Professional Documents
Culture Documents
Document Information
Document Identification POLARIS PMP
Comments / Approval
Date Name Organization/Title
Status
1/15/2020 John Bosso Deloitte / PM Approved for Release
1/22/2020 Megan Pilon DOL/PM Several modifications as well as
some questions/comments.
1/23/2020 Megan Pilon DOL PM Accepted Deloitte changes, made
a couple of
comments/suggestions/question.
1/24/20 Megan Pilon DOL PM Approved.
Table of Contents
1 Purpose....................................................................................................................................4
2 Project Goals and Objectives ............................................................................................5
3 Scope Management Plan ....................................................................................................7
Scope Management ........................................................................ 7
3.1.1 Define Scope ...........................................................................................................7
Scope and Schedule ........................................................................................................................ 7
3.1.2 Validate Scope.........................................................................................................7
3.1.3 Control Scope ..........................................................................................................8
Design and Implementation Principals .................................................. 8
Governance Structure for System Design Decisions ................................. 9
Information, Processes, and Tools to Manage Requirements ...................... 9
Approach to Tracing Requirements Compliance ...................................... 9
Change Control Process, Roles, and Responsibilities ............................. 10
3.6.1 Formal Change Control Process ........................................................................10
Initiating a Change. ........................................................................................................................ 10
Handling a Change Request......................................................................................................... 11
Tools ........................................................................................ 12
Roles and Responsibilities .............................................................. 12
Handling a Change Request that DOL has decided to pursue ................................................ 13
Resolution........................................................................................................................................ 13
3.8.2 Tracking Change Orders......................................................................................13
3.8.3 DOL Standard Change Request Form ..............................................................13
Monitoring Progress Against Scope ................................................... 13
3.9.1 Hybrid Agile Model ................................................................................................13
4 Resource Management Plan ............................................................................................17
Project Work Streams Roles and Responsibilities .................................. 17
Contractor Resources.................................................................... 19
DOL Resources ........................................................................... 21
Contractor Presence On-Site ........................................................... 25
Contractor Staffing Approach ........................................................... 25
Contractor Staff On-boarding ........................................................... 25
Approach to Coordinate Vacation and Holiday Schedules ........................ 26
Monitoring Staffing Levels Versus Project Requirements .......................... 26
5 Schedule Management ......................................................................................................28
Key Schedule Management Concepts ................................................ 28
Approach to Schedule Management .................................................. 28
5.2.1 Develop and Baseline...........................................................................................28
5.2.2 Track Progress and Maintain ..............................................................................29
5.2.3 Refine and Revise .................................................................................................29
5.2.4 Rebaseline (as approved)....................................................................................30
Frequency of Updates ................................................................... 30
1 Purpose
The Project Management Plan (PMP) documents the structure, processes, and resources that will be
used to execute the Professional Online Licensing and Regulatory Information System (POLARIS)
Project for the Washington State Department of Licensing (DOL). These processes and resources will be
utilized to undertake the project work and create deliverables that meet the POLARIS Project contractual
requirements. The PMP covers the organization, approach and timeline, controls, schedule and resource
management, tools, quality management and communication plans. This will provide the foundation to
achieve project goals and communicate how the program will be managed.
The PMP is approved by the project leadership during the early stages of the project and is maintained
throughout the life of the project. It is a living document that is kept up-to-date and should be considered
the primary source for information about the projects’ organization, stakeholder engagement in activities,
and management processes, tools, and terminology. The Deloitte and DOL project managers will review
the PMP as required throughout the project. A formal review will be conducted at the beginning of
Release 2 update it and do a second formal release of the deliverable.
Once the PMP has been approved, the management processes described herein will be the basis for
training the teams in project processes. This training will be included in the team member onboarding
procedures so that new team members are properly trained.
Upon approval, this plan will be baselined and archived in the DOL POLARIS SharePoint Repository.
