Professional Documents
Culture Documents
0 System -
Volume I
Page 0 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Table of Contents
Disclaimer ........................................................................................................ 3
1 About this RFP .............................................................................................. 4
2 Fact Sheet ................................................................................................... 5
3 About Chhattisgarh ........................................................................................ 7
4 About CHiPS ................................................................................................. 8
5 Background Information of Digital Secretariat 1.0 .................................................... 9
5.1 Key Features .......................................................................................... 9
5.2 Current Implementation Status: .................................................................... 10
5.3 Description of Modules ................................................................................. 10
5.4 Digital Secretariat Current Environment ............................................................ 13
5.5 Critical elements of Digital Secretariat 1.0 ...................................................... 14
5.5.1 Logical Architecture ........................................................................... 14
5.5.2 Physical Architecture ......................................................................... 15
5.5.3 Deployment Architecture ..................................................................... 16
5.5.4 Existing Hardware Details ..................................................................... 17
6 Project Overview and Definitions of Digital Secretariat 2.0 ........................................ 17
7 Detailed Scope of Work ................................................................................. 21
7.1 Knowledge transfer and Project Planning ..................................................... 23
7.2 Application Development ......................................................................... 26
7.2.1 System Requirement Elicitation and System Design.................................... 27
7.2.2 7.2.2 Solution Development, Testing and Go-Live of Digital Secretariat 2.0 ..... 35
7.3 Business & Centralize Helpdesk Support ....................................................... 43
7.3.1 Helpdesk ........................................................................................ 43
7.4 Operation & Maintenance of Digital Secretariat 2.0 (post Go-Live) .......................... 45
7.4.1 Application Support and Maintenance ..................................................... 45
7.4.2 Application Monitoring Services ............................................................. 50
7.4.3 User Profile and Account Management .................................................... 50
7.4.4 Periodic Reporting ............................................................................ 51
7.5 Training and Capacity Building .................................................................. 52
7.5.1 Preparation of training aids ................................................................. 53
7.5.2 Training Effectiveness ........................................................................ 53
Page 1 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Disclaimer
The information contained in this Request for Proposal (hereinafter referred to as "RFP") document
provided to the Bidders, by the Chhattisgarh infotech Promotional Society Raipur, hereinafter referred
to as CHiPS, or any of their employees or advisors, is provided to the Bidder(s) on the terms and
conditions set out in this RFP document and all other terms and conditions subject to which such
information is provided.
The purpose of this RFP document is to provide the Bidder(s) with information to assist in the
formulation of Proposals. This RFP document does not aim to hold all the information each Bidder
Page 3 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
may require. This RFP document may not be appropriate for all persons, and it is not possible for the
CHiPS, their employees or advisors to consider the business/investment objectives, financial situation
and particular needs of each Bidder who reads or uses this RFP document. Each Bidder should
conduct its own investigations and analysis and should check the accuracy, reliability and
completeness of the information in this RFP document and where necessary obtain independent
advice from appropriate sources.
CHiPS, their employees and advisors make no representation or warranty and shall incur no liability
under any law, statute, rules or regulations as to the accuracy, reliability or completeness of the RFP
document. CHiPS may, in its absolute discretion, but without being under any obligation to do so,
update, amend or supplement the information in this RFP document.
CHiPS is the state nodal agency for implementing e-Governance Project in the state of Chhattisgarh.
CHiPS invites on behalf of Department of Electronics and Information Technology, Government of
Chhattisgarh, sealed bids (Pre-Qualification bid/ Technical bid/ Commercial bid) from eligible &
reputed System Integrators for IT Solution provider for “Design, Development, Implementation, and
Maintenance of Digital Secretariat 2.0 solution in the State of Chhattisgarh” and provide support for
a total period of 4 years from the day of Go-Live of applications.
Engage Software solution provider to design, develop, and maintain Public service workflow
digitization application, CG Government HRMS application, web portal, mobile app,
document management system and helpdesk services. These components have been bundled
under the umbrella of Digital Secretariat 2.0.
All the components mentioned above can be developed afresh or the existing codebase can be
leveraged. CHiPS has an existing Digital Secretariat 2.0 solution which is currently being used
to provide online G2G services in the state. The proposed system should use proven open
source technology to reduce s/w licensing cost.
Design and Development will involve receiving a knowledge transfer from the existing Digital
Secretariat 2.0vendor of CHiPS.
Page 4 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Study and analyze the existing systems G2G Services. Assessment shall include review of the
current processes/activities performed for delivering the service to the state employees,
operators, key stakeholders and dependencies in service delivery, current level of automation,
non-value added activities/inefficiencies which can be eliminated, district level coordination
and monitoring etc.
Onboard these G2G Services onto the new application developed as a part of Digital Secretariat
2.0 for Go-live.
Assist in training, capacity building and change management of different stakeholders for user
adoption of the systems developed as a part of this initiative.
The aim of the state is to provide complete digital experience to Government Employees. This
will enhance the efficiency and transparency in administration through the implementation of
a comprehensive online workflow application in the all departments of Government of
Chhattisgarh.
Note:
1.CHiPS reserves the right to extend the Term for further period of up to Three (3) Years on the same
terms and conditions, if required.
2. The term CHiPS in this RFP have been used for interchangeably for CHiPS or any
nominated agency by CHiPS.
2 Fact Sheet
1 Tender Number
RFP No.: 71626/CEO/CHiPS/DS/RFP/2021
2 Name of the Work Design, Development, Implementation, &
Maintenance of Digital Secretariat 2.0
Page 5 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
8 Last Date for Submission of Bids 10th May 2021 till 3 pm (Online Submission)
Page 6 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Phone: 0771-4014158
Email : ceochips@nic.in
3 About Chhattisgarh
Chhattisgarh, a 21st century State, came into existence on November 1, 2000. Larger than Tamil Nadu,
it is just the right size, and is also fortunate to have a low population density. Good Governance is the
highest priority in this Fast Track State. There is both policy stability as well as political stability.
Page 7 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Government has been kept small and the State is in excellent fiscal health. Chhattisgarh is truly a land
of opportunities. With all major minerals including diamonds in abundance, it is the richest State in
mineral resources. There are mega industries in Steel, Aluminium and Cement. Chhattisgarh
contributes substantially to the Human Resources of India.
Several hundred students from the State qualify for admissions in prestigious academic institutions
every year. Bhilai, the knowledge capital of the State, alone sends over 50 students to the elite Indian
Institutes of Technology every year. It is large power surplus is attracting power-intensive industries,
and the State is poised to become the power-hub of the nation. Its central location helps easy power
transmission to any part of the country. 12% of India's forests are in Chhattisgarh, and 44% of the
State's land is under forests. Identified as one of the richest biodiversity habitats, the Green State of
Chhattisgarh has the densest forests in India, rich wildlife, and above all, over 200 nontimber forest
produces, with tremendous potential for value addition. One third of Chhattisgarh's population is of
tribes, mostly in the thickly forested areas in the North and South. The central plains of Chhattisgarh
are known as the “Rice Bowl” of Central India. Female literacy has doubled in the last decade, and
male literacy is higher than India's average. Gender ratio is next only to Kerala. Bastar is known the
world over for its unique and distinctive tribal heritage. The BastarDashera is the traditional
celebration of the gaiety of tribal. Many virgin, unexplored tourism destinations are there is all the
parts of Chhattisgarh.
4 About CHiPS
CHiPS, a Registered Society promoted by the Government of Chhattisgarh, is the nodal agency and
prime mover for propelling IT growth and implementation of IT plans in the State. The Hon’ble Chief
Minister heads the High Powered Governing Council of CHiPS It includes Minister for Finance &
Commercial Taxes, Minister for Commerce & Industry, Minster of IT, and Minister for Education,
Minister for Panchayat & Rural Development, Chief Secretary, and a representative from the Ministry
of Information Technology in Government of India and eminent persons from IT industry. A
professional approach is being adopted for the implementationof IT Projects u sing the services of e-
governance experts and consultants from corporate and academia.
Page 8 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
The Digital Secretariat project bought in a radical change in the existing workflow of government
offices of the Indian state of Chhattisgarh. The project achieved the automation of official work flow
for State Government employees.
The system replaced manual file processing in the state secretariat, thereby reducing the time
consumed during file movement, improving archival facilities, and increasing efficiency. The workflow
system also mapped the roles and responsibilities of all levels of government officials for electronic
movement of files. The scanned copy of supporting documents enabled instant reference and
facilitated quick decision making.
HRMS, a module within the project, is a digitised database of all state and district officials. HRMS
model helped achieve information exchange between departments, informed decision making by the
secretariat, extensive monitoring and evaluation of employee records.
The Project was inaugurated by Hon’ble Chief Minister Govt of C.G. on 1 st of October 2013. The system
used e-Governance as the tool to improve the Accountability, Transparency and Effectiveness in
Government administration.
Page 9 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
● 2 Lakh+ files covering 1.36 Cr records across 48 departments digitized and uploaded
● DAK Management, File Management, Meeting, Support Ticket, Leave , ACR, MIS Reports and
IPR have been developed
● Travel Management, EIS, Salary Slip generation modules have been developed.
● More than 2.5 Lakh DAK/File Transaction in State Secretariat
● Over 1000 staff from State Secretariat trained thrice
● 48 departments are using this system in State Secretariat
● HRMS – Implemented Employee Management, Leave, Property Return and Annual
Confidential Report Module
● Available through Android and Hybrid Mobile App
● The Customized System implemented in WCD (e-docket) ,NRDA( Bank guarantee), AG Office
( Court Case Management) and e-Vidhan for CG Vidhansabha with necessary digitization
operation
● DSC/e-sign has been integrated in the system
● DS System received SKOCH award
The Office Automation Application suite has been developed through which the processing of
letters and files can be managed, moved and tracked. List of Modules developed in system are
given below
DAK Management: DAK Management automates the processing of DAK. This includes creation of
DAK (electronic and physical both kind of DAK), movement of DAK in the workflow, tracking of
DAK and their management.
Following features have been developed in this module:
File Management:The File Management shall be automated to cater to the file processing
requirements of Secretariat. It shall ensure that files dealing with any subject in any department
are processed in a similar manner. This includes Creating Inward/Outward, Creating File and moving
it, Monitoring File and Tracking, Generating Order and Maintaining record room for Files and
Correspondences.
Page 10 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Meeting Management and ATR: Meeting Management Module brings productivity into regular
meetings such as weekly, review and project meetings. From creation and scheduling of meetings
to attaching agenda and minutes of the meeting, and action to be taken, collaboration is made
effective. The module also enables cancellation, postponement and nomination of another team
member if the original participant is unable to attend. Post-meeting actions can be assigned based
on the MoM for generating the Action Taken Report.
Page 11 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
HRMS Module:The Human Resource Management System (HRMS) Module redefines routine HR
processes into intelligent processes that promote proactive decision making. For instance, leave
management, includes advanced features like apply, cancel, extend and edit along with automatic
assignment of DAK/File to the Link Officer. The HRMS module also includes travel management, IPR
returns, a centralized employee information system and the generation of the Annual Confidential
Report.
Support Ticket Module: With the Support Ticket Module, Digital Office provides users with a single
Page 12 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
window issue resolving platform, with built-in SLA (Service Level Agreement) information. Tickets
can be raised for oneself and on the behalf of others, which will be queued for the technical team.
The module also enables users to provide valuable suggestions.
