DAFTAR HARGA SATUAN DASAR MATERIAL DAN ALAT

KEGIATAN -
-
PEKERJAAN -
-
-
-
LOKASI -
TAHUN 2021

HARGA SATUAN
NO. URAIAN SATUAN
(RP)

1 2 3 4
A AGREGAT, BAHAN PEREKAT, dan BAHAN JADINYA 0.825
1 Tanah Urug m3 271,000.00 -
2 Tanah Subur m3 125,000.00 -
3 Pasir Urug m3 271,000.00 -
4 Pasir Pasang m3 285,000.00 -
5 Pasir Beton m3 300,000.00 -
6 Abu Batu m3 270,000.00 -
7 Kerikil m3 271,000.00 -
8 Batu Pecah Mesin 2/3 m3 308,000.00 -
9 Batu Pecah 5/7 m3 234,000.00 -
10 Batu Pecah 10/15 m3 249,000.00 -
11 Batu Belah Pondasi m3 249,000.00 -
12 Bata Ringan 100x200x600 m3 8,674.70 -
13 Portland Cement 50 Kg zak 75,000.00 -
14 Portland Cement kg 1,703.57 -
15 Semen Putih zak 92,000.00 -
16 Semen Warna kg 11,000.00 -
17 Sirtu m3 274,000.00 -
18 Beton Ready Mix Mutu K - 175 m3 948,000.00 -
19 Beton Ready Mix Mutu K - 225 m3 969,000.00 -
20 Beton Ready Mix Mutu K - 250 m3 979,000.00 -
21 Biaya Sewa Pompa Beton Ready Mix m3 500,000.00 -
22 Grass Blok Natural 8 cm m2 180,000.00 -
23 Paving Block Natural 6 cm m2 120,000.00 -
24 Kansteen Paving Block 5 x 10 x 15 bh 96,000.00 -
25 Kansteen Jalan 15 x 30 x 60, K-225 bh 96,000.00 -
26 U - Ditch 300x400x1200 bh 348,000.00 -
27 Graffel U 20 cm m1 750,000.00 -
28 Pagar Panel Beton 240.40.5 lbr 890,000.00 -
29 H-Beam, h = 260 cm btg 4,160,000.00 -
30 Biaya Pasang Pagar Panel Beton m2 75,000.00 -
31 Buis Beton Ø 30 cm berikut Galian dan Urugan Kembali m1 67,000.00 -
32 Batu Alam (Terpasang) m2 135,000.00 -
33 Rooster Beton 10x20 (Terpasang) bh 17,000.00 -
34 Pasang WaterStop m1 350,000.00 -
35 Batu Apung m3 316,000.00 -
36 Air L 3.50

B BAHAN KAYU 0.9 -


1 Bambu Ø7 - 10 cm btg 54,000.00 -
2 Kayu Terentang m3 2,500,000.00 -
3 Kayu Albasia m3 2,000,000.00 -
4 Dolken 5 - 7 btg 60,000.00 -
5 Dolken 7 - 10 btg 85,000.00 -
6 Kayu Bakar m3 250,000.00 -
7 Triplek 4 mm 120 x 240 lbr 71,000.00 -
8 Multiplek 9 mm 120 x 240 lbr 134,000.00 -
9 Ijuk kg 55,000.00 -
10 Kayu balok 5/7 m3 2,500,000.00 -

C BAHAN LOGAM 0.9 -


1 Besi Tulangan U-24 Polos kg 11,000.00 -
2 Besi Tulangan U-39 Ulir kg 11,000.00 -
3 Baja Profil IWF/INP/DIR/DIN/CHANEL kg 16,000.00 -
4 Plat Baja Tipis 1.2 mm kg 19,000.00 -
5 Plat Baja Tipis 0,8 mm kg 16,000.00 -
6 Besi Hollow 40x40 @ 6 m, t = 1.8 mm btg 160,000.00 -
7 Besi Hollow Galvanis 40x40 @ 4 m, t= 0.4 mm btg 180,000.00 -
8 Besi Hollow 20x40 @ 4 m, t = 0.4 mm btg 90,000.00 -
Besi hollow 4x6 cm m1 29,000.00
Besi hollow 2x4 cm m1 17,600.00
9 Metal Stud C.75, t = 0.45 mm m1 75,000.00 -
10 Kawat Beton kg 18,000.00 -
11 Kawat Las Listrik kg 35,000.00 -
12 Kawat Duri m1 6,000.00 -
13 Wiremesh M-6, 2.1 x 5.4 lbr 364,000.00 -
14 Wiremesh M-8, 2.1 x 5.4 lbr 672,000.00 -
15 Seng Plat BJLS 30, Lebar 60 cm (1 Roll 50 m) m1 180,000.00 -
16 Seng Gelombang BJLS 25 lbr 162,000.00 -
17 Paku 1 cm s/d 3 cm kg 16,000.00 -
18 Paku 4 cm s/d 7 cm kg 16,000.00 -
19 Paku 8 cm s/d 12 cm kg 16,000.00 -
20 Ramshet 12 cm s/d 20 cm bh 7,500.00 -
21 Pisher Ø 12 cm s. d. 20 cm bh 5,000.00 -
22 Paku Sekrup Ø 12 cm s. d. 20 cm bh 4,500.00 -
23 Paku Ripet bh 2,000.00 -
24 Sekrup Kalsiboard bh 3,500.00 -
25 Paku Pancing 60 x 230 mm bh 3,500.00 -
26 Pisher bh 2,500.00 -
27 Angkur Baud, Ø19 mm bh 35,000.00 -
28 Mur+Ring, Ø19 mm bh 5,000.00 -

D BAHAN ATAP
1 Rangka Atap Baja Ringan (Terpasang) m2 60,000.00
2 Genteng Beton Flat Warna Hitam Cisangkan bh 9,000.00
3 Nok Genteng Beton Cisangkan bh 21,000.00
4 List Plank GRC I = 30 cm m1 75,000.00
5 Alumunium Composite Panel 1.22x4.88 m lbr 550,000.00
6 Penutup Atap Zincalume (Terpasang) m2 350,000.00
7 Rockwool kg 5,000.00
8 Atap Bitumen Onduline Gelombang Motif Genteng 3 mm H.38 lbr 50,900.00
E KUSEN, PARTISI, dan ACCESSORIES 0.9 -
1 Kusen Alumunium Warna 4" Alexindo m1 125,000.00 -
2 Kusen Alumunium Warna 3" Alexindo m1 81,000.00 -
3 Daun Jendela Alumunium Warna Alexindo m1 660,000.00 -
4 Daun Pintu Alumunium Warna Alexindo m1 120,000.00 -
5 Panel Spandrel sek. Alexindo + Assesories m2 350,000.00 -
6 Jalusi Alumunium Warna m2 475,000.00 -
7 Kusen+Daun Pintu PVC Lengkap Engsel/Kunci unit 650,000.00 -
8 Kalsiboard 120 x 240 t = 6 mm ex DN lbr 87,000.00 -
9 Cubicle Ukuran 1,845x2,440, tebal 12 mm m2 730,000.00 -
10 Sealent bh 35,000.00 -
11 Path Lock set 25,000.00 -
12 Pull Handle psg 350,000.00 -
13 Floor Hinges set 980,000.00 -
14 geser Handle psg 150,000.00 -
15 Lever Handle psg 250,000.00 -
16 Tarikan Jendela Alumunium psg 85,000.00 -
17 Body Kunci+Cylinder set 125,000.00 -
18 Rambucis bh 78,000.00 -
19 Engsel Pintu psg 35,000.00 -
20 Engsel Pintu Besi (Engsel bubut) bh 56,000.00 -
21 Door Closer set 1,200,000.00 -
22 Engsel Casement psg 53,000.00 -
23 Kunci Pintu Double Slaag bh 75,000.00 -
24 Kunci Bulat KM/WC bh 25,000.00 -
25 Kunci Pintu besi bh 45,000.00 -
26 Kunci Slot 4" Stainless Steel Di Las bh 75,000.00 -
27 Gembok bh 115,000.00 -
28 Roda Pagar bh 150,000.00 -
29 Jendela Nako bh 75,000.00 -
30 Kunci Tanam bh 45,000.00 -
31 Kayu meranti batu, papan m3 9,400,000.00 -
32 Rell Pintu Geser bh 350,000.00 -
33 Karet Kusen m1 15,000.00 -
34 Plastik m2 100,000.00 -
35 Akrilik lbr 390,000.00 -

