Professional Documents
Culture Documents
Version : 1.1
Prepared by:
Confidential
YSNet Phase II Project
Author’s Details
Name: Lau Hee Kiong Mohd Shahrul Faiz Bin Mohd Nor
Signature:
Date:
Signature:
Date:
Signature:
Date:
Author's Details
Name: Lau Hee Kiong Mohd Shahrul Faiz Bin Mohd Nor
Name:
Designation:
Signature:
Jason Goh Yiam Hong
Project Director
r
.
,
,1/4v
oLoG4,
-/-
15
7,
4,.4 .7
Date:
72.1 i>i)
4vAti o AAfpc''/.
Acknowledged / ' ccept.. By Ministry of Culture, Youth and Sports (MCYS):
• Name:
Designation:
Department:
Signature:
Awang Haji Abd Malik Bin Haji Mohammad
A .1Va. OA \.',;::
„„..------
_) ,c
.;k-
_
_,,
\N ,F,--e4,
•
-,
i-
iv
4;
:f )
)
r
Date: \
21
f
7(10, (3 --_
---- _______-----
\\,,
"r'4 ---......
Date: ''?UtVE; D AB/
-2 ) 1 7 I -2A% \_
Revision History
Document Distribution
Item Distribution Comment
1. Acting Director of Youth and Sports, Department
of Youth and Sports
Acronym/Abbreviation Description
MCYS Ministry of Culture, Youth and Sports
MR Millennium Radius
Table of Contents
1.0! INTRODUCTION ............................................................................................................. 1!
1.1! BACKGROUND ................................................................................................................ 1!
1.2! PROJECT OBJECTIVES.................................................................................................... 1!
1.3! DOCUMENT OBJECTIVE .................................................................................................. 2!
2.0! SCOPE ............................................................................................................................ 3!
2.1! PROJECT INITIATION ....................................................................................................... 3!
2.1.1! Resource Mobilization ........................................................................................... 3!
2.1.2! Project Kick-off ....................................................................................................... 9!
2.1.3! Site Preparation ..................................................................................................... 9!
2.1.4! User Requirement Study ..................................................................................... 15!
2.1.5! Project Initiation Document (PID) ........................................................................ 18!
2.2! PROJECT EXECUTION ................................................................................................... 19!
2.2.1! Discovery ............................................................................................................. 19!
2.2.2! Analysis and Design ............................................................................................ 19!
2.2.3! Develop ................................................................................................................ 19!
2.2.4! Deploy .................................................................................................................. 19!
2.3! PROJECT CLOSURE ...................................................................................................... 20!
3.0! DELIVERABLES & COMPLETION CRITERIA ............................................................. 21!
4.0! PROJECT MANAGEMENT APPROACH ..................................................................... 22!
5.0! PROJECT TEAM STRUCTURE .................................................................................... 25!
5.1! PROJECT ORGANIZATION CHART .................................................................................. 25!
5.2! ROLE AND RESPONSIBILITIES ........................................................................................ 26!
6.0! HIGH LEVEL PROJECT TIMELINE .............................................................................. 28!
7.0! DESIGN SOLUTION ...................................................................................................... 29!
7.1! HARDWARE .................................................................................................................. 29!
7.2! NETWORK DIAGRAM ..................................................................................................... 34!
7.3! SOFTWARE, SYSTEM & APPS ........................................................................................ 35!
7.4! OPERATION CENTRE (BY KONSULTAN MWH)................................................................ 40!
7.5! SPORTS MEDICINE AND RESEARCH CENTRE (BY MCQUIPP) .......................................... 51!
8.0! COMMUNICATION PLAN ............................................................................................. 58!
9.0! ISSUE AND CHANGE MANAGEMENT ........................................................................ 59!
9.1! ISSUE MANAGEMENT .................................................................................................... 59!
9.2! CHANGE CONTROL MANAGEMENT ................................................................................ 59!
10.0! RISK MANAGEMENT ................................................................................................. 62!
11.0! TRAINING PLAN ......................................................................................................... 65!
11.1! ON THE JOB TRAINING ............................................................................................... 65!
11.2! INSTRUCTOR LED CLASSROOM TRAINING .................................................................... 65!
12.0! CLIENT RESPONSIBILITIES ...................................................................................... 67!
13.0! FINANCIAL MANAGEMENT ...................................................................................... 68!
13.1! OTHER EXPENSES ..................................................................................................... 68!
13.2! PAYMENT SCHEDULE ................................................................................................. 68!
14.0! APPENDIX ................................................................................................................... 72!
List of Figures
List of tables
1.0 Introduction
Evolving existing systems in Ministry of Culture, Youth and Sports (MCYS) to support
business process change has been given a new dimension by the development of
Internet technologies. These technologies offer the opportunity for platform-
independent distributed working and allow Government Agencies to consider
radically different ways of accessing and using their information resources. These
technologies are 'open' and solutions are pieced together from heterogeneous
components from different sources.
The proposed system will allow the employees to remain in-sync and informed about
critical company information, policies and work processes. It would keep the office
organized and easily manageable by internal management systems.
The proposed system will allow the planning and organizing youth activities online,
manage facilities booking, and to increase number of member of communities,
without compromising on the factor of security.
With the built in login tool and tightly integrated security, MCYS now can benefit from
a robust system solution that is accessible by authorize personnel by 24/7. Users
can each have permissions, which would enable them to use the shared information
appropriate to them, be they are the administrators, project managers or team
members.
1.1 Background
The Ministry of Culture, Youth and Sports is seeking a solution that will provide an
optimal combination of implementation, change management services and skills
transfer to Department of Youth and Sports staffs whilst also meeting Department of
Youth and Sports critical requirements for functionality and business needs.
6. Event management,
7. Operation Centre
12. SMS and MMS gateway and mobile apps using existing government
approved TELCOs SMS and MMS gateway,
The purpose of this document is to define the project, explain the project
implementation including deliverables and completion criteria, project management
approach, project team structure, high level project timeline, communication plan,
issue and change management, risk management and training plan. It also gives the
direction and scope of the project and acts as a base document against which the
project can be assessed for its progress, issues and ongoing viability questions so
that people joining the team can quickly and easily find out what the project is about
and how it is being managed.
This document provides the basis for a common understanding of the project,
including defining activities that are considered within and beyond the scope of the
project.
Project Management is one of the crucial parts of the deployment for the entire
system development. The project vendor deployed all the necessary project
management control and plans in order to deliver all the required tasks and
deliverables according to timeline and meet the entire preferred requirement by
YSNet.
The project vendor team will kick-off the project according to the proposed timeline.
Key Personnel that will involve in this project are:
Project Role
IC /
No. Name
Passport No. Team / Staff
Sub-Team Category
Project Role
IC /
No. Name
Passport No. Team / Staff
Sub-Team Category
Technical
25. Elpedio Jr Butihin Asas (D1) 51-146267 Team
Support
Technical
26. Mohammad Azmi Hj Hamzah (D1) 00-296988 Team
Support
Site
27. Jonathan Tan (D1) 50-790379 Team
Preparation
Site
28. Kioh Chii Yong (D1) 01-096566 Team
Preparation
Site
29. Nicholas Lau (D1) 50-794146 Team
Preparation
The project vendor engineers and developers appointed for this project not only able
to develop the required system but also able to do integration works with third party
vendors. The project vendor Software Development Unit adopts a well-documented
process, and the engineers are all well equipped with the cross platform skills.