Following features have been developed in this module:
Network CG-SWAN
i. Linux environment
ii. Localization (Unicode) support
iii. Public Key Infrastructure (PKI) along with
smart card for Privacy, Authenticity, Integrity
& Non-repudiation;
iv. Aadhar based authentication process
v. MVC (Module View Controller)
vi. ENS (Electronic Notification Scheduler) for
alert messaging.
vii. NMS (Network Management System) for
network monitoring.
viii. Performance monitoring
Page 13 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Page 14 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
JSP / Reque st
Controll er
Busine ss L ogic
(API, Schedu ler, Authen tication)
DAO
Obj ect Rel atio nal Ma pping
Model
(ORM)
Database
Page 15 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Page 16 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
NO OF
Environme Server Make CP PROCESSOR RAM
PROCE HDD OS
nt Type /Model U (Ghz) (GB)
SSOR
Digital Secretariat 2.o aims to streamline, automate and digitize each department’s execution arm i.e
the directorate and all its offices till district level.The vision of the Digital Secretariat 2.0 Project is to
provide complete digital experience to Government Employees. This will enhance the efficiency and
transparency in administration through the implementation of a comprehensive online workflow
application in all the departments of Government of Chhattisgarh.
The project will bring IT enabled transformation in the Government operations.DAK disposal from
Directorate till district office will be online. Application will be enhanced and revamped to support
state wide rollouts.
Digital Secretariat 2.0 also aims to implement an iHRMS(Integrated HRMS module) that will
automate and digitize all processes of employees from Recruitment till retirement throughout their
service period.The Project will also integrate iHRMS with e-Karamchari,e-kosh i.e. Integrated Finance
Management System.
The Digital Secretariat 2.0 proposes to develop microservices architecture based, API enabled
technology components that will cater to the entire G2G delivery life cycle in the state. These
Page 17 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
technology components aim to transform the efficiency, effectiveness and user experience of how
government operations are executed.
When the functionalities/modules are used by State Government employees,the mobile or web
interface would redirect to the underlying workflow application. The government authorities can also
view applications and provide approvals online.
After confirmation of the action, it will be routed through a workflow specified in theworkflow
application. This will be a low code/no code application, which can help state government line
departments to execute their daily or HRMS related operations in a rapid turnaround time.
Helpdesk application and support services will be available to all the stakeholders and end users in
the government who will use the applications and modules created under Digital Secretariat 2.0 .
In order to ensure smooth functioning of the different technology components, along with continuous
uptake of these new systems under Digital Secretariat 2.0, “Train the Trainer” concept will be adopted.
Their role will be to support government functionaries at the government offices to onboard a new
feature/functionality, customize an existing functionality or assist in any technical challenges they are
facing using the new systems under Digital Secretariat 2.0.
Scalable The system should be scalable. All Govt. offices will use this system as
single source of information related to office and resource
management. Integration with other State owned and Got systems will
be possible through this system.
Standardize The letter/ file management system should be as per central secretariat
guidelines. Other modules would also be developed and implemented
as per standards and guidelines set by GoCG
Reduced cost The system would be able to reduce Govt cost by obsoleting use of
paper, un-necessary travel, stamp and courier cost, resource cost.
The proposed system should use proven open source technology to
reduce s/w licencing cost.
Page 18 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
self-sustainability The system would be sold to any other State Govt/PSU/Central Govt.
after successful implementation in Chhattisgarh. CHiPS will own its
propriety license on behalf of GoCG and generate revenue through this
system.
Definitions
Dak –All communication received/issued by an
office/department.Includeseverytypeofwrittencommunicationsuchasletter,telegram,interdepartmen
talnote,file,fax,e-mail,wirelessmessagewhichisreceived,whetherbypostorotherwise, in
anydepartmentforitsconsideration
Department –Any of the Ministries, Departments, Secretariats and Offices mentioned in the First
schedule to the Government of India (Allocation of Business) Rules, 1961, as amended from ti me to
time. Means any of the Ministry, Department, Secretariat and Office mentioned in the First Schedule
to the Government of India (Allocation of Business) Rules, 1961
Section Means the basic work unit within a Department responsible for attending to items of work
allotted to it. It is generally headed by a Section Officer and includes ‘Cell’,’Unit’ and other like terms.
Note Means there marks recorded on a case to facilitate its disposal , and includes a summary of
previous papers , a statement or an analysis of the questions requiring decision , suggestions
regarding the course of action and final orders passed thereon.
File A collection of papers on a specific subject, assigned a number and consisting of one or more of
the following parts:
(a)Notes
(b) Correspondence
(c) Appendices to Notes/ correspondence
Note -The remarks recorded on a case to facilitate its examination and decision.
iHRMS – iHRMSprovides a simplified solution to employees and admin to access their relevant
information like leaves, staff handbook, Service book, Annual Confidential Reports, Postings and
many other important details relevant to their employment which covers the complete cycle from
onboarding of an employee to their retirement with authorized access to the information available for
various roles.
Page 19 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Following are the list of G2G (Govt. to Govt.) services which will be impacted if this project is
discontinued
Mantralaya Services-
DAK/ File Tracking - With intuitive features such as unique numbering for every file, online noting
with document and comment referencing, the ability to set time and priority meeting, file tracking,
department and section wise file access, and digital signature integration, Digital Office ensures faster
meeting of deadlines and increased collaboration. Automate the workflow of DAK and File handling
through, user can create new file put online note and digitally sign the documents.
Online Leave apply, approval – Leave management as per the rule of Govt. of Chhattisgarh,
system automates the workflow of leave approval. Option has been provided to user fo cancel, reject
and edit leave.
Online IPR filing – Immovable property declaration module through system, it automates the
process of IPR filing.
Online DAK disposalfrom CS office to all departments which includes TL DAK Tracking.
Vidhan-Sabha Portal (integrated with Digital Secretariat)- In which all departments upload their
Annual Report and Financial Budget which is published in e-Vidhan-Sabha portal.
Naya Raipur Development Authority (NRDA)- DAK, Bank Guarantee Module is used in Naya Raipur
Development Authority (NRDA)which is also integral part of Digital Secretariat Portal.
R.S.C.L. (Raipur Smart City Ltd.) - File, DAK, Leave Module used in RSCL
WCD – e-docket- - Integrated part of Digital Secretariat which is used in Women and Child
Development department use this portal for movement of letter.
SO one of the very important objective of Digital Secretariat 2.0 is to ensure that existing services
continue uninterrupted for next 5 years.
Government of Chhattisgarh has envisaged the requirement of a new version of Digital Secretariat
Phase 2 System as a centralized web cum mobile based application which can be accessed by
departmental officials of various departments/ agencies of Government of Chhattisgarh across the
State either on secured intranet and internet using several devices like Laptop, PC and Mobile
Tablets/iPad.
The minimum specified work to be undertaken by the bidder for setting up and operating project has
been categorized as under. However, the SI is expected to conduct a detailed requirement gathering
for validation of requirements already enlisted as a part of this RFP. The SI will have to meet any other
requirements, not listed in the scope of work that may be required in order to establish the fully
functional Digital Secretariat 2.0 system.
Digital Secretariat 2.0 is an umbrella term given to the multiple technology components that will be
developed and is under the scope of work. All the components should be based on Microservices
architecture and be API enabled.
Page 21 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
7. Integration System Should be based on open standards and have API support for
Scope data import & export so that integration with the Common Services
can be done.Integration with IFMS (Integrated Finance Management
System), e-docket etc. is proposed.
1. Integrate with the existing set of state and central government applications and be future
ready for API based integration with upcoming software applications of CHiPS, APIs for
which will be provided to the SI by CHiPS.
2. Maintain and support of existing Digital Secretariat system. The incumbent SI of Digital
Secretariat needs to be relieved from its duties once selected components of Digital
Secretariat 2.0 are operational. Therefore, different components will go-live in three
Page 22 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
different phases, with the components having dependency on the incumbent SI going live
first. After that, development of other phases components will continue and go-live.
During this development phase , Basic operation and maintenance of existing DS 1.0 and
components which have gone live will also continue
3. Once, all the components of Digital Secretariat 2.0are live, the major maintenance and
support phase will continue for a period of 4 years.
It must be noted that entry/start criteria for each phase of the project is dependent upon approval of all
the required deliverables (if any) from the previous phase
1 The SI will have to take a detailed business knowledge transfer from the incumbent SI managing
Digital Secretariat project. The SI will have to undertake guided System Study from the existing
Digital Secretariat .SI and CHiPS officials to understand the existing functioning, Portal
functionalities, manpower structures and any other business information required to formulate the
project plan. Studying of codebase is optional, as the SI may choose to go for fresh development or
customization and prepare a plan accordingly.
2 .Responsibilities of the SI during the Knowledge Transfer Phase shall include the following
(including but not limited to):
i. The new SI will be required to submit a detailed Knowledge Transfer plan at the start of
the KT phase, listing all the activities from their end, including the expectations from
existing SI and CHiPS. A checklist (as part of knowledge transfer plan) needs to be prepared
by the new SI for ensuring proper knowledge transfer. This shall be reviewed and subject to
approval by CHiPS.
ii. The existing SI shall provide all knowledge transfer of the system to the incoming SI to
the satisfaction of CHiPS as per the specified timelines.
iii. The knowledge transfer shall include initial and ongoing training on existing software,
training materials, operations manuals, procedure manuals, source code control and
deployment/ installation guide.
iv. The existing SI shall conduct detailed Knowledge Transfer sessions for the new SI (such
sessions should be recorded by the new SI for future playback) and shall concentrate on the
following:
a) Study of the functional specification documents including the SRS, enhancements log,
user manual documentation of business processes, presentations to CHiPS to confirm
Page 23 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
understanding
b) Identification and deep dive into all available documents (like SRS, enhancement log,
design documents, User Manual etc.)
c) Details of integration with other systems
d) Details and access to the codes, scripts, jobs, etc. for study and assist in understanding
the documentation of existing Digital Secretariat 2.0 and its various components,
understanding of development, support processes, configuration management processes,
etc.
e) Understanding of various environments (development, UAT, Production etc.), and
obtain training on all the existing tools used, processes followed, and activities performed
is optional as the SI will be expected to set up its own environment in cloud.
f) Understanding of existing client end infrastructure and network management, including
the role of SPOCs and other stakeholder’s profiles
g) Walkthrough of the helpdesk setup and solution.
h) Understand the applicable IT policies and their respective status
i) Understanding of all existing issues in existing Digital Secretariat 2.0 IT landscape and
their impact; the issues faced by the existing SI while implementing and managing the
existing solutions and the resolutions for the same; and also, of any special behavior (if any)
exhibited by the overall solution or the integrated applications.
3. It is clarified that new SI is required to deploy technically competent resources, in the specific
solution areas of existing Digital Secretariat 2.0, during the KT phase and Transition phase.
The existing SI shall not be responsible for imparting any basic technical skillset to the
resources of the new SI, which would be deemed as a pre-requisite.
4. The new SI is required to utilize this time in the most efficient and effective manner, to ensure
complete business knowledge of existing Digital Secretariat 2.0. The new SI should deploy its
project management, domain as well as technical manpower to absorb the KT sessions. They
should conduct site visits to get an understanding of the requirements as and when required.
5. The new SI will be required to submit a weekly status report on the progress of KT activities
6. During this phase, the new SI shall be required to submit a report on the detailed
understanding of existing Digital Secretariat 2.0 system and operations, which will be
reviewed by CHiPS and this will form the basis of start of the design phase.
7. The SI needs to prepare an Integrated Project Plan for the entire project. Project plan should
provide a detailed drill down and interdependencies of all activities to be undertaken. This
includes details of tasks, assigned teams for undertaking responsibilities for the task, schedule of
Page 24 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
deliverables and milestones, key assumptions and dependencies, associated risks and mitigation
plans.
