You are on page 1of 22

Overview of Framework

for
Participative Models of Rail Connectivity
and
Domestic & Foreign Direct Investment

Published by
PPP Cell, Infrastructure Directorate
Ministry of Railways, Government of India
Rail Bhavan, New Delhi-110001
December 2014
Overview of Framework
for
Participative Models of Rail Connectivity
and
Domestic & Foreign Direct Investment

Published by
PPP Cell, Infrastructure Directorate
Ministry of Railways, Government of India
Rail Bhavan, New Delhi-110001
December 2014
C O N T E N T S

Foreword i

Messages ii

Introduction 1

Non-Governmental Railway Private Line Model 3

Joint Venture Model 6

Build Operate and Transfer (BOT) Model 11

Customer Funded Model 15

BOT Annuity Model 17

Engineering Procurement
Construction (EPC) Contract 18

Sectoral Guidelines for Domestic/Foreign


Direct Investment (FDI) in Railways 21

Annexure-I: List of Areas/Activity for Private/


Foreign Direct Investment 23

Annexure-II: Projects identified for domestic/foreign


direct investments in Railways 30
FOREWORD MESSAGE

Indian Railways require huge resources to augment its capacity and for modernization. Initiatives for Raising resources through Public Private Partnership for network strengthening and
building rail connectivity to ports and mines have been undertaken successfully by involving modernization is critical for Indian Railways which has to facilitate the economic growth of
customers. A Participative Policy was launched in December, 2012 subsequent to approval of the country.
Cabinet for undertaking rail connectivity and capacity augmentation projects through five
participative models. Financial commitments have already been made for 17 projects under this
Lot of work has been done in last few months in providing a thrust to private investment.
policy. The recent initiative of Government of India for opening up of Foreign Direct Investment (FDI)
in rail sector will also open up large opportunities for investment. Launching of new Model Concession Agreements and sectoral guidelines for Domestic/Foreign
Direct Investment are appreciable steps towards providing a good framework for attracting
The past experience shows that there is need for a transparent, balanced, fair and bankable framework private investments.
under which customers/investors can make investments in the rail sector. Ministry of Railways on the
basis of Participative Policy of December, 2012 has prepared Model Concession Agreements for I am happy to note that PPP Cell of Infrastructure Directorate, Railway Board has published this
different participative models. These agreements prepared by the Committee of Executive Directors document on “Overview of framework for participative models for rail connectivity and
at Railway Board in consultation with Legal Consultant and Ministry of Law provide a framework
Domestic/Foreign Direct Investment.” This document will be a useful source of reference to
for rights and obligations of different parties and risk allocation between them in a fair manner
thereby balancing risks and responsibilities. The agreements will be helpful to Government, investors/customers, consultants and financial institutions in explaining the key private
customers/investors and financial institutions/bankers to give a push to building and strengthening investment policies of Ministry of Railways.
rail infrastructure.
I hope the initiative will go a long way in attracting private investments in Railways.
Sectoral guidelines for Domestic/Foreign Direct Investment have also been prepared by the EDs
Committee in Railway Board after elaborate consultations with the various stakeholders including 5th December 2014
financial consultants, investment companies and Government agencies. These guidelines have
identified certain projects in different permissible areas. Broad salient features under which each
permitted activity can be undertaken are also provided for guidance.

The present booklet provides an overview of the framework for different Participative models, Manoj Sinha
projects to be undertaken through EPC and sectoral guidelines for Domestic/ Foreign Direct Minister of State for Railways
Investment. The overview captures the essence of the detailed agreements and sectoral guidelines. Government of India
I compliment PPP Cell of Infrastructure Directorate, Ministry of Railways for preparing the
agreements and sectoral guidelines. I am sure the document and the initiatives will enable Ministry of
Railways in attracting investments in rail sector.

5th December 2014

Suresh Prabhakar Prabhu


Minister of Railways
Government of India

i ii
MESSAGE INTRODUCTION

Indian Railways have successfully implemented certain port/ mine connectivity projects since
2002 involving its customers and users. A policy for participative models for rail connectivity and
capacity augmentation projects was issued in December, 2012 with the aim of attracting private
investments in building/construction of last mile connectivity's. The policy provides
following five models for implementation of various types of rail-connectivity and capacity
augmentation projects:
i. Non-Government Private Line Model
ii. Joint Venture (JV) model
Indian Railways, an engine of economic growth of the country requires continuous infusion of
funds and technology for its infrastructure and modernization. The resource challenge facing the iii. Build, Operate and Transfer (BOT) model
Railways has led to greater focus on alternative financing mechanisms. Globally, rail sector has iv. Capacity augmentation with funding provided by customers
found limited success with Public Private Partnership (PPP). However, the successful
experimentation on Indian Railways in building last mile connectivities for ports and mines v. Capacity augmentation through annuity model
since 2002 has enabled us to prepare investor friendly Model Concession Agreements which Three of these models (private line, JV and customer funded) involve participation of strategic
balances the interest of Government and private sector in an equitable manner. investors/customers and two other (BOT and Annuity models) are pure PPP models. Subsequent
to the policy, Model Concession Agreements have been prepared by the ED's Committee
Investment companies and financial institutions have given a positive feedback on the model
consisting of ED/Traffic/PPP, ED/Civil/Infra and ED/Finance/PPP for different models in
documents especially the agreement on BOT where Ministry of Railways had given comfort to
consultations with legal consultant and other stakeholders. The approved MCAs have been
the investors by covering part of the traffic risk.
uploaded on IR's website. These Agreements provide framework for balancing risks and
Initiative of opening of Foreign Direct Investment in rail sector by the present Government is an responsibility. New concepts like Reserved Services, Role of Independent Engineer,
important step to provide a framework for attracting investments which will also lead to Performance Guarantee, Escrow Account and Key Performance Indicators have been
modernization and technology infusion. Ministry of Railways has prepared sectoral guidelines incorporated. In BOT Agreement concepts like Projected Revenue, Traffic Risk by Government
for guidance of investors along with a basket of projects. and linking tariff with WPI have also been incorporated. In addition to the aforesaid model
agreements, a model EPC contract document for Railway Projects has also been prepared.
I compliment the PPP Cell of Infrastructure Directorate, Railway Board for the work done in last
one year for building an appropriate policy framework through which Domestic/Foreign Direct To attract Foreign Investment in the rail sector required changes in the policy framework.
Investment can be attracted. Government of India, vide Notification No. S.O.2113(E), dated 22nd August, 2014, reviewed its
policy for private investment in rail infrastructure and amended the list of industries reserved for
This document providing an “Overview of the framework for participative models and public sector under item No. 8 of Schedule-I of the Notification No.S.O.477(E) dated 25th July,
Domestic/Foreign Direct Investment” will enable better understanding of policies and initiatives 1991. Accordingly it has been decided to permit FDI in the following activities of the Railway
undertaken by Ministry of Railways for attracting private investments. Transport sector:
5th December 2014 Construction, operation and maintenance of the following:
(i) Suburban corridor projects through PPP,
(ii) High speed train projects,