The project vendor multimedia designers and programmers posses this skills and
certifications:
• Adobe Flash ActionScript 1.0
• Adobe Flash ActionScript 2.0
• Adobe Flash ActionScript 3.0
• ASP, ASP.net
• PHP
• C#
• Java/ JSP
• iOS
• HTML5
• CSS3
The project vendor engineers combined posses these skills and certifications:
• Microsoft Certified Professional
• Linux Certification
• IBM Blade Certification
• AIX Certification
• VMWare Certification
• Java Certification
No of Years of
Basic Skill
experience
More than 5
Database: Informix , MYSQL , Ms SQL Server
years
More than 5
Operating System:Windows, ,Red Hat Linux, AIX
years
Programming Language:Java, Java Script, PHP, ASP, More than 5
ASP.Net, C# years
More than 5
Development Tools: Eclipse
years
More than 5
Modelling:Rational Rose UML
years
Client Presentation:DHTML with java script, Java Applet, More than 5
CSS, XML years
More than 5
Middle Tier:Java EJB, Spring Framework,Hibernet,Struts
years
Application & Web Server:Apache HTTP Server, Apache More than 5
Tomcat, Websphere Application Server, Web Service years
Application Design Standard:JSP Model2 & MVC using
More than 5
Struts, Component based architecture, n-tier architecture,
years
client server architecture
Java Specification:J2EE (Java mail, EJB, JSP, Servlet, More than 5
JNDI, JDBC) years
More than 5
Protocol:HTTP, SSL, TCP-IP, FTP, HTML
years
More than 5
Knowledge in document imaging system
years
This project will be broken into 8 phases. For each phase, it will be lead by The
project vendor experiences team member.
i) Preparation Scheduling
ii) The development will be held concurrently at two sites which are at:
• Main Office
B-3A-2, Setiawangsa Business Suite, Jalan Setiawangsa 11, Taman
Setiawangsa, 54200 Kuala Lumpur, Malaysia.
• Site Office
Unit 17, 1st Floor Jaya Setia Square, Jalan Berakas, Brunei Muara -
BB2713, Brunei Darussalam.
iii) Equipment
• Application Server
• Database Server
• Web Server
• CENTOS
• PENTAHO
• JOGET V3
• T ALEND Open Studio
• RAM: 4 Gb
• CPU: 2 CPU
• Disk space: 200 Gb
• Application Server
• Database Server
• Web Server
• Enterprise Portal - Enterprise Content Management
System (ECMS) cum Document Management System
(DMS)
• API for SMS Gateway
with the following software and configuration:-
• CENTOS
• PENTAHO
• JOGET V3
• TALEND Open Studio
• RAM: 8 Gb
• CPU: 2 CPU
• Disk space: 200 Gb
A study has been conducted to understand the various processes involved in YSNet
and recommended improvement processes have been identified in BPR
Consultancy Report.
The project vendor will conduct User Requirement Study to re-confirm the findings
and review the recommendations/ conduct new Business Process Re-engineering
(BPR) in line with current changes and requirements especially for new additional
agencies, processes and functionalities within Department of Youth and Sports and
related agencies under Ministry of Culture, Youth and Sports (MCYS) as follows:
1. Youth Section - provide several different youth activities and organize events,
nation-wide and international. It also provides support to youth organizations
and youth self-development programmes.
User Requirement Study will confirm the flow and requirement of:
Youth Section
1. Propose Youth Activities
2. Propose National Youth Activities
3. Organise Youth Activities
4. Organise National Youth Activities
5. Assistance For Youth Activities Of Youth Associations
6. International Youth Events
7. Ship For South East Asia Youth Programme (SSEAYP)
8. Commonwealth Roc
9. Process Financial Assistance For Youth Associations
10. Training For Youth Associations
11. Youth Development Centre Course Planning
12. Youth Development Centre Course Execution
13. Outward Bound School Course Process
14. Outward Bound School Activities Process
15. Propose Youth And Sports Activities In District Process
16. Execute Youth And Sports Activities In District Process
17. Booking Of Facilities In Youth Centre Process
18. Booking Of Hostels In Youth Centre Process
Sports Section
1. Process Financial Support To Take Part In A Tournament
2. Process Time Off From Work And School For Training
3. Process Unrecorded Leave For Overseas Trip
4. Athlete Data Management
5. National Team Selection
6. National Incentives Scheme
7. Sports Association Blueprint And Planner
8. Process Proposal For Sports For All (SFA)
9. Propose Sport Activities For Youth
Operation Centre
1. Assets and Facilities Monitoring system)
2. Multimedia Meeting equipment to include video, projection and internet
access with multimedia desk top PC
3. Integrated and Interactive Geographical Mapping (using satellite image map)
of strategic information with dynamic profiles. The system shall use the
Google Earth platform of EGNC should it be ready during the development
phase of the project.
• MCYS and departments assets and facilities
• Private sector owned assets and facilities (sports, associations,
historical, welfare, cultural etc.)
• Natural disasters
• Poverty mapping
• Heritage sites
• Events and activities
• Others
4. Engage with the existing vendor of Public Works Department Customer Care
Centre, Konsultan MWH for Item 1 and 3 above.
5. Events management including events and activities calendar, profiles,
programmes, committees, budget, scheduling etc.
6. Public access terminals.
During this phase, the project vendor will baseline the project schedule, definition,
scope, deliverables and obtain sign-off from MCYS (This document).
2.2.1 Discovery
2.2.3 Develop
2.2.4 Deploy
This phase is the deployment phase based on the agreed Design Solution and the
Installation Plan at OGPC.
The deployment phase will cover two major sites, namely GNOC1 and GNOC2 at
the following address:
GNOC1:
E-Government National Centre,
GNOC2:
Ministry of Finance,
Level 3, Ministry of Finance Building,
Commonwealth Drive,
Bandar Seri Begawan BE3910,
Negara Brunei Darussalam.
The table 1 below depicts the project deliverables and its acceptance criteria.
Hardware and Refer to Bill of Materials in Purchase Order MCYS Sign off
OTS Software and/or Delivery Order. the
Delivery Order.
Project Closure Project completion form when all the project MCYS Sign off
deliverables are completed and delivered. the Form with
attached Delivery
Order.
In this section, the project management approach includes a number of elements of process
groups, and a control system. The basic project management processes will be used and
major process groups generally include:
• Initiation
• Planning and Design
• Production and Execution
• Monitoring and Controlling
• Closing
1. Initiation Stage
The initiating stage will include a plan that encompasses the following areas:
• analyzing the business needs/ requirements in measurable goals
• reviewing of the current operations
• stakeholder analysis, including users, and support personnel for the project
• Project Initiation Document including costs, tasks, deliverables, and schedule
After the initiation stage, the project is planned to an appropriate level of detail. The
main purpose is to plan time, cost and resources adequately to estimate the work
needed and to effectively manage risk during project execution. As with the Initiation
process group, a failure to adequately plan greatly reduces the project's chances of
successfully accomplishing its goals.