8. The SI’s work plan should be synchronized with the staff deployment plan proposed;
The deployment plan shall clearly define onsite and offsite deployment plan and personnel under
each deployment category along with engagement period for the project.
9 .The SI should preferably use cloud-based project management tool and provide access to the
same to key stakeholders identified by CHiPS. The tool should provide all features related to
project management requirements of the project. Also, the PM tool should preferably have
function to auto update stakeholders over Email/SMS.
10. SI at any point of time during project cycle may have to adopt and use project management tools
provided by CHiPS.
11. The prepared project plan should allow teams to track the progress of various deliverables and
milestones, through the scheduled review mechanisms.
12.The acceptance of the Integrated Project Plan by CHiPS is necessary before proceeding to the
next phase of the project.
13 .Approval by CHiPS of the proposed plan shall not relieve the SI of any of his duties or
responsibilities under the Contract. However, if the SI’s work plans necessitate a
disruption/shutdown in project operation, the plan shall be mutually discussed and developed
so as to keep such disruption/shutdown to the unavoidable minimum.
14. Considering the long-term nature of this project, the SI may make reasonable assumptions for a
time period beyond two years from project kick-off and provide a top level programof work. This
could be detailed further on a quarterly basis as the time horizon for which the program of work
has been created draws closer.
15.The plan so submitted by the SI shall conform to the requirements and timelines specified in
the RFP.
16 .Any time and cost arising due to failure of the SI to develop/adhere such a work plan shall be
to his account.
Note: The list of deliverables are given below, further a detailed list of deliverables have been
provided in as per Project Timelines, Payment Terms & Schedule of RFP Volume1.
Deliverable(s):
1. Integrated Project Plan including:
a) Milestones
b) Resource deployment
c) Risks and their mitigation plan
Page 25 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
d) Dependencies
e) Responsibility matrix
5. Other deliverables include O&M Plan, Test Plan along with User Acceptance Test Plan,
Training Plan, Exit Management & KT Plan and Security Matrix/Plan.
Page 26 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
1. The SI will carry out a detailed assessment to prepare the FRS incorporating the
requirements provided by all the stakeholders.
2. As part of the requirement gathering activity, the SI should study the existing Digital
Secretariat application mainly from the business, process and stakeholder point of view. The
SI may choose to reuse or enhance the existing code or may build fresh technology
components altogether. SI needs to work closely with the existing SI for Digital Secretariat and
CHiPS officials to get all the business knowledge pertaining to the application as part of the
scope of work.
Page 27 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Note: The list of deliverables are given below, further a detailed list of deliverables have been
provided inas per Project Timelines, Payment Terms & Schedule clauses of RFP Volume-1
Deliverable (s):
1. Refined FRS covering the functional requirements, data integration requirements, data
management requirements etc.
2. The document should contain the requirements providing visual screen shots, portal designs,
login pages, reporting formats etc. for various functions and layouts as part of the system, including
the functions of the systems.
The SI has to consult all the concerned stakeholders and design detailed workflows for all the system
requirements. Detailed workflows need to be designed and signed off from CHiPS. The business
requirements for integration of services/systems will be provided but furthermore
integration points may also have to be diagnosed, diagrams charted out by the SI and accordingly
systems will have to be implemented.
1. The SI should provide detailed wireframes and prototypes demonstrating the User
Interface and User Experience of the proposed Digital Secretariat 2.0 system.
Design Considerations
The proposed solution will provide a holistic guide to implement a high performant, scalable,
extensible and secured system while also provisioning for highest data integrity, least downtime,
reduced maintenance and minimum human intervened support activities.
The key system design considerations and implications are elaborated below .
The system deals with personal and sensitive data from multiple departments of both in house and
3rd party stakeholders. There are serious cyber security threats to governance applications in general
from external and internal sources as has been brought to light time and again.
Page 28 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
The system design should provision for a Robust Security as a core feature for Data at Rest and Data
in Motion. Configurable Authentication and authorization with internal and 3 rd Party systems should
be provisioned for. Governance model for Data access should be implemented to revoke and provide
grants to partial contents of a system record. Strong end to end encryption of data (Data at Rest and
Data in motion) must be implemented using applicable measures of strong benchmarked
cryptography, HSM, physical access control, audit trail, monitoring, throttling and robust compliance
processes. System restoration, Impact isolation and recertification of data in eventuality of a Data
breach or Security incident should also be provisioned for.
Security policies and concerns also extend to support and operations personnel. Direct Access to
application servers via ssh, scp, sftp protocols by Operations personnel should be temporary and
restricted to application installation phase. For all practical daily operations, direct access to
application servers via ssh, scp, sftp should be avoided. Instead interfacing Operation Support
applications should be deployed to enable deployments, log analysis. This is important to ensure
security of application data and access trails.
2) Reliability
Given the dynamic, legal and financial nature of the office management system, the sanctity of System
Records and Data accessed through the system is of paramount importance. Responsibility of Data
validation and Data integrity should be restricted to defined Core System components. All System of
Records should have clear Audit trail and anomaly routinues should be set up of early detection and
warnings. System should look to achieve an RPO (Recovery Point Objective) of less than 5 mins and
RTO (Recovery Time Objective) of less than 15 mins. The system is highly transactional and should
support an estimated user concurrency of > 300 while maintaining transactional integrity with
appropriate queuing, messaging, retries and eventing implementations.
3) Scalability
System should be designed to scale both horizontally and vertically by adoption of a loosely coupled
architectural paradigm. A Microservice based approach with clear separation of Data Access, Business
Processing and Data Presentation concerns via creation of Composite services using Granular Services
(Stateless REST APIs) should be adopted. This would provide ability to alter infrastructure for
individual components or modules of the system on demand, as opposed to an overall system upgrade
with higher costs. Asynchronous processing of long running processes and 3 rd Party integrations will
augment system capability, scalability and reduce response time. This approach will allow for
component level tuning, analysis, refactoring and upgrade. Data architecture should provide for a
robust Data indexing and archival processes to support consistent performance with increasing data
volume. Data partitioning and Sharding should be applied to the core data sets. Elastic Search and
Caching augmentation will ensure faster retrieval and reduce complexity and business logic coupling
at application layers.
Page 29 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
The system should be designed as a platform over which client applications can be composed. The
Core platform layer exposes Data access, Workflow and Rule engine features as REST APIs (Open
Standard). This allows a diverse set of independant applications to built over using these APIs. These
federated applications thrive in a Eco system where each of them can be extended, enhanced and
integrated independently thereby allowing for rapid turnaround in inducting the dynamic
requirements both in terms of scale and functionality.
The Core platform should also ensure interoperability of functionality with legacy applications and 3 rd
party systems (ERP implementations etc). This is achieved through In-Channel and Out-Channel
Message Brokers and Data migration strategies. Provisions for Real Time Feed ingestion and
processing should be implemented.
5) Maintainability
The System should feature automated maintenance and recovery as an inherent attribute. Every
component of the system should provide monitoring and metrics gathering interfaces by way of heart
beats, health checks and proactive alerting. Each of the components should be monitored in an non
intrusive manner, metrics obtained such that real time analytical views can be pulled. This is done via
usage of monitoring tools, log analysis both at Network and Application Module level. Module level
issue debugging in a toggeable and secured manner with proper access control should be enabled.
Instead interfacing Operation Support applications should be deployed to enable deployments, log
analysis and metric visualizations. Automated system metric reports should be published with respect
to Performance, Resource Utilization along with configurable alerting thresholds.
A layered approach to Testing the system components should be provisioned where eco system
components can be stubbed, allowing for more agility, reduced inter team/application dependence,
faster issue detection, analysis and mitigation.
Solution Architecture
The SI will develop a detailed design document that meets the users’ requirements captured in the
previous activity. In this activity, the SI shall be required to perform at least the below mentioned
activities:
2. Preparation of Digital Secretariat 2.0 System Design Document specifying the construction
details of the system, each system component’s interaction with other components and
external systems, and the interface that allows end users to operate the system and its
functions
Page 30 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
1 General
Guidelines 1. Solution components should be based on open source technology
and should be provided with necessary support
Page 31 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
11. The IPR for the Digital Secretariat 2.0 Solution would be with
CHiPS.
Page 32 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
a. Development environment
d. Production environment
The diagram below depicts the envisioned solution components and application layers.
Segregation of Data access and Application Business Logic concerns will ensure extensibility and data
integrity of the system while decoupling the custom logic from the core system design.
Page 33 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Client Applications
3 rd Paty A uth
Services
File Mgmt Meeting Correspondence
(LDAP/AD/UiDAI)
SMS Gateway
Business Legal Case Annual Report Attendance
Logic Email
Federation
Office Bulletin HRMS RTI
Legacy Apps
Feed Aggregator Social Integration ...
ERP/COTS
Integration
Application APIs (Extension)
File/Document
Reporting
Core Rule Engine Workflow Engine Store
Framework Out Channel
Data
Broker (Export) Cache/
Access
Entity Metadata Event Queue Elastic
Scheduler Search Data
Provisioning Manager In Channel
Broker (Feeds)
Audit & Logging Notification &
... Message Brokers
Framework Alerts
(Exchange)
These APIs will ensure appropriate validation and data integrity of the system records.
Integration Handles
Page 34 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
This component implements a Data exchange broker to ingest data from external applications into the
system by way of a Data handling pipeline (preprocessing, rejection, data sync).This component allows
for integrating the system with 3rd Party enterprise products and data interchange.
It is also responsible for exposing data feeds from the e-office system to subscribed applications in a secure
manner.
Note: The list of deliverables are given below, further a detailed list of deliverables have been
provided in as per Project Timelines, Payment Terms & Schedule clauses of RFP Volume-1
1. High Level Solution Architecture Document (including ER Diagram and Data Flow
Diagram)
2. High Level Design Document and Low-Level Design Document (including Schema
Diagram)
o Application architecture
o Enterprise architecture
o Database structures
o Security architecture
o Integration architectures
o Network architecture
4. Use Cases
7. All Policy, Plan & Methodology Documents covering aspects mentioned above
7.2.2 Solution Development, Testing and Go-Live of Digital Secretariat 2.0
Development of Digital Secretariat 2.0
1. The SI shall develop the software in accordance with the approved requirement specifications,
design specifications, and according to the project plan and carry out the unit testing of the
software in accordance with the approved test plans. The overall Digital Secretariat 2.0setup shall be
implemented in following environments i.e.
Page 35 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
a) Development environment
d) Production environment
2. The SI needs to provide software configuration, customization and installation reports to CHiPS.
3. The SI should ensure solution sustainability to meet all RFP requirements, any additional
procurement required will have to be taken by the SI with no additional cost to CHiPS
a. The application software developed by the SI must be user friendly so that users can access
it without having extensive training.
b. The lifecycle for each phase should be independent, i.e. different teams should work in
parallel to complete the track activities per the given timelines.
c. The SI shall also supply any other tools required to complete the integrated solution
requirements. For the integrated solution, the SI shall supply:
ii. Tools, documentation and prepare a list of items supplied. Tools shall be part of the
solution. SI should provide technologies matrix.
iii. Supply latest supported version of all software to support the solution and any
other software, tools and bolt-on/add-on application.
1. Development of all components of Digital Secretariat 2.0 as explained at the start of scope
of work section
2. Delivery of Software , Operational/ Technical manuals, Library Files, Setup Programs etc.
3. Integration of all standalone systems developed and enhanced. Also, integration with other
strategically important applications or systems identified during requirement gathering
phase.
