference
, mitigating measures, strategy for alternatives and others were used for this purpose.
The response from the questionniares were coded. Each questionniare was divided into four
sections. Section A was for the Bio- data of the respondents. Section B was for the level of
awareness of EIA in Kogi State while section C and D were for factors affecting EIA and the level
of compliance of EIA respectively.The coding therefore reflects all the variables for each section.
The percentage of each variable was calculated based on the frequency values obtained
from our checklist in each section of the questionniare. The responses were assessed on the likert
five point response continuum scale. The strongly Agreed was rated 5, Agreed was rated 4,
Undecided was rated 3, Disagreed was rated 2, Strongly disagreed was rated 1.The sum of all the
Statistical Packages for Social Sciences (SPSS) version 19 was used for the analysis. The
programme extracted the rated values for each of the variables and trasnforms them to MEAN
which was further used in the Analysis of Variance, Correlation and Principal Component
Analysis.
Principal Component Analysis was used to extract the factors that have the most signifficant
This research project is divided into six chapters starting from the introduction to findings,
conclusions and recommendations.
CHAPTER ONE: INTRODUCTION
This chapter features the background of the study; the statement of the research problem,
aim and objectives of the study and the study area, Literature review, Research methodology and
the plan of the project were covered in this chapter.
CHAPTER TWO
1995.The Edict made the implementation of EIA mandatory through its provision in Section 30(2)
for all project proponents in the State. According to the state legal framework, a list of projects
and activities requiring EIA report were published and the content of Environmental Impact
Assessment report were clearly spelt out in section 13 subsection (2) of Edict No.3 of 1995.
Some of these activities include; Land development scheme covering an area of 50 hectares
or more to bring forest land into Agricultural production, Wood/Timber processing, Saw milling,
Construction of large fish pond, Conversion of hill forest covering an area of 10 hectares,
Conversion of forestland to other uses within the catchment areas of reservoirs, Logging covering
an area of 50 hectares or more, Estate development requiring the acquisition of land of 5 hectares
and above, Any development along the Bank of River Niger and River Benue, Petrol filling station,
Quarry sites for aggregate, marble, limestone etc, Manufacturing or processing industry, Road
development through a virgin land, Abattoirs and the Construction of 3 storey buildings and
above.
The highest body charged with the responsibility of planning and management of the
environment in the state is the Kogi State Environmental Protection Agency (KOSEPA). The
agency exercise both advisory and executive power on environmental matters in the state. The
governing council on the environment at the State level consist of the Secretary to the State
government as the Chairman, Honourable Commissioners for Agriculture and Natural Resources,
35
Works, Transport and Housing, Health and Social Development, Finance and Economic Planning,
Commerce and Industry, Justice, and Education. Other members include the Directors-General for
Department of Lands, Surveys and Physical Development, General Manager of KOSEPA and two
people from the private sector who have distinguished themselves in environmental matters. The
At the Local Government levels, there exist the Committee on Environmental Protection
(CEP). The committee consist of the Chairman of the Council as Chairman. Council Secretary
and other persons with equivalent power as members. The CEP carry out the mandate of KOSEPA
at the Local Government level. Administratively, KOSEPA consist of a General Manager who
oversees all the activities of the Agency. The KOSEPA has four (4) Departments which include,
Monitoring and Enforcement, Finance and Administration. The four Heads of Department and the
1. To formulate and enforce policies and programmes which aim at protecting the
environment of the state. Such policies, regulations and standards to be formulated include
those for solid waste collection and disposal, drainage, and liquid waste management, air
2. To liaise with and co-ordinate the activities of all agencies in the state connected with
environmental and ecological matters and to render advisory services and support to all
Local Governments in the state in areas of flooding and erosion control, solid waste
ecological matters and mobilize the inhabitants of all areas in the state for effective
observance of environmental rules and guidelines for the promotion of a healthy and safe
environment.
4. To monitor sources of toxic pollution in the air, land and water and initiate measures to
ensure pollution free air, land and water throughout the state.
Before KOSEPA was established in 1995, there was an Environmental Sanitation Task
Force in the state. When KOSEPA was established, the edict establishing the Task Force on
Products etc.
The edict gave power to KOSEPA officials to seal off premises where activities that
contravenes its laws are carried out and demolish or remove any construction or structure that does
37
not comply with environmental laws in the state. They were also vested with the power to
The penalty stipulated in the edict include a maximum fine of N1, 000, 000.00 (one million
naira) for illegal toxic or radioactive waste disposal and N500, 000 (five hundred thousand naira)
for non-compliance with state environmental standard and rules. The state also has the power to
imprison Managers and Directors of firms for not more than ten (10) years if they are found to aid
Furthermore, the edict requires an Environmental Impact Assessment Report for at least
v. An identification of the likely or potential impact of the proposed activities and the
alternatives,including the direct or indirect, cumulative,short term and long term effects.
viii. An indication of whether the environment of any other state or Local Government Area or
an area outside Nigeria is likely to be affected by the proposed activities or its alternatives.
ix. A brief and non technical summary of the information provided under items i to vii above.
38
the State include, Ministry of Health, Ministry of Works and Housing, Ministry of Agriculture
and Natural Resources, Urban and Rural Development Authority, Kogi State Water Cooperation
Since the enactment of Edict No 3 of 1995, several project proponents had embarked on
EIA. The level of compliance was observed to be on the increase since 1995. However, the
approach in some cases varies greatly from the National guidelines. The list of twenty seven (27)
development projects with EIA report in the State is contained in Table 2. Table 3 contains a list
of twelve (12) development projects in the State established between 1995-2012 that have no EIA
report. Suprisingly, there are large number of development projects undertaken by the State
Government between1995-2012 without EIA report. Some of the examples include the
Confluence Beach Hotel at Lokoja, Kogi State Fertilizer Company at Anyigba and several road
projects, several borehole projects and several rural electrification projects embarked upon in the
state during the period under study.There are also cases of EIA reports that were prepared and
approved by the State Ministry of Environment.The list of six (6) such development projects is
contained in Table 4.
Table 2: List of Development Projects in Kogi State that was established between 1995 and
2012 with EIA reports
S/N NAME LOCATION PRODUCT
1 Ceramic Industry Oguro Village Ajaokuta Ceramic processing
2 VEE Network Nig. Ltd. Lokoja GSM mobile phone
3 Korean consortium, Ajaokuta, Abuja-Kaduna-Kano Natural Gas Pipeline
4 Nigerian Gas Company Ltd. Geregu Junction Gas supply
5 330KV Transmission line G/Lada-Lokoja-Ajaokuta Electric project.
6 Dangote PLC Obajana Quarry of Limestone
7 Dangote PLC Obajana Cement factory
8 Dangote PLC Obajana Packing lots for vehicles
9 Dangote PLC Ajaokuta-Obajana Gas pipeline
39
Table 3: List of Development Projects established between 1995 and 2012 without EIA
report.
1 Quest II Felele-Lokoja Lime Industry
2 Jakura Marble Industry Lokoja Marble smelting
3 Nimco Feldspar Lokoja Feldspar & Quartz project
4 Marks farms Osara Large scale farming
5 NNPC Mega Station Felele and other places Filling station
6 Confluence beach hotel Lokoja Cafeteria
7 Citizen Petroleum Okene Petrol station
8 Conoil petroleum Okene Petrol station
9 Royiza petroleum Okene Petrol station
10 Total petroleum Ankpa Petrol station
11 Oando petroleum Ankpa Petrol station
12. Lokoja international market. Lokoja. Commercial centre.
Source: Kogi State Environmental Protection Agency (2012).
40
Table 4: List of Development Projects established between (1995 – 2012) that have EIA
which was processed and concluded in the state.
S/N NAME LOCATION PRODUCT
1 Sugar company Ibaji Sugar processing
2 AOB Oil Ventures Ltd Ganaja Road Lokoja Petrol station
3 K Hasarai and Sons Nig. Ltd Ganaja Road Lokoja Petrol station
4 Alternative Impression Nig. Ltd Lokoja Petrol station
5 SIBB Oil Services Nig. Ltd. Lokoja Petrol station
6 SOPPAVIC Nig. Ltd. Ganaja Petrol station
Source: Kogi State Environmental Protection Agency (2012).
The EIA process is the various stages a project undergoes from project proposal to approval
and certification. The FEPA procedural guideline shows nine (9) steps from the conception of the
Project proposal
Screening
Scoping
EIA study
Panel review
Decision making
Monitoring and
Auditing
The project proponents initiate the process through an application to the Federal Ministry of
Environment. A notification form is then completed with all necessary information on the
proposal.
41
project’s category under the mandatory study list. Where there are no adverse effects, the EIA is
issued and permission may be given with appropriate mitigation and monitoring measures. But
where adverse effects exist, the IEE report is sent to the proponent for scoping and preparation of
Terms of Referrence (ToR) and with the ToR the EIA study is carried out using EIA consultants
after which an EIA draft report is prepared and sent to the Ministry.
The Ministry is expected to conclude evaluation of the draft report and set out the review
method which is communicated to the proponent in writting. The review methods always take the
following form, in-house review, panel review public review and mediation.
The public review is published in any of the national dailies for wider coverage and the
EIA draft copy is placed on display for at least three weeks to allow comments from the public
and stakeholders.
The final EIA report is then prepared with answers to review comments and this is
submitted within six months to the responsible officer. Within one month of the receipt of an
acceptable EIA final report, the committee gives approval for EIS followed by EIA
certificate/licence.
The proponent is now free to commence his project with a specified condition. The
progress of the project is monitored to ensure compliance with all the conditions and mitigation
measures.
Environmental audit is carried out periodically to assess both positive and negative impact
of the project. All these process are prescribed in the procedural guidelines prepared by FEPA on
EIA. A good EIA must undergo all the steps as enumerated above. However, in Kogi state, the
Town Planning EIA is more popular and do not operate on a specific guideline. The state
42
government does not give an EIA permit. It is only required of a project proponent to attach an
EIA report to the proposal of their project when seeking for approval from the Urban and Regional
Planning Board. The Board assume that any registered Town Planner is qualified to prepare an
EIA. It is therefore the duty of the project proponent to locate a registered Town Planner to prepare
was analysed in three categories. Table 5, contain the Frequency distribution of the level of
awareness of EIA by the public in the state. Table 6 shows the level of awareness of the
Government staff and Regulatory Agencies and Table 7 reveals the level of awareness of the
Fifteen checklists were used to analyse the level of awareness of each of the category examined.
To avoid concealing of information, some of the questions vary from one respondent to the other
while similar questions were used for the three categories in some cases. The analysis of the results
obtained reflects the awareness level of the three categories of respondents in Kogi State on
The awareness level was analysed based on the frequency values obtained from our
checklists. This enabled us to obtain the mean scores and the freqency counts of the response
values whose sum total is fifteen (15) for every variable. The response was assessed on the Likert
five point response continuum scale. The Strongly Agreed was rated 5, Agreed 4, Undecided 3,
Disagree 2 and Strongly Disagree 1. The sum of all the ratings gave us a total of fifteen points
which was used to analyse the mean score for each variable. Any mean above 4.5 is very high, 3.5
and above is high, 3.4-2.5 express uncertainty and any mean below 2.5 is poor. This appproach
43
was adopted by (SWAP, 2003, Ubachukwu, 2010,) in the analysis of awareness level and it
State) indicates that 76.4% of the public in Kogi State are not aware of Environmental Impact
Assessment in the state, though 2.2% of the respondents were uncertain and unwilling to give an
opinion on the variable. 24.4% of the public agreed that they are aware of EIA in the state. With a
mean of 2.10, it is concluded that the level of awareness of EIA in Kogi State by the public is low
and unsatisfactory.
Item B2 (There are industries and development project in your locality) indicate that 59.7%
of the public agreed there are industries in their locality. 3.2% were uncertain and indecicive, while
37% disagreed with the variable. With a mean of 3.42, it is concluded that there are reasonable
number of industries in Kogi State that requires an EIA. B3 (All the development projects in the
area have an EIA permit for the project) result indicates that 57.7% of the public disagreed that the
industries and development projects have Environmental Impact Assessment Permit. 31.7% of the
public are uncertain about the variable which only 10.7% agreed with the variable. With a mean
of 2.10 it is concluded that the level at which development projects comply with EIA in the state
is low. The result also indicate that the Kogi State government allows industries and development
For B4 (None of the development project in the Area has an EIA permit) result indicate
that 43.9% of the public disagreed with the variable, 32.8% of the public were uncertain and
unwilling to give an opinion on the variable. However, 22.9% of the public agreed that only few
development projects in the area have an EIA permit. With a mean of 2.50 it is concluded that the
number of industries and development projects in the state that have an EIA permit is low and not
44
reasonable enough. B5 (Only few of the development projects in the state have an EIA permit)
result shows clearly that 9.6% of the public disagreed with the variable. 43.1% of the public were
indecisive on the variable. However, 47.1% of the public agreed that only few of the development
projects in the area have an EIA permit. Judging from the responses on variable B3,B4 and B5, it
is very clear that most industries and development projects in the state have no regard for
For B6 (Many EIA public review has been held in your area), the result shows that 65.9%
of the public disagreed that public review on EIA are held in the very area where the project is to
be located. Though 6.2% were not willing to give an opinion on the variable, 27.5% agree that
EIA public review are held in the locality where development projects are sited in Kogi State. With
a mean of 2.18 it is concluded that EIA public review are not held in the area where the
development project is to be sited. This also indicates lack of complaince with EIA Acts. Further
inquiries during the field work shows that the EIA public review were held at Lokoja, the state
capital and this makes it very impossible for the members of the public from the affected area to
attend the public review and bare their minds on the project. B7 (The public review does not
necessarily involve the people from the area where the project was to be sited) shows that 83% of
the public agreed that the public review does not necessarily involve members of the public from
the very area where the project is located. With a mean of 4.31, we conclude that the EIA public
review in Kogi State does not necessarily involve the people from the area where the project is to
be sited. This is a serious contravention of the EIA law which strongly emphasised the involvment
of stakeholders including local host communities and public participation in EIApublic review
process.