Except for minor wording changes or changes to the organization charts and/or resource assignments in
the Governance section, this plan will not be changed without an approved Change Request. The Deloitte
Project Management staff are responsible for updating this document, as required, when resource
assignments change or there is an approved Change Request. The revised PMP will be reviewed and
approved by the DOL EPMO Director prior to being updated in the Document Management System.
Note: this deliverable is an update of the original PMP approved in Release 1.
Consumers:
Increase consumer access to data with more online options.
Provide consumers (or public) the ability to file complaints online.
Improve public safety through more accurate and timely data related to complaint
notifications and agency follow-up.
Business Partners:
Provide online interaction for third parties so data can be submitted in real time.
Increase ability to support open data using modern COTS interface and data exchange
capabilities.
Scope Management
Project scope of the solution is defined in the Requirements, Appendix B of Contract K6512. The scope
of the solution is being further detailed in User Stories developed in the Discovery and Design stages of
the project.
The scope of work is defined in the Scope of Work Appendix C to Contract K6512. The following sections
describe the overall concepts to Scope Management, as well as the major scope activities that occur after
project kick-off follow the scope management lifecycle which includes define, validate, and control scope
throughout the project lifecycle.
3.1.1 Define Scope
Scope confirmation is completed during the early stages of each release and is a joint activity that is
performed by the Deloitte and DOL Team Leads, PMO Staff, and Project Managers. The scope of the
solution differs from the scope of the work. The scope of the work describes the tasks and deliverables
needed to achieve the scope of the solution while the scope of the solution involves the overall features
and components that will produce the defined business benefits.
The Requirements will be loaded into a Requirements Traceability Matrix (RTM) in this case implemented
in the POLARIS SharePoint Site. The RTM will include the requirements, associated business rules, and
user stories (Note: Test scenarios/scripts are included in Azure/TFS as part of the user story.)
The Project Schedule is an important companion document to the scope of work in that it documents:
The major activities and their timing that the team will perform
Accountability (by team and/or organization) for performing those activities
External dependencies and their timings, and the team and/or organization that is responsible for
their completion
Moreover, once the Project Schedule is re-baselined for release 2, it is subject to change control process.
3.1.2 Validate Scope
Once the scope is defined and baselined, both DOL and Deloitte project managers are responsible to
validate scope throughout the project lifecycle. To validate scope, they will confirm:
the work being performed remains in scope, and
Addresses the boundaries of the scope of the solution via contract requirements, design
definition, user stories, and test cases.
The project managers will compare major solution definition deliverables with predecessor deliverables
(e.g., requirements to charter, business rules to requirement, user stories to requirements/business rules,
design to user stories, etc.) to confirm that the original scope is addressed, and additional scope elements
have not been added. Refinements to scope and decisions regarding scope will be documented in the
RTM and Decision Log. The Deloitte and DOL PMs will work to confirm that the refinements and
decisions do not reflect an expansion of scope and will work with staff to mandate that scope issues are
addressed by the team.
The PM will also validate the scope of the project work against the baselined Schedule. This validation
activity confirms that:
Resources are working on their assigned activities and tasks
External teams are working towards meeting the deadlines established in the project Work Plan
3.1.3 Control Scope
The objective of scope control is to manage activities that alter one or more aspects of the project scope,
including schedule, deliverables, functionality, or budget. The scope items described in this section are
baselined after approval and will not be changed without an approved Change Request (see the Change
Control Management section).
In addition, as solution deliverables are approved (such as User Stories demonstrated to Product Owner),
they also fall under the change request process. See flow below.
Standardize processes, procedures and communications to the degree practical across license
programs and types.
Utilize the configurable components delivered in the eLicensing framework rather than custom
developing new functionality where possible.
Execute quickly to meet contractual obligations while allowing for two incremental releases of the
application.
mapped to the original requirements as the last step of the user story grooming process. Deloitte will
work with RTM manager to map the test scripts to the RTM.