Page 36 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
5. Solution Testing.
2. Test cases for UAT would be refined by SI and approval of the same is to be obtained by CHiPS.
3. The Test Plans also include planning for the testing to demonstrate the ability to integrate with
3rd party solutions. The Test Plans should also specify any assistance required from CHiPS and
should be followed upon by the SI.
4. The SI is required to get a sign-off / approval on the Test Deliverables (Strategy, Plan,
Designs and Specifications etc.) in order to commence the testing for the proposed
solution.
5. The SI is required to make all necessary arrangements for testing (integration, system,
functional and user acceptance) including the preparation of test data, scripts where
necessary; and procurement and setup of test environments shall be the responsibility of the
SI.
Note: The list of deliverables are given below, further a detailed list of deliverables have been
provided in as per Project Timelines, Payment Terms & Schedule clauses of RFP Volume-1.
Deliverable(s):
2. There should be provision for all kinds of testing viz. performance, system, integration, load,
performance, stress etc.
Page 37 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
3. User Acceptance Testing needs to be performed for all the systems developed, enhanced and
integrated
GAD will nominate representatives from different user groups/depts based on inputs
from the SI and would facilitate UAT. The SI would make the necessary changes to the
solution to ensure that it successfully passes through UAT. CHiPS will facilitate
coordination between GAD and SI.
It is mandatory for SI to incorporate / consider test cases as part of UAT test cases for
those customized and/or extensions and/or configured functionalities identified
from traceability matrix.
GAD would issue certification of acceptance for which it shall verify availability of all
the defined services as per the contract signed between the SI and CHiPS. The
System Integrator shall be required to demonstrate all the services / features /
functionalities as mentioned in the agreement. Prerequisite for carrying out UAT activity
shall be:
ii. The training requirements as mentioned should be completed before the final
acceptance test.
Licenses/ Manuals/ Brochures/ Data Sheets/ CD/ DVD/ Media for all the supplied components should
be provided to CHiPS
Note: The list of deliverables is given below, further a detailed list of deliverables have been
provided in as per Project Timelines, Payment Terms & Schedule clauses of RFP Volume-1.
Deliverable (s):
1. Test Data
2. Testing Reports
performance is as per requirement. Any additional software and any other components
required to meet the performance SLAs, would be provided by the SI at no extra cost.
2. SI is required to submit the report for the performance testing to CHiPS; the testing will be
monitored by CHiPS or any agency appointed by CHiPS.
3. Performance testing would include load / stress testing. This would need to be carried out on
the exact architecture as would be used in the production environment (solution
architecture as well as computing capacity). All necessary tools to carry out testing would be
provided by SI.
4. SI is required to obtain STQC certificate within 3 months of Go-live of all module and must
maintain the same throughout the contract duration
Note: The list of deliverables are given below, further a detailed list of deliverables have been
provided in as per Project Timelines, Payment Terms & Schedule clauses of RFP Volume-1.
Deliverables:
1. Performance Test Reports
2. Security Certifications
Go – Live
1. For the purpose of RFP, “Go-Live” has been divided into 3 phases.
Go-live phase 1-the enhanced version of all existing modules of DS1.0 with state level
implementation and configuration and customization capability. It will include following
functional components defined in Annexure 1
Go Live Phase 3 –It will include all remaining Functional Requirements defined in
Annexure 1
Page 39 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Security review The software developed for Digital Secretariat 2.0system shall be
audited by the CHiPS or its nominated agency or TPA from a security
and controls perspective. Following are the broad activities to be
performed by CHiPS or its nominated agency or TPA as part of Security
Review. The security review shall subject the Digital Secretariat 2.0
system to the following activities:
Page 40 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Service level The Acceptance Testing and Certification agency shall verify the
monitoring accuracy and completeness of the information captured by the
system Service Levels monitoring system implemented by the SI and
shall certify the same.
The solution deployed for service levels measurement shall be
configured to calculate the penalties as defined in the SLA. The
SI shall provide complete access to the Service Levels
Reporting System/BI tool including the manner in which the
Page 41 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Project CHiPS or its nominated agency or TPA shall review the project
Documentation documents developed by SI including requirements, design,
source code, installation, training and administration manuals,
version control etc.
Any issues/gaps identified by CHiPS or its nominated agency or
TPA, in any of the above areas, shall be addressed by the SI to the
complete satisfaction of CHiPS.
Data quality CHiPS or its nominated agency or TPA shall perform the Data
Quality Assessment for the entire data
The errors/gaps identified during the Data Quality Assessment
shall be addressed by SI before moving the data into production
environment, which is a key milestone for Go-live of the solution.
In case there is any shortcoming (which does not impact any of the Service levels) in the
deliverables as above, CHiPS may, at its discretion, permit Conditional Go-Live. However, SI is
responsible for completion of all related pending activities identified within 3 months or earlier of
conditional GO-LIVE. It is to be noted that the next phase timelines shall be initiated at time of
Conditional Go-Live approval.
Note: The list of deliverables are given below, further a detailed list of deliverables have been provided
in as per Project Timelines, Payment Terms & Schedule clauses of RFP Volume-1.
Deliverable(s):
1. Defe ct Reports
ii. Latest source code, application deployment files, configuration files for entire
solution
Page 42 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Solution Documentation
1. The SI shall document all the installation and commissioning procedures and provide the same
to the CHiPS within one week of the completion of the go-live.
2. The SI shall be responsible for preparing process documentation relating to operation and
maintenance of the solution. The process documents shall be formally signed off by CHiPS.
4. Each process document shall clearly define the roles and responsibilities, detailed steps for
execution the defined task, detailed configuration steps etc.
5. CHiPS expects the SI to document the operations and management processes as per
standards defined in “Compliance to Standards and Certifications” in Volume 1 of this RFP
This track includes setting up a centralized helpdesk support for the from 2nd month onwards after
awarding of contract , meant for smooth user adoption and support of government department
users only. SI will set up the helpdesk and will be provided a space at CHiPS office along with
physical amenities such as office space, internet connectivity, furniture, etc. CHiPS will also bear costs
towards electricity and other physical infrastructure related costs. Laptops & mobile phones along
with helpdesk software costs will be borne by SI.
7.3.1 Helpdesk
Helpdesk will operate on all 7 days (9:00 am to 8:00pm) .Helpdesk will provide technical and
functional support on all modules of DS by phone, email which includes L1 as well as L2 support.
Helpdesk will resolve tickets are in timely and efficient manner as per SLAs defined in Appendix-D
Service Level Agreement
L1 or level 1 support includes interacting with the customers, understanding their problems and
then creating a ‘ticket’ against it. A ‘ticket’, also referred to as ‘incident’ is then routed to the L2 or level
2 support. Sometimes the request/grievance raised by the customer is very minor and can be solved
by the L1 support as well.
L2 or level 2 support manages the tickets which are routed to them by the L1. These
tickets/incidents may require some technical knowledge which the L1 team does not possess, in this
scenario the L2 support takes over.
The minimum services envisaged through the helpdesk includes:
i. Guiding stakeholders on usage of Digital Secretariat 2.0
Page 43 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
1.The SI shall select & arrange for the skilled and qualified manpower required for running
the Helpdesk to respond to queries only after they have been provided with proper training as per
industry standards.
2. During the first year, Helpdesk will provide L1, L2 and L3 support on existing solution DS1.0 till
all phases of DS2.0 go Live. Under this minimum 1 resource will provide L1 Support and minimum 2
resources who will provide technical support (L2 & L3) ,will be deployed in CHiPS till Go Live of all
phases.
Additionally, SI need to deploy minimum 5 support staff in Mantralaya for entire 5 year duration who
will provide functional, hand holding support ,trainings in Mantralaya and directorates.
Till Go Live all the phases, SI will be paid separately for O&M of existing solution as defined in
Section.12 Project Timelines, Payment Terms & Schedule. After that Help-Desk will come under into
regular O&M of Digital Government
3. All the issues on logging shall be assigned a severity level based on definition below. Basic
guidelines for assigning severity are as follows:
Severity Definition
Severity 1 problems are the ones which have a critical business
Level 1 impact. These problems will have any of the following
characteristics:
Complete or part of any service unavailable (including APIs)
Incorrect behavior of the system
Security Incidents
Page 44 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
4. All the responses by the helpdesk support team would be recorded and a quality audit would
be carried out by the CHiPS or its representative.
5. To ensure service quality, CHiPS shall conduct regular and random audits.
In the each year of O&M, SI need to onboard minimum 5 departments (Directorates) and its district
line offices.
Application support includes, but not limited to, production monitoring, troubleshooting and
addressing functionality/availability and performance issues and implementing system change
requests etc. The SI shall maintain the application software in good working conditions; and perform
changes and upgrades to the applications as requested by the CHiPS. All tickets related to any
issue/complaint/observation about the system shall be maintained in an ITIL compliant
comprehensive ticketing solution which should be provided as part of Phase 1 Go live. Key activities to
be performed by the SI during the application support phase are as follows:
Page 45 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
These requirements would be signed off by Department and only then SI will begin work on them.
The activities required to be undertaken by SI for on-boarding are as follows: -
b. Provide technical support for user creation, workflow management of public services and
grievance management
Note: In case there are no requirements from the state government line departments, then
the SI would be expected to continue the O&M activities for the public services already on
boarded to the Digital Secretariat 2.0 solution
Page 46 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
After the Go-live of modules/application, there might be minor configuration changes, alterations
in business processes or additional workflow requirements that may be requested by the respective
departments. These modifications need to be undertaken by the SI on a case to case basis.
3. Compliance to SLA
The SI shall ensure compliance with SLAs of this RFP and any upgrades/major changes to the software
shall be planned by the SI while ensuring that the SLA requirements are met at no additional cost
to the CHiPS.
The initial infrastructure VMs/Servers will be provided by CHiPS. But once VMs are handed
over to SI for Solution deployment , It will be maintained by SI like monitoring all critical
parameters is VM, applying relevant OS Upgrade patches etc
b. The SI shall address all the errors/bugs/gaps in the functionalities of the solution (vis-à-vis
the FRS and SRS signed off) at no additional cost during the O&M phase.
c. All patches and upgrades from use of any open source software shall be implemented by the SI
All patches shall have to be updated on a fixed interval, say quarterly basis. Security patches can
be updated on immediate basis. Each release comes with a risk of system stabilization and
hence periodic updates with full testing needs to be done to mitigate the risk. Technical upgrades
of installation to the new version, as and when required, shall be done by the SI. Any version
upgrades of the software/tool/application will be done by the SI after seeking prior approval
from the CHiPS and submitting the impact assessment of an upgrade as such.
d. Any changes/upgrades to the software performed during the support phase shall be subject
to comprehensive and integrated testing by the SI in order to ensure that the changes
implemented in the system meet the specified requirements and do not impact any other
existing functions of the system. A detailed process in this regard will be finalized by the SI in
consultation with the CHiPS.
e. An Issue log shall be maintained by the SI for the errors and bugs identified in the solution as
well as any changes implemented in the solution and shall be periodically submitted to the
CHiPS team.
Page 47 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
f. The SI will inform the CHiPS (at least on a monthly basis) about any new
updates/upgrades available for all software components of the solution along with a detailed
action report. In case of critical security patches/alerts, the SI shall inform the CHiPS
immediately along with any relevant recommendations. The report shall also contain the SI’s
recommendations on update/upgrade, benefits, impact analysis etc.
g. The SI needs to execute updates/upgrades though a formal change management process and
subsequently update all documentations and Knowledge databases etc.
h. The SI will carry out all required updates/upgrades by following defined processes at no
additional cost.