F BAHAN KACA
1 Kaca Es 5 mm ( ASAHI ) m2 129,800.00 -
2 Kaca Polos 5 mm ( ASAHI ) m2 118,000.00 -
3 Kaca Polos 8 mm ( ASAHI ) m2 350,000.00 -
4 Kaca Rayband 5 mm ( ASAHI ) m2 105,000.00 -
5 Kaca Patri Lokal Terpasang ( ASAHI ) m2 350,000.00 -
6 Kaca Polos 12 mm (ASAHI) m2 215,000.00 -
7 Kaca Tempered 12 mm Terpasang ( ASAHI ) m2 250,000.00 -
8 Kaca Tempered 8 mm ( ASAHI ) m2 225,000.00 -
9 Kaca Tempered 8 mm Lapis Sandblusting m2 265,000.00 -
10 Glass Block DN 20 x 20 bh 75,000.00 -
11 Pasang Jendela Kaca Curtaiwall Panasap Stopsol Silver Green + m2 1,200,000.00 -
Alumunium warna 4" (Terpasang)
12 Plat Alumunium Pb Timbal 3 mm m2 2,800,000.00 -
13 Kaca Pb 10 mm Lb 3,500,000.00 -

G BAHAN FLAPOND
1 Gypsum 120 x 240, t = 9 mm ex. DN lbr 125,000.00
2 GRC 4 mm, 120 x 240 lbr 95,000.00
3 List Profil Gypsum m1 15,000.00
4 List Profil Kayu m1 185,000.00
5 Drop Ceiling Flapond (Terpasang) m1 150,000.00

H BAHAN KERAMIK dan GRANITE TILE


1 Keramik 20 x 20 KW I DN Corak /Warna/Anti Slip m2 98,000.00
2 Keramik Dinding 20 x 25 KM/WC KW I DN Corak m2 105,000.00
3 Keramik Lantai 30 x 30 KW I DN Corak, Polish m2 247,500.00
4 Keramik 30 x 30 KW I DN Corak /Warna/Anti Slip m2 259,875.00
4 Granit Tile 30 x 30 Polish Essenza bh 27,000.00 0.16 6.25
5 Granit Tile 40 x 40 Polish Essenza bh 60,000.00 0.16 6.25
6 Granit Tile 40 x 40 Unpolish Essenza m2 282,975.00
7 Granit Tile 60 x 60 Polish Essenza m2 288,000.00
8 Granit Tile 60 x 60 Unpolish Essenza m2 302,400.00
9 Keramik Dinding 30 x 60 KM/WC KW I DN Corak m2 268,000.00
10 Pearlstone Cor Setempat Natural m2 150,000.00
11 Lantai Vinyl Floor bh 10,000.00

I BAHAN FINISHING
1 Plamir Tembok kg 20,000.00
2 Cat Tembok ICI Eksterior kg 42,000.00
3 Cat Tembok ICI Interior kg 32,000.00
4 Cat Kayu/Besi kg 31,000.00
5 Cat Tembok Vinilex kg 54,000.00
6 Cat Marka / Spotlight kg 45,000.00
7 Water Proofing Master Guard m2 120,000.00
8 Roll Cat bh 12,000.00
9 Kape Tembok bh 7,500.00
10 Kape Kayu bh 9,500.00
11 Prime Coat kg 15,000.00
12 Kwas 3" bh 5,000.00
13 Dempul Halus / Imfra (Wood Filler) kg 5,000.00
14 Terpentin ltr 7,500.00
15 Thiner A ltr 2,500.00
16 Thiner B ltr 3,500.00
17 Ampelas lbr 3,000.00
18 Dempul Kayu kg 19,000.00
19 Meni Kayu / Besi kg 31,000.00
20 Lem Putih FOX kg 87,000.00
21 Lem Kuning kg 105,000.00
22 Minyak bekisting ltr 62,000.00
23 Bahan Bakar Solar ltr 6,800.00
24 Minyak Pelumas ltr 7,500.00
25 Pasang Wallpaper + Border (Terpasang) m2 150,000.00
26 Pekerjaan depan megatik Meja finis Counter/melamik Pelayanan, kaca 6 mm bahan m' 1,500,000.00
lapistop sanblas table lapis green granit, dinding 1.5cm,
27 Gordeng Horizontal Blind (Terpasang) m2 350,000.00
28 Melamin Sending Siller MSS 123 kg 75,000.00
29 Lem Vinyl kg 105,000.00

J BAHAN PERPIPAAN
1 Pipa GIP Medium A Ø 1/2" ( 6 m1 ) btg 186,000.00
2 Pipa GIP Medium A Ø 3/4" ( 6 m1 ) btg 245,000.00
3 Pipa GIP Medium A Ø 1" ( 6 m' ) btg 376,000.00
4 Pipa GIP Medium A Ø 1 1/4" ( 6 m1 ) btg 532,000.00
5 Pipa GIP Medium A Ø 1 1/2" ( 6 m1 ) btg 557,000.00
6 Pipa GIP Medium A Ø 2" ( 6 m1 ) btg 781,000.00
7 Pipa GIP Medium B Ø 3" ( 6 m1 ) btg 1,310,000.00
8 Pipa GIP Medium B Ø 4" ( 6 m1 ) btg 1,878,000.00
9 Pipa Stainlesstell Ø 1/2" ( 6 m1 ) btg 151,000.00
10 Pipa Stainlesstell A Ø 3/4" ( 6 m1 ) btg 192,000.00
11 Pipa Stainlesstell A Ø 3", ( 6 m' ) btg 660,000.00
12 Pipa Stainlesstell A Ø 2,5", ( 6 m' ) btg 637,000.00
13 Pipa Stainlesstell A Ø 2" ( 6 m' ) btg 607,000.00
14 Pipa Stainlesstell A Ø 1" ( 6 m' ) btg 295,000.00
15 Pipa Stainlesstell A Ø 1 1/4" ( 6 m1 ) btg 457,000.00
16 Pipa Stainlesstell A Ø 1 1/2" ( 6 m1 ) btg 457,000.00
17 Pipa PVC Ø 15 mm S.10 m1 21,000.00
18 Pipa PVC Ø 20 mm S.10 m1 26,000.00
19 Pipa PVC Ø 25 mm S.10 m1 31,000.00
20 Pipa PVC Ø 32 mm S.10 m1 38,000.00
21 Pipa PVC Ø 40 mm S.10 m1 56,000.00
22 Pipa PVC Ø 50 mm S.10 m1 76,000.00
23 Pipa PVC Ø 63 mm S.12.5 m1 118,000.00
24 Pipa PVC Ø 75 mm S.12.5 m1 178,000.00
25 Pipa PVC Ø 90 mm S.12.5 m1 86,000.00
26 Pipa PVC Ø 110 mm S.12.5 m1 281,000.00
27 Pipa PVC Ø 140 mm S.12.5 + Pasang m1 448,000.00
28 Pipa BSP dia 4" m1 943,000.00
29 Pipa BSP dia 2" m1 607,000.00