3. Executing Stage
Executing consists of the processes used to complete the work defined in the project
plan to accomplish the project's requirements. Execution process involves
coordinating people and resources, as well as integrating and performing the
activities of the project in accordance with the project management plan. The
deliverables are produced as outputs from the processes performed as defined in the
project management plan and other frameworks that might be applicable to the type
of project at hand.
5. Closing Stage
Closing includes the formal acceptance of the project and the ending thereof.
Administrative activities include the archiving of the files and documenting lessons
learned.
Project Management is one of the crucial parts of the deployment for the entire
system development. The project vendor have prepared all the necessary project
management control and plan in order to be able to deliver all the required tasks and
deliverables according to timeline and meet the entire preferred requirement by
YSNet.
Roles Responsibilities
Project • Represent the key organizations involve in the project oversight
Steering and control, and any other key stakeholder groups that have
Committee special interest in the outcome of the project.
• To act individually and collectively as a vocal and visible project
champion throughout their representative organizations;
generally they approve project deliverables, help resolve issues
and policy decisions, approve scope changes, and provide
direction and guidance to the project.
• To provide resources, assist in securing funding, act as liaisons
to executive groups and sponsors, and fill other roles as
defined by the project.
• To advise on legal and commercial issues.
Danawan • Resource Person to Project Steering committee representing
Project project vendor.
Director
Danawan • Coordinate and manage the project’s procurement.
Account • Coordinate the delivery and sales related matters.
Manager • Deal with any commercial and legal issue arises from change
management process.
Danawan • Responsible for overall project management.
Project • Lead and manage the project team resources.
Manager/s • Prepare status reports and organize project meetings.
• Perform project coordination, project planning, and project
management.
• Monitor quality and costs and maintain the schedule.
• Communicate with MCYS Project Director as sole point of
contact for MCYS.
• Deliverables review and ensures successful completion.
• Acceptance Sign Off.
• Manage the change management processes.
• Ensure project conforms to the IT standards and procedures.
• Coordinate and manage the product trainings for SC with
training providers.
Danawan • Assist Project Manager.
Deputy Project • Perform random quality check on the workmanship and
Manager / QA configuration to ensure quality deliverables
• Review project documentation.
Roles Responsibilities
Engineers • Document and conduct the IAT and UAT.
• Develop the design document, configuration and operational
guide.
• Knowledge transfer to MCYS project team.
MCYS • Overall project oversight and control.
Chairman of • Resolve issues and policy decisions.
Project • Approve scope changes.
Steering • Provide direction and guidance to the project.
Committee • Advise on commercial issues.
MCYS Responsible to MCYS Chairman of Project Steering Committee for
the following:
Project
Director • Project champion.
• Member of Steering committee.
• Single point of contact for Danawan’s PM.
• Co-own project plan.
• Monitor progress of project.
• Assign resources to respective subject matters.
• Organize/schedule meeting facilities and support.
• Verify, approve and sign-off the project deliverables.
MCYS Responsible to MCYS Project Director for the following:
Project • Main coordinator for day-to-day operational tasks of the project
Manager assigned by MCYS Project Director.
• Assist MCYS Project Director in monitoring progress of the
project.
MCYS Responsible to MCYS Project Director for the following:
Senior System • Review and verify the technical deliverables of the project
Analyst (products and solution).
• Coordinate and supervise the technical undertakings and tasks
of the project by the project vendor.
• Coordinate, supervise and verify the conduct of IAT and UAT of
the project.
Table 2: Project Team Member Role and Responsibility
D$J*'4
!""#$
EGNC Data centre !"#$%&'((((((((((((((( !"#$
Prime Minister’s Office, Brunei Darussalam )**"+,%-"(./,"((( !%&$'()*+$#,!-$
Infrastructure As a Service & 0"*"#"'+"(1&2( $
Storage As a Service
5"#-%+"(6( ./,"( (
$$
8%'%$,#9( 8%'%$,#9(&*(:;<,;#"=(>&;,?(/'@(5A&#,$(
."A/#,7"',( ."A/#,7"',(&*(>&;,?(/'@(5A&#,$(
B#&C"+,(1/7"( >51",(
B#&C"+,(0"*"#"'+"( (
$
B#&C"+,(8/'/D"#(.",/%<$((
1/7"( .E(>/,%(F%',%(BD(GC(0;7F<%(
)H7/%<(I@@#"$$( >/,%J#;7F<%KF"<%/H$;E/'JD&-JF'(
:&',/+,(1&J( LLMM4NO(
(
5"#-%+"(0"P;%#"@(
B<"/$"($"<"+,(&'"($"#-%+"2(
Q((((((R(1"S(0"P;"$,(*&#(B#&@;+,%&'(((((((((Q((((((R(1"S(0"P;"$,(*&#(BT:((((((((Q((((((R(U"#7%'/,%&'(0"P;"$,(
((
IJ V'*#/$,#;+,;#"(/$(/(5"#-%+"(Q((((((R(
5A"+%*%+/,%&'( WB<"/$"(*%<<(%'(/,,/+?"@(*(X/Y(
1&,"2(6&#(.8Z(=(A<"/$"(<%/%$"(S%,?(U"<F#;(*&#(A;F<%+(@&7/%'('/7"(
[J 5,&#/D"(/$(/(5"#-%+"((Q((((((R$
5A"+%*%+/,%&'( WB<"/$"(*%<<(%'(/,,/+?"@(*(X/Y$
\$/D"(.;#/,%&'(X6&#(U"7A&#/#9(\$/D"Y$
6#&7( 22344355$
U&( 22344355$
1&,"2(8/]%7;7(*&#($%](X^Y(7&',?$$
( $
)_([/'@S%@,?(:&''"+,%&'(((((((Q((((((R(>"$((Q((((((R(1&$
(
Q1&,"$R(
(
• B<"/$"($;F7%,(,?%$(*(S%,?(*X/Y(/'@(,?"('",S&#E(/#+?%,"+,;#"(@%/D#/7(,&()_1:=(/,(<"/$,(*%-"X`Y(S&#E%'D(
@/9$(F"*&#"(,?"(#"P;"$,"@(@/,"(&*(/AA<%+/,%&'(,&(a+<&;@J$"#-%+"K"D+JD&-JF'b((
• 0"$;<,(&*(5"#-%+"(0"P;"$,(S%<<(F"(%'*(,?#&;D?()<"+,#&'%+(8/%<(X"H8/%<Y$
$
6&#()_1:(T**%+%/<(\$"(
( 1/7"( ./,"(
(
5;F7%,,"@([9( cccccccccccccccccccccccccccccccc( ccccccccc(
678$
( (
!"#%*%"@([9( cccccccccccccccccccccccccccccccc( ccccccccc(
( 91/2$:;$9:%&*<0$/<2$=&:)/01$%1>&*:<$
( (
IAA#&-"@([9( ccccccccccccccccccccccccccccccccc( ccccccccc(
( 91/2$:;$8(1)/&*:<%$/<2$=1)?*>1$@1+*?1)5(
(
. / 0 1 $3(&*(4(
Project Initiation Document v1.0 Page 29
Confidential
YSNet Phase II Project
!