6. Problem identification and Resolution:
a. Errors and bugs that persist for a long time, impact a wider range of users and are difficult
to resolve in turn lead to application hindrances.
b. The SI shall resolve all the application problems through implementation of the identified
solution (e.g. system malfunctions, performance problems and data corruption etc.)
c. Monthly reports on problems identified and resolved would be submitted to CHiPS team
along with recommended solutions.
All planned or emergency changes to any component of the system shall be carried out through the
approved Change Management process. The SI needs to follow all such processes (based on
industry ITSM framework) at all times. For any change, SI shall ensure:
The SI shall define the Software Change Management and Version Control Process. For any changes
to the solution, the SI has to prepare detailed documentation including proposed changes and
impact to the system in terms of functional outcomes/additional features added to the system etc.
The SI shall ensure that software version control is carried out for the entire contract duration.
Page 48 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
The SI shall maintain version control and configuration information for application software and
any relevant system documentation.
9. Training
The SI shall conduct trainings for the system users whenever there is any change in the system
functionality. All Training plans have to be mutually agreed on with the CHiPS team.
The SI shall maintain at least the following minimum documentation with respect to the CHiPS system:
f. Compilation environment
11. The SI shall also ensure that any software system documentation is updated with regard to the
following:
d. U s e r m a n u a ls a n d t r a i n i n g m a n u a ls a r e u p d a t e d t o r e fle ct on -g o in g
changes/enhancements
e. Standard practices of version control and management are adopted and followed
12. All project documents need to follow a proper version control mechanism. The SI will be required
to keep all project documentation updated and ensure the updated project documents are submitted
to the CHiPS by the end of next quarter in case of any change.
13. For application support, the SI shall assign a dedicated software support team to be based at the
CHiPS and SI’s location as a single point of contact for resolution of all application related issues. This
team will receive and resolve all the application related tickets/incidents. In the technical proposal,
Page 49 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
the SI needs to provide the proposed application support team structure including the number of
team members proposed to be deployed along with roles and skills of each. The Application support
team shall comprise of the SI’s employees.
14. Any software changes required due to problems/bugs in the developed software/application will
not be considered as part of change control and will have to be completed by the SI at no additional
cost (even if it requires any enhancements/customizations).
SI shall be responsible for maintaining all the master data for the Digital Secretariat 2.0that would include
the following:
i. Web Portal
2. SI shall provide user support in case of technical difficulties in use of the software,
answering procedural questions, providing recovery and backup information, and any other
requirement that may be incidental/ancillary to the complete usage of the application.
3. The SI shall perform user ID and group management services. The user-id naming &protocol
shall be designed and implemented for all the user ids. Such naming convention and protocol
shall be signed-off with the CHiPS.
4. The SI shall maintain access controls to protect and limit access to the authorized end users
of CHiPS and other concerned stakeholders.
5. The services shall include administrative support for user registration, creating and
maintaining user profiles, granting user access and authorization, providing ongoing user
password support, announcing and providing networking services for users and providing
administrative support related to Digital Secretariat 2.0 Solution.
Page 50 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
6. System administration tasks such as managing the access control system, creating and
managing users, disaster recovery mechanism etc.
7.4.4 Periodic Reporting
The Digital Secretariat 2.0 system shall provide a facility for generating and viewing online, real-time
project, BI and MIS reports for services handled during a specified period, transaction density trends for
any specified periodicity (hourly, daily, weekly, monthly) and any bottleneck situation creating
dependency at any stage. The BI and MIS reporting system shall be an integrated system which shall
provide user-friendly reporting for points of access like – CHiPS and/or Designated monitoring
office. The SI shall provide complete access to the service levels Reporting System including the manner
in which the configuration of the system has been done, SRS and system manuals. Full access to
generate reports from the systems to CHiPS officials or its nominees or GAD .Also, in addition to the
reports that are identified in the RFP, it must be appreciated that so far as a particular data is available
in the system it should be possible to get a report on that for the sake of helping CHiPS or its
designated agencies in analysis and/or decision making.
The system shall provide BI and MIS reporting with multiple “Slice and Dice” options to generate reports
in flexible formats based on user specific needs. The MIS reporting requirements can be stated from
the following perspectives:
The SI would also be provided APIs and requisite permissions for accessing legacy data from the
existing Digital Secretariat 2.0application. This would be handed over during the knowledge
transition period from the Digital Secretariat 2.0 SI. Therefore, Digital Secretariat 2.0 SI will have to
help out the CHiPS officials in retrieving legacy data as per requirement.
From the Digital Secretariat 2.0 system perspective, the reports should present historical, statistical and
predictive views in addition to the daily/weekly/monthly views. In regard to the above, The SI shall
submit the following period reports (but not limited to) to CHiPS:
d. Latest source code, application deployment files, configuration files for entire solution Software
change logs etc.
e. Corrective Action report in response to the any audit findings/ other concerns as identified
by CHiPS
Page 51 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
1. The SI will have to conduct high level orientation workshops for the decision makers in
government departments. The workshops need to be scheduled across the development
lifecycle of Digital Secretariat 2.0 technology components. There should be at least 5 workshops
arranged in one quarter with maximum seating of 20 people to appraise the decision makers on
the recent developments and way forward. Also, this platform may be leveraged to communicate
the support required from decision makers.
2. The SI will have to conduct detailed technical trainings with concerned stakeholders and scheme
implementers on different components of Digital Secretariat 2.0. For each component
developed at least 5 training sessions per quarter need to be arranged with seating of 20-30
people throughout the duration of project. The main aim of these workshops is to enhance user
adoption of the new systems and solve all doubts pertaining to usage of the new systems
4. The workshops and trainings will be arranged by SI at the location decided by CHiPS/
Departments. The costs (Travelling, Lodging, Boarding, etc.) related to trainers and training
material (manual, booklet, diary, pen, etc.) needs to be borne by SI. The infrastructure
(training hall, projector) for training shall be arranged by CHiPS/ Departments.
5. Below are the 3 types of trainings that SI will be required to do for diff.
departments
Train the Trainer Training
The prerequisite of conducting a TTT training session is to identify the Master trainers from
within the organization who would act as the project champions and have adequate knowledge
and information about the usage of DS System. These master trainers may be identified from
the zonal/region/district level and would act as the primary interface for the implementation
team or the Department staff for any operational or process difficulty they may face.
training would majorly be classroom based, however self-learning modules may also be used.
Change Management Training
Region/District level training–The main objective of this training would be to train the
participants about the application functionality, reporting capability, basic IT awareness. The
training would majorly be classroom based, however self-learning modules may also be used.
b. Presentations
c. User manuals.
g. FAQs
3. The SI will maintain a copy of all the training material on the Portal/website and access will be
provided to relevant stakeholders depending on their need and role. The access to training on the
portal would be finalized with CHiPS.
7.5.2 Training Effectiveness
The SI has to ensure that the training sessions held are effective and that the attendees would be able
to carry on with their work efficiently using the guidance provided as part of the training. Hence, it is
necessary that the effectiveness of training sessions is measured. The SI will prepare a
comprehensive feedback form that will capture all necessary parameters on measuring the
effectiveness of the training sessions. This form will be discussed and finalized with the GAD. After
Page 53 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
each training session, feedback will be sought from each of the attendees on either printed feedback
forms or through a link available on the web portal. One member of the stakeholder group would be
involved in the feedback process and he/she has to oversee the feedback process. The feedback received
would be reported to the CHiPS which will share with GAD for each training session.
For each training session, the Service Provider will categorize the feedback on a scale of 1 to 10, where
10 will denote excellent and 1 will denote unsatisfactory.
The training session would be considered effective only after the cumulative score of the feedback as an
outcome of the process [sum of all feedback divided by number of attendees] is more than 6
i. Ensuring Uptime and utilization of the infrastructure handed over to SI and raise alerts as per
SLAs.
ii. In the event of a disaster at DC site, activation of services from the DR site is the responsibility of
SI.
iii. The SI shall be responsible for providing support for all system software at the SDC for the entire
contract period.
iv. On expiration / termination of the contract, SI to handover complete data in the desired format to
the CHiPS which can be easily accessible and retrievable. SI shall also provide support for
transitioning to another SI.
v. SI shall provide provision for viewing live Dashboards for Daily report, utilization etc. through the
monitoring tool/self-provisioning tool.
Page 54 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
vi. SI to provide list of key contact persons with contact details with escalation hierarchy for resolution
of issues and problems. This shall be via an Incident Management system.
vii. MIS Reports - SI shall submit the reports on a regular basis in a mutually decided format. The SI
shall workout the formats for the MIS reports and get these approved by the CHiPS.
Near to the completion of the project/expiry of the contract the SI needs to plan for an exhaustive
Knowledge Transfer exercise which shall ensure that on expiry of the engagement, CHiPS or its
designated agency is able to operate the project going forward and provide services to different
Departments. During an exit management process following key activities (indicative list of activities)
shall be required to be performed by the SI.
1. Transfer of Assets: The SI ensure transfer of assets to CHiPS within three month from the
date of expiry of contract / termination of contract.
2. Co-operation and Provision of Information: During the exit management period, SI shall
allow CHiPS access to information reasonably required to define the then current mode of
operation associated with the provision of the services to enable the client to assess the
existing services being delivered.
3. Confidential Information, Security and Data: The SI will promptly on the commencement
of the exit management period, supply to the CHiPS or its nominated agencies the following:
Information relating to the current services rendered and performance data relating to the
performance of the services; documentation relating to project, Project’s Intellectual Property
Rights; any other data and confidential information related to project; all current and updated
components
Project data as is reasonably required for purposes of the project or for transitioning of the
services to its SI in a readily available format.
At any time during the exit management period, SI will be obliged to provide access of
information to CHiPS and / or any replacing SI in order to make an inventory of the Assets (mainly
Page 55 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
All other information (including but not limited to documents, records and agreements) related
to the services reasonably necessary to enable the CHiPS and its nominated agencies, or its
Replacing SI to carry out due diligence in order to transition the provision of the services to
CHiPS or its nominated agencies, or its Replacing SI (as the case may be).
4. Exit Management Plan: SI shall provide CHiPS with a recommended exit management plan
("Exit Management Plan") which shall deal with at least the following aspects of exit
management in relation to the SLA as a whole and in relation to the Project Implementation, the
Operations and Management SLA and Scope of work definition.
A detailed program of the transfer process that could be used in conjunction with a
CHiPS/Replacement SI including details of the means to be used to ensure continuing
provision of the services throughout the transfer process or until the cessation of the services
and of the management structure to be used during the transfer.
Plans for the communication with such of the SI, staff, suppliers, customers and any related
third party as are necessary to avoid any material detrimental impact on Digital Secretariat
2.0project’s operations as a result of undertaking the transfer;
Plans for provision of contingent support to Digital Secretariat 2.0Project and
CHiPS/Replacement SI for a reasonable period (minimum one month) after transfer.
SI shall redraft the Exit Management Plan annually thereafter to ensure that it is kept relevant
and up to date.
The Exit Management Plan presented by the SI shall be approved by CHiPS or/and its
nominated agencies.
DC/DR document along with updated software documentation and asset registers, and
operational documents will be provide by SI to CHiPS.
The terms of payment as stated in the Payment Schedule include the costs of the SI
complying with its obligations under this Schedule.
During the exit management period, the SI shall use its best efforts to deliver the services.
Payments during the Exit Management period shall be made in accordance with the Terms of
Payment Schedule.
Page 56 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
This Exit Management plan shall be furnished in writing to CHiPS or its nominated agencies
within 15 days from the receipt of notice of termination or three month prior to the expiry this
Agreement.
The SI needs to ensure that the strategic control of entire solution is transferred to CHiPS or its
nominated agency.