The DOL Requirements Manager will be responsible for maintaining the mapping of requirement-to-user-
story linking in the RTM. The actual user stories will be housed and managed in TFS. The RTM will
contain a reference to the user story ID to allow tracking of user stories to requirements.
The test script to-user-story mapping is in TFS.
Initiating a Change.
The scope management process begins with identifying a potential change. Any team member can raise
a potential change, which is then raised to the DOL Project Manager. The DOL Project Manager will
work with the team member, Deloitte Project Manager, and other participants to document the Change
Request using the Change Request form. It will be first reviewed to ensure it is not a duplicate of an
existing Change Request, and checked for validity and adequate information to begin analysis. All
Change Requests, their statuses, and any associated documentation will be maintained in POLARIS
SharePoint log.
Change Request status will be maintained according to the following status definitions:
The DOL Project Manager will then facilitate an analysis of the Change Request to determine its impact
to scope, cost, schedule, and quality. Impact analysis may include some or all of the following items:
Baselines affected
Formal Configurable Items affected, such as a specific components of system functionality or
infrastructure design
Description of the change and a discussion of how it would impact the various components and
processes of the POLARIS project
New or modified requirements
Evaluation of risk items associated with the Change Request
Effort analysis (including tasks, resources, durations, and their impact to the overall project
schedule)
Dependencies and/or conflicts
Compliance with existing standards
Impact on other pending and scheduled changes
Cost impact
Impact if Change Request is not implemented
Alternatives to the proposed Change Request
Final recommendations
Change Request analysis will result in establishing a criticality measure. Criticality characterizes the
relative urgency of the change with respect to the POLARIS project. The determining criteria shown in the
following table identify how quickly a change must be incorporated in order to achieve success in the
current phase of the project:
Change Requests are reviewed by the DOL and Deloitte Project Managers and Project Team. The DOL
Project Manager will submit to the Enterprise Program Management Office Director, Project Sponsor,
Steering Committee, and/or Executive Sponsor the completed Change Request Form and associated
impact analysis with the Project Managers’ and Project Team’s recommendations for approval,
disapproval, or escalation.
All approved Change Requests must be signed off by the appropriate level as described below.
The Enterprise Project Management Office Director and Project Sponsor can sign for a change
that has no impact to a project payment milestone, can be addressed within the current allocated
budget and fiscal year (including contingency), and has only a minor impact on functionality with
no impact on the Agency’s ability to deliver services to constituents.
All other Change Requests will be raised to the Business Sponsor and/or Executive Sponsor for
review and approval.
Where a Change Request is denied, there may be alternative actions (e.g., implement a
workaround for a functional gap) to be executed. If so, these efforts will be initiated and managed.
Once the efforts are initiated and managed, the Change Request can be closed.
Where a Change Request is approved, there may be many activities required such as project
budget/schedule/resource changes and task execution. Once changes are implemented, and
reviewed, the Change Request can be closed.
The DOL Project Manager will update the in-progress Change Requests for any status changes. The
DOL Project Manager will send notification of the change status to the POLARIS Project team members
and stakeholders affected by the decision.
Approved Change Requests will then be submitted to Deloitte using the processes identified in the
contract.
Tools
The tools used to support the scope management process include:
Requirements Traceability Matrix (RTM)
Team Foundation Server (TFS)
Change Request Log
Change Request Document
Resolution
If the Parties are unable to agree to the terms for the Change Order, either party will escalate the Change
Order Request through the Issue Resolution Process defined in the contract.
3.8.2 Tracking Change Orders.
All Final Change Orders will be tracked by Deloitte and Deloitte shall provide DOL with a monthly status
report on performance of Final Change Orders within ten (10) business days of the beginning of each
month.
3.8.3 DOL Standard Change Request Form
The change request form template is located here.
The change log is located here.
The functional teams will have a relatively large number of user stories defined at a relatively granular
level. These stories are expected to be addressed through configuration of the application rather than
classic development work. As a result, the completion of each individual story is a relatively low level of
effort.