46
On B8 (People from the locality do not like to attend public review on EIA even when they
are invited), the result shows that 76.7% of the public disagreed with the variable. 20.8% of the
public agreed with the variable, 2.6% are uncertain about the variable. With a mean of 1.68, it is
concluded that people from the area are ready and willing to attend EIA public review when invited
without paying the cost of attending. For B9 (Only the community heads and highly placed
individuals are invited for EIA public review), the result indicates that 84.9% agreed that only
community heads and highly placed individuals in the society are invited for EIA public review.
With a mean of 4.43, there is a strong indication that only community heads and highly placed
individuals in the locality are invited for EIA public review. Further inquiries during the fieldwork
revealed that the community heads and those that are often invited by the project proponents for
EIA public review are often given free transportation to the venue and entertainment during the
review. This always affects their attitude and disposition towards the EIA public review.
B10 (Members of the public are often given the opportunity to give their opinion on the
EIA of the project in their area during public review) a mean score of 2.77 indicates that members
of the public are not given opportunity to air their opinion on the EIA of the project in their area
during public review. Similarly during fieldwork, the youths of Okobo of Enjema district in Ankpa
local government area of Kogi State where Goldsfield coal mining company is located complained
that though their youth leader was invited for the public review which took place in Lokoja, all
their request, concerns, disagreements and suggestions on the EIA were not considered at all.
They complained further that they have no access to the copy of the EIA document.
For B11 (members of the public need more enlightenment on EIA) the result shows that
89% of the public agreed that members of the public in Kogi State need enlightenment on
47
Environmental Impact Assessment. With a mean of 4.5, there is a strong indication that the public
B12 (There is no relevance of EIA to development projects in the area) the result shows
that 85.8% of the public disagree with the variable. Though 3.0% were uncertain and indecisive,
only 11.2% of the public agree with the variable. With a mean of 1.54 there is a strong indication
B13 (The project proponents always show genuine readiness to accommodate the
complaints and suggestions of the public) the result shows that 60% of the public disagreed with
the variable. A mean of 2.62 is low or poor to accept the variable. This result further revealed that
the project proponents do not show gueniune readiness to accommodate the complaints and
suggestions of the public. To further justify this result, despite the strong contention raised by the
project Igala in the National Dailies on the EIA of the Goldsfield coal mining at Okobo and other
parts of Igala land, the company still went ahead and commenced their project without regard to
B14 (The project proponents always run away from organizing public review because of
the cost involved). result revealed that 86.3% of the public agreed with the variable. With a mean
of 4.68, it is concluded that project proponents in Kogi State run away from organising public
review because of the cost implications even though such cost is assumed to be built in the EIA
budget..
B15 (The public has never raised any serious contention during EIA public review), the
result shows that 63.1% of the public agreed that the public has not raised any serious contention
during EIA public review in Kogi State. A mean of 3.68 indicates that the public seldom raised
contention during EIA public review and this is because the project proponent besides selecting
48
those to attend the review also sponsor them by paying for the cost of their transportation and
refreshment.
Further studies conducted in the area on the awareness level of EIA in Kogi State can be
seen in Table 6 and Table 7. Table 6 contain the frequency distribution of response from the EIA
Regulating Agencies and government staff while Table 7 contain those from projects proponents
Adebola (2012) in an interview during the field work conducted in Kabba, stated that both
the public and the government in Kogi State care less about EIA. He gave an example of a surface
well serving a particular household in Kajola, Kabba which dried up as a result of the drilling of a
borehole which was approved by the state .This resulted into a conflict between the owners of the
well and the owner of the borehole. He explained that if an Environmental Impact Assessment for
the borehole project was conducted, the effect of it on the well in the area would have been known
and solutions would have been proffered before the drilling of the borehole.
Similarly, the Head of Works Department of Kabba/ bunu Local Government Area,
Mallam Mohammed in an interview, said it is not clear what the government is doing on EIA in
the state. He gave an example of an EIA document forwarded to his office by Etisalat Network
provider for a Base Station in the area. He explained further that the document was very scanty
and looks more like an extraction. He said that beyond sending the document to him, he was never
In Table 6, B1 (Environmental Impact Assessment is known to all the staff in your office.)
has a mean score of 3.76 indicating that significant number (75.2%)of the Regulators are aware of
Environmental Impact Assessment in the state. Since the Regulators in this category are in one
way or the other involved directly in EIA regulation in their varous offices, the result is not out of
place. B2 (There exist an EIA report for all the development projects embarked upon by individuals
and governments in the state), result indicate that 79.23% of the regulators disagreed with the
variable. 11.32% were uncertain and unwilling to express their opinion on the variable. Only
9.54% of the regulators agreed with the variable. With a mean of 2.19 it is concluded that the
number of projects with EIA report existing in the state is not significant enough. It shows that a
good number of development projects executed in the state by individuals and government do not
have EIA report. B3 (EIA reports are recieved, screened and approved regularly in your office).
With a mean score of 2.9 there is an indication that EIA reports are not prepared regularly in the
state. The mean score (2.18) for B4 (EIA take a long period of time to get approval from the
government), indicates that EIA approval does not take a long time to obtain from government in
Kogi State. Result shows a mean of 2.18 indicating that EIA does not take a reasonable time before
getting approval from the Government. Further enquiries during fieldwork revealed that most EIA
documents in the state does not follow the National guidelines. Some of the EIA docments were
processed and approved in the state without being refferred to the Federal Ministry of Environment
for approval. Table 3 contains some examples of projects with such EIA report. Besides, the EIA
policy in the state does not require any license or permit from the State government. The project
proponent is at liberty to choose any registered Town planner to prepare an EIA for him. With the
Town Planning seal, the EIA document is considered authentic. B5 (There are more than one
agency regulating EIA in Kogi State), result indicates that 86.01% of the regulators which
51
constitutes mainly Government staff working in the various regulating Agencies agreed with the
variable. The mean score is 4.29 and with this, we conclude that there are more than one agency
regulating EIA in Kogi state. It was observed from the fieldwork that over four agencies regulate
EIA in the state. Some of these agencies include the State Ministry of Environment, Federal
Ministry of Environment, Kogi State Environmental Protection Agency, Kogi Town planning
Board and others. B6 (EIA is prepared regularly and submitted for approval in Kogi State) has a
mean score of 3 19. The result is an expression of uncertainty among the regulators.This is because
the Town Planning EIA which is popular in the State is prepared and submitted regularly without
any recourse to the Federal procedural guideline.On the other hand, the Environment EIA is not
prepared regularly in the state. The result of B7 (Members of the public are very much aware of
EIA in Kogi State), shows that 15.08% of the regulators agreed with the variable.3.77% were
uncertain and undecisive, while 81.12% disagreed with the variable. With a mean of 2.28 we
conclude that members of the public in the study area are not very much aware of EIA in the state
B8 (members of the public need more enlightenment on EIA in Kogi State), with a mean
score of 4.81, there is indication that large number of the regulators agreed that members of the
public need more enlightenment on EIA. This result strongly agreed with the response of the public
Item B9 (Our Agency has done a lot to improve public awareness on EIA in Kogi State),
has a mean score of 2.77, indicating that 60.37% of the regulators disagreed with the variable.
This shows that all the Agencies regulating EIA in Kogi State have done little to improve public
State), 96.22% of the regulators agreed to the variable. With a mean of 4.69, the result show a
strong acceptance of the relevance of EIA to sustainable environmental management. B11 (There
are institutions across the state where EIA specialists are trained) .Rresult shows that 83.01%
disagreed with the variable. With a mean of 1.57, we conclude that there are no institution in the
state where EIA specialists are trained. For B12 (The state government is strongly enforcing EIA
in Kogi State), result shows that 77.35% of the regulators disagreed with the variable. the mean
score is 2.40 which show that the State Government is not enforcing EIA in the State. Our
observation from the fieldwork revealed that there are quite a good number of government projects
in the state without an EIA report. Similarly, the state government was found to have
commissioned many private development projects without EIA. For example The Confluence
Beach Hotel, Kogi State Biotic Fertilizer company and others were commissionned without EIA
permit.
B13 (All the Local Government Area has been empowered to enforce and monitor projects
to ensure strong compliance with EIA) indicates that 75.46% of the regulators disagreed with the
variable. The mean score is 1.87. It was observed that most local government council are not aware
of the provision of the Committee on the Environmenment as contained in the Edict, no 3 of 1995.
For example, the Liaison officer 1 for Ankpa and Lokoja local governments declined responding
to our interview claiming that it is the Environmental Health officer of the Council that has such
mandate. Meanwhile, the Edict provided that the Liaison Officer 1 of the Council is the Secretary
of the Committee on the Environment. This shows that the awareness of EIA is very low in the
state.
53
The result of B14 (There is a strong political will on EIA by the Government of the state),
shows that 82.92% of the regulators disagreed with the variable. With a mean of 1.64 we conclude
that there is no strong political will on EIA by the state Government. B15 (The public is not ready
to incoporate EIA policies into their projects in Kogi state) result indicates that 67.91% of the
regulators agreed with the variable. The mean score is 3.68 showing that the public in the Kogi
State are not ready to incorporate EIA policies into their projects according to the view of the
Regulating Agencies.
Table 7, shows the Frequency Distribution of Responses from project proponents and
Kogi State) has a mean score of 3.99 indicating that most project proponents in the state have heard
of EIA. B2 (It takes this office a long period to obtain EIA permit from the Government) has a
mean score of 3.01 showing that 52.51% of the project proponents agree that it takes a long period
to obtain EIA permit from the Government. The result indicates uncertainty from the respondents.
B3 (Because of the long time it takes to obtain an EIA permit, we normally commence
development project long before the permit is released) indicate a mean score is 3.08. The result
shows that 51.88% of the project proponents agreed that they commence their development project
long before the approval of the EIA permit. This is a serious contravention of the EIA Law. Our
observation from the fieldwork revealed that the Federal Ministry of Environment granted Dangote
Plc a provisional license to commence a project in the State while the EIA process was still
ongoing. Similarly,the Goldfeild coal mining company at Okobo in Ankpa local government of
the state commenced their operation long before the EIA public review was held.
B4 (The EIA for your project was approved long before the commencement of the project)
has a mean score of 1.96 indicating that 69.55% of the project proponents disagreed with the
variable. In other words, most of the company commenced their project before the approval of the
55
EIA. For B5 (The demand for EIA permit by the institutions that grants the company loan to start
the project was a Pre-condition that cannot be avoided) with a mean score of 3.69, the result shows
For item B6 (There are more than one office regulating EIA in Kogi State) , result shows
that 73.91% of the project proponents agreed that there are more than one office regulating EIA in
B7 (All the EIA regulating Agencies in Kogi State have overlapping functions), result
shows that 64.9% of the project proponents agreed that all the EIA regulating agencies have
overlapping functions. It was noted from the fieldwork that beside having overlapping
functions,there is a kind of scramble for who handles EIA in the state to the extent that some of
the regulatory agencies do avoid attending EIA public review because of the feeling that they were
For B8 (Project proponents are unduly delayed in the process of trying to obtain an EIA
approval), the mean score is 3.30. The result shows that 56.51% of the project proponents agreed
that they were unnecessarily delayed in the process of trying to get EIA permit. B9 (Proponents
are often discouraged from undertaking EIA because of Funding Regulating Agencies), has a mean
score of 3.43. The result indicates that 52.07% agreed with the variable. Our finding from interview
during the fieldwork revealed that it is difficult for the project proponents to adequately mobilise
all the EIA regulating agencies financially and until that is done, the EIA process cannot run
smoothly. B10 (There is always apathy on the part of stakeholders in the EIA process), result
expressed uncertainty from the respondents as 86.95% of the project proponents were not willing
to give their opinion on the variable. B11(Project proponent often prefer to tip EIA regulating
officers in order to get the approval for their project within a short time), result indicates
56
uncertainty from the project proponents as 69.56% of the respondents declined giving information
on the variable.
B12 (Project proponents are compelled by law to prepare EIA at all cost in Kogi State),
has a mean score of 3.17.The result indicates uncertainty from the respondents. B13 (EIA is of no
relevance to the growth of your company) with a mean score of 2.56 the project proponents
accepted that EIA of relevance to the growth and development of their project. B14 (The only
relevance of EIA to your company is just to satisfy the donor agency in order to obtain loan), result
indicates uncertainty as 26% of the project proponents were undecided and unwilling to give their
opinions on the variable. For B15 (Huge sum of money is spent on processing EIA in Kogi State)
the mean score is 1.86, indicating that 82.5% of the project proponents who are project proponents
and company staff disagreed that huge sum of money is spent in processing EIA in Kogi state.