Arunendra Kumar (iii) Dedicated freight lines,


Chairman, Railway Board
Ministry of Railways,
Government of India

Overview of Framework for Participative Models of


iii Rail Connectivity and Domestic & Foreign Direct Investment 1
(iv) Rolling stock including train sets, and locomotives or coaches manufacturing and
maintenance facilities, Non-Governmental Railway Private Line Model
(v) Railway Electrification,
(vi) Signaling systems,
(vii) Freight terminals,
(viii) Passenger terminals,
Need for the framework The present model aims to encourage
(ix) Infrastructure in industrial park pertaining to railway lines or sidings including electrified construction of private lines as multi user
Sea ports, large mines, logistic parks, and
railway lines and connectivity's to main railway line; and facilities as distinct from private sidings
other similar industries / industrial cluster
which are used by one or more pre-specified
(x) Mass Rapid Transport Systems. which serve large number of customers
users. The framework agreement of the
require efficient rail connectivity. Such
Ministry of Railways in November 2014 has also approved and notified sectoral guidelines for model permits maximum control of creating
utilities are like Indian Railways, which serve
Domestic and Foreign Direct Investment based on the recommendations of the Committee of such facilities to project developer/ owner.
various customers and are part of the logistic
Executive Directors consisting of ED/Traffic/PPP, ED/Infra (Civil), ED/Finance/PPP,ED/EE/ While implementing this model Zonal
chain. For such facilities, provision of
Development, ED/Mechanical/Projects and ED/Signal Development. Railway should try to minimize/optimize the
first/last- mile connectivity to the main
cost of construction and fasten the pace of
The present compendium provides an Overview of the five Models of Participative railway line needs to be construed as an
required approvals and avoid application of
Policy, framework of EPC contract and sectoral guidelines for Domestic and Foreign integral part of the main project.
private siding rules on such lines unless the
Direct Investment. The rail connectivity to such utilities/clusters framework or guidelines explicitly provide for
could be developed by the owner/ such application. Since the line will be a
concessionaire of the facility as private private infrastructure there is no concession
railway line by acquiring land and making period for transfer of assets to the Government.
investment in the line. This would be
NGR line to be Railway Administration
declared as Non-Government Railway for
public carriage of mostly goods but also Under the framework agreement,
passengers, if needed. All the relevant rules Government recognizes that the line built by
and regulations of Railways provided in the the developer on a private land is primarily a
Railway Act 1989 connected with the private infrastructure. Hence, there is no
operational, commercial and maintenance concession period for transfer of assets to the
aspects will be applicable to the Non- Government. However, since Ministry of
Government Railway. The owner/ developer Railways is required to pay user charges to
of the Non-Government Railway will be a the developer and since the line is to be
provider of fixed infrastructure. Funding, utilized by multi users, it is treated as
construction, maintenance and renewal of Railway Administration under the Railway
assets will be done by the owner of the Act, 1989. Treating project developer as
facility. The infrastructure will be used by the Railway Administration will allow them to
Indian Railways for transport of goods undertake construction and maintenance
including that of other customers, using their activity efficiently.
own freight wagons and locomotives. Indian
Construction, Monitoring and
Railways will pay to such Non Government
Supervision of Rail System
Railways user fee for usage of the
infrastructure. As the Rail System will be a private

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
2 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 3
infrastructure the developer at its own cost Operation & Commercial Reserved Services to be provided by construction of any new rail line or siding
and expense design, engineer, procure, Railways taking off from the rail system. However,
Indian Railways will provide seamless
construct, operate and maintain the rail developer will not bear any cost in relation to
operation on private line and IR network. Railways under the agreement have
infrastructure in terms of the agreement. The cost of such siding.
However, station staff and station operation undertaken to provide certain services which
developer has to undertake construction of
normally will be undertaken by the cannot be undertaken by the developer. Such Passenger Services
rail system within the specifications and
developer. The commercial activities related services have been named as Reserved MoR may undertake passenger services on
standards of MoR in a time bound manner.
to freight handling at the terminal will be Services. These Reserved Services pertain to the rail system with the consent of Developer.
For monitoring of construction, developer is done by goods clerk posted by IR whose cost providing rolling stock, crew, locomotion, However, all costs of operating such
required to appoint an Independent Engineer shall be borne by IR. Operations on the fixing of tariff, booking and delivery of passenger services shall be borne by MoR.
(IE) at its own cost. Any observation by private line by Developer, if required, can be consignment and safety examination of Cost of construction of any additional
Zonal Railways on drawings had to be permitted. rolling stock. This means Railways will facilities to facilitate passenger services shall
communicated in a time bound manner. undertake operation of trains on the Rail
Performance of Rail System be shared as mutually agreed by the
Zonal Railway is also bound to issue safety System. The charges for such Reserved developer and MoR.
certificate and commercial service certificate The developer has to maintain the Rail Services will be recovered as specified in
within a time bound manner. D&G charges System so that it achieves a minimum the agreement. Station operation and Termination
of 0.25% will be charged by concerned average speed of freight trains on quarterly management is expected to be handled by the Ministry of Railways (MoR) shall terminate
Zonal Railways from the developer in basis. This indicator captures the developer although the Agreement provides the agreement in case of default as specified
case construction of Rail System is being an option of this to the developer. in the agreement. Upon termination, MoR
performance of the Rail System . In case Key
done by the developer. No additional shall be entitled to take control of the railway
Performance Indicator (KPI) is not achieved, The developer will have to pay for railway
charges as specified for private sidings land and the assets built by the MoR.
damages at the rate of 1% of the user fee for staff , hire charges of wagons, locomotives
should be charged. Developer is also required to pay all direct
particular quarter will be levied on the and cost of running repair of wagons not
Zonal railway shall inspect and certify the developer for every 10% shortfall subject to a included in wagon hire charges, cost of costs incurred by MoR as consequence of
maintenance of the Rail System at least once maximum of 5% of the user fee. The damages fuel/energy, cost of crew. The overhead costs default. Similarly, developer can also
a year on payment of inspection charges are more in the nature of deterrent and not a at best Zonal Railway average will also be terminate the agreement in case of default
specified in the Agreement. revenue stream for MoR. charged only on the cost of crew, running by MoR. MoR in such case will be
repair of wagons and cost of railway staff. required to pay all direct costs incurred by
Technical Parameters Safety
This has been provided so as to insulate the the developer.
The Rail System will be built as per standards The responsibility for safety on the Rail developer from the impact of the system Approval
and specifications specified by Ministry of System will be that of the developer. The inefficiencies of Railways.
Railways. Since no investments of MoR are required in
safety requirements of railway shall apply to
Fare building such lines, the proposal will be
Maintenance and Capacity Augmentation all phases of construction, operation and
The developer does not have the flexibility to approved by Zonal Railways. The project
of Rail System maintenance. The developer has to ensure
charge their own tariff. IR tariff will be developer will submit a Detailed Project
The maintenance of the Rail System has to be adequate facilities for rescue operation on the
charged on the project line. Report (DPR) which establishes project cost,
undertaken by the developer. Service Rail System. Zonal Railway shall arrange
land requirement and other project
standards as enshrined in the agreement will relief and evacuation at the cost of developer, User Fee component requirements to Zonal Railway.
need to be observed. The developer will be if requested in writing by the developer.
MoR shall pay user fee as provided in the This report will be considered by Zonal
responsible for safety on the Rail System. In Concession Fee agreement. The developer will pay the cost of Railway and approval granted. In case
case the average daily traffic exceeds 120% reserved services as specified in the agreement. developer wants to obtain 'in-principle'
of the system charted capacity, the developer Ministry of Railways will provide land for
approval in absence of Detailed Project
will undertake necessary modifications to inter connection in a time bound manner at a Sidings
Report (DPR), the same will be approved by
augment capacity. nominal lease fees of rupee one per annum.
Ministry of Railways is entitled to undertake Railway Board.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
4 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 5
NTKM threshold. For this purpose the traffic project, has to construct the rail system in a
will be measured after a period of 25 years time bound manner, and can undertake
Joint Venture Model from signing of concession agreement. maintenance either itself or through Ministry
However, the concession period shall not be of Railways under a separate agreement.
less than 25 years or extended beyond 35
years. There would be no termination Financial close
payment in the event of natural expiry of
the concession period or attainment of the The Joint Venture Company has to achieve
Need for the framework regarding the bankability of projects as per said traffic. financial close within one year from the
the existing agreements. Many of these issues effective date. Extension of the same can be
In some railway projects, sanctioned or were addressed in the participative model The model provides flexibility to joint granted subject to payment of damages to
proposed to be sanctioned, it may be possible policy of December, 2012 which is the basis venture Company for entrusting construction Ministry of Railways at the rate of 0.1% of the
to identify the interested stakeholders who of the Model Concession agreement. and maintenance work. performance security for each day of delay.
may participate in funding to expedite
execution. Such projects can be The new policy of 2012 permits any of the Joint Venture line to be Railway Construction, Monitoring and
implemented through formation of a Joint Railway PSUs to participate in the joint Administration Supervision of Rail System
Venture (JV) with equity participation by the venture formed to implement the projects.
strategic investors. Two initial projects Already Joint Ventures have been formed Under the framework agreement, The JV has to undertake construction of rail
(Surendranagar-Pipavav Gauge Conversion with participation of Konkan Railway Government recognizes that the line built by system within the specifications and
and Hassan-Mangalore Gauge Conversion) Corporation (Jaigarh Port connectivity) and the joint venture company will be a Railway standards of MoR in a time bound manner. JV
with IRCON (Coal projects in Chhattisgarh). Administration under the Railway Act, 1989. must ensure transparency in project
through this route were implemented by
Such treatment on one hand grants certain procurement, however, it can entrust
Ministry of Railways. Subsequently five
The participating railway PSU or Ministry of rights to the joint venture company and also construction through IR or its agencies. For
New Line project for connecting various
Railways can undertake project subjects them to certain obligations under the monitoring of construction, JV is required to
ports (Kandla, Dahej, Krishnapatnam,
development. Railway PSU as far as possible Railway Act. Treating joint venture as appoint an Independent Engineer (IE). Any
Paradip and Angul- Sukinda) have been
should invest its own funds in the Joint Railway Administration will allow them to observation by Zonal Railways on drawings
undertaken through Rail Vikas Nigam
Venture. The Railway PSUs should call for undertake construction and maintenance need to be communicated in a time bound
Limited (RVNL). Under the Participative
Expression of Interest (EOI) for selection of activity efficiently. manner. Zonal Railway is also bound to issue
policy of 2012 issued by Ministry of
joint venture partners. The debt by joint safety certificate and commercial service
Railways these JV's will now be formed as Role of Joint Venture Company
ventures so formed should be raised without certificate within a time bound manner. D&G
per the guidelines of Joint Venture issued by
any guarantee from Government of India. charges of 0.25% will only be charged from
Department of Expenditure vide OM No: The joint venture company has to acquire the developer in case construction of Rail
24/PF.II /2009 dated 21st July 2009 with the Since the model is based on the guidelines of land in the name of Ministry of Railways for System is being done by the JV.
two deviations. First, selection of private the JV issued by the Department of construction of rail system or Railway may
sector equity partners will be done through Expenditure, the cap on return on equity as in acquire the land on behalf of JV, if so Zonal Railway shall inspect and certify the
Expression of Interest (EOI) on the basis of some of the existing Agreements has been requested. The company will construct, maintenance of the Rail System at least once
pre-defined technical qualifications based on removed. To address the issue of windfall maintain and operate rail system in terms of a quarter on payment of inspection charges
parameters like net worth, minimum gains the Agreement provides a review of the agreement. The company has to ensure specified in the Agreement.
threshold of equity participation etc. and concession in terms of traffic materialization commitment from its concerned shareholders
second project can be assigned to the JV by after a period of 25 years from signing of regarding having made 25% investment in Technical Parameters
Ministry of Railways on nomination basis. concession agreement. The concession target facilities. This will avoid creation of
joint ventures with non-serious shareholders. The Rail System will be built as per standards
period of 30 years will be reduced or
Number of issues was raised by the joint The joint venture company has to raise and specifications specified by Ministry of
extended symmetrically depending upon
venture companies formed by RVNL finance required for implementation of the Railways.
traffic exceeding/ going below a Projected