PQ07(:/=(
!
7"8	( 5,&#/>"( 0"FD%#"C(
1&4( 5"#-"#( 6#&+"$$&#( 1",@&#A(B/#C( 6#&CD+,%&'( .7E(
:;<=( 5%?"(:;<=( *&#(G"$,%'>H(
./0"10%"22%3&4516%7'%89030%71%:&30%89";%&;0%103<03%30=>7302!
OCC%,%&'/I(M'*/,%&'(
7"8	(:;<=! 65')/'$&(42+7'$)$(')/4,8/9$:4($');<$/'(2'(8/9$*<)*$$('=>+('/$<+-<'($*<),$?@A$4:$0'04(.1$
456'!"!7!!
456'!,!7!
5,&#/>"(:;<=( 65')/'$&(42+7'$)$(')/4,8/9$:4($');<$/'(2'(8/9$*<)*$$('=>+('/$5)(-'($*<),$BCD@A$4:$/*4()-'1$
456'!"!7!!
456'!,!7(
/(01!3!23!3!
!
Table below shows the complete listings of the hardware that have been proposed to
YSNet. For hardware that is End of Life or End of Sales, change request form will be
submitted to MCYS for approval.
(i) Microsoft Windows Server2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 100GB Hard disk Space
2.3 Database Server 02
(i) Microsoft Windows Server2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 200GB Hard disk Space
(ii) Microsoft SQL Server 2012, 64 bit x64 Standard Edition 1 unit
2.4 Middleware Talend/BI Petaho/BPM Joget Server 02
(i) Redhat Enterprise Linux Server for 32/64-bit x86, 8GB RAM, 200GB 1 unit
Hard disk Space
3 CLOUD STORAGE / BACK-UP
3.1 Production Storage Requirements
(i) Netapps 4TB Usable Hard disk Space 1 unit
(ii) FortiBalancer 1000, 8 x 10/100/1000 ports, 2 x SFP ports (2SX SFP 1 unit
included) incl. Forticare support
B DISASTER RECOVERY ENVIRONMENT (COLD DR)
[utilizing EGNC CLOUD infrastructure]
1 VIRTUALISATION FARM
1.1 DR Web Servers & DotNetNuke
(i) Microsoft Windows Server 2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 100GB Hard disk Space
1.2 DR YSNet Apps Server
(i) Microsoft Windows Server2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 100GB Hard disk Space
1.3 DR Database Server
(i) Microsoft Windows Server2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 200GB Hard disk Space
(ii) Microsoft SQL Server 2012, 64 bit x64 Standard Edition 1 unit
1.4 Middleware Talend/BI Petaho/BPM Joget Server
(i) Redhat Enterprise Linux Server for 32/64-bit x86, 8GB RAM, 200GB 1 unit
Hard disk Space
1.5 DR Storage Requirements
(i) Netapps 4TB Usable Hard disk Space 1 unit
C DEVELOPMENT ENVIRONMENT [utilizing EGNC CLOUD infrastructure]
1 VIRTUALISATION FARM
1.1 Database Server
(i) Microsoft Windows Server2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 200GB Hard disk Space
(ii) Microsoft SQL Server 2012, 64 bit x64 Standard Edition 1 unit
(iii) VisualStudio 2012 Ultimate Edition 1 unit
1.2 YSNet Development Server
(i) Centos Linux Server for 32/64-bit x86, , 8GB RAM, 200GB Hard disk 1 unit
Space
D UAT & TRAINING ENVIRONMENT [utilizing EGNC CLOUD infrastructure]
1 VIRTUALISATION FARM
1.1 YSNet Training Server 1
(i) Microsoft Windows Server2012, 64 bit Standard Edition, IIS, 8GB 1 unit
RAM, 200GB Hard disk Space
1.2 YSNet Training Server 2
(i) Centos Linux Server for 32/64-bit x86, 8GB RAM, 200GB Hard disk 1 unit
Space
E OTHERS [NON-SYSTEM HARDWARE]
1. Ethernet cable & Fiber Patch Cord SC/FC 1 lot
2. Sony 65” wall mounted LCD widescreen full HD capable monitor with 7 units
wall mounting brackets and online capacity
3. Secured Door (using Biometric Access Control)
(i) AC-215 Networkable Controller c/w battery charger & back-up battery 1 unit
and server: VeriTrax Management Software
(ii) Rosslare AYC-W6500 PIN & Fingerprint Reader 2 units
(iii) ECP-05-WD: 600 lbs Electromagnetic lock, Emergency Door 1 lot
Release, Door Monitor, Installation & wiring incl. testing and
commissioning
4. Multimedia PC incl. Console and Online capability: DELL Inspiron 60 units
One 2330
5. Customized Multimedia PC table top mounting 60 units
6. Bosch Desktop Wireless PA system @ 30 users
(i) CURD Conference Control Unit with SD recorder and digital feedback 2 units
suppressor
(ii) Conference Chairman Unit Ultro 2 units
(iii) Conference Delegate Unit Ultro 58 units
(iv) Conference extension cable assy 5M 2 units
(v) Testing & Commissioning 1 lot
7. DP Titan Quad 1080p 3D projector incl. Titan Quadr Lens and 1 lot
calibration, training, testing & commissioning
8. Elitescreen VMAX380XWHPL US4 ceiling mounted large projection 1 unit
screen for Dewan DiGadong
9. Public Access Terminal: Dell Optiplex 9010 All-in-one 5 units
10. Inventory & Stock Control system 1 lot
11. Tagging station 2 units
12. Zebra ZM400 Barcode Laser Jet printer 2 units
13. CipherLab 1500 Hand-held Barcode scanner 5 units
14. Video Conferencing: Cisco Edge95MXP Precision HD camera with 1 unit
accessories
15. Video Conferencing: Cisco Edge75MXP Precision HD camera with 3 units
accessories
F OPERATION CENTRE (Consultant WMH Scope of Work)
1. Call Centre Desktops: Dell OptiPlex 990 Desktop Slim Tower PC 5 units
2. Call Centre Laserjet Printer: HP Laserjet 5200 1 unit
3. Call Centre Headsets: Plantronics type 5 units
4. Call Centre Network Cables and Misc. items inc. 3COM Layer 3 48 1 lot
Port switch 10/100/1000 switch & CAT6 cabling
5. Local File Server and GIS Database Server: Local (Virtualised) 1 unit
EGNC MOF
Core Core
Switch Switch
Firewall Firewall
Switch
Switch EMC Data Domain
NetApp
Filer NetApp
Filer
Application Web Application Web Database Server Database Server Application Web
Server Server Server Server Server Server
VM Environment VM Environment
Tablet!
Client!
Smart!Phone!
Client! Application!
Servers!
Internet!
PDA!Client!
Web!
Servers!
Database!
Servers!
Laptop!Client!
PC!Client!
It is stated that “a study has been conducted to understand the various processes
involved in YSNet and recommended improvement processes has been identified in
streamlining the processes. The To-Be work processes and Gap Analysis
documentation are attached as Annex 2.1 - BPR Consultancy Report. Tenderers
need to re-confirm the findings and review the recommendations / conduct new
Business Process Re-engineering (BPR) in line with current changes and
requirements especially for new additional agencies, processes and functionalities”.