K BAHAN MEKANIKAL
1 Stop Kran 3/4" KIT bh 43,000.00
2 Stop Kran 1" KIT bh 56,000.00
3 Check Valve 1/2" bh 75,000.00
4 Double Neple bh 85,000.00
5 Water Mur 1/2" bh 45,000.00
6 Gate Valve 1/2" bh 45,000.00
7 Kran Stainless Lokal Kait bh 70,000.00
8 Shower Dengan Tiang Setara san Ei bh 750,000.00
9 Shower Tanpa Tiang bh 350,000.00
10 Kran Tembok San Ei dia. 1/2" bh 35,000.00
11 Kran Tembok ITAP dia. 1/2" bh 54,000.00
12 Kran Bebek San Ei dia. 1/2" bh 75,000.00
13 Kran Bebek San ITAP dia. 1/2" bh 83,000.00
14 Washtafel Lengkap TOTO LW. 230 unit 880,000.00
15 Closet Jongkok Poslin Warna TOTO unit 350,000.00
16 Closet Jongkok Standard Putih Poslin TOTO unit 750,000.00
17 Closet Duduk Warna Standard TOTO C 240 Lengkap unit 3,200,000.00
18 Washtafel Bulat Warna Standard Lengkap unit 650,000.00
19 Urinoir Lengkap TOTO Warna Standard lengkap unit 950,000.00
20 Penyekat Poslin Urinoir TOTO lbr 500,000.00
21 Kitchen Zink Stainless Standard Lokal ( 1 Lobang ) bh 3,500,000.00
22 Bak Mandi Fiberglass Standard Lokal bh 450,000.00
23 Roof Drain Stainless Stell 4" bh 145,000.00
24 Floor Drain Stainlessstell 2,5" bh 280,000.00
25 Tangki Air Kap. 1000 ltr unit 1,900,000.00
26 Pompa Air "Jet Pump" 250watt "SANYO" unit 4,500,000.00
27 Pemasangan Pipa PPR-PN10 dia. 20 mm m¹ 69,000.00
28 Pemasangan Pipa PPR-PN10 dia. 25 mm m¹ 75,000.00
29 Pemasangan Pipa PPR-PN10 dia. 32 mm m¹ 82,500.00
30 Pemasangan Pipa PPR-PN10 dia. 40 mm m¹ 95,600.00
31 Gate Valve Dia. 40 mm bh 75,000.00
32 Gate Valve Dia. 32 mm bh 75,000.00
33 Jet Washer bh 156,000.00
34 Paper Holder bh 150,000.00
35 Soap Holder bh 150,000.00
36 Pemasangan Bio Septictank Kapasitas 7 m³/hari Lengkap dengan Aksesories, Set 89,000,000.00
galian, pondasi dan Instalasi
37 Pekerjaan Pemasangan Pompa Transfer Kapasitas 100 liter/menit Head 60 meter unit 5,600,000.00
lengkap dengan Gate Valve, Strainer, Check Valv dan Aksesories
38 Pekerjaan pembuatan sumur Bor Minimal kedalam ± 45 Meter unit 8,500,000.00
39 Pekerjaan Pemsangan Pompa Zet Pump 1.5 kW lengkap dengan Gate Valve, unit 3,500,000.00
Strainer, Check Valv dan Aksesories Pendukung Lainnya
40 Pekerjaan Pemasangan Roof Tank Kapasitas 1 m³ unit 5,400,000.00
Lengkap dengan Gate Valve, Header dan aksesories lainnya -
41 Pekerjaan Pemasangan Pompa Booster 150 Watt lengkap dengan Gate Valve, unit 4,500,000.00
Strainer, Check Valv dan Aksesories Pendukung Lainnya
42 AC Split Wall Kapasitas 18.000 btu/h unit 4,500,000.00
43 AC Split Wall Kapasitas 24.000 btu/h unit 5,400,000.00
44 AC Ceilling Cassete Kapasitas 35.830 btu/h unit 8,900,000.00
45 Pemasangan Ex-haust Fan unit 600,000.00
46 AC Split Wall Kapasitas 12.000 btu/h unit 3,800,000.00
47 Pemasangan alat pemadam api kapasitas 6 Kg bh 1,890,000.00
48 Water Drain set 2,300,000.00
49 Seal Tape bh 5,000.00
50 Knee Pipa Udara 1,5" bh 3,500.00

L BAHAN ELEKTRIKAL 0.8 #NAME?