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
6 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 7
Maintenance and Capacity and evacuation at the cost of JV, if requested for the rail system will be calculated based on shortfall/excess in the actual traffic, the
Augmentation of Rail System in writing by the JV. proportionate distance but after setting aside concession period will be reduced or
the terminal charges as applicable at the time extended in terms of this agreement.
The maintenance of the Rail System can be Concession Fee of signing of the agreement. In case the rail However, the concession period shall not be
undertaken by the JV or can be entrusted to system involves a terminal, the applicable less than 25 years and will not be more than
Ministry of Railways through a separate Ministry of Railways will provide land for terminal charge would be paid to the JV 35 years.
Agreement. Service standards as enshrined in inter connection in a time bound manner at a company as part of user charges in addition to
the agreement will need to be observed. The nominal fee of rupee one per annum. the apportioned earning as per the agreement. Traffic Guarantees from Shareholders
costs of maintenance are not part of the
Reserved Services and have to be separately Reserved Services to be provided by In case the viability /bankability of the rail The traffic guarantees are not mandatory
borne by the JV. The JV will be responsible Railways system to be built by the JV company under this model. This is because the equity
for safety on the Rail System. In case the involves provision of the inflated milage holders take the risk in proportion of their
Railways under the agreement have investments. However, such guarantees can
average daily traffic exceeds 120% of the for the rail system, the entire additional
undertaken to provide certain services which be taken to mitigate the demand risk.
system charted capacity, the JV will earning on this account will be part of User
cannot be undertaken by the JV. Such Wherever such guarantees are taken, MoR
undertake necessary modifications to fee to be paid to the JV company without any
services have been named as Reserved has also to provide counter guarantee for
augment capacity. share to MoR. However MoR reserves the
Services. These Reserved Services pertain to provision of assured rolling stock.
right to review the percentage of inflated
Operation providing rolling stock, crew, locomotion,
milage on yearly basis depending upon the
station operation, fixing of tariff, booking Compensation for Breach of Agreement
growth of traffic on the rail system and
Indian Railways will provide seamless and delivery of consignment and safety
sensitivity of price to demand.
operation. examination of rolling stock. This means In case JV is responsible for any material
Railways will undertake operation of trains Sidings default or breach of agreement, it shall pay to
Performance of Rail System on the Rail System. Zonal Railways will MoR all direct costs suffered by MoR. MoR
retain 50% of the apportioned revenue as a Ministry of Railways is entitled to undertake has to pay all direct costs in case of its
The JV has to maintain the Rail System so cost for providing such Reserved Services construction of any new rail line or siding material default.
that it achieves a minimum average speed of inclusive of overhead charges, central taking off from the rail system. However, JV
freight trains on quarterly basis. In case Key charges and any incidental charges. The cost will not bear any cost in relation to cost of Passenger Services
Performance Indicators (KPIs) are not of maintenance of Rail System is not part of such siding.
achieved, damages at the rate of 1% of the the Reserved Services cost. The reason for MoR may undertake passenger services on
user fee for particular quarter will be levied not including cost of maintenance of the Rail Escrow Account the rail system with the consent of
on the JV for every 10% shortfall. The System in the Reserved Services is to achieve Concessionaire. However, all costs of
damages are in the nature of deterrent to the efficiency in maintenance through JV. The joint venture company has to open an operating such passenger services shall be
JV and are not a revenue stream for MoR. escrow account. This account will receive borne by MoR. Cost of construction of any
Fare all inflows of funds and withdrawals will additional facilities to facilitate passenger
Safety have to be strictly as per the provisions of services shall be shared as mutually agreed
The JV does not have the flexibility to charge the agreement. by the developer and MoR.
The responsibility for safety on the Rail their own tariff. IR tariff will be charged on
System will be that of JV in case the the project line. Concession period Termination
maintenance is undertaken by them. The
safety requirements of railway shall apply to User Fee Under this model, the normal concession Ministry of Railways (MoR) shall terminate
all phases of construction, operation and period is 30 years. However, at the expiry of the agreement in case specified defaults are
maintenance. The JV has to ensure adequate MoR shall pay full apportionment of revenue 25th year, the actual NTKM should be not cured within 60 days period. Similarly,
facilities for rescue operation on the Rail as user fee after deducting the cost of compared with the estimated NTKM for the JV can terminate the agreement if MoR fails
System. Zonal Railway shall arrange relief Reserved Services. The apportioned earning concession period. In case there is to cure its default within 90 days. Ministry of

