Costing sheet
< 1km - 8 days < 1km - 12 days
Enquiry Title : Interprint Deco M Sdn Bhd 1km - 10 days 1km - 14 days
Our reference : 2km - 14 days 2km - 20 days
RFQ reference : 3km - 16 days 1 branching 3km - 25 days
Customer : WOG 4km - 20 days 4km - 30 days
Length : NPS 6 - 120 mtr & NPS 4 -156 mtr 5km - 25 days 5km - 40 days
Product / Scope BOM & Description Uom Brand Supplier Unit Cost Qty
Mob Demob Preliminaries, Mobilization, Transportation lot 500.00
Lodging 800.00 0
Lorry Crane ( loader) 40ft - subject to area 3,000.00 2
Total Item
Total Cost
Total 500.00 Contigency
Contigency
Outsource No Days Unit Cost Total
Amount
Manpower
Supervisor 1 7 290.00 2,030.00
Fitter 1 7 255.00 1,785.00 Total Item
Helper 2 7 225.00 3,150.00 Total cost
0 0.00 0.00 Margin
Consummable Total 6,965.00 Selling Price
White tape, Paint, arrow, etc 1 300.00 300.00
300.00
Total Material
Cost
-
-
6,000.00
260.00
90.00
400.00
160.00
180.00
100.00
100.00
270.00
-
-
1,200.00
-
-
-
1,050.00
350.00
980.00
360.00
100.00
11,500.00
Cost
11,500.00
7765.00
19265.00
Contingency
19,265.00
0.00
Margin
19,265.00
31.20%
28000.00