1 Saklar Hotel ex. Broco bh 125,000.00 -
2 Saklar Engkel ex. Broco bh 150,000.00 -
3 Saklar Seri ex. Broco bh 185,000.00 -
4 Stop Kontak ex. Broco bh 45,000.00 -
5 TL.TYPE RM 300 DVD 2X36 watt unit 1,200,000.00 -
6 TL.TYPE BL 2X36 watt unit 850,000.00 -
7 Lampu Down light RD 100, PL 14 W unit 150,000.00 -
8 Baret Kotak Cover acrylic, TLR 20W unit 850,000.00 -
9 Lampu TL 18 Watt Lengkap+Trafo "Philif" unit 1,950,000.00 -
10 Lampu TL Circle 32 Watt Lengkap+Trafo "Philif" unit 2,200,000.00 -
11 Lampu PL 14 Watt Lengkap +Fiting bh 150,000.00 -
12 Lampu Pijar 25 watt bh 75,000.00 -
13 Instalasi Titik Lampu (Kabel NYM 3x2,5 " PRIMA", Pipa Conduit 7/8", ttk 135,000.00 -
klem & isolasi) -
14 Instalasi Titik Stop Kontak (Kabel NYM 3x2,5 " PRIMA", Pipa Conduit 7/8", ttk 145,000.00 -
klem & isolasi) -
15 Kawat BC ( Tembaga) 50mm ( 1m' = 0,17kg ) kg 53,000.00 -
16 Jarum Penangkal Petit " SPLiZT" bh 346,000.00 -
17 Pentanahan Penangkal petir ttk 3,200,000.00 -
18 Pentanahan Panel/Grounding daya ttk 2,900,000.00 -
19 Panel Lengkap + Box uk.30x60cm unit 5,000,000.00 -
20 Panel MDP (MAIN DISTRIBUTION PANEL) unit 6,500,000.00 -
21 Panel Ukuran 1000 x 800 x 400 mm set 600,000.00 -
22 MCCB 250 A, 3P, 36 kA buah 350,000.00 -
23 MCCB 160 A, 3P, 36 kA buah 285,000.00 -
24 MCCB 100 A, 3P, 30 kA buah 187,000.00 -
25 MCCB 25 A, 3P, 10 kA buah 135,000.00 -
26 Digital kWh Metering buah 1,900,000.00 -
27 Ampere Meter buah 800,000.00 -
28 Volt Meter Meter buah 950,000.00 -
29 Current Transformer buah 350,000.00 -
30 Fuse dan Lampu Indicator buah 450,000.00 -
31 Manual Interlock System unit 750,000.00 -
32 Aksessories & Alat Bantu ls 2,000,000.00 -
33 Wirring & Instalasi ls 500,000.00 -
34 Panel SDP (SUB DISTRIBUTION PANEL) unit 750,000.00 -
35 Panel Ukuran 800 x 500 x 250 mm set 350,000.00 -
36 MCCB 160 A, 3P, 36 kA buah 350,000.00 -
37 MCCB 16 A, 3P, 10 kA buah 285,000.00 -
38 Panel PP/LP.A unit 750,000.00 -
39 MCCB 125 A, 3P, 18 kA buah 245,000.00 -
40 MCB 16 A, 3P, 6 kA buah 145,000.00 -
41 MCB 16 A, 1P, 2.5 kA buah 145,000.00 -
42 MCB 10 A, 1P, 2.5 kA buah 135,000.00 -
43 MCB 6 A, 1P, 2.5 kA buah 125,000.00 -
44 Panel PP/LP.B unit 750,000.00 -
45 Instalasi Kabel dari panel SDP ke PP/LP-A m' 350,000.00 -
NYY 4 x 50 mm2 + NYA 6 mm (Terpasang)
46 Instalasi Kabel dari panel Utama ke PP/LP-B m' 350,000.00 -
NYY 4 x 50 mm2 + NYA 6 mm (Terpasang)
47 Cable Cage System Ukuran 400x50 mm m' 750,000.00 -
48 Lampu 2 x TLD 36 Watt, Recessed Mounted unit 540,000.00 -
49 Lampu 1 x TLD 36 Watt, Recessed Mounted unit 245,000.00 -
50 Lampu Downlight PL Ess 11 Watt Ex. Artolite/Phillips unit 185,000.00 -
51 Lampu TLD 18 Watt, V-shape Ex. Artolite/Phillips unit 275,000.00 -
52 Lampu Wastafel, GMS TLD 18 Watt Acrylic Cover Ex. Artolite/Phillips unit 350,000.00 -
53 Lampu Downlight Halogen 50/12V Ex. Artolite/Phillips unit 250,000.00 -
54 Down Conductor Kabel BCC 50 mm m' 500,000.00 -
55 Penyambungan Line Telepon (4 Line) ls 235,000.00 -
56 Pemasangan Unit PABX (3 Co line, 40 Line Ext. ) set 1,750,000.00 -
57 Basic Key Service Unit ( 3 Co - 8 Hybrid Ext. ) unit 890,000.00 -
58 Expand Key Service unit ( 3Co - 8 hybrid Ext.) unit 750,000.00 -
59 Interface Board ( 3Co, 16 SLT ) unit 4,500,000.00 -
60 Digital Telephone + Speaker phone (LDP-7224D.STG) 3 line1 24 button unit 230,000.00 -
61 Faximile Telephone ( 1 line Co) unit 750,000.00 -
62 MDF T100 + LSA 60 Pair + Magazine Arrester unit 3,500,000.00 -
63 Surge Protection Belkin (4 way + Telepon Protection ) unit 2,860,000.00 -
64 Instalasi kabel dari MDF ke TTB-1 ( ITC 40 x 2 x 0.6 mm ) m¹ 125,000.00 -
65 Instalasi kabel dari MDF ke TTB-2 ( ITC 20 x 2 x 0.6 mm ) m¹ 125,000.00 -
66 Telepon Terminal Box (TTB) unit 230,000.00 -
67 Pemasangan Outlet Telepon RJ11 unit 230,000.00 -
68 Pemasangan Single Line Telepon unit 230,000.00 -
69 Pemasangan Hub 24 ports unit 450,000.00 -
70 Rack Mounting Switch 9U lengkap dengan Aksesories unit 9,000,000.00 -
71 Instalasi Kabel Data Cat.6e titik 167,000.00 -
72 Instalasi Kabel Fiber Optic/meter m¹ 350,000.00 -
73 Pemasangan Outlet Data IT unit 167,000.00 -
74 Pemasangan Audio System Untuk Pemanggil Antrian unit 1,500,000.00 -
75 Rack Sound System Lengkap dengan Aksesories unit 9,000,000.00 -
76 Power Amplifier 240 Watt unit 3,500,000.00 -
77 Pagging microphones unit 1,850,000.00 -
78 Pemasangan Speaker Kolom unit 350,000.00 -
79 MCFA ( MASTER CONTROL FIRE ALARM ) Semi Adressable System 2 Zon unit 5,400,000.00 - #NAME?
80 Terminal Box Fire Alarm (TB-FA) unit 2,340,000.00 -
81 Rate Of Raise Detector unit 650,000.00 -
82 Photo Electric Smoke Detector unit 750,000.00 -
83 Manual Break Glass unit 1,250,000.00 -
84 Alarm Bell unit 750,000.00 -
85 Indicator lamp unit 350,000.00 -
86 Instalasi Kabel fire alarm titik 145,000.00 -
87 Pemasangan Master CCTV (Ruangan kontrol ) unit 890,000.00 -
88 Digital Video Recorder 8 Channel, 1Tera Byte Mass Storage unit 750,000.00 -
89 Rack Cabinet CCTV lengkap dengan Aksesories unit 9,000,000.00 -
90 LCD Display 20" for DVR unit 2,900,000.00 -
91 Pemasangan Fix Dome Camera unit 450,000.00 -
92 Instalasi Kabel Power titik 135,000.00 -
93 Instalasi Cable Coaxial RG-6 titik 135,000.00 -
94 Pemasangan MATV set 350,000.00 -
95 Parabola Satelite Antena " TelkomVision" unit 1,500,000.00 -
96 Digital Video Receiver "Telkom Vision" unit 1,500,000.00 -
97 Rack Cabinet MATV lengkap dengan Aksesories unit 9,000,000.00 -
98 UHF Antena 17 Element unit 95,000.00 -
99 Booster unit 450,000.00 -
100 Pemasangan Spliter unit 85,000.00 -
101 Pemasangan Coupler unit 85,000.00 -
102 Pemasangan Outlet TV unit 85,000.00 -
103 Instalasi Cable Coaxial RG-6 titik 178,000.00 -
104 Lampu PL 25 watt + Fitting bh 75,000.00 -
105 Lampu PL 18 Watt bh 75,000.00 -

M BAHAN KONTRUKSI JALAN


1 Hotmix AC-WC ton 1,410,000.00
2 Aspal, 1 Drum 155 kg kg 450,000.00
3 Aspal Curah kg 350,000.00
4 Emulsi ltr 13,000.00
5 Aspal Minyak kg 15,000.00

N SEWA ALAT BERAT


1 Tandam Roller 6 - 8 Ton jam 350,000.00
2 Tire Roller 8 - 10 Ton jam 350,000.00
3 Roller Vibrator 5 - 8 Ton jam 350,000.00
4 Pedestrian Roller jam 500,000.00
5 Roller Pneumatic 8 - 15 Ton jam 500,000.00
6 Wheel Loader 1 - 1,6 m3 jam 528,000.00
7 Crane 10 - 15 Ton jam 528,000.00
8 Exavator Backoe ( Short ) jam 470,000.00
9 Exavator Backoe ( Long ) jam 470,000.00
10 Concrete Mixer 0,125 m3 jam 500,000.00
11 Concrete Mixer 0,3 - 0,60 m3 jam 500,000.00
12 Genset jam 380,000.00
13 Draklint jam 380,000.00
14 Track Loader 75 - 100 HP jam 450,000.00
15 Buldozer 100 - 150 HP jam 404,000.00
16 Exavator 80 - 100 HP jam 470,000.00
17 Motor Grader 100 HP jam 404,000.00
18 Pneumatic Drill Hammer jam 350,000.00
19 Sheep Foot Roller jam 350,000.00
20 Stone Crusher jam 350,000.00
21 Teractor Equipment jam 500,000.00
22 Screening Plent jam 500,000.00
23 Asphalt Finisher jam 500,000.00
24 Asphalt Melting Kalte jam 500,000.00
25 Asphalt Sprayer jam 350,000.00
26 Asphalt Mixing Plate jam 500,000.00
27 Sprayer, Self - Prop 1000 L jam 350,000.00
28 Stamper, Viberator Plate jam 350,000.00
29 Crusher / SCB jam 350,000.00
30 Concrete Vibrator jam 350,000.00
31 Pick UP jam 350,000.00
32 Dump Truck 3 - 4 m3 jam 500,000.00
33 Dump Truck 5 Ton 125 HP jam 500,000.00
34 Flatblade Truck 3,5 Ton jam 500,000.00
35 Truck 3/4 jam 500,000.00
36 Truck Fuso jam 500,000.00
37 Mesin Las Listrik 18 PK jam 350,000.00
38 Mesin Pompa Air 3" jam 350,000.00
39 Jack Hammer jam 350,000.00
40 Compressor 4000 - 6500 L/M jam 450,000.00
41 Pump Water 70 - 100 mm jam 350,000.00
42 Trailler, Towed 1 Ton jam 350,000.00
43 Water Tanker 3000 - 4500 Liter jam 450,000.00