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
8 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 9
Railways in case of JV's default during the with bankability report. Inflated mileage
operation period shall pay to the JV an should not normally be the basis for
amount equal to 90% of the debt due less
Build Operate and Transfer (BOT) Model
justifying unviable projects. The Railway
insurance cover and 70% of the amount PSU should ensure that requisite clearance of
representing Additional Termination concerned agencies is available for the target
Payment. In case termination is on account of facilities for which line is being constructed
MoR's default, JV will be paid an amount (in case of ports, mines, industrial
equal to full debt due plus 150% of the cluster/logistics park etc.). The Railway PSU Need for the framework communication between the concessionaire
Adjusted Equity and 115% of the amount should structure the project so as to limit the and MoR.
representing Additional Termination equity of MoR. Railway PSU as far as For the projects where it is not possible to
Payment. possible should participate in the project by identify any stakeholder, a BOT type model Conditions Precedent
utilizing funds from their own reserves. is suitable. Under this model the concession
Approval The rights and obligations under the
Railway Board depending on the documents will be awarded through competitive
agreement are subject to fulfillment of
will either give 'in-principle' clearance in the bidding. The concessionaire will design,
The Railway PSUs participating in the joint conditions precedent specified in the
first instance or will process for the approval build, finance, construct and maintain the
venture will undertake project development agreement. MoR has to procure the right of
of project. In case the project is already project line for a concession period of 25
to establish project costs, land requirement, way, approvals and permits etc to implement
sanctioned, only approval of Railway Board years subject to variation based on actual
project design, other project components and the project. The concessionaire needs to
is required, after necessary financial due traffic materialization vis-à-vis threshold
project bankability. Zonal Railway approval provide performance security and should
diligence, for implementing the project traffic indicated at the time of bidding.
should be taken for the DPR and the same execute escrow agreement, substitution
through joint venture route. Premium/grant (Viability Gap Funding) will
should be submitted to Railway Board along agreement, financing agreement as
be the bidding parameter. Demand risk, is
conditions precedent. Delay in fulfillment of
shared between concessionaire and MoR.
such conditions requires payment of
Since such railway systems will be mostly
damages to the tune of 0.1% of the
embedded systems, Indian Railways will
operate the trains on the rail system for performance security by MoR and 0.2% of
ensuring interoperability. the performance security by concessionaire
subject to maximum of 20%.
Concessionaire to be Railway
Administration Financial close

Under the framework agreement, The Concessionaire has to achieve financial


Government recognizes that the line built by close within 180 days from the date of the
the concessionaire will be a Railway agreement. Extension can be granted subject
Administration under the Railway Act, 1989. to payment of damages to Ministry of
This facilitates construction and maintenance Railways at the rate specified in the
by the concessionaire. agreement.

Golden Share Utility shifting

The concessionaire shall allot one equity The cost of utility shifting would be borne by
share in favour of MoR (Golden Share). The MoR. The reason is that MoR will have better
purpose of this clause is not to interfere into control on the costs of utility shifting through
the day to day functioning of the various government agencies than the
concessionaire but to facilitate better concessionaire

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
10 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 11
Construction, Monitoring and of the project time and again so as to affect Safety traffic as is conventionally done. A growth in
Supervision of Rail System timely delivery of infrastructure thereby projected traffic by itself may not get
The responsibility for safety on the Rail
affecting the revenue stream to the translated into corresponding revenue
The Concessionaire has to undertake System will be that of concessionaire. The
concessionaire. growth as Indian Railways operates different
construction of rail system within the concessionaire has to ensure adequate facilities
class of traffic with different freight rates.
specifications and standards of MoR in a time Technical Parameters for rescue operation on the Rail System. Zonal
Provision of projected revenue will provide
bound manner. The concessionaire is Railway shall arrange relief and evacuation
The Rail System will be built as per standards reasonable certainty and comfort to the
expected to complete the construction within at the cost of concessionaire if requested in
and specifications specified by Ministry of concessionaire to manage its finances
a period of four years. For monitoring of writing by the concessionaire. Safety audit at
Railways. effectively throughout the concession period.
construction, MoR shall appoint an least once a quarter has to be carried out.
To provide comfort to investor from any
Independent Engineer (IE). The cost of IE Maintenance and Capacity Augmentation
Concession Fee uncertain variation in freight rates the base
will be jointly shared. The purpose of of Rail System
tariff, i.e. the tariff applicable during the RFQ
appointment of IE and cost sharing is to Ministry of Railways will provide land at a
The maintenance of the Rail System shall be year is escalated annually at a rate linked
ensure neutrality of IE. Any observation by nominal fees of rupee one per annum.
undertaken by the Concessionaire or can be with WPI.
Zonal Railways on drawings need to be
entrusted to Zonal Railways on payment of Reserved Services to be provided by
communicated in a time bound manner. MoR shall pay 50% of apportionment of
costs. Maintenance requirements as Railways
The clearance of drawings shall be deemed to freight revenue as user fee. MoR would
enshrined in the agreement will need to be
be granted after the expiry of specified Railways under the agreement have guarantee 80% of the projected revenue
observed. Damages are paid to MoR in case
period. Zonal Railway is also bound to issue undertaken to provide certain services which during any year. In case actual user fee in a
concessionaire fails to rectify the defect
safety certificate and commercial service cannot be undertaken by the concessionaire. particular year is in excess of 120% or 150%
within the period specified in the agreement.
certificate within a time bound manner. D&G Such services have been named as Reserved of the projected revenue, 50% or 75% of the
Such damages are not in the nature of
charges of 0.25% will only be charged from Services. These Reserved Services pertain to excess revenue respectively will be paid to
revenue stream for MoR but more as a
the concessionaire in case construction of providing rolling stock, crew, locomotion, MoR by the concessionaire. This system has
deterrent to the concessionaire.
Rail System is being done by the station operation and management, fixing of inbuilt incentive for the concessionaire to
concessionaire. Operation tariff, booking and delivery of consignment make efforts to bring more traffic.
and safety examination of rolling stock. This
Zonal railway shall inspect and certify the Indian Railways will provide seamless The apportioned earning for the rail system
means Railways will undertake operation of
maintenance of the Rail System every month operation. will be calculated based on proportionate
trains on the Rail System. Zonal Railways
on payment of inspection charges specified in Performance of Rail System distances after setting aside the terminal
will retain 50% of the apportioned revenue
the Agreement. charges. In case the rail system to be built by
for providing such Reserved Services
The concessionaire has to maintain the Rail the concessionaire serves a terminal, the
Change of scope inclusive of overhead charges, central
System so that it achieves the Performance terminal charge as notified by MoR from
charges and any incidental charges. The cost
While a change of scope is permissible if Indicators specified in the agreement. time to time will be paid to the concessionaire
of maintenance of Rail System is not part of
MoR feels necessary, the agreement provides Failures to achieve these will result in as a part of the User Fee.
the Reserved Services cost.
that MoR shall have to make an advance damages to MoR. Key Performance
Indicators (KPIs) are provided in the The agreement provides for minimum
payment of 20% towards the cost of change Fare
agreement. These indicators capture escalation on projected revenue annually. In
of scope as agreed. This advance payment
IR tariff will be charged on the project line. the eventuality that such growth does not
ensures commitment of MoR towards change performance of the overall rail system
through average speed and also capture User Fee fructify during the concession period,
of scope. Also MoR cannot change the scope,
safety of the rail system by ensuring railway may decide to charge inflated
if it results in cumulative costs exceeding A new concept of projected revenue has been
performance on certain specified safety mileage for the rail system. However, the
20% of the total project cost. Such a clause introduced in this model instead of projected
parameters. additional earning on account of inflated
ensures that MoR does not change the scope