1. Before Go Live of each phase and after UAT sign off , SI need to get Information Security
Audit done from CERT-In empanelled vendors of GOI /GoCG at its own costand submit its
closure report within 15 days after go-live.
2. The SI is required to get a detailed STQC Audit within 3 months after completion of go-Live
of all 3 phases.
v. Penetration Testing
vi. SLA Reporting System, Audit trails configuration and monitoring process
vii. IT Security Process Audit (in line with ISO 27001 standards)
This will be covered under Milestone -8, M8 as per Project Timelines, Payment Terms &
Schedule clauses of RFP Volume-1.
3. During O&M Phase, SI need to get Information Security Audit done from cert-in empanelled
vendors of the developed Digital Secretariat 2.0Solution every Year, cost of which will be
borne by CHiPS. For the same, SI will get the system audited by 3rd party auditors as per
directions of CHiPS. Further, SI shall provision an option for online audit option for Auditors
such as CAG.
4. Functional audit should cover at least the following (but not be limited to):
i. User Authentication
Page 57 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Segregation of Duties
Testing process
Quality assurance
8. Scope of work also covers evaluating the confidentiality, safety & security of the data &servers,
assess & strengthen the security posture of IT systems and networks for protection against
external threats, by way of remote infrastructure security assessment, internal threats, by way
of on-site infrastructure security assessment and integrated system threats, by way of
application security assessment.
9. Confidentiality: All documents, information and reports relating to the assignment would be
handled and kept strictly confidential and not shared/published/supplied or
disseminated in any manner whatsoever to any third party.
Third Party Code Review
Page 58 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
1. The SI is required to support an annual Third Party Code Review done for the developed
solution. The cost of conduct of third party code review will be borne by the CHiPS.
2. Planning for the Third Party Code Review needs to be done in consultation with CHiPS. The
SI needs to update all relevant documentation and make available the latest source code for
the purpose of third party audit.
3. The ‘Third Party’ to conduct the Code Review should be the OEM for the development platform
for the first time. Thereon, CHiPS in consultation with SI shall decide on the agency to
undertake such review
iv. Performance parameters being considered at all the tiers of the solution
vii. Performance and load test results review5. The cost of rectification of any
recommendations shall be borne by the SI.
5. All suggestions and recommendations that are required to be incorporated as a result of
the third-party audit shall be the responsibility of the SI.
9. Ensuring the staff members and other stakeholders attend the training programs as per the schedule
defined by the SI and agreed upon by CHiPS.
10. Undertake agreements with stakeholders for integration with their systems.
11. Provide sign off on the deliverables of the project.
5. Procure, install and manage Helpdesk ,SLA management, Server monitoring & Project
Management tools. Before accepting the tool and its reports, CHiPS will duly audit the tools.
8. Provide necessary support for the resolution of bugs, patches & upgrades of the software
solution.
9. Provide necessary technical support to CHiPS for the purpose of identification of hardware
requirements.
11. Design various manuals like User manual, Trouble Shooting manual etc. for the system.
13. Any other services which is required for the successful execution of the project.
17. Adherence to all notifications and communication set forth by CHiPS in context of the scope of
services.
Page 60 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
iii. To avoid implementation of any changes which is not reviewed, approved or analyzed.
iv. To control the impact of changes and minimize the effect on effective as well as efficient service
delivery.
3. The CHiPS will be authorized to review, approve and schedule all changes to the Digital
Secretariat 2.0application. All decisions of the CHiPS will be final and binding on all parties
involved.
4. Change Management Life Cycle: The life cycle of all changes initiated during the contract period
of the SI.
6. The O&M team will do all change requests at no extra cost to CHiPS.
Page 61 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
9. The functional requirements given in the RFP are indicative only and not exhaustive in any manner
and/or kind and/or form and shall be finalized in consultation with CHiPS during Software
Requirement Specification.
10. All the development / customization/ configuration must meet the requirements for security,
performance and ease of use for operations, administration and management.
11. Any report whose data is residing in the Digital Secretariat 2.0solution or which can be arrived
at by using some logic on the available data will not fall/ qualify as change request.
The entire change request process will be implemented as mentioned below. The proposed timelines
for each steps / activity and the corresponding responsibility center is also shown in the table below:
3. The CHiPS will discuss and provide adequate responses to the CHiPS
queries / suggestions from the SI on the requested
change. If the change is very big , it will take necessary
approvals from state steering committee and
communicate the final decision with the SI.
6 requesting
SI will thendepartment.
initiate the change following a standard SDLC SI
procedure like requirements gathering, design,
development and testing, etc., as required, along with
proper documentation at each stage.
Page 62 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
15. Any change requirement not pertaining to items and scope listed or elaborated in the current RFP
can be undertaken by CHiPS through separate service provider(s); further, in case of additional
volume of work (beyond the indicated volume in the RFP), CHiPS has an option to undertake
such additional work through separate service provider(s).
10 Project Governance
1. The project would require a close supervision and appropriate project control for successfully meeting
the objectives and its timely completion. The following stakeholders / Committees / working groups
are proposed for adequate program governance:
Under the chairmanship of GAD Principal Secretary, participating departments and state
Project management unit will review and approve Project report prepared by the vendor
Will include members from participating departments to provide domain expertise during the
entire length of the project and help in building up a sustainable model for the services
wherein processing of manual applications will be completely discontinued.
Decision making support for policy, regulatory and other relevant changes and on issues
relating to the GPR needs approval in Project Steering Commitee
Take an appropriate decision on the mode and degree of integration of the process, systems
and institutional infrastructure of various Government Departments as well as the
infrastructure created under Project to ensure service enablement and delivery.
Oversee the functioning of the Project and providing necessary guidance and assistance.
Page 63 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
3. State Project Management Unit (SPMU) would comprise of a team of CHiPS & its consultant
who would be responsible for monitoring all the project implementation, operations and
maintenance activities, on behalf of CHiPS, and provide status reports, action taken
reports, recommendation on deliverables, risks, etc.
4. SPMU would be responsible for addressing all issues related to proposed change requests by the
SI. The committee would approve / reject (as case may be) all proposed change requests from the
SI, following an appropriate Change Control Process defined in the RFP.
6. Project Delivery Team: They will be the actual project delivery team deployed at CHiPS by
the SI and will work on all areas of the implementation phases. They may also constitute of various
other teams as required for successful implementation
7. The SI shall form a project team comprising the following key positions:
i) Project Manager – Technical Lead (for management of day to day operations of the project)
v) Business Analyst
8. Project Review Meetings: The following will be required to be undertaken by the SI during the
duration of the project:
Page 64 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
SI is required to prepare a detailed Action Taken Report for all meetings to ascertain and maintain a
log of actions required and taken for successful project delivery
11 Manpower requirement
1. SI has to provide proposed resources for all the roles as mentioned in the pt. 12.16. The proposed
resources must be part of the project team and must be available for discussion with the client at
CHiPS, Raipur.
2. SI shall assess the requirement of resources to design and implement the solution including number,
skill sets and duration and provision the same for implementation of this project.
3. SI has to necessarily maintain a team of requisite size of skilled professionals as per the
requirements of the project.
4. SI shall propose the team structure and deployment plan of resources onsite for the project.
5. The resources proposed must not be changed unless replaced with equivalent or higher
qualification and experience.
6. The manpower shall be deployed by the SI for executing operations, management and
maintenance of the Digital Secretariat 2.0 system, as per terms specified in this RFP and agreed
with CHiPS
7. SI shall ensure that all the resources deployed for Digital Secretariat 2.0(including its sub-
contractors/OEM) undergo suitable trainings in relation to processes to be operationalized under
Digital Secretariat 2.0, security aspects of the project and maintain the confidentiality of data.
8. The personnel deployed should be adequately trained and adequate in number to meet all
operational, technical, functional and other requirements of the infrastructure and processes of
the Digital Secretariat 2.0.
9. The SI would be required to maintain personnel files with the following details of the
personnel deployed at CHiPS:
c. ID proof photocopy (any one of Aadhaar, Passport, PAN card or any Central/ State
Government issued ID card)
10. CHiPS would be provided a copy of all these documents (updated on a monthly basis or before
joining) and may conduct an audit for compliance purpose to check minimum qualification
requirements specified above.
11. Electronic / Biometric attendance registers will be maintained by CHiPS and SI is required to provide
Aadhaar details of team deployed to CHiPS. SI will maintain adequate leave reserve for personnel
deployed.
12. The personnel deployed by the SI (or by sub-contractor/OEMs) should be their employees and
they will have absolutely no claim to any category of appointment in any Government organization.
The terms of employment for the personnel deployed by the SI shall be strictly as agreed between
them and the SI. Also, the SI shall be completely responsible to personnel deployed by him for
payment of salary, perks, incentives, any monetary and non-monetary compensation and all
statutory contributions like Insurance, ESI and PPF, meeting requirements of Central
Minimum Wages Act, etc. Any touting activity taken up by any of the SI personnel will be taken
very strongly against SI and necessary action will be taken by the CHiPS against the personnel
and/or SI.
13.The team which mandatorily needs to be deployed onsite at CHiPS/Departments is given in the
table below
Page 66 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
50%
Infrastructure
availability(3
3. Specialist/System 100% availability Yes
days availability
Administrator (1)
in a week)
50%
DBA /Database availability(3
4. 100 % availability Yes
Specialist (1) days availability
in a week)
IT Applications
5. Expert(Full stack) (1 100 % availability 100 % availability Yes
resource)
Business Analyst(1
6. 100 % availability 100 % availability Yes
Resource)
25%
availability(2
7. UI/UX specialist 100 % availability No
days availability
in a week)
SI will be
Developers (Full evaluate the
8. Stack)(Min 5 years . number to meet Min.2 resources No
experience) the timeline and
deploy accordingly
SI will be evaluate
Mobile App developer the number to
9. (Hybrid App )(Min. 5 meet the timeline Min.1 resource No
years experience) and deploy
accordingly
SI will be evaluate
the number to
Tester(Min. 3 year
10. meet the timeline Min.1 resource No
experience)
and deploy
accordingly
For existing
application L1 Support –
Technical Helpdesk
L1 Support-Min. 1 Min. 2 resources
11. (L1,L2 & L3) Support No
resource L2 & L3 – Min.2
Resources
L2& L3-Min. 2 resources
technical resources
Page 67 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
11.1 Sub-contracting
The following is the list of functionalities/ requirements for which the SI may provision for sub-
contracting service (only one sub-contractor) for the Digital Secretariat 2.0 project.
3. Quarterly self-certification by the SI that all personnel deployed are either employees of the
SI or allowed under the established sub-contracting arrangements should be submitted to
CHiPS.
Page 68 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
c) CHIPS retains the right to request discontinuation of sub-contracting of activities at any time
during the contract period and such activities will have to be performed by the SI directly or
by a subcontracting agency acceptable to CHIPS.
d)The SI will be responsible for meeting all obligations of its sub-contractors and the delivery
of goods and services mentioned in all volumes of this RFP. The SI will be solely responsible for
all acts of its sub-contractors
e) CHiPS reserves its right to subject the sub-contractors to security clearances as it deems
necessary and ALL the personnel of the sub-contractor before they are appointed to the Digital
Secretariat 2.0project.
2. The SI will be responsible for:
a) The management of its sub-contractors who are a part of the proposal and for the delivery of
all products and services in accordance with the agreement.
b)The supply, delivery and installation, commissioning of all products and providing all services
as submitted in their proposal.
c) Internal arrangement between the SI and its sub-contractors is left to the SI, subject to
relevant clauses in Volume - 3 of this RFP.