O TANAMAN
1 Tanaman Rumput Gajah m2 85,000.00
2 Tanaman Pohon Mangga t.2m phn 350,000.00
3 Tanaman Pohon Palm Raja t.3m phn 375,000.00
4 Tanaman Pohon Keras/Pelindung tinggi batang 3.m phn 500,000.00
5 Semboja Bali Tinggi batang keras 3m (warna merah, Putih & kuning) phn 750,000.00
6 Tanaman Kecil t. 50 cm (pareasi) phn 25,000.00

Depok, 2021
DAFTAR HARGA SATUAN DASAR UPAH

KEGIATAN -
-
PEKERJAAN -
-
-
-
LOKASI -
TAHUN 2021

HARGA SATUAN
NO. URAIAN SATUAN
(RP)

1 2 3 4
1 Pekerja Orang / Hari 125,000.00
2 Tukang Batu Orang / Hari 150,000.00
3 Kepala Tukang batu Orang / Hari 160,000.00
4 Tukang Kayu Orang / Hari 150,000.00
5 Kepala Tukang Kayu Orang / Hari 160,000.00
6 Tukang Besi Profil / Tukang Las Orang / Hari 150,000.00
7 Kepala Tukang Besi Profil / Tukang Las Orang / Hari 160,000.00
8 Tukang Besi Beton Orang / Hari 150,000.00
9 Kepala Tukang Besi Beton Orang / Hari 160,000.00
10 Tukang Cat Orang / Hari 150,000.00
11 Kepala Tukang Cat Orang / Hari 160,000.00
12 Tukang Gali Orang / Hari 150,000.00
13 Kepala Tukang Gali Orang / Hari 160,000.00
14 Tukang Pipa Orang / Hari 150,000.00
15 Kepala Tukang Pipa Orang / Hari 160,000.00
16 Mandor Orang / Hari 180,000.00
17 Operator Orang / Hari 180,000.00
18 Pembantu Operator Orang / Hari 125,000.00
19 Supir Truk Orang / Hari 160,000.00
20 Kenek Truk Orang / Hari 125,000.00
21 Upah Pasang Instalasi Lampu Titik 150,000.00
22 Sewa Excavator jam 470,000.00
23 Upah Pasang Instalasi Stop Kontak Titik 150,000.00
14 Tukang Listrik Orang / Hari 150,000.00
15 Kepala Tukang Listrik Orang / Hari 160,000.00

Depok, 2021
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA, dan PARTISI

HARGA SATUAN JUMLAH HARGA (RP) JUMLAH HARGA (RP)


NO. URAIAN SATUAN
(RP) BAHAN UPAH BAHAN+UPAH
1 2 3 4 5 6 7
1 PASANG PINTU TYPE P1 UNIT
Bahan
7.0000 m1 Kusen Aluminium Warna 4" 125,000.00 875,000.00 875,000.00
6.6000 m1 Bingkai Daun Pintu Aluminium Warna 120,000.00 792,000.00 792,000.00
1.4400 m2 Kaca Polos 5mm 118,000.00 169,920.00 169,920.00
0.6400 m2 Kaca Es 5 mm 129,800.00 83,072.00 83,072.00
1.0000 psg Lever Handle 250,000.00 250,000.00 250,000.00
1.0000 bh Body Kunci+Cylinder 125,000.00 125,000.00 125,000.00
1.0000 psg Engsel Pintu 35,000.00 35,000.00 35,000.00
59.6000 m1 Sealant 35,000.00 2,086,000.00 2,086,000.00
20.0000 bh Paku Sekrup 4,500.00 90,000.00 90,000.00
10.0000 bh Paku Ripet 2,000.00 20,000.00 20,000.00
8.0000 bh Pisher 2,500.00 20,000.00 20,000.00
Tenaga Kerja :
0.0070 oh Pekerja 125,000.00 875.00 875.00
0.0070 oh Tukang Besi 150,000.00 1,050.00 1,050.00
0.0007 oh Kepala Tukang Besi 160,000.00 112.00 112.00
0.0003 oh Mandor 180,000.00 54.00 54.00
Sub Jumlah : 4,548,083.00
Keuntungan Max. 10% : 454,808.30
Jumlah : 5,002,891.30
Dibulatkan : 5,002,800.00
2 PASANG PINTU TYPE P2 UNIT
Bahan
6.0000 m1 Kusen Aluminium Warna 4" 125,000.00 750,000.00 750,000.00
6.2000 m1 Bingkai Daun Pintu Aluminium Warna 120,000.00 744,000.00 744,000.00
1.4400 m2 Kaca Polos 5mm 118,000.00 169,920.00 169,920.00
0.6400 m2 Kaca Es 5 mm 129,800.00 83,072.00 83,072.00
1.0000 psg Lever Handle 250,000.00 250,000.00 250,000.00
1.0000 bh Body Kunci+Cylinder 125,000.00 125,000.00 125,000.00
1.0000 psg Engsel Pintu 35,000.00 35,000.00 35,000.00
59.6000 m1 Sealant 35,000.00 2,086,000.00 2,086,000.00
20.0000 bh Paku Sekrup 4,500.00 90,000.00 90,000.00
10.0000 bh Paku Ripet 2,000.00 20,000.00 20,000.00
8.0000 bh Pisher 2,500.00 20,000.00 20,000.00
Tenaga Kerja :
0.0070 oh Pekerja 125,000.00 875.00 875.00
0.0070 oh Tukang Besi 150,000.00 1,050.00 1,050.00
0.0007 oh Kepala Tukang Besi 160,000.00 112.00 112.00
0.0003 oh Mandor 180,000.00 54.00 54.00
Sub Jumlah : 4,375,083.00
Keuntungan Max. 10% : 437,508.30
Jumlah : 4,812,591.30
Dibulatkan : 4,812,500.00
3 PASANG PINTU TYPE P3 900x2400 UNIT
Bahan
5.7000 m1 Kusen Aluminium Warna 4" 125,000.00 712,500.00 712,500.00
6.0000 m1 Bingkai Daun Pintu Aluminium Warna 120,000.00 720,000.00 720,000.00
1.4400 m2 Kaca Polos 5mm 118,000.00 169,920.00 169,920.00
0.6400 m2 Kaca Es 5 mm 129,800.00 83,072.00 83,072.00
1.0000 psg Lever Handle 250,000.00 250,000.00 250,000.00
1.0000 bh Body Kunci+Cylinder 125,000.00 125,000.00 125,000.00
1.0000 psg Engsel Pintu 35,000.00 35,000.00 35,000.00
59.6000 m1 Sealant 35,000.00 2,086,000.00 2,086,000.00
20.0000 bh Paku Sekrup 4,500.00 90,000.00 90,000.00
10.0000 bh Paku Ripet 2,000.00 20,000.00 20,000.00
8.0000 bh Pisher 2,500.00 20,000.00 20,000.00
Tenaga Kerja :
0.0070 oh Pekerja 125,000.00 875.00 875.00
0.0070 oh Tukang Besi 150,000.00 1,050.00 1,050.00
0.0007 oh Kepala Tukang Besi 160,000.00 112.00 112.00
0.0003 oh Mandor 180,000.00 54.00 54.00
Sub Jumlah : 4,313,583.00
Keuntungan Max. 10% : 431,358.30
Jumlah : 4,744,941.30
Dibulatkan : 4,744,900.00
3 PASANG PINTU TYPE P4 UNIT
Bahan
0.2304 M³ Kayu meranti batu, papan 9,400,000.00 2,165,760.00 2,165,760.00
1.0000 psg Pull Handle 350,000.00 350,000.00 350,000.00
1.0000 bh Body Kunci+Cylinder 125,000.00 125,000.00 125,000.00
1.0000 psg Engsel Pintu 35,000.00 35,000.00 35,000.00
Tenaga Kerja :
1.0000 oh Pekerja 125,000.00 125,000.00 125,000.00
2.0000 oh Tukang Kayu 150,000.00 300,000.00 300,000.00
0.2000 oh Kepala Tukang Kayu 160,000.00 32,000.00 32,000.00
0.0500 oh Mandor 180,000.00 9,000.00 9,000.00