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
12 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 13
mileage will not be part of the User Fee to be Compensation for Breach of Agreement
paid to the concessionaire in any way. This
would facilitate management of down side
In case concessionaire is responsible for any Customer Funded Model
material default or breach of agreement, it
traffic risk being undertaken by railways.
shall pay to MoR all direct costs suffered by
Escrow Account MoR. MoR has to pay all direct costs in case
of its material default.
The Concessionaire company has to open an
escrow account. This account will receive all Termination Need for the framework deposited for the sole purpose of the project
inflows of funds and withdrawals will have to and will undertake construction and
Ministry of Railways in case of Some of the financially viable rail projects
be strictly as per the provisions of the operation of the rail system. Indian Railways
concessionaire default during the operation already sanctioned by MoR need to be fast-
agreement. MoR has to ensure that at the will make payment to the customer in the
period shall pay to the concessionaire an tracked to match with new capacities or
transfer date at least 5% of the total user fee form of rebate.
amount equal to 90% of the debt due less expansions being planned by major
for the preceding year should be available in
insurance cover and 70% of the amount customers. It is proposed to take project Construction, Monitoring and
the escrow account for meeting any liabilities
representing Additional Termination Payment. advance from such customers who may be Supervision of Rail System
after termination.
In case termination is on account of MoR's willing to come forward to invest in
Concession period default, Concessionaire will be paid an amount Indian Railways will undertake construction
augmentation of the capacity. In return,
equal to full debt due plus 150% of the of the rail system. The completion certificate
Under this model, the normal concession Railways will pay upto 7% of the amount
Adjusted Equity and 115% of the amount for the project will be issued by Chief
period is 25 years. In case the user fee on invested through freight rebate on freight
representing Additional Termination Payment. Engineer of the Zonal Railway if the line is
th
expiry of 20 year is falling short / exceeding volumes moved on the project section every
not constructed even within 180 days of
the projected revenue by 4%, the concession Approval year till the funds provided by the project
the schedule completion date, IR will have to
period will be increased / decreased by six beneficiary is recovered with interest at a rate
The project development and preparation of pay damages.
months for every 2% shortfall/enhancement. equal to the prevailing rate of dividend
DPR to establish financial viability and Rebate
However, the concession period shall not be payable by Railways to General Exchequer at
bankability will be done by Ministry of
less than 20 years and will not be more than the time of signing of the agreement.
Railways. Once the financial viability is Indian Railways shall pay the customer an
30 years. Normally MoR should start the The project is to be treated as Railway annual maximum rebate equivalent to 7% of
established with or without Viability Gap
process of reviewing the performance of the Project the disbursed amount along with interest. The
Funding (VGF), RFQ can be launched
rail system in terms of revenue at the start of rebate should not exceed the freight amount
either through Railway Board or by Zonal
19th year and should carry out such review The project will be sanctioned as a railway
Railway or through Railway PSU. PPP-AC in any accounting year. The Zonal Railway
annually after the end of 20 years to project after necessary due diligence and
route will need to be adopted for appraisal of on submission of annual claims from the
implement the provisions of the agreement. after ensuring availability of fund on the basis
such projects before final sanction of customer will pay the amount of rebate
of MOU/agreement entered into between
appropriate authority. within 30 days and will undertake post audit
Railways and customers wishing to fund the
of payments subsequently.
project in full or part.
Operation and Maintenance
Funding by the Customer
Indian Railways will provide seamless
The customer shall arrange and deposit the
operation and maintenance.
amount in the escrow account in accordance
with the disbursement schedule. Escrow Account
Obligations of Indian Railways An escrow account will be opened. This
account will receive all inflows of funds and
Indian Railways will spend the money so

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
14 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 15
withdrawals will have to be strictly as per the account of MoR's default, MoR shall pay to
provisions of the agreement. the customer an amount equal to 120% of the
disbursed amount. Similarly in case of
BOT Annuity Model
Default and Termination
customer's default, IR shall be entitled to
The failure to make disbursements of forfeit the disbursed amount.
investment amount will be treated as
Approval
customer's default. Similarly, IR will default
in case construction, operation and The project will be approved as a Railway Need for the Framework Selection of Concessionaire
maintenance is abandoned or rebate is not Project.
provided continuously. Upon termination on For projects where user charges cannot The Project will be appraised, approved
sustain the required private investment, an and awarded as laid out for Government
alternative to the user charge based BOT PPP project.
model is required, to execute various
Land and Utility
important projects of doubling, 3rd line,
fourth line etc. The Annuity model provides Land and utility shifting will be done by MoR
the framework to execute such projects or its entity.
which may not be covered under BOT model.
Nature of Concession
The Annuity model is also applicable to
execute such projects where it may not be The Concessionaire will be responsible for
possible to find funding from any specific financing and construction. Supervision and
user. Under this model, the construction risks Certification of construction will be done by MoR.
are allocated to the concessionaire and other Operations
risks such as traffic risk and all direct &
indirect political risks are assigned to the Train Operations and Maintenance will be
Authority. done by MoR. MoR will manage stations,
signals, level crossing gates etc.
Project Development
Revenue
Indian Railways will be responsible for
project formulation, DPR, Survey , Scale Payment to concessionaire will be through
Plans etc. The bidders will carry out their own annuity which is determined through
due diligence. competitive bidding.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
16 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 17
while payments are linked to specified stages or delays caused by or attributable to
Engineering Procurement of construction as compared to payment for the Authority.
Construction (EPC) Contract individual items/units under the item rate
Selection of contractor
contract. Awarding contract for a lump sum
price ensures predictability and financial
Selection of the contractor will be based on
discipline, both for the contractor and
open competitive bidding. All project
the Government. The contract price is
parameters such as the contract period, price
subject to adjustment on account of price
Need for EPC contracts challenges on Jammu-Udhampur rail link. adjustments and technical parameters are to
variation during the contract period as per
However, in railway sector, EPC model has be clearly stated upfront, and short-listed
specified formula.
Railways had hitherto been undertaking been extensively and successfully used by bidders will be required to specify only the
construction projects through the Delhi Metro Rail Corporation (DMRC) over Technical parameters lump sum price for the railway project. The
conventional item rate contracts where the the years. Accordingly, the processes for bidder who seeks the lowest payment should
Government provides the detailed design as design approval, supervision and monitoring The Model EPC Agreement specifies the win the contract.
well as the estimates of quantities for etc. have been incorporated in the Model required design standards and allows the
different items of work (Bill of Quantities). EPC Agreement as per the systems being Contractor to design and construct the project Risk allocation
Payments to the contractor are made on the followed in DMRC. using best practices to achieve quality,
basis of measurements of the work done in Projects risks such as soil conditions and
efficiency and economy as compared to the weather or commercial and technical risks
respect of each item. Experience in railway Model EPC Agreement item rate contract that relies on a single relating to design and construction have been
projects shows that item rate contracts are design provided by the Government.
The aforesaid drawbacks of item rate assigned to the Contractor. The Government
prone to excessive time and cost overruns due
contracting can be addressed by adopting the accepts its liability to pay damages to the
to delays in design and drawing, variation in Only the core requirements of design and
EPC approach that relies on assigning the Contractor for any delays in handing over the
items and quantities and inadequate fund construction of the railway project that have a
responsibility for investigations, design and land, approvals from road authorities for road
provisions as allocation of construction risks bearing on the quality and safety of assets are
construction to the contractor for a lump sum over-bridges/under-bridges at level
are largely to the Authority. Considerable to be specified and enough room would be
price determined through competitive crossings, environment clearances, shifting
time of Project Engineers is consumed in left for the contractor to add value. This
bidding. The objective is to ensure of utilities and approvals in respect of
dealing with variations in quantities, would provide the requisite flexibility to the
implementation of the project to specified engineering scale plan, signalling
introduction of Non-Schedule Items and contractor in evolving and adopting the interlocking plan and route control chart.
variation in contract price. standards with a fair degree of certainty efficient designs without compromising on
relating to costs and time while transferring the quality and safety. Design and Construction
The growing requirements of the economy the construction risks to the contractor.
will necessitate faster expansion of the Contract period The EPC agreement specifies the dates on
freight network through new capacity This Model EPC Agreement provides a which different sections of the land will be
creation. Considering that improved and contractual framework that specifies the The contract period is determined on a handed over to the Contractor. It defines the
modernised project execution capabilities allocation of risks and rewards, equity of project-specific basis depending on the scope of the railway project with precision
would be critical for speedy capacity obligations between Government and the volume of construction work involved. The and predictability to enable the Contractor to
creation, it has been decided to adopt the Contractor, precision and predictability Contractor shall be liable to pay Damages at determine its costs and obligations. It also
Engineering, Procurement and Construction of costs, force majeure, termination and the rate of 0.05 per cent for each day of delay lays down a ceiling of 10 per cent of contract
(EPC) mode of contracting for construction dispute resolution, apart from transparent beyond the specified date of completion, price to cater for any changes in the scope of
of railway projects. and fair procedures. subject to the total amount of Damages not project, the cost of which the Government
exceeding 10 per cent of the Contract Price. will bear.
On Indian Railways, EPC model has been The Contractor also has full freedom to plan However, the Contractor shall be entitled to
used earlier in a limited way for constructing the construction schedule for efficient use of time extension arising out of delays on The Contractor shall carry out survey and
some bridges posing technological its manpower, equipment and other resource account of change of scope and force majeure investigations and also develop designs and