From an interview with the Director, Town Planning Board, Kogi State, we learnt that the
Board is not responsible for giving EIA permit in the state. He further stated that any Registered
Town Planner is very qualified to give EIA permit in Kogi State. In addition to that, he said the
cost of an EIA permit in Kogi State depends largely on the Town Planner concerned and the
bargaining power of the Project proponent. He added that the government of Kogi State does not
100
90
80
70
60
Percentage %
50
40
30
20
10
0
Public Proponent Regulators
of the three categories of the respondents. The first item on the three questionnaires are the same
The awareness increases from the public to the project proponent and the regulators. Only
21.4% of the public agree they are aware of EIA in Kogi State. 82.6% of the project proponent
agreed they are aware of EIA while 90% of the staff of the regulating Agencies agreed they are
aware of EIA. The percentage is high because, since they must come to hear of it either as a
requirement for the donor agency to grant them loan or as a prerequisite for the registration of their
company. The regulating agencies have the law, the mandate and the enforcement whether they
understand it in full or not, the EIA is ever before them. The low level of awareness by the public
in Kogi State poses a big challenge to EIA in the state and disagree with the opinion of Nwafor
(2006) which states that the driving force in environmental policy as well as EIA in the USA as in
other developed countries of the world is their public awareness on the interaction between
environment and development. With low public awareness, it is difficult to achieve the objectives
of EIA.
58
Our findings, on the current practice of EIA in Kogi State shows there are many EIA
We also found out that any registered Town Planner is qualified to prepare EIA.
They operate a seperate law regulating EIA beside the Federal Government procedural
There is serious confusion in the operation of the three EIA systems in the state. The Town
Planning EIA that seems more popular lack specific quidelines for operation.
The level of compliance of development project with EIA (according to our finding) is
seen to be high with private projects than public project. There was no record of any state
project with a comprehensive EIA. The EIA for the dredging of the river Niger was the
only EIA for Federal projects in the state. However almost all the multi national projects
CHAPTER THREE
1. The use of responses from the Public, project proponents and Government staff as contained
in the three categories of questionnaire was used to explain the level of compliance.
From questionnaire I, (response from the public) Item D1, Table 8 (Kogi State operates a
seperate law on EIA apart from the national guideline), result shows that 80.5% of the public in
Kogi State agreed with the variable. With a mean of 4.18 we conclude that Kogi State operates a
seperate law different from the National guidelines on Environmental Impact Assessment. The
edict no.3 of 1995 on EIA differs in many ways from the Federal Government policy on EIA. D2
(All the Local Government in the State has the power to give EIA permit), 62.9% of the
respondents disagreed with the variable indicating that local governments in the state does not
have power to give EIA permit. The mean score is 2.17, which is very low for us to accept the
variable. However, from the fieldwork we noted that the Local Government’s Department of
Environmental health is vested with the power of enforcing EIA policy in the State. D3 (The State
Ministry of Environment always organise awareness programs to educate the public on EIA),
result shows that 78.2% of the respondents disagreed with the variable. With a mean of 1.38, it is
60
concluded that the State Government is yet to start organising awareness programs on EIA for the
public. The result also indicates that the public in Kogi State is not well informed about EIA and
For variable D4 (The State Ministry of Environment strongly enforce EIA in the State),
result indicates that 78.3% of the respondents disagreed with the variable. A mean of 1.79 is low
for us to accept the variable. The enforcement of EIA in the State is very low because it was
observed during our fieldwork that though the State EIA Edict provided that petroleum pumping
station requires an EIA report, we discover that many of them even within the State Capital Lokoja,
does not have an EIA permit. For instance, a petroleum service station shares boundary with a
motor park at Ganaja junction which is ever busy with travellers and business people. This should
never be if the EIA regulators are actually enforcing the EIA policy . D5 (EIA has been made
mandatory for project proponents in the State in all cases) The mean score is 1.94 which is very
low and indicates that EIA has not been made mandatory for development projects in all cases.
Though the Government policy on EIA provided that EIA is mandatory for development project,
our finding during fieldwork shows that there are many Government owned projects across the
State without an EIA report. For D6 (The State Guidelines on EIA differs in many ways from the
Federal proceedural guidelines) , 85.6% of the respondents agreed that the State guidelines on EIA
differs in many ways from the Federal proceedural guidelines. With a mean of 3.91 we accept the
variable. Similarly, D7 (The State Ministry of Envinronment and the Federal Ministry of
Environment operate the same guidelines on EIA proceedure), 70.7% of the public that were
interviewed disagreed with the variable. The mean score is 2.06 which is low for us to accept the
variable.
61
For D8 (There are many EIA reports in the State without approval from the Federal
Ministry of Environment ), the result shows that 79.9% of the respondents agreed with the variable.
With a mean of 4.33 we strongly accept that not all EIA report in the State have approval from the
development projects with EIA because the EIA act emphasize that license should be obtianed
from the Federal Ministry of Environment at the completion of each EIA process before the
commencement of any development. This is not the case with Kogi State according to these results.
For D9 (There are no cases of EIA being rejected or disapproved in Kogi State), has a mean score
of 3.41 which is an indication of uncertainty amoung the respondents. D10 (The public has no
access to copies of EIA reports), result shows that 77.4% of the public agreed with the variable.
63
With a mean score of 3.93 we accept that the public in Kogi State do not have access to EIA
reports. Since they do not have access to the EIA document, it is difficult for them to know what
The result for D11, (There are some Institutions and Agencies in the Sate that train people
on the best way to operate EIA in the State), shows that 74.6% of the public disagreed with the
variable. A mean score of 1.83 is too low for us to accept the variable. D12 (The large number of
Agencies regulating EIA with overlapping responsibilties in the State has further advanced EIA in
the State) has a mean score of 1.70 which is low to accept the variable. In summary, 75% of the
public were of the view that a large number of Agencies regulating EIA in the state does not
For D13 (The large number of Agencies regulating EIA with overlapping responsibilties
in the State seems to confuse and discourage project proponents in carrying out EIA), result
indicates that 82.4% of the public agreed with the variable. With a mean score of 4.38 we conclude
that a large number of regulating Agencies with overlapping responsibilities often confuse and
discourage project proponents in the State. For D14 ( The emphasis to do EIA in the State is
mostly on multinational projects) the result indicate that 78.3% of the public agreed with the
variable. The mean score is 4.31 indicating that the emphasise to carry out Environmental Impact
For D15(EIA reports has been adopted as sound tool for decision making by the State
Government in environmental matters), result shows that 69.7% of the respondents disagree with
the variable. This indicates that 69.7% of the public in Kogi State are of the opinion that, EIA has
not been adopted as a tool for decision making in Kogi State. With a mean score of 2.6 we
concluded there is low compliance of development projects with EIA provisions in the State.
64
Variable D16 (The State Government is yet to adopt EIA as a tool for decision making policy),
result indicates that 73.7% of the public agree with the variable meaning that 73.7% of the
respondents are of the opinion that Kogi State Government is yet to adopt EIA as tool for decision
For D17 (The State is yet to establish an Agency to punish project proponents who fail to
comply with EIA regulations), result indicates that 82.9% of the public agreed with the variable
meaning that the government is yet to establish an Agency vested with the responsibility of
punishing EIA defaulters. With a mean score of 4.33, we conclude that EIA enforcement is lacking
in Kogi State. For variable D18 (The State is very strict on EIA mandates and had revoked the
license of those conpanies that failed to comply with EIA), result shows that 69.0% of the public
disagreed with the variable. With a mean score of 2.06 we conclude that the State Government is
not strict on EIA mandates.This also indicate a weak and low level of compliance with EIA .
The result for D19 (All the State and Federal projects in the State have an EIA permit) has
a mean score of 2.40 which indicates that not all the state and Federal projects in the State have
EIA permit. For D20 (The government does not commission any project without an approved EIA
permit), result indicates that 72% of the public disagreed with the variable. The mean score of 1.92
The Frequency distribution of responses from questionniare (2) is the response from the
questionnaire administered on the Government Staff who served mainly in Agencies that are
D1 (Kogi State operates a seperate law regulating EIA apart from the National guideline
on EIA), result indicates that 92.43% of the respondents disagreed with the variable. The mean
score is 2.07 showing that Kogi State does not operate a seperate law apart from the National
guideline on EIA. However, there is a clear evidence on the existence of Edict no 3 of 1995 on
EIA. The Edict contain the principles and policies of the State on EIA matters. For D2 (State
Ministry of Environment forward all EIA reports to the Federal ministry of Environment for
approval ) the mean is 1.98 indicating that the State Ministry of Environment do not usually
forward EIA reports to the Federal Ministry of Environment before giving approval. This is serious
contravention of the EIA act. However, from the fieldwork conducted in the State we discovered
two kinds of EIA reports.The EIA of the Environment and Town planning EIA.The EIA of
multinational companies like Dangote cement factory, Western Ceramics and others were made to
observe both the National and the State guidelines on EIA. But those for State projects and some
private projects like the Ibaji Sugar Company, Petrol stations, Estates and others were processed
and approved in the State without reference to the National guidelines on EIA.
The result of D3 (All the Local Government Areas in Kogi State has the power to give EIA
permit) has a mean score of 2.32 which is low. It show that Local Government in Kogi State do
not have such power. For D4 (EIA has been made mandatory for project proponents in Kogi State
in all cases), 64.35% disagreed with the variable meaning EIA has not been made mandatory for
development projects in the State in all cases. The mean score of 1.72 suggest a low compliance
67
with EIA Act. For D5(There is no strategy for enforcing EIA in Kogi State), result indicates that
67,92% of the respondents agreed that there is no strategy for enforcing EIA in the state. With a
mean score of 3.63 we conclude that the State has not developed a strategy for enforcing EIA. This
indicates a low level of compliance with EIA Act. For D6 (The State guidelines on EIA differs in
many ways from the Federal procedural guidelines) with a mean score of 3.34, there is indication
that the State guidelines differs from the Federal guidelines. Further inquiries during the field work
revealed that almost all the steps of EIA processes outlined in the guideline like initial examination,
scoping, terms of reference, panel review, EIA proposal, and others were not emphasised in the
State EIA process. We also discovered that any registered Town Planner is qualified to prepare
EIA in the State. The state does not give EIA permit, rather it is only required before an approval
can be given for a development project. It is clear that the Town planning EIA and the environment
based EIA are being confused as having the same procedure in the State.
For D7 (There is no Agency in Kogi State that keep records of projects without EIA report),
result shows that 71.68% of the respondents agreed with the variable. With a mean score of 3.78,
we conclude there is no Agency established in the State to keep records of development project
without EIA reports.We noted during the fieldwork that to get records of those industries in the
State without EIA report was difficult. For D8 (There is good relationship between State Agencies
and Federal Agencies regulating EIA in Kogi State), the mean score is 4.34 which suggest that
there is a good relationship between the State and Federal Agencies regulating EIA in the State.
For D9 (All the State and Federal projects in Kogi State have EIA permit), 84.90% of the
respondents disagreed with the variable. The mean score is 1.81 indicating that not all State and
Federal projects in the State has an EIA permit. From the fieldwork conducted in the State, it was
found that State projects like the Confluence Beach hotel in Lokoja, the Lokoja international
68
market, the state Biotic fertilizer company at Anyigba, are good examples of state projects without
For D10 (No EIA report has ever been disapproved in Kogi State) with a mean score of
3.28 we conclude that EIA has scarcely been disapproved in Kogi State. D11 (There is an EIA
monitoring team in the State), the mean score is 2.91 indicating there is no functional EIA
monitoring team in the State. For D12 (The State Ministry of Environment ensure proper
implementation of EMP enshrined in the EIA) almost half of the respondents disagreed with the
variable. The mean score is 2.88 which is not strong enough for us to accept the variable. For D13
(The cost of monitoring the company on EMP implementation is the responsibility of the
government), 14.8%, of the respondents were undecided and refused to give their opinion on the
variable, 60.37% disagreed with the variable. With a mean score of 2.16 we conclude that there is
no proper monitoring of the EMP implementation by the project proponents because of the cost of
monitoring. Further inquiries from the fieldwork revealed that it is the proponents that are
responsible for the cost of monitoring the implementation of the EMP outlined in the EIA. The
company is to pay such an amount as decided by KOSEPA. After the payment of the amount
required, KOSEPA monitoring team normally undertake the monitoring. The monitoring is often
delayed and sometimes cancelled because of the refusal of the company to pay the required amount
of money.
For D14 (There is an existing data bank on the environment in Kogi State to encourage
EIA preparation), the mean score is 2.04 indicating there is no data bank on the Environment in
Kogi State to aid the preparation of EIA. For D15 (The State can boast of well trained individuals
in all aspect of the environment and other natural sciences to handle EIA procedures),has a mean
score is 2.16 indicating the lack of well trained personnel in the field of environment and other
69
natural sciences to handle EIA procedures. This is further confirmed by the fact that any registered
Town Planner is qualified to prepare EIA. Most of these Town Planners single handedly prepare
EIA without regard to the fact that EIA required a multi disciplinary approach ( Sani , 2012).
