II: TASKS
Recall the synchronous discussion on the Project Time Management. (Session recording are
available on the Google Drive repository)
III: QUESTIONS
(Note: In answering the problems, use a clean letter-sized paper for each item. Place your
scanned solutions and answers in the prescribed template as image.
University of the East
Manila Campus
College of Engineering
Computer Engineering Department
3. Given the tasks for Project ABC, perform crashing. Use the prescribed format below.
Assuming that there will be an additional cost of PHP 750.00 per man-day.
University of the East
Manila Campus
College of Engineering
Computer Engineering Department
What is the best duration the project can be completed when crashed? How much will
it cost?
The best duration that the project can be completed when crashed is 10 man-
days and the project cost is P18,700.00.
How much is the least possible cost of the project? In how many man-days?
The least possible cost of the project is P18,650.00 and the number of man-days
is 11 days.