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
18 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 19
drawings in conformity with the provided in the Agreement. It ensures that
specifications and standards laid down in the payments are made for works conforming to Sectoral Guidelines for Domestic/Foreign
Agreement. Government's engineer shall the Agreement and commensurate with the Direct Investment (FDI) in Railways
review the design and drawings to ensure that stages of completion of works. Works have
these conform to the scope of the project, been broadly divided into three categories,
design standards and specifications. The EPC namely, civil and track works, signaling and
agreement also stipulates provisions for telecommunication works and electrification
quality control and quality assurance. works, which could be taken together under a
single project or separately under different Objective vi. Holistic approach must be followed to
Monitoring and Supervision projects. Each item of work has been further ensure that the complete rail system all
To augment capacity, modernize and bring
sub-divided into stages and payment will be components rail, traction, rolling stock,
Monitoring and supervision of construction efficiency through technology up-gradation
made for each completed stage of work. signaling are compatible to ensure
are proposed to be undertaken through on Indian Railways network and to generate
efficient and safe train operation and
railway engineer to be designated as A provision has been made for damages finances for undertaking these activities from
achieve the objective.
'Authority's Engineer'. He would be assisted which the Contractor shall pay to both domestic and foreign investors.
by requisite organizational support for day- Government for not achieving the prescribed vii. Projects involving public carriage of
to-day interaction between the Authority and General Guidelines
milestones. Government will pay bonus to passenger would require safety
the contractor. Typical organizational the Contractor for completion of the project i. These sectoral guidelines pertaining to certification from Central government or
structure proposed to be followed for before the scheduled completion date. FDI complement the existing FDI its authorized entity before it is
Authority's Engineer shall be in line with the guidelines issued by Department of commissioned.
organizational set up being followed by Defects liability period
Industrial Policy and Promotion.
DMRC for monitoring and supervision of viii. For rolling stock operating on IR
their EPC contracts. The Authority's Though normally a defects liability period of ii. These sectoral guidelines pertaining to network, Inspection and Safety
Engineer will act as a single window for one year is specified in most contracts, a FDI do not override any laws/ Certification will be done by MoR or its
coordination with the contractor. defects liability period of two years has /regulation/rules issued by other authorized entity.
been specified in the Agreement in order
Government Departments regarding Rail
The Agreement provides for the schedule to provide additional comfort to the ix. FDI beyond 49% of the equity of the
projects unless expressly specified in
indicating the timeline within which Government. investee company in sensitive areas
Authority will ensure the clearances of these guidelines or in any of the
(border areas) from security point of
design proposals submitted by the contractor. Termination dispute resolution Concession/Contract agreements
view, will be brought before the Cabinet
Any comment by the Authority on the design pertaining to specific Rail Projects.
Committee on Security (CCS) for
proposals submitted by the contractor will be In the event the Government terminates the
Agreement on account of any of the specified iii. Ministry of Railways (MoR) reserves the consideration on a case to case basis.
communicated in totality once in a time- right to verify the antecedents of the
bound manner as indicated in the schedule. defaults of the Contractor, the Agreement x. Project proposals for Domestic/Foreign
allows the Government to forfeit the foreign collaborators and domestic
The clearance of drawings shall be deemed to Direct Investment in Railways (except
performance security of the Contractor. promoters including their financial
be granted after the expiry of specified period where no administrative approval is
in case no remarks/clearances are given by Similarly, defaults by the Authority are standing and credentials in rail or
required) can be submitted to
the Authority. proposed to qualify for adequate related sector.
Adviser(Infrastructure), Railway Board
compensatory payments to the contractor.
iv. Adequate safety and security procedures by Investor/Customer/Zonal Railway
Milestone based payments The Agreement also addresses issues relating
to dispute resolution and provides a should be in place during project along with a brief concept note including
A simple and rational method for estimating mechanism for the same. implementation and operation. objective, scope, benefits, market
interim payments to the Contractor has been potential, tentative project cost, probable
v. No unfair practices leading to unfair
financing options, pricing and economics
competition can be adopted by Investors.
for consideration of Railway Board.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
20 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 21
xi. PPP Cell along with concerned xv. For Projects pertaining to building Annexure-I
Directorates will assess the technical and rail connectivity's through Non
financial viability of the proposal, if felt Governmental model (Private Line), List of Areas/Activity for Private/
necessary, with the help of consultants. through Joint Venture and through
Foreign Direct Investment
If the proposal is found fit to Customer Funding under the
proceed further, the concerned Zonal Participative Model Policy of December
Railway/customer/ investor will be 2012, no bidding is required. For NGR
advised for further necessary action. For and JV projects the project developer/JV
Projects under Joint Venture (JV) models will submit the Feasibility Report along Sl. Area Permitted activity Salient features of Model Limit of FDI
No.
of the Participative policy 2012, “In with Bankability Report. Final Approvals
principle approval” will be granted by for such projects will be based on 1. Suburban All new suburban • Project Development by MOR or 100%
corridor corridor projects are its entity. investment
Railway Board. such reports. projects permissible when • Land, clearances and utility permissible.
through PPP. launched through PPP shifting by MoR.
xii. All Projects of rail connectivity's under xvi. After necessary technical and financial route by MoR. The • Design freedom to
NGR model of the participative policy due diligence the project would be developer can construct, concessionaire
2012 will be granted “in-principle appropriately structured (under various maintain and operate the
corridor within the • Model Concession Agreement
approval” by Railway Board. General PPP models) by PPP Cell of Railway concession period. for urban railways issued by
Manager of concerned Zonal Railway Board. Entire bid process management Planning Commission will be
adopted with project specific
will appraise and approve the project for including issue and finalization of RFQ / changes.
rail connectivity with existing IR RFP will be done by Zonal Railways. • Revenue stream to be the tariff
network under advice to Railway Board. collected by the concessionaire
xvii. If the project requires VGF, the approval along with revenue from real
xiii. In case any project involves adoption of of Ministry of Finance (Department of estate development, if any.
transparent bidding route, the Zonal Economic Affairs) would be taken • Concerned State Government to
enter into a State Support
Railway will get the Project Feasibility through PPP-AC procedure by PPP Cell Agreement.
Report along with the Detailed Estimates of Railway Board.
of the Project prepared. Railway Board 2. High speed Construction, • P r o j e c t D e v e l o p m e n t b y 100%
xviii.The concessionaire selected would be train projects. maintenance and Developer. investment
will undertake market survey, traffic operation of any new
free to establish SPVs and bring FDI. • MoR may on best effort basis, if permissible.
forecasting and financial modeling high speed train projects required, acquire land for the
including identification of risks and risk xix. The monitoring of the approvals of the which do not require project at the cost of developer
any linkage with Indian and facilitate transfer of such land
mitigation measures through an projects at different levels will be railway Network and on long term lease
independent financial consultant. coordinated by Advisor (Infrastructure), which are above 250 • Design freedom to developer.
Railway Board. kmph including supply
xiv. Model documents [Request for of rolling stock can be • Tariff freedom to developer
undertaken by the subject to maximum limit as
Qualification (RFQ), Request for xx. FDI is not permitted in Rail Operation specified by the Government or
developer.
Proposal (RFP) and Concession except in the activities listed in its entity.
Agreement (CA)] for each type of Project Annexure-I where it is specifically Construction, • Project Development by MOR or 100%
will be prepared by Railway Board. mentioned. Annexure-I provides the maintenance and its entity. investment
Project specific documents (RFQ, RFP & permissible activity under each potential operation of all new • Land, clearances and utility permissible.
high speed train projects shifting by MoR or designated
CA) would be prepared by Zonal Railway area along with limits of FDI and salient above 250 kmph Authority.
based on the model documents approved features. Annexure-II provides a list of including supply of
rolling stock can be • Design freedom to
by Board. potential projects. concessionaire.
undertaken by the