In view of that, the project vendor team of Business Analysts and system Analysts
will re-confirm the findings and review the recommendations / conduct new Business
Process Re-engineering (BPR) before any customisation work is carried out.
Detail Business Process will be determined during User Requirement Study phase.
In summary, the project vendor will deliver all applications for YSNet that can be
access under a single logon window; to be installed and execute in the Application
Server. These applications can be accessed either via Intranet or Internet technology
depends on the locations and the security access level of the users. In addition the 4
existing application will be integrated into the YSnet environments so as the
information and reporting of these 4 applications can be accessed by all users in a
seamless YSNet environments.
Below diagram shows the overview of the proposed 3—Tiers System Architecture
Design.
The proposed YSNet application was designed using the 3-tiers application
architecture. 3-tier application architecture provides a model for us to create a
flexible and reusable YSNet application. By breaking up an application into tiers, we
only have to modify or add a specific layer, rather than have to rewrite the entire
application over, if YSNet decide to change technologies or scale up. YSNet
application consists of the following primary component layers:
i. The web/presentation tier incorporates our customized user interface
components.
ii. The user interface includes Graphical User Interface (GUI) components
and/or be completely text based. A user interacts with an application through
its presentation layer by clicking a button or filling up a form for submission.
iii. The application tier or business logic tier houses the application proper, this
means any domain specific knowledge components needed to power the
functionality of the application reside at this layer. All the business logic and
new Business Process Re-engineering (BPR) workflows requirements will be
built in here in the application.
iv. The data tier exists to allow the application layer to capture and maintain
application state data. The data layer takes the form of MS-SQL database in
the database server.
Table below shows the complete listings of the software that have been proposed to
YSNet. For software that is End of Life or End of Sales or subject to the input from
OGPC team whether we only need to cater for GNOC1 (Active Site) deployment,
change request form will be submitted to MCYS for approval for the change of
software.
Product/
Item
Version Description Manufacturer Qty
No.
No.
A PRODUCTION+ENVIRONMENT
1. MS Windows Server 2012 Standard Edition
(i) P73-05897 WinSvrStd ALNG Lic SAPk MVL 2Proc Microsoft 6
(ii) P73-05898 WinSvrStd ALNG SA MVL 2Proc Microsoft 6
2. Microsoft SQL Server 2012 Standard Edition
(i) 7NQ-00302 SQLSvrStdCore ALNG LicSAPk MVL 2Lic CoreLic Microsoft 2
(ii) 7NQ-00292 SQLSvrStdCore ALNG SA MVL 2Lic CoreLic Microsoft 2
3. Red Hat Enterprise Linux Server
(i) Red Hat Ent Linux Server for 32/64-bit x86 Redhat 2
4. BI
Pentaho
(i) Business Pentaho Business Reporting Pentaho 2
Analytic
5. Middleware
Talend
(i) Talend Open Studio VS 2.0 Integration Talend 2
Open Studio
6. Portal, Document Management System (DMS)
(i) DotNetNuke DotNetNuke Enterprise Edition DotNetNuke 2
7. Business Process Management (BPM)
(i) Joget Joget Workflow V3 Joget.org 2
8. Antivirus Software
(i) EPB-CU Endpoint Protection-Business-Competitive Upgrade Sophos 8
9. SSL Certification
(i) Digicert SSL Plus Digicert 1
B DISASTER RECOVERY ENVIRONMENT (COLD DR)
1. MS Windows Server 2012 Standard Edition
(i) P73-05897 WinSvrStd ALNG Lic SAPk MVL 2Proc Microsoft 3
(ii) P73-05898 WinSvrStd ALNG SA MVL 2Proc Microsoft 3
2. Microsoft SQL Server 2012 Standard Edition
(i) 7NQ-00302 SQLSvrStdCore ALNG LicSAPk MVL 2Lic CoreLic Microsoft 1
(ii) 7NQ-00292 SQLSvrStdCore ALNG SA MVL 2Lic CoreLic Microsoft 1
3. Red Hat Enterprise Linux Server
(i) Red Hat Ent Linux Server for 32/64-bit x86 Redhat 1
4. BI
Pentaho
(i) Business Pentaho Business Reporting Pentaho 1
Analytic
5. Middleware
Talend
(i) Talend Open Studio VS 2.0 Integration Talend 1
Open Studio
This section introduces the key resources who will be engaged on this project. The
schematic below presents our proposed management structure.
Konsultan MWH has a strong locally based group of engineers and designers who
will be responsible for delivering this project.
7.4.2 Methodology
This section outlines the key aspects of our implementation approach
Key Outcomes
The key outcomes from this phase will be reviewed at Management Review Meeting
# 1. They will include:
! Confirmation of scope and concept for detailed design in Phase 2
! Draft workflows identified and agreed (i.e. what processes the project will
improve)
! Preliminary configuration of Customer Service application loaded with sample
data for demonstration
Project Execution Plan (PXP) This methodology and any refinements discussed with
you will form the basis of our project execution plan (Quality Plan). The Plan will also
detail monthly reporting requirements, reporting lines, financial forecasts and key
deliverables.
Business Process Workshops We will conduct two ½ day workshops to explore the
current state of work processes associated with Customer Service Management. We
will need a cross section of people (8-10) to attend these workshops so that we may
understand the full end-to-end processes targeted for process improvement:
• Management of the various forms of contacts between MCYS and their clients
• Management of customer service requests and resulting MCYS activities
• Management of youth and sports programmes and activities
• Client Service Management (CSM) and monitoring
• Consolidated reporting for better decision and policy making
The workshops involve exploring issues, problems and concerns with existing
procedures and identifying gaps based on our expertise and knowledge of global
best practice. Following the workshops we will present the core end-to-end process
areas we will target for improvement.
We will also draft high-level workflows of each process area and these will form the
basis of defining the scope of improvements. The improvements will be introduced
through a combination of streamlined processes, concise manuals, software support
systems (Maximo and ArcGIS) and effective on-job training.
Once we have clearly stated the “Unmet Needs” and “Core Improvement Objectives”
for this project we will confirm the stated Functional Requirements of the system.
Example workflow for “Responding to Tanker Requests” (Department of Drainage and Sewerage)
Investigate Available Data Sources and Systems We have not budgeted for any
data collection under Stage 1 and 2 of this project. We will investigate existing data
sources within MCYS and under this subtask we will gather the information and
determine what can practically be incorporated in the Phase 1 rollout. This will
include investigating the current use of iMMS for building maintenance and how this
asset base can or should be integrated.
We will establish a standalone Development Environment for use during the MCYS
pilot configuration and testing stage.
Our proposed solution will provide MCYS with the following key outcomes:
! An easy to use intuitive application
! An enterprise solution that is scalable and highly configurable (it can be made
very simple)
! A browser-based architecture – it can run on any machine without installing
software
! Map based interface – you can switch between map and database views
! ESRI certified – our solution integrates seamlessly with desktop GIS (ArcMap)
! A global user base – there are regular User Conferences for Maximo and
ArcGIS users around the globe. You will be part of a wider AMS community.