For D16 (The Government does not commission any development project without an
approved EIA permit) The mean score is 1.76 which is very poor for us to accept the variable. It
was further discovered during the fieldwork that the Government of Kogi State has commissioned
many development projects without EIA permit. Beside,there are many State owned projects
without EIA. For D17 (Our Agency monitors the implementation of project EMP routinely every
three months), 43.39%, of the respondents were undecided and refused to give their opinion on the
variable, 28.30% of the respondents agreed with the variable while 28.30% disagreed with the
variable. With a mean score of 2.94, we conclude there is no routine monitoring of EMP enshrined
with overlapping
responsibilities in
the state has
further advanced
EIA in the state
D13 The larger number 8 6 7 1 1 23 3.82
of agencies 34.78% 26% 30.43 4.3% 4.3%
regulating EIA in %
the state seems to
confuse and
discourage project
proponents in
carrying out EIA
D14 The emphasis to 8 12 1 _ 2 23 4.04
do EIA in the state 34.78% 52.17% 4.3% 0% 8.6%
is mostly on
multinational
projects
D15 EIA reports are 5 3 10 5 _ 23 3.34
now adopted as a 21.73% 13% 43.41 21.73 0%
sound tools for % %
decision making
by the state
government in
environmental
matters
D16 The state 1 6 6 10 _ 23 2.90
government is yet 4.3% 26% 26% 43.41 0%
to adopt EIA as a %
tool for decision
making policy
D17 The state is yet to 10 7 1 3 2 23 4.36
establish an 43.41% 30.43% 4.3% 13% 8.6%
agency to punish
project proponents
that failed to
comply with EIA
regulations
D18 The state is very 1 _ 6 8 8 23 2.04
strict on EIA 4.3% 0% 26% 34.78 34.78%
mandate and had %
revoked the
licenses of those
companies that
failed to comply
72
Our analysis of questionniare 3 Responses from project proponents and company staff are
as follows. D1 (Kogi State operates a seperate law regulating EIA apart from the National
guideline on EIA) has a mean score of 3.09 . We therefore conclude that Kogi State has a separate
law regulating EIA apart from the National guidelines. For D2 (All the Local Government Areas
in Kogi State has the power to give EIA permit) , the mean score is 1.39 which is very low for us
to accept the variable. D3 (The State Ministry of Environment always organise awareness
programs to educate the public on EIA), With a mean of 2.8 , it indicates that the State Government
is yet to start organising awareness programs on EIA for the public. The result also indicates that
the public in Kogi State are not well informed on EIA provisions and this demonstrates a low level
of compliance
For D4 (The State Ministry of Environment strongly enforce EIA in the State), 65.21% of
the respondents disagreed with the variable. With a mean of 2.22 we conclude the State is yet to
start enforcing EIA procedure. D5 (EIA has been made mandatory for project proponents in the
State in all cases) has a mean score of 2.39 which demonstrates that EIA has not been made
mandatory for development projects in all cases. For D6 (The State guidelines on EIA differs in
many ways from the Federal procedural guidelines). a mean of 3.58 made us to accept that the
State guidelines on EIA differs in many ways from the Federal guideline. D7 (The State Ministry
73
of Envinronment and the Federal Ministry of Environment operates the same guidelines on EIA
procedure), shows that 56.20% of the respondents disagreed with the variable. The mean score is
For D8 (There are many EIA reports in the State without approval from the Federal
Ministry of Environment ) , the result shows that 82.6% of the respondents were undecided and
refused to give their opinions on the variable. With a mean score of 3.13, the result demonstrates
uncertainty. For D9 (There are no cases of EIA been rejected or disapproved in Kogi State), the
mean score is 3.17 which is moderate and expresses uncertainty from the respondents. D10 (The
public has no access to copies of EIA reports), result shows that 52.17% of the respondents agreed
with the variable. With a mean score of 3.04 we accept that the public in Kogi State do not have
For D11, (There are some Institutions and Agencies in the State that train people on the
best way to operate EIA in the State), result shows that 64.72% of the respondents disagree with
the variable. With a mean score of 1.78 , we conclude that there is no Agency in the State that
train people on the best way to operate EIA in the State. D12 (The large number of Agencies
regulating EIA with overlapping responsibilties in the State has further advanced EIA in the State),
the mean score is 2.17 which is low for us to accept the variable. However, 52.13% of the
respondents were of the view that the large number of Agencies regulating EIA in the State does
The result of D13 (The large number of Agencies regulating EIA with overlapping
responsibilties in the State seem to confuse and discourage project proponents in carrying out EIA),
indicates that 60.78% of the respondents agreed with the variable. With a mean score of 3.82 we
conclude that a large number of regulating agencies with overlapping responsibilities often confuse
74
and discourage project proponents in the State. We noted from the fieldwork that even when a
company has processed full EIA with the Federal Ministry of Environemnt, at the State level, there
is a strong demand on the same company to process another EIA on the buildings and if the
company has many buildings, an EIA has to be conducted for each building which is frustrating
and discouraging. For D14 (The emphasis to do EIA in the State is mostly on multinational
projects), result indicates that 86.95% of the respondents agreed with the variable. The mean score
is 4.04 indicating that the emphasis to carry out Environmental Impact Assessment in the State is
on multinational projects.
For D15 (EIA reports are now adopted as a sound tool for decision making by the State
Government in Environmental matters) the mean score is 3.34 which is moderate and expreses
uncertainty from the respondents. D16 (The State Government is yet to adopt EIA as a tool for
decision making policy), the mean score is 3.9 which expreses uncertainty from the respondents..
For D17 (The State is yet to establish an Agency to punish project proponents that failed
to comply with EIA regulations), result indicates that 73. 84% of the respondents agreed with the
variable meaning that the Government is yet to establish an Agency vested with the full
responsibility of punishing EIA defaulters .The mean score is 4.33. For variable D18 (The State is
very strict on EIA mandates and had revoked the license of those companies that failed to comply),
The result shows that 69.56% of the respondents disagreed with the variable. With a mean score
of 2.04 we conclude that the state Government is not strict on EIA mandates. This also indicate a
For variable D19 (All the State and Federal projects in the State have EIA permit), has a
mean score of 2.26 which indicates that not all the State and Federal projects in the State have EIA
permit. For D20 (The Government does not commission any project without an approved EIA
75
permit), result indicates that 60.82% of the respondents disagreed with the variable. With a mean
score is 2.26, there is every indication that there is poor compliance with EIA provisions in Kogi
State.
A cursory look at the analysis from the responses of the Public, Government Staff and
Project Proponents in the State on EIA, one can conclude that the level of compliance with EIA in
90
80
70
60
Percentage %
50
40
30
20
10
0
Public Regulators Proponents
Fig. 5 shows the level of agreement on item D1 of the three different questionnaires
administered which is the same for the three categories of respondents. 82.4% of the public and
82.6% of the Project Proponents agreed that Kogi State operates a separate law on EIA apart from
the National guidelines. Only 13% of the regulators agreed with the item. The existence of Edict
No 3 of 1995 is a strong proof. The regulators were only trying to conceal information. Where
there are two separate laws on a particular issue, it means there is conflict and the conflict in this
case has a negative influence on the commitment of the public to EIA provisions in Kogi State.
76
However, to ascertain this conclusion, we shall take a further look at some facts from
existing publicactions and EIA drafts and final reports to see whether the available EIA reports in
the State measure up to the standard set by the Federal Government guidelines and world best
practices.
In Kogi State, some of the major development projects that have EIA permit were
extensively criticised by different scholars and groups. A close look at some of the comments by
these critics on each EIA reports further justified that there is low level of compliance of
Development projects with Environmental Impact assessment delivery in Kogi State. Some of the
EIA reports used for this purpose include the EIA for the dredging of River Niger, EIA of ZUMA
828 Coal Minning at Okobo in Ankpa Local Government, the EIA of Dangote Cement Company,
the EIA of Dam Construction by Dangote Cement Company and the EIA of Gas pipeline by
Beside, the EIA mentioned above, there are several EIA documents which were prepared
and approved by the State Urban and Regional Plannming Department. These were not considered
for review because it does not follow a specific guideline in their preparation.
The dredging of the lower River Niger was a project of the Federal Government of Nigeria.
The project comprises 572 km and affects 152 communities on the bank of the River Niger in eight
states which include Anambra, Bayelsa, Delta, Edo, Imo, Kogi, Niger and Rivers State. Apart from
the dredging, the project is also supposed to establish seven Inland ports in Agenebode (Edo state),
Idah (Kogi state), Yenegoa (Bayelsa state), Agnata (Anambra state) and Ogbabe (Delta state) as
77
well as the rehabilitation and expansion of the Onitsha river Port and the establishment of a river
training Institute.
(2) To promote cheaper and safer means of transportation for Agricultural produce from the hinter
land.
(3) To promote the growth of commerce and trading activities in the affected communities.
(4) To enhance access to hydro electricity generated from Kanji Dam by the affected communities.
Though as good as the objectives of this Development projects are, large number of people living
in 152 communities shall be affected there is need for proper consultation and good EIA before
the commencement of the project. However, the EIA was found with the following and many other
faults..
According to Egboka (2009), the EIA of the dredging of River Niger has not complied
with the provisions of the EIA acts. He stated that the EIA was never completed before the
commencement of the project. But suprisingly, while anticipating the completion of the EIA, the
Federal Government signed the project contract and work commenced without due regards to
proper evaluation of the EIA of the project. He also argued that the EIA reports were not made
available to the public in the 152 communities affected by the project including those in Kogi State
for proper review and comments. In otherwords, the EIA was not given good public review. He
stated further that the communities were denied the access to participate in, see and review the
EIA report. They were not given the opportunity to participate in the design and implementation
The Nigerian Inland Waterways Authority, (NIWA) which is a body in charge of Inland
ports in Nigeria was not involved in the dredging projects. The state Environmental protection
Agency of the affected states were not fully involved. He also noted that, since the EIA was not
completed, those communities that were supposed to be resettled were not resettled and adequate
In view of these shortcoming and others, the EIA of the dredging of the river Niger which
is a Federal project did not comply fully with the provision of EIA Acts.
According to Wolf et al (2001), a number of concerned communities along the proposed water
way and throughout the Niger Delta have voiced concerns about its potential environmental, social
and economic impacts. They contended that they were not consulted or even contacted during the
preparation of the EIA report. He stated further that the communities believed they were
misrepresented in the report which has not been made available for public review and comment.
According to Wolf et al(2001), the dredging contract, was awarded in advance of draft
EIA report preparation. This also contravenes the provisions of the EIA Act. He also stated that
out of the four objectives of the dredging project, the EIA only covered one of the objectives. He
further pointed out that round table seminars were held in 1999 at Warri on 17th April, Onitsha
3rd May, and Lokoja on 20th May all prior to the completion of the draft EIA report which was
The objective of this project was the mining of coal to generate an alternative source of
energy for the country. The project is to affect three Local Governments in Kogi East senatorial
district. The local governments are Ankpa, Omala and Dekina. In a press release in April 2010, a
79
group called Project Igala raised strong objections on coal exploration and mining in Kogi state.
The objections were founded on the weaknesses and shortcomings of the EIA of the project which
include:
1. The choice of Open cast method was not clearly justified in the EIA report.
2. Issues of gas emissions, air pollution, ecological degradation, land and water contamination
3. There was scanty attention to the provision of health facilities for the affected communities.
4. There was no justification on the legal issues around the lease of land for use by the mining
company.
The group also fault the company on the ground that people from the affected communities
were not consulted or contacted during the preparation of the EIA. The group concluded that the
EIA for the company lacked integrity and was full of error. For instance, Okaba which is a villlage
in Kogi State was said to belong to Benue state in the EIA. This justifies the fact that EIA
consultant might not have done serious field work before the EIA report.
However, despite the objection and suggestions for a new EIA to be prepared, the company
commenced their mining operation long before the EIA review forum was conducted. Beside the
shortcomings enumerated above, the EIA public forum was held on a Sunday in Lokoja and only
few people were in attendance. Many people who desired to attend could not do so at the expense
The public forum on the EIA was like a political forum for the Managing Director of the
company to present his manifesto. He said: “Infact, as I am talking to you now, we are already
engaging some universities in Ukraine where I had my background , to training and give free
80
education which we are going to sponsor the children in the host communities. This statement
The justification for the project was the need to meet the cement demand of Nigeria, 85%
of which is currently being imported. In addition, Nigeria loses huge amount of foreign exchange
in the importation of cement despite the fact that raw material deposits abound in the country.
Furthermore, Nigeria is in dire need to diversify her economy from a single commodity economy
(petroleum) and the project shall contribute to achieving that need. This justification is as contained
Despite the above justification, the advisory review of the cement EIA conducted by a
working group of the commission for Environmental Impact Assessment in the Netherland has
The project commenced with site clearing in June, 2003 and construction started in April,
2004. However, there was a draft copy of an EIA made available in July, 2004; while the final EIA
report was still in progress, the Federal Ministry of Environment gave the company a provisional
approval. All these indicates that the project commenced long before the EIA procedure was
completed.
The advisory group observed that crucial information in the EIA reports were missing.
They said that construction work for the project started without the approval of the EIA reports
by the Federal Ministry of Environment. Consequently, important decision had been made. This
renders the EIA of no effect because important decision had already been taken.