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
22 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 23
Sl. Area Permitted activity Salient features of Model Limit of FDI Sl. Area Permitted activity Salient features of Model Limit of FDI
No. No.
concessionaire in case • Model Concession Agreement 4. Rolling stock Construction, • No Administrative approval of 100%
the project is launched for urban railways issued by including train maintenance and MOR required in cases where no investment
on PPP or Planning Commission will be sets and operation of new procurement commitment is permissible.
under Government to adopted with suitable locomotives or locomotive/wagons/ made by MOR and no land lease
Government customization. coach coaches/train sets from IR is involved.
Cooperation. • Revenue stream to be the tariff manufacturing manufacturing facilities • MOR may on best effort basis, if
collected by the concessionaire and can be undertaken by
along with revenue from real required, acquire land for the
estate development, if any. maintenance Developer project at the cost of developer
facilities. and facilitate transfer of such land
• Viablity Gap Funding from
Government of India/Premium on long term lease.
for PPP project if required. • Land for rail connectivity in case
required will be provided on
Upgradation of the • Project Development by MOR or
lease.
existing Indian Railway its entity.
network for speed above • Operations and Maintenance by • Revenue from open market sales
120 kmph or semi high MOR or its entity. or from exports.
speed. • Maintenance of IR owned rolling
stock will be undertaken by MoR
or its designated Authority. Construction, • Land by private/MoR. 100%
• Right of Way by MoR or maintenance and • Connectivity by MoR. investment
designated Authority. operation of new • Bidding route to be adopted with permissible.
• Upgradation of existing locomotive/wagons/ bidding criteria being lowest bid
infrastructure by Concessionaire. coaches/train sets price for identified quantity.
• Concessionaire owned Rolling manufacturing facilities/
stock and its maintenance will be maintenance facilities
permissible with MOR approval. (including POH/Mid-
• Revenue stream through life rehabilitation of
Annuity/predefined share of rolling stock facility)
earning. can be undertaken in
case the project is
3. Dedicated Construction, • Project Report by Developer 100%
freight lines. maintenance and investment launched on PPP
• In principle Approval by MOR
operation of freight • Revenue sharing and O&M cost permissible.
lines under Non as per NGR (Private Line) Model However, in Renovation, • BOT/Annuity
Government Railway Agreement. joint venture maintenance and
model (Private Line) of projects under operation of any
Participative policy • Train operations by private Participative
2012. partners also permissible ,only on Policy 2012, existing locomotives/
certain private lines ,with prior 26% equity wagons/ coaches/train
approval of MoR will continue sets manufacturing/
to be held by maintenance facilities
Ministry of (including POH /Mid-
Railways or its life rehabilitation of
PSUs. rolling stock facility).
Construction and Joint Venture/BOT Model Agreement
maintenance of freight will govern the conditions. For rolling stock manufacturing facilities where MoR has invited
lines/mixed traffic lines Tr a i n O p e r a t i o n s i n c l u d i n g bids, the technology shall be brought in India and manufacturing
on the existing IR maintenance of rolling stock will be must be done in India with Transfer of Technology to MoR after
network. undertaken by MoR or designated predefined period.
Authority.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
24 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 25
Sl. Area Permitted activity Salient features of Model Limit of FDI Sl. Area Permitted activity Salient features of Model Limit of FDI
No. No.
5. Railway Construction, • Right of Way by Concessionaire. 100% 7. Freight Construction/ • Complete private investment 100%
Electrification maintenance and • Revenue stream will be annuity investment terminals/ upgradation, • M o R t o f a c i l i t a t e r a i l investment
operation of power based on saving in electricity permissible Logistics maintenance and connectivity under appropriate permissible.
transmission lines and tariff as a result of power Parks. operation of non-IR model
its ancillary facilities. purchase from power generating owned freight terminals. • Train operation including
companies. maintenance of IR owned rolling
stock will be undertaken by MoR.
Construction and • BOT/Annuity • Railway Land for connectivity at
maintenance of railway • Operation of electric traction on Re.1/- per annum.
electrification projects IR owned network will continue • Revenue sharing under
on the existing IR to be done by MoR. Concession Agreement.
network or new • Rolling stock can be procured
network. under extant policy of MoR.
6. Signaling Construction, • No Administrative approval of 100%
system maintenance and MoR is required in cases where investment
operation of new rail no procurement commitment is permissible. Construction/ • Transfer of Assets at pre
made by MoR and no land lease upgradation and specified nominal value
signal component
from IR is involved maintenance of any • Rail Connectivity by MoR
manufacturing facility.
• MoR may on best effort basis, if new/existing freight • Revenue sharing under
required, acquire land for the terminal owned by concession Agreement
project at the cost of developer MoR. • Train operations and
and facilitate transfer such land maintenance of IR owned
on long term lease Rolling Stock at such terminals
• Revenue from open market sales, will be the responsibility of
or in case such units are set up on MoR.
request of MoR, competitive
bidding route to be adopted with 8. Passenger Construction/ • Real estate development to be the 100%
bidding criteria being lowest bid terminals Redevelopment, revenue stream investment
price for identified quantity. terminal management • B i d d i n g C r i t e r i a t o b e permissible.
and maintenance of the premium paid by the
passenger terminals. concessionaire
Construction and • BOT/ Annuity • Train operation including
maintenance of new maintenance of IR owned rolling
signaling system on IR stock will be undertaken by MoR.
network or on any new
network
Construction, • BOT/Annuity
maintenance, terminal
Upgradation of signaling • Annuity
management and train
system on IR network
operation at passenger
terminals on standalone
private passenger
Signal equipments should be based on fail-safe design and meet
corridors/suburban
functional requirements. Software based vital signaling
equipments/systems should be validated and certified by a corridors/high speed
reputed Independent Safety Assessor (ISA) company to comply lines under concession
to Safety Integrity Level 4 (SIL4). from MoR.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
26 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 27
Sl. Area Permitted activity Salient features of Model Limit of FDI Sl. Area Permitted activity Salient features of Model Limit of FDI
No. No.
9. Railway Investments in • Land by private/railway 100% 12. Non- Construction, • Land lease by MoR at Re.1/- per 100%
Technical construction, • Revenue stream on competitive investment Conventional maintenance and annum if power is produced for investment
Training maintenance and bidding for identified number of permissible. Sources of operation of facilities use on IR or else at commercial permissible.
Institutes. operation of any trainees. Energy. producing power rates in other cases
training/education through non- • Revenue from open market sales,
facility either of MOR conventional sources of or in case such units are set up on
or outside MOR energy (solar, tidal or request of MOR, competitive
pertaining to wind). bidding route to be adopted with
training/providing bidding criteria being lowest bid
Construction, price for identified quantity.
education in areas maintenance and
pertaining to railways. • Appropriate Power Purchase
operation of facilities Agreement will be structured.
producing
10. Testing Construction, • Land by private/ railway 100% biodiesel/Alternate Fuel.
facilities and maintenance and • Revenue from open market sales, investment
laboratories. operation of any new or in case such units are set up on permissible. 13. Mechanized Construction, • Land lease by MoR at Re.1/- per 100%
testing facilities request of MOR, competitive Laundry maintenance and annum investment
pertaining to railway bidding route to be adopted with operation of facilities • Bidding criteria will be the lowest permissible.
bidding criteria being lowest bid tariff for identified units
activities including price for identified quantity.
laboratories.
14. Rolling stock Purchase/leasing for use • Extant policy of MoR to be 100%
procurement on IR network/private applicable. investment
Renovation, • BOT/Annuity lines permissible.
maintenance and
operation of any 15. Bio-toilets Installation and • Annuity 100%
existing testing facility maintenance of Bio- investment
pertaining to railway toilets in passenger permissible.
activities including coaches
laboratories.
16. Technological • Construction and • BOT/ Annuity 100%
solutions for maintenance of • For ROB / RUB revenue investment
11. Concessioning Renovation, operation • Transfer of Assets at pre specified 100% manned and ROB/RUB /Limited collection through Toll permissible.
of standalone and maintenance of nominal value investment unmanned Height Subway
passenger standalone passenger • Right of Way by IR permissible. level crossings • Installation and
corridors corridors including • Bidding criteria will be minimum maintenance of
(branch lines, branch lines, hill Safety Systems for
grant / maximum premium/Track
hill railways railways level Crossing gates.
Access Charge offered.
etc). • Concession period will be 10-15
years. 17. Technological • Installation and • Annuity 100%
solutions to maintenance of investment
improve Asset failure permissible.
Only operation by
Safety and detection systems
private operator on reduce (Track/ OHE/
payment of Track accidents Rolling
Access Charge but Stock/Signaling etc.)
maintenance including • Automatic self
maintenance of IR propelled Track/
owned rolling stock by OHE parameter
MoR. recording cars.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
28 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 29
Annexure-II Sl. Project Kms Cost Probable Mode of Bidding Parameter
No. (Rs in Crore) Execution
Projects identified for domestic/foreign 5 Durg-Rajnandgaon 31 152.99 BOT/Annuity VGF/Annual premium.
3rd line
direct investments in Railways 6 Wardha(Sewagram)- 76.3 297.85 BOT/Annuity VGF/Annual premium.
Nagpur 3rd line
(76.3 km)
7 Kazipet-Vijaywada 219.6 1054.35 BOT/Annuity VGF/Annual premium.
3rd line with
electrification
The list of projects mentioned below is indicative and new projects can be added or listed projects (219.64 km)
can be deleted depending on the outcome of project specific detailed technical/financial due 8 Bhadrak-Nergundi 80 837.33 BOT/Annuity VGF/Annual premium.
diligence by Ministry of Railways (MoR) after submission of the techno economic feasibility report 3rd line (80 km)
and financial/revenue model. Similarly the models of execution indicated are also indicative and 9 Sambalpur-Talcher 174.1 679.27 BOT/Annuity VGF/Annual premium.
can be changed depending on assessment later. The projects will be implemented only when found (174.11 km)
to be financially viable and bankable with VGF admissible (20% of the cost of the project or as 10 Manoharpur- 30 258.2 BOT/Annuity VGF/Annual premium.
modified from time to time) as per current VGF policy of Ministry of Finance. Bondamanda
3rd line (30 km)
11 Rajkharswan- 20 174.49 BOT/Annuity VGF/Annual premium.
1. Suburban Corridor projects through PPP Chakradharpur
3rd line (20 km)
Sl. Project Kms Cost Probable Mode of Bidding Parameter
No. (Rs in Crore) Execution 4. Rolling stock including train sets and locomotives or coach manufacturing and
1. CSTM-Panvel 49 14,000 DBFOT Premium/Viability maintenance facilities
Gap Funding(VGF)
Sl. Project Quantity Cost Probable Mode of Bidding Parameter
No. (Rs in Crores) Execution
2. High speed train projects
1. Rail Coach Factory, for 500 1,200 BOT/BOO/JV/ Annuity Lowest price per
Sl. Project Kms Cost Probable Mode of Bidding Parameter manufacture of modern 3 EMU/ EMU/MEMU
No. (Rs in Crore) phase MEMU/EMU MEMU
Execution
coaches equipped with coaches
1. Mumbai-Ahmedabad 534 63,180 DBFOT/ Government to Premium/VGF IGBT technology at annually
High Speed Corridor Government cooperation. Kachrapara.
(Subject to confirmation of
2. Chennai-Banglore- - - DBFOT/ Government to Premium/Viability requirement)
Mysore Government cooperation. Gap Funding(VGF)
2. Rail coach factory for 400 550 BOT/BOO/JV/ Annuity Lowest price per
manufacturing of coaches coach
3. Freight lines Aluminum coaches at per
Palakkad (Subject to annum
Sl. Project Kms Cost Probable Mode of Bidding Parameter confirmation of
No. (Rs in Crore) Execution requirement)
New Lines
3. Periodic overhauling of 180 300 BOT/BOO/JV/ Annuity Lowest price of POH
1 Dankuni-Gomoh 282 4500 BOT/Annuity VGF/Annual premium. wagons at Sonpur wagons per wagon
2 Whitefield-Kolar 52.9 353.45 BOT/Annuity VGF/Annual premium. per
(52.9 km) annum
3 North- South DFC - - BOT/ Annuity VGF/ Annual premium 4. Midlife rehabilitation of 250 185 BOT/BOO/JV/ Annuity Lowest price of
Doubling coaches at Anara coaches rehabilitation per
4 Ajmer-Bangurgram 48.43 144.57 BOT/Annuity VGF/Annual premium. per coach.
(48.43 km) annum