Key Outcomes
The key outcomes from this phase will be reviewed at Management Review
Meeting # 2. They will include:
! Final draft of process workflows
! Users trained and competent in system use
! Final configuration of applications (Maximo/ArcGIS)
The areas highlighted in the figure below are the core modules we believe will be
required to meet the draft Functional Requirements and which will be confirmed
following the business process workshops. There will be additional licensing costs
payable to IBM for the use of these modules over and above the licensing levels in
place for MOD. Our fee proposal includes an allowance for this.
The key benefit of a proven solution like Maximo is its level of “configurability” out of
the box to fit the needs of a given implementation. We don’t see any need to
“customise” (via coding) Maximo for the MCYS implementation.
Note that the functional requirements desired by MCYS for its Customer
Service Management system will require us to configure some changes into the
workflow and structure deployed at MOD’s ‘140’ centre. We believe these
improvements may also benefit MOD. Once configured on the MCYS
deployment we would recommend showing to MOD and if they wish to adopt
we could implement the changes free of charge. This collaboration further
highlights the benefits of an enterprise deployment.
Note that the functional requirements desired by MCYS for its Client/Customer
Service Management
History of Maximo: MRO was first founded as PSDI back in 1968, where they had
continuous success in Project Management up until 1988 when they decided to
move into the client/server market with an
Asset Management System called Maximo.
1991 saw the first Windows Based client
server release of Maximo, with the first web
based release coming in 2001. Maximo 6
was made available in April 2005 taking the
web based approach even further by
making all aspects of the system, including
system setup and database configuration,
web based . IBM Corporation acquired MRO
in 2006 and Maximo is now part of the IBM
Tivoli Software group.
Maximo Browser-based User Interface
Our fee proposal for this task also includes the procurement of hardware.
ArcGIS software is used to capture, create, organize, maintain, analyse and visualise
information related to location. Among these core capabilities, mapping - i.e., the
Provided a data sharing agreement is agreed between MOD and MCYS, the
“AMSViewer” application will provide MCYS staff with quick access to mays of Active
service requests, road search functions, maps of population demographics and any
other key spatial data that is available within the Ministry.
This item includes a budget to procure a single desktop ArcGIS editor license to
enable MCYS to print maps and keep any spatial data up to date.
Some parts of the system may actually go “live” early in this task and users will be
asked to run them in parallel with existing processes. For example, the recording of
complaints could go live but MCYS staff continue to use the paper forms in place at
present.
Piloting of the system in a Development (test) environment will allow us time to see
how users interact with the system and make adjustments as needed. We will also
assess the appropriateness of standard coding and the way information is entered
and retrieved from the system.
Rollout Support Experience has proven that our knowledge transfer methods work in
the Brunei environment. They are based on having core team of local MWH and
Government “trainers” who work with all end users to deliver on-job training. We run
formal training workshops immediately prior to systems going live in a test
environment so users follow-up the workshops with practical application of their
skills. Another key to successful knowledge transfer is to have a test environment
where users can “play” without impacting system integrity or data quality.
During the first few weeks of the rollout we will have at least one of our staff full time
in the Call Centre to assist staff when required. We always expect the unexpected
during the go-live process no matter how prepared the project team and how well
thought out the process, refinements always occur during the initial few weeks of a
go-live. Our local team, with its proven technical expertise and roll-out experience
can rapidly respond to these “unforeseen” refinements.
Often however, it is the users understanding of the system and its functionality that
cause problems during a go-live and once again having a full-time staff member on
site will mitigate these issues.
Post-Rollout Support We will continue to provide on-call support following the initial
2-3 week go-live period. This 2-month post-implementation support period will
include regular visits to the centre and remote reviews of the data quality and
integrity (we will be able to access your system from our established site office at the
Department of Roads)
SMS Operating Costs Part of our envisaged solution is the enablement of an sms
message service to enable sending alerts, acknowledgements and reminders to
stakeholders and customers. The extent of messaging will be determined during the
workflow mapping process (Task 1.2). Under this item in our financial proposal we
have budgeted for 12-month of usage costs associated with the message server
(but not the recipients of the sms)
Key Outcome
These tasks are all subject to available funding and can be implemented
independently. However, our experience shows that it is a false economy to attempt
to implement a sustainable change in six months. We recommend careful
consideration of these “additional” items as we believe they will guarantee
embedment of the change and we believe they will increase the benefits of the
system.
# Real-Time, live display of call traffic flow: All calls being received, being
answered, having been abandoned and completed can be displayed for the
supervisors monitoring.
# Intelligent Call Routing: Based on location of call or caller interaction
A provisional budget of B$400,000 has been recommended for this item and would
be scoped more fully should Stage 3 budgets be approved.
IT Support Technician This is the first line of support provided by our onsite IT
technician and GIS technicians (50% of full-time equivalent). Our experience shows
that the majority of service requests relate to minor issues which they will be capable
of dealing with directly. Our IT technician will become part of the MCYS office.
While their primary responsibility will be to support the CSM environment they will be
available to the whole Ministry to assist with day-to-day IT tasks such as installing
printers, cleaning viruses, upgrading software, adding users to the mapping
application and the likes.
CSM System Support In addition to the above hardware and general IT support we
will provide wider Maximo/ArcGIS support for a period of 2 years. MWH has
estimated that a total of 240 hours per year (~8 weeks) of support from Marc Robson
and Richard Chua will be sufficient for providing system refinements, custom
reporting, advanced training and general trouble shooting needs.
This 240 hours of support will be provided at the request of MCYS or if the need is
identified by our on-site technicians. Hours will be tracked and reported in our
quarterly claim. The two years of Maximo maintenance support is also budgeted
under this item.
A provisional budget of B$310,000 has been recommended for this item and would
be scoped more fully should Stage 3 budgets be approved.
For more than 20 years, leading edge research organizations throughout the world
have relied on NDI for innovative measurement solutions. NDI measurement
systems are used in various research fields such as:
• Gait analysis • Physical rehabilitation • Motor control research
• Kinesiology • Biomechanics • Neuroscience research
• Speech therapy • Spine research • Ergonomics
Researchers worldwide depend on data collected with NDI’s motion measurement
systems. NDI’s Optotrak Certus is the first choice among researchers requiring
exceptional accuracy, high speed data collection or real-time feedback.
The speed and accuracy of NDI’s Optotrak Certus allows for the capture of
significant data that would be missed at slower collection speeds and lesser
accuracies.
Custom software programs can be easily adapted through NDI’s application
programmer’s interface, allowing for unique experiment design, including real-time
feedback. Additionally, NDI’s standard software allows for powerful data collection,
transformation and viewing.
NDI’s Optotrak Certus, with optional components, can simultaneously collect data
from force plates, eye trackers, EMG systems, foot pressure sensors and many other
peripheral devices.
NDI provides the solutions to make your research a success.
1 1
The statistical RMS accuracy
The statistical figure is figure
RMS accuracy determined accordingaccording
is determined to a measurement protocol protocol
to a measurement specific to the NDI
specific to product. Please contact
the NDI product. YSNet
PleaseNDI NDIPhase
for more
contact II Project
information.
for more information.