The Functional Team, which includes the financial work stream, will use a Kanban approach in Release
2. This means that user stories will be developed during the discovery/design phase and will be groomed
and approved by the DOL Product Owner. Once a user story is approved by the product owner, it is ready
for development. The development team will then pull from the user stories that are ready where it is
then developed, unit tested, functionally tested, and demonstrated to a DOL SME. If the DOL SME
approves the user story, it is then set to “Ready for PO Demo” in TFS and is demonstrated as part of a
complete flow when flow is complete to the DOL Product Owner or delegate. If the DOL Product Owner
approves the user story, it is marked “Closed,” which means it is ready for System Integration Testing. If
the DOL Product Owner does not approve the user story, it is marked “Dev Rework” and the defects are
remediated by the development team and re-enters the workflow at the DOL SME Demo task.
The Data Team and the Integration Team will follow the hybrid agile approach similar to what was used in
Release 1. All teams will share the same states and statuses in TFS. The primary difference is that the
Data and Integration Teams will structure their work in Sprints and not on the rolling basis that is used by
the Functional Team.
All user stories will need to be mapped to a requirement – Deloitte will not work any item in TFS that is not
mapped to a requirement.
Below is an overview of the user story approval process – from initial draft through DOL Product Owner
approval and closure.
The user stories will be pointed for the Data and Integration Teams prior to the start of the sprint. For the
Functional Team, the level of effort in hours will be added to the user story prior to the DOL Product
Owner approval. Data will be reported at least weekly on:
Target Points/Hours in the sprint or development period
Number of Points/Hours in Development
Number of Points/Hours passed quality assurance
Number of Points/Hours closed (per Product Owner demo approval)
For those teams using Sprints, as the sprint is completed the total number of points or hours passed and
the number of points or hours deferred to a future sprint will also be reported.
The user stories will be uploaded to Microsoft TFS and grouped by sprint (for Data and Integration
Teams) or by “Ready for Development.” The stories will then be tracked through a set of statuses. The
statuses are:
% Complete for
Step User Story Status Tracking
Purposes
1 New 0
2 Analysis and Design
3 Ready for Dev
4 Dev In progress
5 Dev Rework
6 Dev Complete
7 Ready for Testing
8 Testing in Progress
9 Ready for Demo
10 SME Approved 95
11 Closed 100
As user stories move through the development and validation process their status and percent complete
will be updated in TFS so that reports can be created on the progress within the sprint and against the
overall backlog
Metrics: Velocity will be determined by planned velocity vs actual velocity. DOL and Deloitte will develop
the reporting format based on the metrics above.
The Resource Management Plan outlines how the project work is organized around teams of resources
and then goes on to summarize the resources and processes required to execute on the project on both
the Deloitte and DOL side.
The objectives of the plan are to:
1. Define the resource numbers, roles and requirements for the core project team.
2. Define the resource numbers, roles and requirements for DOL and other stakeholder participation
beyond the core team.
3. Identify the approach to placing and replacing key and non-key team members.
4. Identify the approach to coordinating holiday and vacation schedules.
5. Describe the monitoring of staffing levels versus project requirements.
Function or Primary
## Description
Activity Responsibility
1 Project Provides project management and oversight of the Joint Activities
Management project, managing the project teams, monitoring and
managing scope and schedule and reporting status and
progress
2 Product Ownership Managing the compilation of user stories, configuration DOL
data and other design components against the
requirements of DOL. Providing oversight on the
development to confirm that the project is being
implemented in accordance with the specifications (user
stories)
Making or managing the making of decisions impacting
the design and implementation of the solution
3 Functional / This work stream focuses on implementing business Joint activities Deloitte
Configuration requirements related to the licensing, enforcement, and
financial processes through configuring the eLicensing
solution.
DOL to provide User Story acceptance criteria, demo
reviews and approvals. Deloitte responsible for
configuration and development.
