WORK SCHEDULE
PROJECT TITLE:
TO SUPLY AND INSTALL ABS PIPE VARIETY SIZE AT KLCC GARDEN
WORKING DAYS
1 ENGINEERING 4 day
- Apply work permit
- Mobilization and preparation at site
- Safety brefing
2 Construction 45 day
- Digging works (manual)
- Lowering pipe
- Backfilling works c/w compaction
- To raise up existing 3 unit valve
3 Testing 4 day
- Pipe size 4 inch
- Pipe size 2 inch
4 Re-instatement work 4 day
- Grass
- Interlocking
5 Housekeeping 3 day
REMARKS