Other shortcomings of the cement and power plant include: The EIA report does not
sufficiently comply with the World Bank guidelines. The transportation of cement and gypsum
81
will involve 500 to 1000 truck movement per day. Related environmental and social impact of this
movement have not been considered. Also, the trade metal contents of the raw materials have not
been investigated and as such, no mitigation measure was spelt out in the EIA report.
The objective of the quarry (mining) is to supply the cement factory with marble, clay,
laterite, and marl raw materials from a deposit to be opened up at a distance of 8km from the
factory. According to the advisory commission, the mining site was cleared in June, 2003 and the
EIA for the mining was planned to be available for review in July, 2004. To this end, it was clear
that work had commenced on site prior to the review of EIA report.
The EIA report lacks public participation as the community affected by the project complained of
lack of consultation and access to the EIA report. The advisory commission also observed that,
the EIA report is incomplete, with significant gaps in the provision of information and therefore
does not contain sufficient information for decision making. Other shortcomings of the EIA
The site description and the mining stages were not accompanied by clear drawings,
ground water flow-direction, hydraulic conductivity and effective porosity was missing.
The consequences of the use or release of replenished groundwater on the river discharge
The EIA does not address the impact of the diversion of the Mimi River and a few smaller
The disposal of waste material and its impact and mitigation measures has not been
considered
Beside these major weaknesses, there are several observable minor errors and shortcomings of the
The objective of this project is to supply the water needed for the running of the cement
factory which is about 1.8 million tonnes of water per year. Another objective is to ensure
According to the advisory commission, the Dam construction started in the months of May,
2004 prior to the preparation of the EIA. The EIA for the dam construction was planned to be
available for review in July 2004. It is important to note that as at the time of the commencement
of the project, there was no approval from the Federal Ministry of Environment.
Though in general, the EIA document is of good quality the advisory commission noted amidst
other shortcomings, that the EIA lacked an integrated watershed of Adankolo to provide insight in
the water availability and the opportunities for use. The EIA does not consider an assessment of
The objective of this project is to supply the factory with the natural gas needed to fire the
raw materials and to support the power station for regular supply of light. The construction started
with the right of way cleared in July, 2004 prior to the preparation of the EIA final report which
was scheduled to be available by July, 2004.There was a provisional approval by the Federal
The advisory commission observed that the EIA report is incomplete and does not meet
international standards. They noted that the most environmentally friendly routine of the pipeline
has been elaborated in the EIA and approved by the Federal Ministry of Environment. However,
observation on ground showed that the cleared right of way did follow another shorter (cheaper)
route not respecting safe distance to communities. This is a very serious flaw of the EIA and the
EIA Act. It is a strong indication of low level of compliance with EIA procedures.
Other shortcomings include, safety analysis not being fully included for the two rights of way in
the EIA. There was no clear mitigation measure and lots of error.
Generally, the Dangote cement company and its subsidiary projects has the following
The EIA shows that, the compensation of the affected community has not clearly been
reserve have not been considered. The EIA has not considered the impacts of the high growth rate
of the population of the adjacent community which shall be as a result of company. The EIA also
failed to consider the effect of the increase in traffic in the area which shall be consequent on the
In summary it is clear from publications and the existing EIA reports that there is low level
of compliance of development projects with EIA procedures in the state. All the multi-national,
private and Federal Government projects in the state commence prior to the preparation of EIA
reports. As such, important decision on the project had already been taken. There was a serious
lack of public participation in all the EIA of the development projects observed in the state.
84
Some individuals were interviewed during the field work, and their responses indicates a
low level of compliance of development project with EIA provisions in kogi state. Adebola,
(2012), in an interview during the field work conducted in Kabba, Kogi West Senatorial District
stated that both the public and the government in Kogi State are careless about EIA. He cited a
case of a well serving a particular household in Kajola, Kabba which dried up as a result of the
drilling of a borehole which was approved by the state government resulting in conflict between
the owner of the well and the owner of the borehole. He explained that if an Environmental Impact
Assessment for the borehole project was conducted, the effect of it on the well in the area would
have been known and solutions would have been proffered before the drilling of the borehole.
Similarly, the Head of Works Department of Kabba Bunu Local Government Area,
Mohammed, (2012), in an interview, said it was not clear what the government was doing on EIA.
He gave an example of an EIA document forwaded to his office by Etisalat network provider for
a Base Station in the area. He explained further that the document was very scanty and looked
more of an extraction. He said that beyond sending the document to him, he was never again
In the words of Sani, the Area Town Planner of Ankpa Local Government Area, the Zuma
828 Nigeria Limited held their public review on Sunday and it was never announced to the public
in the affected Local Government Area. According to him, he is the representative of the State
Town Planning Department in Ankpa Local Government Area. His duty is to ensure compliance
of development projects with the regulations of the state Town PLanning Department which
includes the EIA provisions. He lamented that despite that,he was not aware of when the public
forum for the EIA was held. Only few individuals were selected to attend the review by the
85
company. He said he learnt of it much more later from other sources. He concluded that Zuma
828 Nigeria Limited, a coal mining company, located at Okobo in Enjema district of Ankpa Local
Government of Kogi State started their Mining activities long before they conducted the public
review. He further stated that the public review was done without his knowledge.
Similarly, Abdullahi, (2012), the Area Town Planner for Kabba/Bunu Local Government
Area said in an interview that the Town Planning Board is responsible for giving EIA permit in
the State. He further stated that any Registered Town Planner is very qualified to prepare EIA in
Kogi State. In addition to that, he said the cost of an EIA permit in Kogi State depends largely on
the Town Planner concerned and the bargaining power of the Project proponent. He added that the
government of Kogi State does not in any way charge project proponent for EIA permit.
In an interview with Abdul, (2012), the youth leader of Okobo village where the Zuma 828
Nigeria limited is operating a coal mining, he said he was fortunate to attend the public forum on
the EIA organised by the company in Lokoja. He regreted that many of the people who desired to
attend the forum could not make it because beside being held on a Sunday, most of them were not
able to raise the transport fare to Lokoja which is about two hundred (200) kilometres away. He
also lamented that he had asked the company several times for a copy of the EIA and he was denied
having a copy.
Similarly, during a two day workshop organised for Health and Environmental Officers of
Local Government Council of Kogi State in 2013, by JEMDTAS Nigeria Technical Limited in
collaboration with the Local Government Service Commission on the theme: “Environmental
Management and Sustainable Development”; all the Environmental Health officers from the 21
local government areas of the State unanimously complained that, they have difficulties
discharging their duties as a result of regular interference from their employer who in a bid to
86
favour some politicians, make it difficult for them to carry out their duties. Ironically, these
environmental officers were employed by the State to monitor, interprete environmental laws and
possibly fine defaulters. From the result of these interviews one can conclude that there is low
level of compliance of development projects with the provisions of EIA in Kogi state.
87
CHAPTER FOUR
4.1 Analysis of the factors Affecting EIA provisions by the Public in Kogi State
The public in Kogi State were interviewed on the factors affecting Environmental Impact
Assessment in Kogi State. The instrument used contained sixteen variables which have been
A look at the result of the correlation matrix in Table 11 shows that some of the variables
are positive and strongly correlated. For example, C3 and C1, C7 and C2, C9 and C2, C6 and C4
etc while others are negative and weakly correlated e.g. C8 and C1, C4/C1, C13/C2, C14/C3 etc.
Analysis (PCA) to transform the attiributes into an orthogonal values. The PCA result is shown in
Table 12.
Table 11: Correlation Matrix of factors affecting EIA provisions in Kogi State by the
public.
Correlation C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16
C1 1.000
C2 .155 1.000
C10 .053 -.008 -.709* -.502 -.116 -.490 .278 .112 .004 1.000
C11 .003 .965* -.285 .072 .239 .094 .902* .256 .950* .093 1.000
C12 .033 -.037 -.710* -.543 -.160 -.519 .242 .062 -.025 .998* .075 1.000
C13 .009 -.122 -.699* -.574 -.203 -.539 .158 .011 -.109 .991* -.002 .996* 1.000
C14 .335 .982* -.014 .193 .278 .076 .908* .355 .997* .012 .928* -.018 -.103 1.000
C15 .056 -.111 -.672* -.569 -.203 -.552 .169 .022 -.093 .993* -.001 .997* .999* -.084 1.000
C16 .186 .983* -.242 .175 .352 .109 .973 .433 .981 .172 .961 .142 .057 .973 .069 1.000
Table 12: Rotated Component Matrix of factors affecting EIA provisions in Kogi State
By the public.
Component
CODE QUESTIONS 1 2 3 4
C1 The cost of obtaining EIA permit from the government is
.171 .018 -.142 .975
very high
C2 There are many EIA consultants resident in Kogi state. *.985 -.066 .161 .011
C3 There is no indigenous EIA consultant resident in kogi state. -.160 -.724 -.184 .646
C4 Most EIA consultants in Kogi State are expatriate .090 -.444 *.892 .001
C5 Most EIA consultants available in Kogi State are qualified to
.222 -.057 *.960 -.160
prepare EIA
C6 There is always good public participation before an EIA
.047 -.429 *.825 -.366
report is completed
C7 The public normally responds positively to the call to attend
*.912 .240 .332 .001
public review on EIA
C8 The public review on EIA normally holds in the very area
.272 .165 *.946 .062
where the project is to be established
C9 There is normally positive contribution by the public during
*.986 -.060 .103 .112
public review on EIA.
C10 The opinion of the public does not really count in the
.071 *.994 -.076 .012
preparation of EIA document.
C11 There are several shrtcuts to get EIA permit in Kogi state. *.985 .024 -.006 -.171
C12 The public review on EIA in kogi State is not more than an
.049 *.991 -.121 -.011
entainment
C13 The cost of sponsoring a public review on EIA is borne by
-.032 *.988 -.150 -.025
the project propoment and is quiet discouraging
C14 The people in the areas where the project is to be sited do not
always want to support EIA public review until they are *.977 -.054 .091 .187
settled with material gift
C15 The public in Kogi State careless about EIA. -.022 *.989 -.144 .022
C16 The government careless about EIA permits *.981 .114 .153 .039
Eigen value 6.525 5.336 2.912 1.227
% of
explained 40.782 33.350 18.198 7.670
variance
Cummulative
% of 40.782 74.132 92.330 100.000
variance
*Significant loadings exceeding ± 0.75 at 95% confidence level.
Extraction Method: Principal Component Analysis.
Rotation Method: Varimax with Kaiser Normalization.
A rotation converged in 5 iterations.
The Pearson’s correlation matrix was used to test the interelationship that exist between
the variables. PCA was further used to transform the attributes into orthogonal values. The PCA
extracted four components from sixteen variables. The four components account for 100% of the
total variance.
89
Component I is significantly loaded on six variables which include C2, C7, C9, C11, C14,
and C16. C2 (.985) shows there are many EIA consultants resident in Kogi State. This indicates
that EIA consultants are available. The result agreed with the analysis of the interview in chapter
three which reveals that all the Town Planners (Registered) are qualified to prepare EIA in Kogi
State. However, EIA is all embracing and required a multidisciplinary approach in preparation and
presentation. A situation where an individual, because he or she is a registered town planner can
single handedly prepare an EIA for a project is a total deviation from the National Procedural
guideline on EIA. C7 (.912) shows that the public normally respond positively to the call to attend
public review on EIA. There has been a record of peaceful EIA public review in the state. However,
some project proponents do restrict attendance to public review on EIA to village Heads and highly
placed individuals. Others have even fixed EIA public review at odd times in order to restrict
attendance and probably avoid much spending. C9 (.986) indicate that the public in Kogi State
However, there are questions on whether those contributions are in the interest of the
environment or for self gratification. The significant loading on C11 (.985) shows that there exist
several shortcut to get EIA permit in Kogi State. Some examples of these shortcuts have already
been mentioned in the previous chapters where a project proponent can get through one registered
Town planner to get an EIA prepared. It was also revealed that some multinational projects got a
provisional (Temporary) EIA permit to commence their project while the EIA process is still on
going. These show a serious contravention of the EIA procedure. C14 (.977) shows that the local
people from the area where the project is to be sited do not always want to support EIA public
review until they are settled with material gifts. This shows that their participation and positive
90
contributions during EIA public review as indicated by variable C7 and C9 above have to do with
inducement.
After collecting material gifts from the project proponent, the local people submitted
completely to EIA presentation by the project proponent without raising any serious contention.
C16 (.981) has significant loading which shows that the government of Kogi State is careless about
EIA permits. This means that the state lacks the political will to ensure effective EIA procedure in
the state. And if the political will is not there, then many things will go wrong with the EIA policy
in the State. The underlying factor for component I is lack of monitoring and evaluation of EIA
procedure. The component has an Eigen value of 6.525 and explains 40.78% of the total variance.
Component II has high significant loadings on C3, C10, C12, C13, and C15. The significant
loadings on C3 (-0.724) has a negative signs meaning the variable is inversely related to the
component. It shows that the EIA consultants in Kogi State are indigenes. C10 (.994) reveals that
the opinion of the public does not really count in the preparation of EIA document. This explain
that whatever the contribution from the public and no matter how good, does not really matter.