Sub Jumlah : 3,141,760.00


Keuntungan Max. 10% : 314,176.00
Jumlah : 3,455,936.00
Dibulatkan : 3,455,900.00
4 PASANG PINTU PVC KM/WC UNIT
1.0000 Unit Kusen +Daun Pintu PVC lengkap engsel/kunci 650,000.00 650,000.00 650,000.00
0.1500 ls Alat Bantu 650,000.00 97,500.00 97,500.00
0.0500 ls Upah Pasang 650,000.00 32,500.00 32,500.00
Sub Jumlah : 780,000.00
Keuntungan Max. 10% : 78,000.00
Jumlah : 858,000.00
Dibulatkan : 858,000.00
5 PASANG PINTU P2 UNIT
4.8500 m1 Kusen Aluminium Warna 4" 125,000.00 606,250.00 606,250.00
5.7000 m1 Bingkai Daun Pintu Aluminium Warna 120,000.00 684,000.00 684,000.00
1.5800 m2 Kaca Polos 5 mm 118,000.00 186,440.00 186,440.00
1.0000 psg Lever Handle 250,000.00 250,000.00 250,000.00
1.0000 psg Body Kunci+Cylinder 125,000.00 125,000.00 125,000.00
1.5000 psg Engsel Pintu 35,000.00 52,500.00 52,500.00
26.2000 m1 Sealant 35,000.00 917,000.00 917,000.00
12.0000 bh Paku Skrup 4,500.00 54,000.00 54,000.00
12.0000 bh Paku Ripet 2,000.00 24,000.00 24,000.00
8.0000 bh Pisher 2,500.00 20,000.00 20,000.00
0.1500 ls Alat Bantu 2,919,190.00 437,878.50 437,878.50
0.0500 ls Upah Pasang 2,919,190.00 145,959.50 145,959.50
Sub Jumlah : 3,503,028.00
Keuntungan Max. 10% : 350,302.80
Jumlah : 3,853,330.80
Dibulatkan : 3,853,300.00
6 PASANG JENDELA TYPE J1 UNIT
10.9700 m1 Kusen Aluminium Warna 4" 125,000.00 1,371,250.00 1,371,250.00
2.4900 m2 Kaca Polos 5 mm 118,000.00 293,820.00 293,820.00
43.8800 m1 Sealent 35,000.00 1,535,800.00 1,535,800.00
24.0000 bh Paku Skrup 4,500.00 108,000.00 108,000.00
12.0000 bh Pisher 2,500.00 30,000.00 30,000.00
0.0500 ls Alat Bantu 3,338,870.00 166,943.50 166,943.50
0.1500 ls Upah Pasang 3,338,870.00 500,830.50 500,830.50
Sub Jumlah : 4,006,644.00
Keuntungan Max. 10% : 400,664.40
Jumlah : 4,407,308.40
Dibulatkan : 4,407,300.00
7 PASANG KACA PB UNIT
1.2000 m1 Kusen Aluminium Warna 4" 125,000.00 150,000.00 150,000.00
1.0000 Lbr Kaca PB 10 mm 2,800,000.00 2,800,000.00 2,800,000.00
1.2000 m1 Sealent 35,000.00 42,000.00 42,000.00
12.0000 bh Paku Skrup 4,500.00 54,000.00 54,000.00
6.0000 bh Pisher 2,500.00 15,000.00 15,000.00
0.0500 ls Alat Bantu 3,061,000.00 153,050.00 153,050.00
0.1500 ls Upah Pasang 3,061,000.00 459,150.00 459,150.00
Sub Jumlah : 3,673,200.00
Keuntungan Max. 10% : 367,320.00
Jumlah : 4,040,520.00
Dibulatkan : 4,040,500.00
8 PASANG PINTU KACA 8mm UNIT
Bahan
6.0000 m1 Kusen Aluminum 4" 125,000.00 750,000.00 750,000.00
7.0000 m1 Frame Daun Pintu 120,000.00 840,000.00 840,000.00
3.7000 m2 Kaca polos 8" 350,000.00 1,295,000.00 1,295,000.00
1.0000 pcs Handle 150,000.00 150,000.00 150,000.00
2.0000 pcs rel 350,000.00 700,000.00 700,000.00
Tenaga Kerja :
0.1000 oh Pekerja 125,000.00 12,500.00 12,500.00
0.1500 oh Tukang Kayu 150,000.00 22,500.00 22,500.00
0.0220 oh Kepala Tukang Kayu 160,000.00 3,520.00 3,520.00
0.0100 oh Mandor 180,000.00 1,800.00 1,800.00

Sub Jumlah : 3,775,320.00


Keuntungan Max. 10% : 377,532.00
Jumlah : 4,152,852.00
Dibulatkan : 4,152,800.00
ANALISA HARGA SATUAN PEKERJAAN

yang 1,115 M

HARGA JUMLAH HARGA (RP) JUMLAH HARGA (RP)


NO. URAIAN SATUAN SATUAN
(RP) BAHAN UPAH BAHAN+UPAH
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN A
1 PEKERJAAN BONGKARAN M3 ###

###
Tenaga Kerja : ###
5.0000 oh Pekerja 125,000.00 625,000.00 625,000.00
0.2500 oh Mandor 180,000.00 45,000.00 45,000.00
Sub Jumlah : 670,000.00
Keuntungan Max. 10% : 67,000.00
Jumlah : 737,000.00
Dibulatkan : 737,000.00
2 PAGAR SEMENTARA DARI SENG GELOMBANG, h = 2 m M1 ###
Tenaga Kerja :
0.4000 oh Pekerja 125,000.00 50,000.00 50,000.00
0.2000 oh Tukang Kayu 150,000.00 30,000.00 30,000.00
0.0200 oh Kepala Tukang Kayu 160,000.00 3,200.00 3,200.00
0.0200 oh Mandor 180,000.00 3,600.00 3,600.00
Bahan :
1.0000 lbr Seng gelombang, BJls 25 162,000.00 162,000.00 162,000.00
1.2500 btg Dolken kayu dia 8 - 10/400 cm 85,000.00 106,250.00 106,250.00
0.0720 M3 Kayu 5/7 2,000,000.00 144,000.00 144,000.00
0.0600 kg Paku biasa 2" - 5" 16,000.00 960.00 960.00
0.4500 kg Meni besi 31,000.00 13,950.00 13,950.00
Sub Jumlah : 513,960.00
Keuntungan Max. 10% : 51,396.00
Jumlah : 565,356.00
Dibulatkan : 565,300.00
3 PEMBUATAN DIREKSI KEET M2 ###
Tenaga Kerja :
2.0000 oh Pekerja 125,000.00 250,000.00 250,000.00
ANALISA HARGA SATUAN PEKERJAAN

yang 1,115 M

HARGA JUMLAH HARGA (RP) JUMLAH HARGA (RP)


