AS PER ORDER / CONTRACT AS PER ACTUAL DELIVERY / WORKS DONE


Qty Previous This Period To-date Remaining
Item Description UOM Unit Rate Amount
nos days/hrs % Qty Amount % Qty Amount % Qty Amount % Qty Amount

A SUPERVISION
1 Supervisor / Safety Officer pax 1 30 1,500.00 3.00 3.00 27.00
B SKILLED WORKERS -
2 Foreman pax 2 30 1,000.00 6.50 6.50 53.50
3 Alloted Overtime hrs 120 125.00 4.00 4.00 116.00
4 Leadman pax 3 30 700.00 0.00 - 90.00
5 Alloted Overtime hrs 180 87.50 375,375.00 0.00 134,779.22 - 134,779.22 180.00 240,595.78
6 Carpenter/Steelman/Mason pax 120 30 680.00 124.00 124.00 3,476.00
7 Alloted Overtime hrs 7200 85.00 143.50 143.50 7,056.50
C NON-SKILLED WORKERS -
8 Helper/Laborer/Timekeeper pax 24 30 550.00 21.00 21.00 699.00
9 Alloted Overtime hrs 1440 68.75 32.50 32.50 1,407.50
D GENERAL REQUIREMENTS - - - -
10 NBI/Medical pax 150 1,500.00 225,000.00 70.00 105,000.00 70.00 105,000.00 80.00 120,000.00
11 PPE pax 150 2,250.00 337,500.00 70.00 157,500.00 70.00 157,500.00 80.00 180,000.00
12 Full Body Harness pax 40 3,000.00 120,000.00 20.00 60,000.00 20.00 60,000.00 20.00 60,000.00
13 Accommodation lot 1 80,000.00 80,000.00 - - - 1.00 80,000.00
14 Transportation lot 1 120,000.00 120,000.00 - - - 1.00 120,000.00
15 Mobilization pax 150 1,000.00 150,000.00 70.00 70,000.00 70.00 70,000.00 80.00 80,000.00
16 Demobilization pax 150 1,000.00 150,000.00 - - - 150.00 150,000.00

Total Amount VAT Exclusive 1,557,875.00 0% - 34% 527,279.22 34% 527,279.22 66% 1,030,595.78

Summary
NOTES BY P&C: For goods, quantities are base on the GRN. Prpgress Billing #1 392,500.00
For accomplishments, all quantities are verified by the Operation's Team. Prpgress Billing #2 134,779.22
For equipment, all quantities are based by DTR signed by Operation's Team. Total 527,279.22
All unit cost/rates are aligned in the PO/Contract.

Prepared by:

SHARLENE P. MANALOTO
Quantity Surveyor