The EIA process continues with or without any contribution from the public. A good example can
be taken from the case of Goldfeilds Coal Mining in the state where the EIA was strongly opposed
by a group called project Igala.The opposition does not in any way stop the company from carrying
out their businesse as the case of Zuma 828 in Okobo of Ankpa local government where the
operation had commenced long before the public review was held. C12 (.991) shows that public
review on EIA in Kogi State is not more than an entertainment. The public just gatherered for the
review after they must have been settled by one gift or the other and listen to whatever the project
proponent had to tell them and afterward without much argument or complaint or contributions
departed to their various homes. It is usually a mere entertainment and a contravention of the EIA
91
procedure because this defies good stakeholder’s participation in the EIA process. The high
significant loadings on C13 (.988) shows that the cost of sponsoring a public review on EIA which
is borne by the project proponent is quite a discouraging factor in the EIA process. Beside the
amount that is paid directly to the government as bills for the permit, other expenses and logistics
are also taken care of which all together amount to huge sum of money which most project
proponents felt should be used for starting up the project. C15 (.989) shows that the public in Kogi
State are careless about EIA. The local people are not really bordered whether the Development
Project coming to their locality has EIA or not. Sometimes, they are consumed by the enthusiasm
of having the project around them. They count what they stand to benefit from the project rather
than the negative consequences of the project. The underlying factor here is public disregard for
EIA. The component has an Eigen value of 5.336 and account for 33.35% of the total variance.
Component III has significant loadings on four variables which include C4, C5, C6 and
C8. The high significant loadings on C4 (.892) indicates that most EIA consultants available in
Kogi State are expatriates. This has to do largely with locations and the available development
projects in the area. The areas where there are multinational projects like the Dangote Cement
factory, the EIA consultants are not indigenes of the state and some are expatriates. These projects
are covered by the Environment EIA system. However, there are so many cases of EIA prepared
and approved in the state under the Town Planning EIA system where consultants are mostly
Registered Town Planners from the state. C5 (.960) indicates that most EIA consultants available
in the state are qualified to prepare EIA. C6 (.825) shows there is always good public participation
before an EIA report is completed. All this reflect on the location where a multinational project is
in place. There is a serious dichotomy between the attitudes and expressions of the public in the
area where there is state and private projects and those areas where there are multinational project
because the approach to EIA procedures by these project proponents differs. C8 (.946) shows that
92
the public review on EIA normally holds in the very area where the project is to be established.
The public review on EIA in Kogi State normally holds in the state capital Lokoja. The area around
Lokoja definitely finds it very convinient but when the project is to be sited in a location far away
from the state capital, the local people may not find it convenient. The underlying factor here
borders on the issue of stakeholders involvement in EIA process. The component has an Eigen
Component IV is significantly loaded on C1 (.978). It shows that the cost of obtaining EIA
permit from the government is very high. The cost here may not mean only the amount paid as bill
for the permit but, could also involve the amount spent on logistics as well as the waiting period.
Many proponents could run out of patience if the waiting period is unduly extended. The
underlying factor is high cost of obtaining an EIA permit. The component has an Eigen value of
The PCA result for the factors affecting the level of compliance of development projects with EIA
by the public identifies four components to have significant effect on the compliance of
The underlying factor for component I is lack of monitoring and evaluation of EIA
procedure and the component defining variable is C2 (there are many EIA consultant resident in
Kogi State with high positive loading of .985. The high positive loading indicates many EIA
consultants which refers to registered Town Planners. The state EIA process approves any
registered Town Planner to prepare EIA. With the Town Planner’s seal on an EIA document in
Kogi state, the EIA is authentic and unquestionable. This situation devoid monitoring and
evaluation of EIA process. Component II has public disregard for EIA as the underlying factor
with C10 (the opinion of the public does not really count in the preparation of EIA document as
the component defining variable with a high positive loading of .994, there is an indication that
the public in Kogi State are already aware that their opinion does not really matter in EIA
The underlying factor for component III is stakeholder involvement and the component
defining variable is C5 (most EIA consultants available in Kogi State are qualified to prepare EIA.
For component IV, the underlying factor is high cost of obtaining EIA permit and the component
defining variable is C1 (.978) the cost of obtaining EIA permit from the government is high.
approval of any registered Town Planner to prepare EIA has create a situation that allows many
EIA consultant in the state. The situation also resulted to neglence on EIA monitoring and
evaluation. The high cost of obtaining EIA permit, does not only mean the amount paid as bill to
the government but it also include the time lost and amount spent on logistics.
94
4.2 Analysis of the Factors Affecting EIA Compliance by EIA Regulators in Kogi State
The various agencies incharge of regulating EIA in Kogi State both at the state
headquarters and the local government levels were interviewed on the factors affecting EIA
provisions in the state. The same instrument was used to interview the public in Kogi State and the
The result of the response from the regulating agency is shown below.
Table 14: Correlation matrix of factors affecting EIA Compliance in Kogi State by
the Regulators.
A careful look at the result of the correlation matrix contained in Table 14 revealed that
some of the variables are positively correlated like C2/C1, C7 and C1, C8/C2, C11/C2, C11/C3
C9/C5, C9/C6 etc. while others have high negative correlation e.g. C10/C2, C15/C4, C13/C6,
C13/C8 etc.
95
The effect of the inter-correlation was reduced by the application of PCA to transform the
attributes into orthogonal values. The result of the PCA is contained in Table 15.
components. Component I have high significant loadings on eight variables which include C3, C5,
C6, C9, C11, C12, C14 and C16. The high significant loading on C3 (.986) shows there is no
96
indigenous EIA consultant resident in Kogi State. This depends largely on the type of EIA policy
in focus. For the EIA of the environment, there are few indigenous EIA consultants in the state.
But for Town Planning EIA there are many indigenous consultants resident in the state. The high
significant loading on C5 (.986) is a reflection of the Town Planning EIA. This shows that most
EIA consultants in the state are qualified to prepare EIA. These consultants are Registered Town
Planners. C6 (.835) shows there is always good public participation before an EIA report is
completed. The public participation here does not involve public review in the case of Town
Planning EIA. It is only when it involves environment EIA that public review is carried out.
C9 (.988) shows that there is normally positive contribution by the public during public
review on EIA. The review is usually peaceful and without much contention. The high significant
loadings on C11 (.993) shows that there are several shortcuts to get EIA permit in Kogi State.
Though these shortcuts are not legal, it cut across the two EIA policies operating in the state.
C12 (.894) shows that the public review on EIA in Kogi is not more than an entertainment.
The public only gathered to listen to the project proponent as he presented the EIA in form of
political manifestoes full of promises and many at times without questions and suggestions, the
people departed to their homes. The high loading on C14 (.986) reveals that the local people from
the area where the project is to be sited do not always want to support EIA public review until they
are settled with material gifts. This indicates why they always contribute positively during EIA
public review. It also shows why the public review is like a mere inducement. The loadings on
C15 (.977) shows that the public in Kogi State is careless about EIA. What they care about is the
initial benefit they want to derive from the project that is coming to their land, not the negative
impact of the project. The underlying factor in this component is poor concern for EIA provisions.
The component has an Eigen value of 8.712 and account for 54.44% of the total variance.
97
Component II has high significant loading on three variables which include C10, C13, and
C15. The high significant loading on C10 (.974) shows that the opinion of the public does not
really count in the preparation of EIA documents. Where public review on EIA is conducted in the
state, it is just to fulfill the requirement. The suggestions, cries and complaints of the public are
Loading on C13 (.950) shows that the cost of sponsoring a public review on EIA is borne
by the project proponent and is quite discouraging. Project proponents spent much money in trying
to organize a public review. Most of them are often discouraged by the cost and rather choose a
shortcut or skip it. C15 (.977) shows that the public in Kogi State are careless about EIA. Since
they know their opinion will not count, they have lost interest and sometimes for the fact that they
have been induced by the project proponent, they may not border themselves about future negative
occurrence. Many at times, the Federal government often gives provisional approval for EIA
permit to project proponent while the EIA process is yet to be completed. In that case, whatever
the public opinion of the project does not count in any way. The underlying factor in this
component is poor public participation in EIA process. The component has an Eigen value of 4.104
Component III has high significant loadings on three variables which include C1, C4, and
C7. The high significant loading on C1 (.835) indicates that the cost of obtaining EIA permit from
the government is very high. The cost here involves the amount paid directly as bill to the
government as well as the time spent in waiting for the approval and the cost of organizing public
review. The high significant loading on C14 (-0.826) has a negative impact indicating that the
variable is inversely related to the other variables in this component. Consultants engaged by
98
multinational companies are mostly expatriates while those engaged by the Town Planning EIA
policy are indigenes. This accounts for the negative impact in the loadings of the variables.
C7 (.751) shows the readiness of the public to attend public review on EIA. The positive
response does not necessarily indicate an interest on the environment and sustainable development
rather on self gratification. The underlying factor in this component is high cost of EIA. The
component has an Eigen value of 2.167 and account for 13.54% of the total variance.
Component IV has high significant loadings on two variables C2 and C8. The high loading
on C2 (.844) is an indication that many EIA consultants are resident in Kogi State. This significant
loading is a reflection of the consultants of the Town Planning EIA who are mostly registered
Town Planners. C8 (.727) indicates that the public review on EIA normally holds in the very area
where the project is to be established. As pointed earlier, the Town Planning EIA which is more
popular in the state does not require any elaborate public review. All that it takes to complete the
EIA is done in the locality of the project. The underlying factor in this component is stakeholder’s
involvement. The component has an Eigen value of 1.017 and explains 6.35% of the total variance.
Table 16: The relative strength of the underlying factors that determine the factors affecting
the Compliance of Development Project with EIA by the Regulators in Kogi State.
S/N Component Underlying Component Defining Relative Cumulative
factor Variable contribution contribution
1 I Poor concern for C11 (.993) There are 54.44% 54.44%
EIA provision several shortcuts to get
EIA permit in Kogi State.
2 II Poor public C15 (.977) The public in 25.65% 80.10%
participation in Kogi State careless about
EIA processes EIA
3 III High cost of EIA C1 (.835) The cost of 13.54% 93.64%
permit obtaining EIA permit
from the government in
very highl
4 IV Stakeholders C2 (.844) There are many 6.35% 100%
involvement in EIA consultant in Kogi
EIA State
Source: Author, 2012
99
The relative strength of the underlying factors that determine the factors affecting the compliance
of development project with EIA by the regulators in Kogi State identifies four components which
are as follows.
Component I has poor concern for EIA provision as the underlying factor and the
component defining variable is C11. (There are several shortcuts to get EIA permit in Kogi state.
The high positive loading of .995 suggests there is strong agreement on the variable. The relative
contribution of the variable to the component is 54.44%. The underlying factor for component II
is poor public participation in EIA process and the component defining variable is C.15 (.977).
The public in Kogi State are careless about EIA. For component III, the underlying factor is high
cost of EIA and the component defining variable is CI (835). The cost of obtaining EIA permit
from the government is high. The underlying factor for component IV is stakeholders involvement
in EIA and the component defining variable is C2 (.844). There are many EIA consultants in Kogi
state.
There is a kind of chain effect in the component defining variables of the underlying factors
seen here because there are many EIA consultant who are mainly registered Town Planners, EIA
monitoring and evaluation is not taken seriously and that created a careless attitude on the public
in Kogi state. Similarly, because the cost in terms of bills paid to the consultants, time spent in
waiting, amount spent on logistics is high, and many project proponents seek shortcuts to get
approval. There are cases of even provisional approval granted by the Federal Ministry of
Environment for a project without a complete EIA. There are also cases of project that commenced
4.3 Analysis of the Factors affecting the Compliance of Development Projects with EIA
Kogi State, representatives of project proponents across the state were interviewed. The instrument
for the interview contained sixteen variables which were subjected to principal component
analysis. The result shows that three components were extracted to explain the total variance.
Table 17: Correlation Matrix of factors affecting EIA Compliance in Kogi State by the
project proponents.
C1 1.000
C2 .915* 1.000
C10 .765* .935* -.520 -.107 .758* .687* .980* .735* .936* 1.000
C11 -.597 -.291 .524 .023 -.043 .445 -.203 -.388 .053 -.188 1.000
C12 .456 .732* -.456 -.203 .538 .669* .860* .479 .849* .920* .083 1.000
C13 .642* .779* -.695* -.267 .481 .415 .879* .556 .750* .928* -.345 .903* 1.000
C14 -.228 .076 .526 .209 .334 .711* .101 .013 .378 .109 .913* .274 -.155 1.000
C15 .885* .997* -.415 .013 .914* .748* .970* .852* .955* .949* -.226 .770* .787* .139 1.000
C16 .825* .981* -.382 -.021 .934* .828* .968* .802* .984* .941* -.104 .789* .755* .252 .991* 1.000
The correlation matrix of the factors affecting EIA provisions in Kogi State by the project
proponent is contained in Table 17. A look at the correlation matrix shows that some of the
attributes like C2/C1, C5/C1, C8/C2, C9/C1, C10/C11, C12/C2, C13/C7 are positive and strongly
correlated while others like C11/C1, C3/C2, C7/C3, C11/C8, etc. have high negative correlation.
101
Most of the attributes here have high positive correlation. To reduce the effects of the inter-
correlation, we used PCA to transform the attribute into orthogonal values as shown in Table 18.