NO. URAIAN SATUAN SATUAN
(RP) BAHAN UPAH BAHAN+UPAH
1 2 3 4 5 6 7
2.0000 oh Tukang Kayu 150,000.00 300,000.00 300,000.00
1.0000 oh Tukang Batu 150,000.00 150,000.00 150,000.00
0.3000 oh Kepala Tukang Kayu 160,000.00 48,000.00 48,000.00
0.0500 oh Mandor 180,000.00 9,000.00 9,000.00
Bahan :
1.2500 btg Kayu dolken dia 8 - 10/400 cm 85,000.00 106,250.00 106,250.00
0.1800 M3 Kayu papan terentang 2,500,000.00 450,000.00 450,000.00
0.8500 kg Paku biasa 2" - 5" 16,000.00 13,600.00 13,600.00
1.1000 kg Besi strip 16,000.00 17,600.00 17,600.00
35.0000 kg PC 1,703.57 59,625.00 59,625.00
0.1500 M3 Pasir pasang 285,000.00 42,750.00 42,750.00
0.1000 M3 Pasir beton 300,000.00 30,000.00 30,000.00
0.1500 M3 Split 271,000.00 40,650.00 40,650.00
0.1200 m3 Bata Ringan 8,674.70 1,040.96 1,040.96
0.2500 lbr Seng plat, BJls 25 180,000.00 45,000.00 45,000.00
2.0000 bh Jendela nako 75,000.00 150,000.00 150,000.00
0.0800 M2 Kaca polos 118,000.00 9,440.00 9,440.00
0.1500 bh Kunci tanam 45,000.00 6,750.00 6,750.00
0.0600 lbr Plywood 4 mm 71,000.00 4,260.00 4,260.00
Sub Jumlah : 1,733,965.96
Keuntungan Max. 10% : 173,396.60
Jumlah : 1,907,362.56
Dibulatkan : 1,907,300.00
RINCIAN BILL of QUANTITY

KEGIATAN : PEMBANGUNAN GEDUNG RAWAT INAP COVID

RUMAH SAKIT UMUM DEPOK

PEKERJAAN : I. STRUKTUR

II. ARSITEK

III. MEKANIKAL dan ELEKTRIKAL

LOKASI : JL. Moch. Muhtar

TAHUN : 2020

HARGA SATUAN JUMLAH HARGA


NO URAIAN KUANTITAS SATUAN
(RP) (RP)