12 Project Management
SI will deploy an open source project management tool to manage and operate all processes of the
project using a proven SDLC methodology in consultation with CHiPS. The SI is required to
design and implement a comprehensive and effective project management methodology and use
efficient and reliable PM tool/application with access provided to identify stakeholders.
The SI shall address at the minimum the following using PM Tools:
Page 69 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
4. Measure project deadlines, progress of the project against set deadline, budget figures, and
performance objectives
7. Provide Dashboards
9. During the project implementation the SI shall report to the CHiPS, on following items:
11. Audit trail and searchable history of all artifacts presented and approved shall be
maintained on tool/application where admin password shall be in the custody of CHiPS
12. This tool/application shall be used, maintained and enhanced as per CHiPS requirement
throughout the project lifecycle for all software, documentation, project, control or change
requests
13. The SI should maintain a document repository and shall maintain version control of the
documents using the document management solution with appropriate controls for
document approvals
SI at any point of time during project cycle may have to adopt and use project management tools
provided by CHiPS.
2. The SI shall carry out a Risk Assessment exercise and document the Risk profile of the project
based on the risk appetite and prepare and share the enterprise risk register. The SI shall
develop an issues management procedure to identify, track, and resolve all issues faced on
Page 70 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
the project. The Risk management plan and issue management procedure shall be carried out
in consultation with CHiPS.
3. The SI shall monitor, report and update the project risk profile. The risks should be discussed
with CHiPS and a mitigation plan should be identified during the project review/status
meetings. The Risk and Issue management should form an agenda for the Project Steering
Committee meetings as and when required
4. Through the duration of the project, CHiPS will periodically review the Traceability Matrix.
CHiPS would provide the final approval once they are satisfied that all requirements are met.
The detailed project timelines, milestones, list of activities, deliverables and payment schedule
during the project life cycle have been provided in the table below. The SI will have to prepare
detailed project plan as per the details outlined in the table.
Payment Terms
a. The Invoice will be submitted after achievement of every Milestone. The payment will be
Page 71 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
b. The Invoice will be submitted after every quarter during Operation and Maintenance Phase.
The payment would be made within 30 days after submission of Invoice.
c. All taxes, duties and other charges of the products and services to be duly paid by the SI.
d. The SI shall satisfactorily perform work as specified under the Tender to the CHiPS. CHiPS
will release the requisite payment upon receipt of the invoice, which would be verified within
2 weeks of receipt of the invoice.
e. All payments agreed to be made by CHiPS to the SI in accordance with the Bid shall be
inclusive of all, statutory levies, duties, taxes and other charges whenever levied/ applicable
including costs of maintenance, if any and CHiPS shall not be liable to pay any such levies/
other charges under or in relation to this Contract and/ or the Services.
f. No invoice for extra work/ change order on account of change order will be submitted by the
selected bidder unless the said extra work/ change order has been authorized/approved by
CHiPS in writing.
g. The payment shall be made to the SI after deduction of all applicable penalties, taxes, etc.
h. In case of any changes by Government in statutory levies, duties and taxes then actual levies,
duties and taxes on the date of billing would prevail.
i. CHiPS shall be at liberty to deduct penalties from the invoices raised by the SI as calculated
by CHiPS for non-adherence to Service Level Agreements as mentioned in Appendix D-
Service Level Agreement.
j. All payments to the SI shall be subject to the deductions of tax at source under Income Tax
Act, and other taxes and deductions as provided for under any law, rule or regulation. All
costs, damages or expenses, which CHiPS, may have paid or incurred, for which under the
provisions of the Contract, the SI is liable, and CHiPS shall deduct the same from any dues to
the SI. All payments to the SI shall be made after making necessary deductions as per terms
of the Contract.
k. For Products and/ or Services supplied from outside India, the SI shall be entirely responsible
for all taxes, stamp duties, license fees, and other such levies, payable in India.
l. For Products and/ or Services supplied locally, the SI shall be entirely responsible for all
taxes, duties, license fees, etc., incurred until delivery of the contracted Products or Services
to CHiPS.
Page 72 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Page 73 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Page 74 of 121
RFP for Selection of SI for Design, Development, Implementation and Maintenance of CG Digital Government 2.0 System -
Volume I
Page 75 of 121
14 Compliance to Standards and Certifications
Information Security/ Operational Integrity & Security ISO 27001 certification (or above) *
Management
Operations ISO 9001 certification (or above) *
Page 76 of 121
Solution Element Standards
IT Governance COBIT
Document the Operations and Management Standards ISO 20000-1:2011 or relevant latest
standard
b) Apart from the above the SI need to ensure compliance of the project with Government of
India’s IT security guidelines including provisions of:
The Information Technology Act, 2000” (revised 2008) and amendments thereof and
Guidelines and advisories for information security published by Cert-In/MeitY
(Government of India) issued till the date of publishing of tender notice. Periodic changes in
these guidelines during project duration need to be complied with.
c) The SI shall also adhere to the relevant guidelines and standards (as applicable) issued by
CERT-IN, MeitY and Government of India including the following –
Page 77 of 121
d) Along with the guidelines of GoI, the SI should ensure compliance with State guidelines
and acts, inclusive of and not limited to, Open API policy and Chhattisgarh Aadhaar Act, 2018
along with Aadhaar Act, 2016.
e) SI should register that, changes should be made in the system, in accordance with any
Central/State Government Act - concerning data security and privacy, and data sharing - passed
during the period of system development/implementation.
Required office automation areas are as follows. Details of which is elaborated in succeeding
paragraphs :
Page 78 of 121
FR16 – Dashboard and MIS reports
FR17 – Grievance Management System for Government Employees
FR01 Correspondence/Letter Management System & FR02 File & Office Note Management :
DS II completely automates file & DAK management from creation to archival of files and DAK. All decisions can be
captured in the file itself and remain intact throughout the lifetime of the file. Effective transformation to paperless
office environment by providing functionalities like electronic correspondence/file creation, management, movement
and performance of related tasks flagging, indexing, noting, referencing, search/ retrieval, Digital Signature.
Features -
The system should be capable & configurable enough for complete File & Letter Life Cycle
Management.
Integration with e-Sign for digital signature
Publish orders/letter to web portal in public domain
The System shall support integrated in - built viewer for viewing documents (PDF/Word/PPT).
The system shall facilitate zoom-in/zoom-out, zoom percentage and Zoom Lens to zoom in on a part
of image and other image operations like Invert, rotate, etc.
The system shall provide facility of putting text, graphic and image annotations on scanned document
pages.
The mobile application should have support for retrieval and archiving of documents.
System should support integration with Stylers / Voice to text /Touch Screens for text input
Document Management System
Integration with latest Business Analytics tool to prepare dashboard which can give insights in
efficiency of file disposal, DAK Disposal, tracking of pendency in various departments, performance
of employees /Departments
System should define process of maintain following registers online - DAK, Avak, Javak,Stock and
Asset register
Page 79 of 121
Meta data capturing
Document upload along with OCR CAM Scanning through mobile App
Bulk document upload
Verification and acceptance of scanned copies by designated authority
FR05 Travel Management and TA/DA :
Travel management module is proposed to ease the process of booking and approvals during official travel, this will
act as a single window system from where request to reimbursement process will be monitored.
Features -
User group creation as per the policy
Add / Update entitlement/allowance accrording to the policy
Workflow for request and approval
Advance and Expense settlement
Features -
Enter vidhansabha/parliamentary query into system
Route the query to the concerned department to record the necessary information
Consolidate input received from departments into reply
Get approval for parliament query reply on workflow
The system should send the alerts to the department officials through email, dashboard alerts, and
send reminders on deadlines for query response before the due date
The system should record the status of vidhansabha/parliamentary query
Features -
System should be able to enter RTI query
System should be routing the query to the concerned department to record the necessary
information
System should collate information from the respective departments and create a response
System should create a workflow for the approval
Page 80 of 121
The system will set a deadline and priority for the resolution of RTI request based on the type of
RTI request as per the departmental policy and provide option for setting deadlines and priority for
exceptional cases
Online Record Management System will redefine SOPs how records (Files ,etc) will be stored manually as well as in
Online mode
Features –
It will also be capable of keeping track of the different versions of modified documents by different
users.
It will maintain Online register of Manual records along with Online register of Files and DAKs
Centralized Document Repository with folder wise categorization
Managed subscriptions and sharing of Docs
Folder Layout for easy navigations
Features –
Man Power Planning
Recruitment
Confirmation
Transfer Posting, Joining and Deputation
Seniority List
Promotion
Increment / Pay Fixation - Time Bound Pay Scale Enhancement
Attendance Management
Leave Management which includes all types of leaves (EL , CL, Commutated etc.)
Annual Confidential Report (ACR)
Training and Learning Management including Training Implementation
Payroll Processing
Other Employee Entitlement – Loans and Advances
Other Employee Entitlement – Claims (TA & Medical Reimbursement)
GPF / Part Final
Departmental Enquiry
Page 81 of 121
Court Case
Awards
Employee Grievance Redressal
Employee Exit - Superannuation
Employee Exit (Other Exits) –(Death ,Termination, VRS and Resignation,
Compulsory Retirement and Absorption/ Samvillyan)
Immovable Property Return (IPR) Module
Digitization of E-Service book for all Depts.
Attendance Management including integration with biometric.
Integration with iFMS (Integrated Finance Management System)
System should display booking status/ availability status in grid format for weekly/ monthly.
Page 82 of 121
Features –
Capability to Create a Court Case file which will include various case details such as Case no, Case
Type, Date of Filing, Case details, Court Order details, Hearing date, Order date etc.
Capability to add various documents in the Court Case file related to the case such as OIC from dept,
hearing dates
Capability to provide alerts for the upcoming hearings.
Capability to Cross-reference all dates for one case, one client, one attorney, a group, or the entire
office.
Capability to generate the Case Diary having complete details and history of the cases.
Capability to provide a mechanism for analysis of work flow, case status, and types of cases opened
and closed
Capability to maintain an audit trail of entries and changes
Page 83 of 121
FR17 Grievance Management System for Government Employee
Using these module government employees can raise their issue which will be directly routed to the concerned
department. To avoid discontent among employees that can arise out of real or imaginary reasons.
Features –
Fair and speedy means of dealing with complaints.
Procedure should be sufficiently simple so that it can easily and quickly be explained to each new
employee.
Module Name Department & existing employee on boarding & New Employee Registration
Page 84 of 121
Once super admin has activated the department ,
DO-005 employee data from karmic sampada will be visible Valid only for existing employees
in each employee's login
DO-012 Employee will enter rest of the details and submit the
same with OTP / DSC
Page 85 of 121
Employee recruitment
Module Name Employee recruitment
Req. ID Requirement Business Rule (if any)
Posting
Page 86 of 121
System should allow configurable workflow for approval of
requests i.e. number / designation of stakeholders in
PO-006 workflow etc. must be allowed to be changed by department
admin
PO-009 System should send back requests to dealing clerk that are
rejected by US/ Secretary
Service book:
Page 87 of 121
SB-003 System should not allow to modify non-editable fields
for e.g. DOB , Date of Joining etc.