Component I has high significant loading on twelve variables which include C1, C2, C5,
C6, C7, C8, C9, C10, C12, C13, C15 and C16. The high significant loading on C1 (.868) indicates
that the cost of obtaining EIA permit from the government is very high. This also agreed with the
102
result from the two other categories of the respondents. C2 (.991) shows that, there are many EIA
consultant resident in Kogi State is a reflection on the Town Planning EIA. C5 (.912) shows that
most EIA consultants available in Kogi State are qualified to prepare EIA. This largely depends
on the type of EIA policy. C6 (.764) indicates that there is always good public participation before
an EIA report is completed. C7 (.961) shows that the public normally respond positively to the call
to attend public review on EIA. C8 (.863) shows that the public review on EIA normally holds in
the area where the project is to be established. The significant loading on variables C5, C6, C7,
and C8 depends largely on the type of EIA policy in question. As noted earlier the town planning
EIA is most popular in the state. The requirements are not as cumbersome as those of the Ministry
of Environment. The issue of public participation and public review which is fundamental in the
Ministry of Environment’s EIA process is not a serious issue in Town Planning EIA as currently
C9 (.961) indicates that there is normally a positive contribution by the public during EIA
public review. The public review is always peaceful and the public normally consent to the EIA
report. C10 (.950) indicates that the opinion of the public does not really count in the preparation
of EIA documents. This applies to the two EIA policies in the state. In as much as the Town
Planning EIA does not really seek the opinion of the public in the preparation of EIA, the EIA of
the environment seldom consider the opinion of the public. C12 (.784) shows that public review
on EIA in the state is not more than an entertainment. It is always a forum where people gather,
listen to the presenter and depart home without raising much contention on fundamental issues that
affects them. C13 (.779) reveals that the cost of sponsoring a public review on EIA is borne by the
project proponent and is quite discouraging. Some of the project proponents skip public review
because of the cost. C15 (-0.997) shows that the public in Kogi State is careless about EIA. The
understanding and interest of the public on environmental matters is low. C16 (.992) shows that
the government of Kogi State is careless about EIA permit. There is low political will on the part
103
of the government to enforce EIA permit. This is in line with finding of Tundu (1999) who states
that the promotion of private foreign investment has created fears that putting investors to rigorous
and public scrutiny of their projects on environmental grounds and depriving the economy of this
badly needed foreign direct investment. The underlying factor in this component is poor concern
for EIA provisions. The component has an Eigen value of 10.182 and account for 63.63% of the
total variance.
Component II has high significant loading on two variables which include C11 and C14.
The high significant loading on C11 (.982) is an indication that there are shortcuts to get EIA
permit in Kogi State. This agrees with the findings of Kerdeman (2009) who opines that Nigeria
is one of the greatest violators of EIA regulations due to poor participation, corruption, and /or
down playing of EIA. C14 (.959) shows that the people in the area where the project is to be sited
do not always want to support EIA public review until they are settled with material gifts. The gift
serves as an inducement and explains why they seldom raise contentions. The underlying factor
here is inducing support for EIA process. The component has an Eigen value of 3.051 and explains
Component III has high significant loadings on two variables C3 and C4. The high
significant loading on C3 (.811) shows that there is no indigenous EIA consultant resident in the
state. C4 (.950) indicates that most EIA consultant in Kogi State are expatriates. The loading on
C3 and C4 reflects largely on the EIA of the environment where a multidisciplinary approach is
required. The consultants of most multinational companies in the state are non-indigenes. The
underlying factor of this component is accessibility to qualified EIA consultant. The component
has an Eigen value of 2.082 and account for 13.0% of the total variance.
104
Table 19: The relative strength of the underlying dimension of factors that determine the
factors affecting the compliance of Development Project with EIA by the Proponent
S/N Component Underlying Component Defining Relative Cumulative
factor Variable contribution contribution
1 I Poor concern C16 (.992) The government 63.63% 63.63
for EIA careless about EIA permit.
provision
2 II Inducing C11 (.982) There are several 19.0% 82.70%
support for shortcut to get EIA permit in
EIA process Kogi State
3 III Accessibility C4 (.950) Most EIA 13.0% 95.71%
to qualified consultant in Kogi State are
EIA expertraites
consultant
Source: Author, 2012
The PCA result for the factors affecting the compliance of development project with EIA by the
The result extracts three components which include component I poor concern for EIA.
The component defining variable is C16 (.992). The government is careless about EIA permit. The
The government of Kogi State lack the political will to drive environmental impact
assessment. This can be seen in the fact that the state does not give EIA approval neither does it
concern itself with the status of the consultants that prepare EIA in the state. Beside, there is no
record of any state project with a complete EIA. The underlying factor for component II is inducing
support for EIA process and the component defining variable is C11. There are several shortcuts
to get EIA permit in Kogi state. The careless attitude of the government for EIA process has created
a situation where everybody do what he wants thereby given room for financial and material
The underlying factor for component III is accessibility to qualified EIA consultants and
the component defining variable is C4. (.950) Most EIA consultant in Kogi State are expertriate.
105
All the EIA consultants used for all the multi-national projects and industries in Kogi State are
expertriates. The cost and access to these consultant is quiet expensive and discouraging. Some
project proponents choose to abandon the EIA process because of the cost of sponsoring it. This
agrees with the findings of Kakonge (2006) who states that in most developing countries, experts
are foreign and the few indigenuos experts are poorly renumerated. In Nigeria, few EIA indigenous
100
90
80
70
60
Public
50
Regulators
Proponent
40
Percentage %
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Fig. 6 shows the variation in the responses of the three categories of respondents on the factors
affecting the Compliance of Development Projects with EIA provisions in the state. To avoid
106
concealing of information, the same checklist was used for each of the category to bring out the
fact. It is clear from their responses on variables 2, 4, 6, 8, 9, 10, 12, 13, 15 and 16 that there is
strong agreement between the respondents on these variables. Only in few cases like variables 1,
3, 5, 7 and 14 where there is margin between the opinions of the regulators and those of the public
and the project proponent. However, the margin notwithstanding there is a strong agreement in the
opinion of the public and project proponent. This justify that the result is valid to some extent.
The result reflects strong agreement between the response of the three categories of
respondents used for this study. The result also agreed with the opinion of Kerdeman (2009) that
Nigeria is one of the greatest violators of EIA regulations due to poor public participation,
corruption and downplaying of EIA. She also identified Nigeria to have a weak civil society and
mass poverty as factors responsible for poor participation in EIA process. The result also agreed
with the findings of the World Bank (1998) which identified poor implementation of framework,
CHAPTER FIVE
The result of our findings indicates a low level of compliance of development projects with
EIA policy in Kogi State. The low compliance as we observed can partly be blamed on the
challenges of the policy itself which except resolved will continue to impede effective
There are too many EIA regulators with similar or overlapping responsibilities in the
country as well as in Kogi state. There are three independent EIA systems in the Country: one for
the petroleum sector (Governed by the Directorate of Petroleum Resources, DPR), another for the
urban and regional planner’s development control (governed by local government councils and the
town planning divisions of the State Ministries of Lands), and yet another which attempts to span
all sectors (governed by the FMENV). By 1992, all the three systems had in one form or the other
advanced legislations stipulating proactive pollution control with measures including impact
assessment, mitigation and project approval. Consequently, the pattern of the three EIA systems
varies significantly as one can observe. The DPR EIA evolved from the 1969 petroleum
regulations in Nigeria and it apparently have an indigenous concern, the EIA Decree of (1992) is
patterned after the NEPA act of USA and this obviously covers all the sectors of the economy. On
the other hands, the Town and Country planning EIA is patterned after the United Kingdom Town
This variation in the styles and operation has not just caused confusion for the applicants
but, also compels them to repeat EIA preparation to satisfy all the systems with the attendant
108
duplication of time and resource. Consequently most of them have to resolve to shortcuts and skip
Beside, these three EIA systems, the Part III, section 24 of act 58 of 1988 permits the States
and Local Government Councils to establish their own environmental protection bodies for the
Protection Agency were established in all the State of the Federation. In Kogi State, the State Edict
on the environment and the National Procedural guidelines on EIA are at variance on many issues.
When the Federal Environmental Protection Agency was scrap in 1999 and the Federal Ministry
of Environment was created to take up its functions, most state did not scrap their state
Environmental Protection Board, rather they established State Ministry of Environment to run
concurrently with the SEPA. Hitherto, Kogi State EIA regulating bodies include the Federal
Ministry of Environment Field office, State Ministry of Environment, Kogi State Environmental
Protection Agency, Kogi State Town Planning Board and Kogi State Urban and Regional planning.
It is practically difficult for a proponent to satisfy all the regulating bodies and this really affects
compliance.
Another major challenge of the policy is the Exception to the EIA Decree as contained in
Section 15 of the decree which states that EIA is not required where in the opinion of the agency
the project is in the list of projects which the president, commander in chief of the Armed Forces
or the Council is of the opinion that the environmental effects of the project is likely to be minimal.
The provision of this section give ultimate power to the President to decide which project requires
EIA and which one should not be subjected to EIA. The expertise of the president to determine the
effect of a given project on the environment is questionable. The same Section of the Decree also
Consequently many development projects that require EIA like the National Stadium, in
Abuja. The dredging of the River Niger, the Federal power projects in the six Geo-political zones,
and several State projects in Kogi State like the Kogi State International Market at Lokoja, Kogi
State Biotic Fertilizer Company at Anyigba, Kogi State Confluence Beach Hotel at Lokoja were
not subjected to EIA because the President or the Governor decided there was no need and so be
it.
The issue of enforcement is yet another major challenge facing the effective implementation
of EIA in Nigeria. When Decree 86 was promulgated in 1992 and amended in 2004, there was no
enabling law for its enforcement until in 2007 when the National Environmental Standards and
all Environmental laws, guidelines, policies, standards and regulations. It also has the
conventions and treaties on the environment. However, the NESREA Act creates a number of
conflict and duplication in the functions of the Federal Ministry of Environment. Even with the
Act, NESREA has limitation in enforcement particularly with regards to Federal and State projects.
It is good to note that, Kogi State have all the laws and regulations on the environment. It has a
good number of regulating Agencies but lack seriously in enforcement of the laws and regulations.
Though according to the state edict, KOSEPA is charged with the responsibility of enforcing
environmental laws and regulation, we observed that the heat and pressure from other regulating
Agencies and particularly Town planning Board has made it impossible for the Agency to operate
effectively. Beside, KOSEPA is lacking in staff strength and the few available have little or no
expertise ability to carry out their function. Funding is also another constraint of the Agency. The
annual budget of the state for the Agency according to our findings is not always accrued to it.
110
Staff are not well paid and some time were denied their salaries for over six months. In these
Though the EIA Decree 86 of 1992 as amended in 2004 operates procedural guidelines, we
observe a low degree of advertisement of the guideline. The public and stakeholders in most cases
lack the knowledge of the process and procedure of EIA in the country. They are not aware of their
right to public hearing on proposed project or their rights to object to proposed development that
could affect the sustainability of their environment. During the fieldwork, we discovered the
indigenes of Obajana and Okobo both in Kogi State to be helpless and handicap over the terrible
effects of the activities of development projects on their entire livelihood. If these people are aware
There is inadequate baseline data for the preparation of a quality Environmental Impact
The issue of EIA consultant in Kogi State must be addressed with all seriousness. Currently
any registered Town Planner is a qualified EIA consultant. This may work for the Town and
Country Planning EIA but not for the other EIA system. Environmental Impact Assessment is a
comprehensive task that requires a multi disciplinary approach and should not be handled by an
individual.
The following suggestions has been put forward after a careful observation of some of the
challenges facing EIA in Kogi State with the view that when implemented EIA will become a
We suggest that the three EIA systems should be harmonized to operate under one
procedural guideline. From our observation the Decree 30 of 2004 is most comprehensive and has
111
wide coverage and as such it best captures the criteria of good EIA system. The DPR and Town
planning EIA are more or less specific in style and methodologies. The Section 24, Part III of Act
58 of 1988 should be amendment to make all the States and Local Government Councils to comply
with the Act of the Federal Government rather than encouraging them to establish their own
regulating bodies.
The Section 15 of the EIA Decree should be amended. The President should not be given
ultimate authority to decide on environmental matters because sometimes he may allow sentiments
to override National interest. When EIA was established in USA 1969, the President made himself
EIA policy that the state Government edict should be amended and specific function should be
given to each of the Agencies regulating EIA in the state. We also suggest that fund should be
made available for the operation of the Agencies and staff salaries should be paid promptly. There
should be workshops, seminars and training programs for the staff of all the Agencies regulating
5.2:1. Suggested strategies for effective implementation of EIA for the Regulators
It is practically the duty of the government to popularise her policies and laws while the public
has the duty to obey the law of the land. We therefore suggest that awareness campaign on the
EIA, processes and procedure should be carried out frequently to acquaint the public and
There is need for adequate data to prepare quality EIA.We suggest that the Federal
Ministry of Environment should establish a data bank on all the aspect of the Environment and
112
make it accessible to both public and the EIA consultants.The Kogi State Geographic Imformtion
Sytem (GIS) should be equip with state of the art equipment to assist the public in locating
Public participation and stakeholder’s involvement should be taken seriously and every
participant should make sustainable environment the uttermost priority. In this case, the regulating
This shows why harmonizing EIA system is not only necessary but urgent. The state edict
5.2:2 Suggested strategies for effective implementation of EIA for the public
For the public, we suggest that since ignorant is not an excuse in law, people should strive
to aquaint themselves with government policies and regulations. The Federal Government has
established a feild office for the Federal Ministry of Environment to bring the operation of the
Ministry closer to the people. It therefore the responsibility of the individuals to seek for
imformation and help when there is need. Forinstance, copies of all the EIA draft and final report
conducted in the state are available in the Ministry field office and can be accessed by any
The public should strive to ensure compliances to terms of reference mentioned in the EIA
document by insisting on its implementation by the project proponents and stop looking for
monetary inducement.