1 2 3 4 5 6=5X3
A PEKERJAN PERSIAPAN

1 Pekerjaan Bouplang 132.00 m² 70,248.50 9,272,802.00


2 Pekerjaan Bongkar Atap Awning & Awning ( Pembersihan dan Perbaikan Kembali) 132.00 m² 29,051.30 3,834,771.60
3 Pas.Banner nama proyek 1.00 BH 110,000.00 110,000.00
4 Penyelenggaraan SMK3 1.00 Set 4,056,250.00 4,056,250.00
JUMLAH I : 17,273,823.60
B PEKERJAAN STRUKTUR
PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi Pile Cape dalam 1meter 51.00 m3 82,075.00 4,185,825.00
2 Pek. Galian Tanah Pondasi Sloof 24.80 m3 82,075.00 2,035,418.96
3 Pek. Urugan Pasir, t = 5 cm 1.24 m3 888,602.40 1,101,844.76
4 Pek. Lantai Kerja, t = 15 cm 3.72 m3 1,019,709.60 3,793,243.23
PEKERJAAN PILE CAP
1 Beton Site mix K-225 51 m3 1,180,636.80 60,212,476.80
2 Besi Ulir 7905 kg 12,967.50 102,508,087.50
PEKERJAAN SLOOPING PONDASI STRUKTUR
1 Pekerjaan Beton Site mix K-225 Slooping 4.96 m3 1,180,636.80 5,855,840.46
2 Pekerjaan Pembesian Slooping 818.38 kg 12,967.50 10,612,388.04
3 Pekerjaan Bekisting Slooping 25.80 m2 102,887.40 2,654,443.48
PEKERJAAN STRUKTUR BETON K-225
1 Pekerjaan Beton Site Mix K -225 Untuk Kolom 16.80 m3 1,180,636.80 19,834,698.24
2 Pekerjaan Beton Site Mix K-225 Untuk Slab & Slab Dak 18.00 m3 1,180,636.80 21,251,462.40
3 Pekerjaan Beton Site Mix K-225 Untuk Balok 14.53 m3 1,180,636.80 17,158,194.61
PEKERJAAN STRUKTUR BESI
1 Pekerjaan Pembesian Untuk Kolom 2,604.00 kg 12,967.50 33,767,370.00
2 Pekerjaan Pembesian Untuk Slab & Slab Dak 1,710.00 kg 12,967.50 22,174,425.00
3 Pekerjaan Pembesian Untuk Balok 1,598.63 kg 12,967.50 20,730,234.53
PEKERJAAN BEKISTING STRUKTUR
1 Pekerjaan Bekisting Untuk Kolom 168.00 m2 237,111.00 39,834,648.00
2 Pekerjaan Pembesian Untuk Slab & Slab Dak 120.00 m2 237,111.00 28,453,320.00
3 Pekerjaan Pembesian Untuk Balok 43.60 m2 237,111.00 10,337,802.49
JUMLAH II : 406,501,723.50
C PEKERJAAN DINDING
1 Pasangan Dinding Hebel dengan adukan dry mortar termasuk beton praktis dan perapihan 276.13 m2 116,744.60 32,236,336.16
2 Plesteran drymix tebal 12,5 mm + acian satu sisi termasuk perapihan 552.25 m2 107,424.80 59,325,775.50
3 Keramik dinding ukuran 300x300mm termasuk adukan, grouting dan perapihan tile ex Roman (setara) Kamar Ma 11.25 m2 299,264.00 3,366,720.00
4 Cat dinding emulsion paint ex. Vinilex termasuk perapihan 574.65 m2 14,709.10 8,452,643.15
5 Pekerjaan Dinding Lapis Timbal pada R. Radiologi 1.00 Ls 122,100,650.00 122,100,650.00
JUMLAH III : 225,482,124.81
D PEKERJAAN PINTU dan JENDELA
R. Ante Pintu Almunium Include Clear Glass ukuran 1.200mm x 2.800mm, dengan kosen pintu, termasuk
1 4.00 unit 5,091,574.35 20,366,297.42
hardware aksesories dan pemasangan.
IGD Pintu Almunium Include Clear Glass ukuran 1.700mm x 2.800mm, dengan kosen pintu, termasuk
2 4.00 unit 7,213,063.67 28,852,254.68
hardware aksesories dan pemasangan.
R. Radiologi Pintu Almunium Include Clear Glass ukuran 1.600mm x 2.400mm, dengan kosen pintu, termasuk
3 1.00 unit 5,818,942.12 5,818,942.12
hardware aksesories dan pemasangan.
R. Radiologi Pintu Almunium Include Clear Glass ukuran 1.000mm x 2.400mm, dengan kosen pintu, termasuk
4 1.00 unit 3,636,838.82 3,636,838.82
hardware aksesories dan pemasangan.
R. Gas Medis Pintu Besi Include Clear Glass ukuran 2.100mm x 2.400mm, dengan kosen pintu kayu, termasuk
5 1.00 unit 7,637,361.53 7,637,361.53
hardware aksesories dan pemasangan.
R. Gas Medis Pintu Almunium Include Clear Glass ukuran 900mm x 2.000mm, dengan kosen pintu kayu,
6 2.00 unit 3,683,868.40 7,367,736.80
termasuk hardware aksesories dan pemasangan.
7 Pintu KM/WC 3.00 unit Err:509 Err:509
Jendela Almunium ukuran 800mm x 1.900mm dan Jendela Almunium, termasuk Hardware dan aksesories
8 1.00 unit 6,868,524.07 6,868,524.07
terpasang Rapih
Jendela Almunium ukuran 2.000mm x 500mm dan Jendela Almunium, termasuk Hardware dan aksesories
9 2.00 unit 4,518,765.84 9,037,531.68
terpasang Rapih
Jendela Almunium ukuran 900mm x 1.200mm dan Jendela Almunium, termasuk Hardware dan aksesories
10 5.00 unit 4,880,267.11 24,401,335.53
terpasang Rapih
Pek. Bouven WC Jendela Almunium ukuran 1.000mm x 500mm dan Jendela Almunium, termasuk Hardware
11 2.00 unit 6,778,148.76 13,556,297.51
dan aksesories terpasang Rapih
JUMLAH IV : Err:509
E PEKERJAAN KERAMIK
1 Homogenous ukuran 600x600mm termasuk adukan, grouting dan perapihan Tile ex Roman (setara) 190.80 m2 352,310.00 67,220,748.00
2 Plint Homogenous ukuran 10x600mm termasuk adukan, grouting dan perapihan Tile ex Roman (setara) 72.67 m1 79,765.00 5,796,123.73
3 Keramik ukuran 300x300mm termasuk adukan, grouting dan perapihan tile ex Roman (setara) (KM Mandi) 9.90 m2 264,647.32 2,620,008.47
4 Floor Hardener Cat 72.67 m2 255,562.30 18,570,434.53
JUMLAH V : 94,207,314.72
F PEKERJAAN FINISHING
1 Plafond gypsum flat tebal 9 mm, rangka hollow / UFC, aksesories pemasangan dan perapihan (seluruh area) 190.80 m2 214,911.00 41,005,019.23
2 Plafond gypsum tebal 9 mm termasuk rangka hollow / UFC, aksesories pemasangan dan perapihan (bathroom) 9.90 m2 214,911.00 2,127,618.92
3 List Shadow Line 72.67 m1 29,764.00 2,162,801.06
4 Cat plafon emulsion paint ex. Vinilex termasuk perapihan 190.80 m2 42,933.10 8,191,635.48
JUMLAH VI : 53,487,074.69
G PEKERJAAN SANITARY
1 Closet Duduk include Flush button termasuk jetspray Terpasang 3.00 unit 4,315,458.00 12,946,374.00
2 Floor drain Terpasang 3.00 unit 341,555.00 1,024,665.00
3 Roof drain Terpasang 4.00 unit 341,555.00 1,366,220.00
JUMLAH VII : 15,337,259.00
H PEKERJAAN MEKANIKAL
1 Pekerjaan Pipa Air Bersih 2" 56.00 m1 95,412.50 5,343,100.00
2 Pekerjaan Pipa Air Hujan 25.00 m1 128,562.50 3,214,062.50
3 Pekerjaan Pipa Kotor 89.00 Lot 155,700.00 13,857,300.00
JUMLAH VII : 22,414,462.50
I PEKERJAAN ELEKTRIKAL
1 Pekerjaan Instalasi Stop Kontak With Cabel NYM 3x2,5mm Maksimal panjang 5m 15.00 titik 303,312.50 4,549,687.50
2 Pekerjaan Instalasi Saklar With Cabel NYM 3x2.5mm Maksimal panjang 5m 22.00 titik 303,312.50 6,672,875.00
3 Pekerjaan Cabel Try 30.00 m1 #NAME? #NAME?
4 Pekerjaan instalasi Lampu TL 2X18 watt 9.00 titik 875,062.50 7,875,562.50
5 Pekerjaan Instalasi Lampu Downlight 10watt 19.00 titik 1,023,750.00 19,451,250.00
6 Pekerjaan Armatur Stop Kontak 15.00 titik 88,812.50 1,332,187.50
7 Pekerjaan Armatur Saklar Seri 5.00 titik 107,250.00 536,250.00
8 Pekerjaan Armatur Saklar Tunggal 17.00 titik 74,750.00 1,270,750.00
JUMLAH VIII : #NAME?
JUMLAH Err:509
PPN 10% Err:509
TOTAL Err:509
Pembulatan Err:509
RINCIAN BILL of QUANTITY

Paket Pekerjaan REHABILITASI RUANG SCREENING

Peningkatan Pelayanan dan Penunjang Pelayanan BLUD

Sumber Dana BLUD RSUD Kota Depok

Tahun 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN KUANTITAS SATUAN BOBOT MINGGU PERTAMA MINGGU KEDUA KETERANGAN
(RP) (RP)

1 2 3 4 5 6 = 5X3 1 2 3 4 5 6 7 1 2 3 4 5 6 7
A PEKERJAN PERSIAPAN WAKTU PELAKSANAAN
14 HARI KERJA
101
1 Persiapan 1.00 ls 700,000.00 700,000.00 1.55 1.55

81
B PEKERJAAN DINDING
1 Pekerjaan Pasang Alumunium 88.00 m' 277,270.00 24,399,760.00 53.90 8.98 8.98 8.98 8.98 8.98 8.98
61
2 Pekerjaan Pasang dinding gypsum 10.00 m2 284,000.00 2,840,000.00 6.27 1.57 1.57 1.57 1.57
3 Pekerjaan Pasang dinding Akrilik 20.00 m2 401,200.00 8,024,000.00 17.72 2.95 2.95 2.95 2.95 2.95 2.95
41
4 Pekerjaan Pengecatan dinding interior 20.00 m2 50,100.00 1,002,000.00 2.21 0.55 0.55 0.55 0.55

C 21
PEKERJAAN PINTU
1 Pekerjaan pasang pintu alumunium 2.00 unit 4,152,800.00 8,305,600.00 18.35 3.06 3.06 3.06 3.06 3.06 3.06
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14

TOTAL BOBOT 45,271,360.00 100.00


BOBOT RENCANA PERHARI 1.55 8.98 8.98 13.61 13.61 16.56 16.56 6.01 6.01 2.95 3.51 0.55 0.55 0.55
KOMULATIF BOBOT PERHARI 1.55 10.53 19.51 33.12 46.73 63.29 79.86 85.87 91.88 94.83 98.34 98.89 99.45 100.00

Depok Juni 2021


Direktur

Hasyim Azhari
PERSIAPAN BH TB
Pengukuran 6.6 4.6 11.2
JUMLAH 11.2

PEKERJAAN DINDING
Pasang dinding alumunium 63.7 63.7
Pasang dinding gypsum 10 4 14
Pasang dinding plastik 11.5 7.5 4 23
Pengecatan dinding Interior 28
JUMLAH 128.7

PEKERJAAN PINTU dan PARTISI


PINTU SLIDENG PARTISI dan aksesoris 2 2
JUMLAH 2