CloseClose
FocusFocus Far Focus
Far Focus
NDI INTERNATIONAL
NDI INTERNATIONAL HEADQUARTERS:NDI EUROPE
HEADQUARTERS: GmbH GmbH
NDI EUROPE NDI ASIANDI
PACIFIC
ASIA PACIFIC
MEASUREMENT VOLUMES
CANADAMEASUREMENT
CANADA VOLUMES:
GERMANY GERMANY HONG KONGHONG KONGto one of two volumes: close or far. Combine up to
Tel: + 1 Tel:
(877) 634-6340 The Position SensorTel:in+the Optotrak Certus System isTel:pre-calibrated
+ (852)
+ 1 (877) 634-6340
eight Position Sensors
49Tel:
(77 +32)
49 939
(77 19 00
32)
toinfo@ndieurope.com 939 19 00
create a much larger or a unique Tel: 2802
volume.
2205
+ (852) 2802 2205
Email: info@ndigital.com
Email: info@ndigital.com Email: Email: APinfo@ndigital.com
Email: APinfo@ndigital.com
Email: info@ndieurope.com
Website:The Position
www.ndigital.com
MEASUREMENT
Website: VOLUMESSensor Website:
www.ndigital.com in the Optotrak
www.ndieurope.com Certus System
Website: is pre-calibrated to one of two
www.ndigital.com
Website: www.ndigital.com
Website: www.ndieurope.com
volumes: close or far. Combine up to eight Position Sensors to create a much larger
Copyright The Position
2004 Northern Sensor
Digital in the
Inc. All rights Optotrak
reserved. Certusproduct
Due to continuous System is pre-calibrated
improvement, to one
1.7 mare subject
specifications of two
to change volumes:
without notice. NDI close or far.
is a registered Combine
trademark upDigital
of Northern to Inc.
Copyright 2004 Northern Digital Inc. All rights reserved. Due to continuous product improvement, specifications are subject to change without notice. NDI is a registered trademark of Northern Digital Inc.
or a unique volume.
eight
The Optotrak
The
CertusPosition
Optotrak Certus is Sensors to create
is a general metrology instrument.
Other patents pending.
a general metrology
Use inaa much
instrument.
particularlarger
Use in a particularor a unique
application must volume.
be determined
application must be
by the user. NDI products and their application or use may be covered by NDI patents.
determined by the user. NDI products and their application or use may be covered by NDI patents.
Other patents pending.
Printed in Canada - July 2004 NDI P/N 8300176
Printed in Canada - July 2004 NDI P/N 8300176
1.7 m
0.9 m 1.7 m
CLOSE VOLUME
approximate dimensions
0.5 m 3.0 m
0.9 m 1.7 m
1.5 m
CLOSE VOLUME
approximate dimensions
0.5 m 3.0 m
1.5 m
2.6 m
2.6 m
FAR VOLUME
approximate dimensions
3.5 m
1.3 m
FAR VOLUME
approximate dimensions
3.5 m
1.2 m
1.3 m 6.0 m
2.2 m
1.2 m
6.0 m
2.2 m
MOBILE READY
• Real-time data entry via browser or mobile devices
• Data can be entered by coaches and athletes from separate locations
• Individual or group reports can be generated from anywhere
• Athletes can access their results and reports online.
UNIQUE FEATURES
• Team monitoring dashboard
• Daily email alerts
• Monitors individual and team training load and analysis using the session RPE
(sRPE) method
• Modular structure: training monitoring, fitness testing, questionnaire, feedback
collection, injury tracking information
• Track date over months and years
• Automatically interpret test results with sport-specific standards
• Collect and analyze athletes' feedback after training and competitive events
• Track injuries and record injury history
• Manage rehabilitation programs
• Secure, user friendly and accessible 24/7 by all major web browsers and mobile
devices
1 Identified equipment deviation list in Bill of Kiong High 10-July-13 Hj Zaini 31-July-13 Identify the equipment which are EOS In
Materials due to End of Life, End of Sales, or EOL so that Change Request can Progress.
Technology Update, etc. be submitted as soon as possible to
MCYS for approval.
2 Change of software to be installed in Kiong High 10-July-13 Hj Zaini 31-July-13 Identify the software which are In
OGPC Infrastructure since software are needed at GNOC1 so that Change Progress.
only needed at GNOC1 (production site) Request can be submitted as soon as
possible to MCYS for approval.
Risk
Potential Risk Effect on Project Mitigation Plan
Category
Risk
Potential Risk Effect on Project Mitigation Plan
Category
Sufficient access Affect the overall High • Key responsibility for the
to MCYS’s project schedule. Project Management
resources and Team.
information
available to allow • The Project initiation
the time-scales Document highlights
for the project to roles and
be met. responsibilities.
• Communicate plan
widely.
Risk
Potential Risk Effect on Project Mitigation Plan
Category
Internal users: Key users of YSNet including Director, Deputy Director, Head of Sections
Course Title Course Format Number of Total Duration Proposed Size per Venue
Contents Sessions per (Hours) per Number of Class
Course Course Classes
Internal users: Key users of YSNet including Head of Units, Senior Officers, Officers, Youth and Sports Workers and Clerks
Course Title Course Format Number of Total Duration Proposed Size per Venue
Contents Sessions per (Hours) per Number of Class
Course Course Classes
!PRICING'SCHEDULE'FOR'HARDWARE''
! '' ! ! !
! ! ! ! !
PRICING'SCHEDULE'FOR'IMPLEMENTATION'AND'RELATED'SERVICES''
PERCENTAGE+ ACCUMULATIVE+
MILESTONE+ TASK+DELIVERY+ +AMOUNT++
(%)+CLAIM+ %++CLAIM+
COMPLETION+OF+PROJECT+INITIATION+
IMP+#+1+ DOCUMENTS+ !603,978.00!! 15%! 15%!
++ Sub'Total':' +603,978.00++
COMPLETION+OF+USER+REQUIREMENT+
IMP+#+2+ STUDY+
MR!Enterprise!Service!Bus!Engine!for! !
IMP+#+2.1+ workflow!&!Financial!(License)! !543,580.20!!
IMP+#+2.2+ Youth!Development!Module! !120,795.60!!
Athlete!and!Coaches!Management!
IMP+#+2.3+ System!Module! !72,477.36!!
Youth!and!Sports!Association!
IMP+#+2.4+ Management!Module! !84,556.92!!
Assets!and!Facilities!Management!
30%! 45%!
IMP+#+2.5+ Module! !72,477.36!!
National!Service!Programme!
IMP+#+2.6+ Management!Module! !120,795.60!!
IMP+#+2.7+ Event!Management!Module! !108,716.04!!
Integrated!Billing!System!and!
Integration!to!!e\Payment!System!
IMP+#+2.8+ Module! !24,159.12!!
SMS!and!MMS!Gateway!and!Mobile!
IMP+#+2.9+ Apps!Module! !60,397.80!!
++ Sub'Total':' +1,207,956.00++
COMPLETION+OF+REALIZATION+STAGE+
IMP+#+3+ (PILOT)+ !!
MR!Enterprise!Service!Bus!Engine!for!
IMP+#+3.1+ workflow!&!Financial!(License)! !543,580.20!!