System should allow uploading of the required documents PDF document be allowed of size
SB-005
max 3 MB each
System should send service book the login of concerned This is only valid for new
SB-014 department’s DDO for verification employees
Page 88 of 121
Notification should be sent to
System should allow DDO to add review comments
reporting officer in case of certain
SB-018 against service book entered by employee
fields only.(To be identified later)
Employee Confirmation
Page 89 of 121
Tentative list of details
• Probation Period
• ACR Details
The System should allow the user to fetch details for the • Any Complaints/ Enquiry
CONF-003 employees from relevant modules /details against the employee
• Supervisor feedback
• Overall work conduct
• Mandatory requirements for
confirmation
System should allow department user to view confirmation
CONF-004 criteria
First reminder to be sent on 30
days before confirmation date
Second reminder to be sent on 20
System must send reminders to department user for days before confirmation date
CONF-005 pending confirmations (nearing end date and beyond Third reminder to be sent on 10
end date) days before confirmation date
Daily reminder to be sent after
confirmation due date
Page 90 of 121
Employee Increment
Employee Transfer
Page 91 of 121
Req. ID Requirement Business Rule (if any)
TR-012 System should allow GAD sect.to edit the fields as identified
during requirements stage
Page 92 of 121
This module will be integrated with all other modules of
TR-018 HRMS for e.g. Service book , ACR, enquiry , payroll etc.
Leave Management
Page 93 of 121
Tentative leave types -
Earned leave
Half pay leave
Commuted leave
Leave not due Extra-
ordinary leave
Leave to probationer, a person on
probation and an apprentice Leave
preparatory toretirement
Leave beyond the date of retirement,
System should allow definition of leave type compulsory retirement or quitting of
LM-001 master which will enable super admin to define service
leave types. This shall be configurable Maternity leave Paternity
leave
Child Adoption Leave
Special disability leave for injury
intentionally inflicted
Special disability leave for accidental injury
Power to grant special disability leave
Power to grant leave Other than special
disability leave
and study leave
System should auto credit leave account of every Earned leave in advance in two
LM-005 Government servant who is serving in a installments of 15 days each on 1st
department other than a Vacation Department as January and 1st July every calendar year.
per defined rules
Page 94 of 121
1. Applications for leave on grounds
other than ill health should be
System should not allow user to apply leaves after made at least three weeks before such date.
LM-010 the prescribed time limit 2. This limit would be six weeks if the
leave applied for is preparatory to
retirement.
Page 95 of 121
System should allow employee to upload Bond
to be executed by A Government servant in
LM-023 permanent / not in permanent employ when
proceeding on study leave or extension of study
leave (Where ever required)
Page 96 of 121
The System should send a notification to the employee
ACR-010 along with all required user(s) once the grades are freezed
by the final authority in the hierarchy
The System should allow the authorized user (in this case
ACR-013 accepting authority) to scrutinize the representation
ACR-016 The System should allow the authorized user to access all
the service records of the employee
The System should allow the authorized user to change the
ACR-017 final comments and expunge any of the comments provided
Grievance Management
Page 97 of 121
System should allow department user to send the grievance
GM-006 to other department in case wrong department is selected
by the user
Departmental Enquiry
Page 98 of 121
System should allow concerned officer to generate
EN-009 statement of pending cases on a monthly basis which
describes the status of the cases.
Page 99 of 121
System should check the length of the service basis joining 20 years of service length is
EE-013
date of the employee mandatory for applying VRS
System should allow concerned officer to view the VRS
EE-014
and approve or raise queries
System should allow employee to edit the form and upload
EE-015
document if required
System Administration
During the 4 years of O & M period any migration activities required to be carried out due to
change in Infrastructure, Software, etc. should be done by bidder at no extra cost. This will not
be considered as any change request and should be done by deployed O&M team
Integration
System should be based on open standards and have API support for data import & export so that
integration with the Common Services can be done.
General
The following standards may be adhered to the project:
Web Standards will be followed to ensure consistency across the web pages. The site will
be best viewed with latest Internet Explorer and standard screen resolution.
All interface/pages performing similar functionality will have consistent look and feel.
Appropriate titles will be given to each page. The titles will specify the functionality of the
page.
Access to the functionality of the application will be controlled based on the user type.
Navigation facilities will be provided to navigate from one page to another page with
minimum number of clicks.
The selection and navigation related facilities in all screens must be standard. Buttons will
be labeled appropriately. The input screens will require least number of key presses and
mouse clicks.
Customized error messages for invalid input will be provided in all the pages whereas
completion/confirmation messages will also be displayed on successful processing of data
Operational Requirements
Recoverability
In any course of failure system should be ready for fallback mechanism. The system can switch
from PR to DR site immediately in case of system failure.
To manage hardware failure, data will be backed up on tape drives at regular intervals
The database must be capable of being restored to its condition of no more than 1 hour
before the corruption occurred.
Performance
The portal for Digital Secretariat 2.0 will match the user expectations with regard to performance
requirements. Creation of necessary ICT infrastructure will be created at State IT headquarters,
government departments and for other stakeholders. Further, trial/test run will be conducted
across the state with participation of authenticated users of different departments. This will help
to understand how fast the system handles individual requests in order to figure out the average
response time. Trial/Test run will also provide information on throughput in terms of no. of
requests the system can handle and concurrency in terms of no. of users working simultaneously.
Based on the outcomes, system will be tuned for optimum performance. Optimum performance
will ensure minimum time which a user has to spend for getting the response to avail any service
through the Digital Secretariat 2.0 portal.
Data retention
The system shall retain application information for infinite time. Different forms of data include
system documentation, audit records, database records, access records etc. System shall archive
the data from time to time as defined by the system administrator.
Conventions/standards
• There is a Force Majeure event affecting the SLA which is beyond the control of the SI.
• The non-compliance to the SLA is due to reasons beyond the control of the SI.
Note:
• Theft cases, by default, would not be considered “beyond the control of SI”. However, in
certain cases, based on circumstances and certain locations, the CHiPS may agree to qualify
as “beyond the control of SI”. The same may be mutually agreed and signed between the SI
and the CHiPS.
• Power shut down of less than 1 hour would not be considered as “beyond the control of SI”.
• SI is also required to note that in case of SLAs not being made applicable for cases considered
as “beyond the control of SI”, the SI would still need to replace the component (if it is not
functional as per SLA) within the SLA defined for resolution of Critical/ High/ Medium/ Low
Priority level incidents.
D.1 Definitions
For the purposes of this service level agreement, the following definitions and terms shall have meaning
as tabulated below:
# Term Definition
a. Uptime Shall mean the time period for the specified services / components with
the specified technical service standards are available to the users.
Uptime, in percentage, of any component (Non-IT and IT) can be
calculated as:
b. Downtime Shall mean the time period for which the specified services /
components with specified technical and service standards are not
available to the user department and excludes downtime owing to
Force Majeure & Reasons beyond control of the SI.
c. Not Keeping Shall mean that the SI does not deploy the proposed quantity and
Manpower quality of manpower to meet the system requirements or a person
deployed is not reporting to duty.
f. Response Time Time elapsed between receipt of request at the server and issuance of
(For Software) response by the server
g. Resolution Shall mean the time taken (after the incident has been reported at the
Time (For helpdesk) in resolving i.e. diagnosing, troubleshooting and fixing the
Incidents) reported incident
h. Non-Working All Sundays, 2nd and 3rd Saturdays of Months and all Public Holidays
Days declared by Government of Chhattisgarh
j. Days All Working and Non-Working days (365 days in a calendar year)
k. 24*7 Three shifts of 8 hours every day, this is applicable for all seven days of
the week without any non-working days
l. Scheduled The time that the System is not in service due to a scheduled activity as
Maintenance defined in this SLA. The scheduled maintenance time would not be
Time during 16X7 (7:00 am to 11:00 pm) timeframe. Further, scheduled
m. Scheduled The scheduled operating hours of the System for the month. All
operation time scheduled maintenance time on the system would be deducted from the
total operation time for the month to give the scheduled operation time.
The total operation time for the systems and applications will be
24X7X365 (per year).
n. “Helpdesk The support centre which shall handle Fault reporting, Trouble
Support” Ticketing and related enquiries during this contract. Helpdesk support
is to be provided as per service window defined in this RFP.
This section describes the SLA framework for this contract comprising of the following:
Responsibilities of parties
Reporting procedures
Issue management procedures
Management escalation and contact map
SLA change control
SI is responsible for delivering the services described in scope of work as per the service
levels detailed in this document.
Additionally, SI is responsible for:
o Reporting problems to the CHiPS as soon as possible
o Enable the CHiPS to monitor the SLA
o Providing early warning of any organizational, functional or technical changes that
might affect SI’s ability to deliver the services described in the SLA
o Resolve the production incidents in a timely manner
Immediate action will be taken to identify problems and follow up with appropriate
action to fix identified and those reported issues as quickly as possible.
Overall coordination with CHiPS for effective implementation
Any changes to the levels of service provided during the term of the Service Level Agreement will
be requested, documented and negotiated in good faith by CHiPS and SI. CHiPS or SI can request
a change. Changes will be documented as an addendum to this attachment and, consequently, the
Contract. If there is any confusion or conflict between the Contract and this document, the Tender
and its addendums, the Contract will supersede.
The parties may amend this SLA by mutual agreement in accordance. Changes can be proposed
by either party. The SI’s representative may initiate an SLA review at least bi-annually, if required.
Unresolved issues will be addressed using the issue management process described in Clause
Section D.2.3 of this document.
The SI’s representative will maintain and distribute current copies of the SLA document as
directed by CHiPS. Additional copies of the current SLA will be available at all times to authorized
parties.
All negotiated SLA changes will require changing the version control number. As appropriate,
minor changes may be accumulated for periodic release (e.g. every quarter) or for release when a
critical threshold of change has occurred.
Category SLAs
Category-I: Manpower
Service Availability
1 System Usage Always Available- No
Reporting(with Penalty
Detailed MIS) MIS Reports /Online
Reporting tool Not Available -0.25% of
total quarterly invoice
value
Application
Performance for If Response time < 2
Critical sec ,NoPenalty.
Applications
If Response time >2
(DAK,File,IHRMS)
sec<8sec,2% of
Transaction quarterly invoice per
meeting the incident reported.
Response Time would be calculated as time
prescribed Target elapsed between sending a request from client to
If Response time
Response Time (2 server and receiving the response. Response time
>8sec,5% of
seconds) for of services to be measured at an interval of 30 quarterly invoice per
Business minutes and all transactions not meeting incident reported.
Transactions for prescribed Target response time is recorded in
critical Application Monitoring Tool.
2 components
With in 1 month – No
Liquidated Damage
Software Patches
and Updates Number of days elapsed from the availability of >1month Rs 5000 per patch
latest patches on the system components.
4
Document Captured Values in System Log, Monitoring tool. If Retrival Time>2 seconds<8
Retrieval Time
Retrieval Time: Average of 2 second on retrieval of seconds-1 percent of
(File, Letter, quarterly invoice per
an average size of file, which is in use within last
Report ,Scanned
three months ;with 2000 concurrent users logged- incident reported
Documents )
in on the system with sizeable data in database If Retrieval Time > 8 second-
5 percent of quartely invoice
5 per incident reported
Security
Security Vulnerabilities Closure To be measured in number of • No Delay: No Liquidated
(Security vulnerabilities detected days of delay (or part thereof) damage
during Periodic Security beyond prescribed time-limit of • Delay (<=7 days): Rs. 50,000 per
Assessment (Vulnerability 7 days. incident per day
Assessment, Penetration Testing, • Delay (> 7 days): Rs. 1,00,000
etc.) should be closed within pre- (One Lakh) per incident per day
defined timelines.)
Category-VI: Helpdesk
Response Time
Definition Details
Service Level Till go-live, the monthly reports are required to be submitted by the SI. After go-
Requirement live, the quarterly reports are required to be submitted by the SI. These reports
should be submitted within prescribed time-limit as follows:
Liquidated Monthly Reports: Rs. 10,000 (Ten Thousand) per incident of delay per week
damage for Non-
Quarterly Reports: Rs. 50,000 (Fifty Thousand) per incident of delay per week
achievement of
SLA Requirement