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
30 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 31
Sl. Project Quantity Cost Probable Mode of Bidding Parameter 7. Passenger Terminals
No. (Rs in Crores) Execution Sl. No. Project
5. Locomotive maintenance Barauni Rs. 300 crore BOT/BOO/ Lowest maintenance
depots. (ECR) BOOT/Annuity cost per locomotive. 1 Habibganj
Daund 2 Shivaji Nagar
(CR) 3 Anand Vihar
Mughal- 4 Bijwasan
sarai
(ECR) 5 Chandigarh
Bonda- 6 Surat
munda
7 Gandhinagar
(SER)
8 Manglore
9 Ernakulam
5. Railway Electrification Projects 10 Vijayawada
Sl. Project Kms Cost Probable Mode of Bidding Parameter 11 Nagpur
No. (Rs Crores) Execution 12 Byappanahalli
1. Katwa-Azimganj-Nalhati 200 229.26 BOT/Annuity VGF/Annual 13 New Bhubneshwar
& Azimganj- premium.
Tildanga/New Farakka
8. Railway Technical Training Institutes.
Sl. Project Quantity Cost Probable Mode of Bidding Parameter
6. Signaling System
No. (Rs in Crores) Execution
Sl. Project Kms Cost Probable Mode of Bidding Parameter 1. Advanced Training 6 Training 1,200 BOT/BOO/JV/ Annuity Lowest price per
No. (Rs in Crores) Execution Institute (ATI) for Centres – EMU/MEMU
training of Technical with Driving
1. Agra-Gwalior, A route: 118 250 Cr. BOT/Annuity VGF/Annual staff and Loco Pilots Simulators
provision of automatic premium. Mughalsarai
(ECR)
signaling along with train Kurla (CR)
protection system to Asansol (ER)
enhance line capacity. Vishakapatnam
(ECoR)
Kanpur (NCR)
2. Gwalior Burhpura A 126 280 Cr. BOT/Annuity VGF/Annual Avadi (SR)
route: Provision of premium.
automatic signaling along
with train protection 9. Mechanized Laundry
system to enhance line
capacity Sl. Project Quantity Cost Probable Mode of Bidding Parameter
No. (Rs in Crores) Execution
3. Burpura-Bina, A Route: 126 270 Cr. BOT/Annuity VGF/Annual 1. Mechanized laundries 1T/2T/3T/5T 100 BOT/BOOT/BOO/ Lowest Cost for
premium. at identified locations per day JV/Annuity identified quantity.
Provision of automatic
of different capacities.
signaling along with train
protection system to
enhance line capacity.

Overview of Framework for Participative Models of Overview of Framework for Participative Models of
32 Rail Connectivity and Domestic & Foreign Direct Investment Rail Connectivity and Domestic & Foreign Direct Investment 33
Contact Persons

Adviser/Infrastructure +91 11 23389215 advinf@rb.railnet.gov.in

Executive Director/ Traffic/PPP +91 11 23782539 edtppp@rb.railnet.gov.in

Executive Director/ Infra(Civil) +91 11 23382839 edinfrac@rb.railnet.gov.in

Executive Director/ Finance/PPP +91 11 23382783 edfppp@rb.railnet.gov.in

Overview of Framework for Participative Models of


34 Rail Connectivity and Domestic & Foreign Direct Investment

You might also like