IMP+#+3.2+ Youth!Development!Module! !120,795.60!!
Athlete!and!Coaches!Management!
IMP+#+3.3+ System!Module! !72,477.36!!
Youth!and!Sports!Association!
IMP+#+3.4+ Management!Module! !84,556.92!!
Assets!and!Facilities!Management!
30%! 75%!
IMP+#+3.5+ Module! !72,477.36!!
National!Service!Programme!
IMP+#+3.6+ Management!Module! !120,795.60!!
IMP+#+3.7+ Event!Management!Module! !108,716.04!!
Integrated!Billing!System!and!
Integration!to!!e\Payment!System!
IMP+#+3.8+ Module! !24,159.12!!
SMS!and!MMS!Gateway!and!Mobile!
IMP+#+3.9+ Apps!Module! !60,397.80!!
!! Sub'Total':' +1,207,956.00++
!PRICING'SCHEDULE'FOR'MAINTENANCE'
! '' ! ! !
!
PERCENTAGE+ ACCUMULATIVE+!
MILESTONE+ TASK+DELIVERY+ +AMOUNT++
(%)+CLAIM+ %++CLAIM+
++ 1ST+YEAR++ ++ ++ ++
MAINT+#+1+ 1st!Quarter! 56,877.00! 25%! 25%!
MAINT+#+2+ 2nd!Quarter! 56,877.00! 25%! 50%!
MAINT+#+3+ 3rd!Quarter! 56,877.00! 25%! 75%!
MAINT+#+4+ 4th!Quarter! 56,877.00! 25%! 100%!
++ Sub'Total':' 227,508.00+ !! !!
++ 2nd+YEAR++ !! !! !!
MAINT+#+5+ 1st!Quarter! 57,550.00! 25%! 25%!
MAINT+#+6+ 2nd!Quarter! 57,550.00! 25%! 50%!
MAINT+#+7+ 3rd!Quarter! 57,550.00! 25%! 75%!
MAINT+#+8+ 4th!Quarter! 57,550.00! 25%! 100%!
!! Sub'Total':' 230,200.00+ !! !!
++ Total'['MAINTENANCE']':' +457,708.00++ ++ ++
! ! ! ! !
! ! GRAND+TOTAL++OF+SOFTWARE+++ ! ! !
HARDWARE+++SERVICES+++
!! MAINTENANCE+ +7,329,292.00++
! !
14.0 Appendix
!" #$%&'($)* "+,$-./0 1-$,- 2.0.%3 0*
=5>=?
4 !"#$%#$&'(%)*+,'"( -./%0123 !45%6-76879- :;<%-979679/
5 =>=*?@&A%+:%('&?'*%B%"+&(*="(%$@A&@&A 9%012 !45%6-76879- !45%6-76879-
6 7/0-,$8-'1.90.09 4':$; </0'=6>=?>46 </0'=6>=?>46
@ )*+,'"(%@&@(@=(@+&%?+"C!'&(=(@+&$ 96%0123 (DE%6/76879- !45%9.76879-
A B,/C*8-'B,/9,*%%'D*E/,-% A':$;% #+*'=@>=?>46 </0'4=>=?>46
? B,/C*8-'FG$H+$-./0'D*G.*I'$0:'D*E/,-% 6':$;% #+*'=@>=?>46 #3+'=?>=?>46
J "*-$.H*:'B,/C*8-'K/,&'EH$0 4=':$;% #+*'=@>=?>46 </0'4J>=?>46
L B,/C*8-'D.%&'<$0$9*)*0-'BH$0'M.08H+:.09'$%%/8.$-*:').-.9$-./0'$8-./0%N A':$;% #+*'=@>=?>46 </0'4=>=?>46
O B,/C*8-'!%%+*'P/9'M.08H+:.09'$%%/8.$-*:',*%/H+-./0%N A':$;% #+*'=@>=?>46 </0'4=>=?>46
4= )*+"C*'!'&(%B%?'F@G'*# 9HH%0123 !45%9I76J79- $1K%6976H79/
44 1+Q).%%./0'/R'73$09*'D*S+*%- 6':$;% </0'4O>=L>46 K*:'54>=L>46
45 7/0R.,)$-./0'/R'T.HH%'/R'<$-*,.$H'R,/)'<7U1 5':$;% #3+'55>=L>46 2,.'56>=L>46
46 BH$8.09'B+,83$%*'V,:*, 4':$; </0'5?>=L>46 </0'5?>=L>46
4@ "*H.G*,;'B*,./:'/R'(*-I/,&'W'<*:.8$H'X$,:I$,* 4==':$;% K*:'5L>=L>46 1$-'44>=4>4@
4A 7+%-/)'"*8H$,$-./0'W'#;E*'YEE,/G$H'R/,'X$,:I$,* 6':$;% </0'46>=4>4@ K*:'4A>=4>4@
4? "*H.G*,;'B*,./:'/R'1/R-I$,*% 6L':$;% #+*'5J>=L>46 K*:'4?>4=>46
4J 7+%-/)'"*8H$,$-./0'W'#;E*'YEE,/G$H'R/,'1/R-I$,*% @':$;% #3+'4J>4=>46 #+*'55>4=>46
4L 1.90'VRR'/R'1/R-I$,*'"*H.G*,;'V,:*, 6':$;% K*:'56>4=>46 2,.'5A>4=>46
4O "*H.G*,;'/R'FS+.E)*0-%'-/'7+%-/)*,'1.-*% A':$;% 2,.'5@>=4>4@ #3+'6=>=4>4@
5= 1.90'VRR'/R'X$,:I$,*'"*H.G*,;'V,:*, =':$;% 1$-'=4>=5>4@ 1$-'=4>=5>4@
54 )*+,'"(%'L'"C(@+& -M/%0123 !45%9.76879- :;<%9.79679/
55 @53K1NN1K<45 9//O68%0123 :;<%9-76I79- !45%-976-79/
56 1/R-I$,*'!0%-$HH$-./0'.0'Z<K$,*'MF[(7N 45':$;% 2,.'46>=O>46 1$-'5L>=O>46
5@ (*-I/,&'FS+.E)*0-'!0%-$HH$-./0'MF[(7N A':$;% </0'=6>=5>4@ 2,.'=J>=5>4@
5A B7'!0%-$HH$-./0 J':$;% </0'4=>=5>4@ #+*'4L>=5>4@
5? Z.:*/'7/0R*,*08.09'FS+.E)*0-'!0%-$HH$-./0 6':$;% #+*'=@>=6>4@ 2,.'=J>=6>4@
5J T./'<*-,.8'"//,'Y88*%%'!0%-$HH$-./0 A':$;% </0'4=>=6>4@ </0'4J>=6>4@
5L T/%83'"*%&-/E'K.,*H*%%'BY'1;%-*)'!0%-$HH$-./0 A':$;% </0'4J>=6>4@ </0'5@>=6>4@
B$9*'4
J$K*'4
G$6*'>
;$F*'J
F$8*'>
H$B*'D
K$G*'A
C$L*'B
?$L*'J
J$O*'B>
M$Q*'66
L$7*'B>
?$U*'<4
L$7*'CD
- End of Document -