The public should show concern and care for the environment and strive to protect it at all cost.
5.2:3 Suggested strategies for effective implementation of EIA for the project proponents
The following suggestions are made for effective implementation of EIA process and
procedure.
The project proponent should seek to understand the EIA sytem most relevant for their
project. While we advocate for a harmonization of the three EIA system for effective compliane,
we strongly suggest that the project proponent must have a good knowledge of which EIA system
is most relevant to his project because by doing so unnecessary expenses may be avoided. For
instance, an estate development project should not run away from the Town and Country EIA.
Petroleum refinery and service stations are best handled by the DPR EIA, while industrial projects
The proponents should provide assurance that the required regulations are met through self
determination, self regulation, goal setting and negociated agreements to complement existing
legislation.They should ensure that a section is created in the company to handle environmental
issues and fund should be devoted for it. Staff should be highly motivated with adequate equipment
We also suggest that the proponent should be alive to the Environmental Management Plan
(EMP) enshrined in the Environmental Impact Statement (EIS) and pursue it not because some
CHAPTER SIX
From the study of the analysis of the compliance of development project with
Environmental Impact Assessment in Kogi state, the result indicates that the level of compliance
is low owing to so many reasons particularly that there are many regulators with overlapping
responsibilities. Since the proponents must satisfy all the regulators before obtaing an EIA permit,
there is always duplication of efforts, lost of resources and time. Most proponents acquire foreign
grants to sponsor their pr oject as the case with the Obajana cement factory and if the gestation
period for EIA is too long, it create room for financial inducement and down playing of the EIA
system.We also observe that the Kogi State Edict no 3 of 1995 is at variance with the EIA decree
30 of 2004 on many issues. To this extent, the edict should be harmonized with the decree to avoid
conflict. Inadequate base line data for EIA preparation, lack of political will on the part of the
government and weaknesses in the formulation of EIA policy both at Federal and State level are
From the PCA analysis conducted on the response of the public to the factors affecting the
level of compliance of development project with EIA in Kogi state, the result identified four
components as underlying factors affecting the compliance of development projects with EIA.
Component (I) improper handling of EIA procedure. Component (II) improper stakeholders
engagement, Component (III) Issues of proper consultation on EIA procedure, and Component
(iv) Cost of obtaining EIA permit. Similarly, the response of the regulators on the factors affecting
the compliance of development project with EIA idendified four components which include
Component (I) poor concern for EIA provisions, Component (II) poor public participation in EIA
115
process, Component (III) high cost of EIA permit and Component (iv) issues of stakeholders
involvement in EIA process. In the same way , the response of the project proponent on the factors
affecting the compliance of development project with EIA identified three components as
underlying factors affecting compliance. Component (I) poor concern for EIA provision,
Component (II) inducing support for EIA process and Component (III) issues of accessibility to
The findings of this work indicates low compliance of development project with EIA
provisions and it means the environment of the state particularly those of the six Local Government
Areas with major developmental projects are more prone to environmental degradation than
before. For example, the people and land of Okobo in Ankpa Local Government Area where Zuma
828 coal mining industry is located are already facing serious deforestation, atmospheric pollution,
water problems and others. The story is the same with Obajana community where Dangote cement
factory is located. Besides, there are lots of negative social and health impacts like increase traffic,
rise in the cost of living, high rate of prostitution, etc on the environment of the affected areas.
However we acknowledge the fact that Kogi State has taken serious steps to maintain sustainable
environmentare all indications of the intention to pursue sustaitability. The Town Planning EIA
which has gain strong acceptance in the state has no specific guidelines for its operation.Since all
these are already in place, a little effort in harmonizing and restricting of the EIA policy will make
great difference.
6.2 Recommendations
We recommend that first and foremost awareness campaign should be given priority in
the state. If possible this should be done regularly on the state media like radio stations, television
116
stations and newspapers. Periodic workshops and seminars should be organised by the government
to sensitize the people on the danger of their disregard for the environment. Students should be
taught environmental education at all levels so that they can learn how to safegard the environment.
NGOs and tertiary institutions should organise training for people on environmental management
We also recommend that the state Edict on EIA should be harmonised with the national
guidelines on EIA . Where variations exist the national guidelines should have prefrence. There
should be a total overhurling of KOSEPA. This should involve the review of its mandates, staff
We recommend that proper attention should be given to EIA mandates by the state
government. The goverment should mandate all state development projects to embrace EIA
procedure and no project should be commisioned without an acceptable EIA report. The
government should avoid interupting the EIA regulating agencies in their duties, and staff should
Finally we recommend that the state government should emback on intensive research
works to map out major industrial locations in the state. This will provide a road map for agencies
responsible for EIA activities and also help them to identify new industries (particularly those
6.3 Conclusion
With our findings on this study, we conclude that EIA in Kogi State does not operate a
specific guideline on Environmental Impact Assessment and falls below World best practices.
There is poor concern for EIA process from the public, the regulators and the government and the
project proponent and owners of companies are taking advantage to pollute, devastate and degrade
117
the environment. The rich who are the owners of the industries are more conscious of their profit
than sustainable environmental development. Similarly, the Government pursues job creation and
poverty reduction at the expense of the environment and subject the poor and the less priviledged
which form the bulk of the population to environmental hazards and sufferings. We observe a
collaboration between the Government and the project proponents (the rich) to degrade and
devastate the environment.A lot of resources that could have been used for meaningful
development projects were spent on fighting soil erosion, deforestation and flooding in Ankpa,
Dekina, Idah and Ibaji local government areas between 2010 and 2015.Caution should be taken to
REFERENCES
ABUBAKAR. A. (2010). Yobe State Awaits EIA report on Kafin-Zaki Dam. Daily Trust 18th
August 2010.
ABUKAKAR A. (2010). NESREA Seals Telcoms most in Ilorin. Daily Trust 26th August 2010.
ADENIYI, I.F (1998) Analytical Techniques and Quality Assurance in EIA Study: In Capacity
Building for Environmental Impact assessment in the Benue Trough pp. 66 – 78.
ADEGOKE, O.S (1999) A welcome Address by Principal Consultant at the Capacity Building
Workshop for Environmental Impact assessment in the Benue Trough Held at Hill Station
Hotel Jos 22nd – 25th June 1999.
ADEWOYE, R.O (1999) An Opening Remarks at the Opening Ceremony of the Capacity Building
Workshop for Environmental Impact assessment in the Benue Trough Held at Hill Station
Hotel Jos 22en – 25th June, 1999. FME(1999).
AHMAD, B and WOOD, C.M (2000) in Wood 2003. Enviromental impact assesment in
developing countries: conference on new directions in impact assesment for development:
methods and practice .EIA Centre School of Planning and Landscape University of
Manchester.
AINA, P.O. (1994), National Briefing on the Implementation of EIA in Nigeria. November 1994,
Federal Environmental Protection Agency, Abuja.
AINA, P.O. (1999). Data Acquisition for Environmental Impact Assessment; Baseline
Environmental Studies. In Adegoke, O.S and Adewoye, R O (eds) Capacity Building for
Environment Impact Assessment in the Benue Trough. FME (1999).
ALO, B.I (1999) Environmental Impact Assessment (EIA) Process. In Adegoke, R.O and
Adewoye, R O. (Eds) Capacity Building for Environmental Impact Assessment in the
Benue Trough. FME (1999)
ELSEVIER, B.V (2009). “EA Legislation and Practice in Central and Eastern Europe and the
Former USSR, Comparative Analyses”. Environmental Impact Assessment Review Vol.
21, Issue 4 July 2001, pp. 335 – 361. http://www.sciencedirect.com/science? Print out
10/7/2009.
IBRAHIM Gaidam (2009). Why we opposed proposed construction of Kafin-Zaki Dam. The
Nation; November 12, 2009
ILEBANI, D (1999). A Good will Message by the Resident Representative of the World Bank at
the Opening Ceremony of the Capacity Building Workshop for Environmental Impact
Assessment in the Benue Trough held at the Hill Station Hotel, Jos from 22nd – 25th June,
1999. Proceedings of a Workshop.FME (1999)
121
KOGI STATE ENVIRONMENTAL PROTECTION AGENCY. (1995). A Bill for A Law for the
Establishment of Kogi State Environmental Protection Board. Lokoja.
LOHANI, B. W., EVANS, J.W., EVERITT, R. R., LUWIG, H., CARPENTER, R. A. AND TU,
S. L. (1997). Environmental Impact Assessment for Developing countries in Asia: Asian
Development Bank.
NGERI, S.B. (2010). Environmental Compliance Monitoring. A paper presented at the workshop
on strategies for a more effective EIA process in Nigeria organized by Federal Ministry of
Environment between 16th – 17th September 2010.
NWAFOR, J.C (2006). Environmental Impact Assessment for Sustainable Development: The
Nigeria Perspective: EDPCA Publications, Enugu.
NWAFOR J.C. (2007). Conducting an EIA on Project: Principles and procedures with a case
study of Thermal power projects. A paper presented at a 3 – day workshop on
Environmental Impact Assessment for public and private sector projects organized by the
Nigerian Society of Engineers (NSE) Enugu Branch. 1st – 3rd August, 2007.
PROJECT APPRAISAL FOR DEVELOPMENT CENTRE (PADC) 1981: A manual for the
Assessment of major Development proposals, HMSO, London.
SWAP (2003). Priority Waste StreamProject. Household HazaduousWaste Project, WASP LTD
UK
TOLBA (1981). Quoted in Nwafor, J.C (2006) Environmental Impact Assessment for Sustainable
Development, The Nigerian Perspective. EDPCA Publications.
WEAVER, A. AND SIBISI S, (2006). “The Art and Science of Environmental Impact
Assessment”. Science in Africa Online Magazine.
http://www.scienceinAfrica.co.za/2006/october/eia.htm.
WORLD BANK (1991). Environmental Aspect of Bank Work OD. 4. 01. Environmental Policies,
October 1991.
WORLD BANK (1998). Development of an Environmental Action Plan for Kogi, State Nigeria:
Triple “E” Systems Associate LTD.
124
APPENDIX A
Department of Geography,
Faculty of Social Sciences,
University of Nigeria,
Nsukka,
2nd December, 2012.
Dear Respondent,
Kindly help me fill the questionnaire to the best of your knowledge and understanding. Be
assured that the information given shall be used for academic purpose and be treated confidentially.
Thanks for your contribution to knowledge and desire for a safe and sustainable
environment.
Yours sincerely,
APPENDIX B
QUESTIONNAIRE
INSTRUCTION: Read through the questions carefully and tick correctly to the best of your
Name of Company----------------------------------------------------------------------------------
Office Address----------------------------------------------------------------------------------------
Rank--------------------------------------------- Destination----------------------------------------
INSTRUCTION: Please tick the box provided for eachof the following questions depending on
your knowledge.
SA= Strongly; Agreed A=Agreed; UD=Undecided; D=Disagreed; SD=Strngly Disagreed
QUESTIONNAIRE FOR RESPONSES BY THE PUBLIC ON ENVIRONMENTAL
IMPACT ASSESSMENT (EIA)
CLUSTER B
CLUSTER C
CLUSTER D
CLUSTER B
CLUSTER C
CLUSTER B
CLUSTER D
RESPONSES ON THE LEVEL OF COMPLIANCE OF DEVELOPMENT PROJECTS
WITH EIA BY THE PROJECT PROPONENTS
CODE QUESTIONS SA A UD D SD
D1 Kogi State operates a separate law regulating EIA
apart from the national guidelines
D2 All the local government in the state has power to
give EIA permit
D3 The state ministry of environment always organise
awareness programs to educate the public on EIA
D4 The state ministry of environment strongly enforce
EIA in the state
D5 EIA has been made mandatory for project
proponents in the state in all cases
D6 The state guidelines on EIA differs in many ways
from the federal procedural guidelines
D7 The state ministry of environment and the federal
ministry of environment operate the same
guidelines on EIA procedure
D8 There are many EIA reports in the state without
approval from the Federal ministry of environment
D9 There are no cases of EIA being rejected or
disapproved in kogi state
D10 The public has no access to copies of EIA reports
D11 There are some institution and agencies in the state
that train people on the best way to operate EIA in
the state
D12 The large number of agencies regulating EIA with
overlapping responsibilities in the state has further
advanced EIA in the state
D13 The larger number of agencies regulating EIA in
the state seems to confuse and discourage project
proponents in carrying out EIA
D14 The emphasis to do EIA in the state is mostly on
multinational projects
D15 EIA reports are now adopted as a sound tools for
decision making by the state government in
environmental matters
D16 The state government is yet to adopt EIA as a tool
for decision making policy
D17 The state is yet to establish an agency to punish
project proponents that failed to comply with EIA
regulations
135
CLUSTER C