5 Integration This work stream implements integrations to other Joint Activities
systems as specified in the scope of the project Deloitte implements new
integrations
DOL executes development
on legacy systems and
coordinates and manages
integration partners
7 Data The data is extracted from the legacy systems and is Joint Activities
Conversion/Cleanin placed into an intermediate staging area managed by DOL Data cleaning
g DOL. DOL and Deloitte will work together to map the DOL – Source to Staging
Function or Primary
## Description
Activity Responsibility
data from the staging area to the target Salesforce Deloitte - Staging to Target
structure. The data in the data staging environment gets
transformed to match the POLARIS data model and then
the Deloitte team will load that transformed data into the
application
While the primary responsibility lies with the party specified in the table above, their ability to complete
their activities significantly depends on the other party participating actively and providing necessary
inputs / decisions. For example, Configuration work stream depends heavily on inputs and timely
approvals from DOL, while the OCM work stream depends on the training materials and train-the-trainer
session delivered by Deloitte.
Contractor Resources
Deloitte is providing a range of resource to undertake the project work. The resource model for the team
is presented in the table below.
Work will be done in a range of locations. Some resources will work largely or exclusively remotely while
the core solution and project management teams will largely be onsite. Where project requirements
allow, staff that live remote to the project site will use a model where they are onsite 3 to 4 days a week
and work from their home location 1 or 2 days per week. Where project needs dictate, staff will be onsite
5 days per week. Occasionally, some portion of the largely onsite project team may work remotely some
weeks.
The Deloitte staffing model is as follows:
DOL Resources
The Department of Licensing (DOL) has assembled a project team to execute on the delivery of
POLARIS alongside Deloitte. The following table outlines the key roles that are required to deliver the
project. DOL may choose to supplement these roles with additional positions to spread responsibilities
across multiple people and take advantage of specific skill sets.
Role No Start
## Resource Skills Duration
Date
1 EPMO Director Oversight of the project, Issue Program 1 In place Part-time
resolution escalation management
2 Project Manager Day to day management of the Project and 1 In place Full-time
project program
Conformance of solution to management
requirements Licensing
Scope management experience
Project Communications Team leadership
3 Deputy Project Manages different teams/ work Project and 1 In place Full-time
Manager streams as needed, supports program
process development and other management
project Team
communication/coordination Leadership
needs.
4 Information Ensures project is adequately State enterprise 1 In place Full-time
Services Resource resourced from a technical technology
Manager view point, manages technical experience
Role No Start
## Resource Skills Duration
Date
issues and risks associated with Project
the project, works with the management
Information Services Division experience
Leadership team to address Solution
project issues/risks. leadership
5 Technical Responsible for assisting with State enterprise .5 In place Part-time
Solutionist technical issues and risks technology
associated with the project experience
Project
management
experience
Solution
leadership
6 Product Owner Primary leadership and Strong 1-3 In place Full-time
management of the understanding of
requirements and design of the WA DOL
solution business and
Owns the vision for the future requirements
of operations and the system to Understanding
support it of the vision for
future
operations
7 Subject Matter Work with Deloitte Functional Deep 4-8 In place Full-time
Experts – team to interpret requirements understanding of and Part-
Licensing – and provide configuration data the business and time
Release 2 and information to allow system
development of user stories for requirements for January
their primary area of expertise their area of 2019 – June
First level review of user responsibility 2019
stories and other configuration
and design information
8 Subject Matter Work with Deloitte Functional Deep 6 In
Experts (SMEs) – team to interpret requirements understanding of
Regulatory – and provide configuration data the business and Part-time
Release 2 and information to allow system
development of user stories for requirements for
their primary area of expertise their area of
First level review of user responsibility
stories and other configuration
and design information
8 User Experience Provides DOL standards and Enterprise 1 In place Part-time
practices regarding UX to the system user
implementation team experience
Participates in demonstrations
and playbacks and provides UX
input to the implementation
team
Lease with Deloitte User
Experience staff
9 Financial Lead SME resource for financial Strong 1 In place Full-time
functionality across license understanding of
types. DOL financials
Role No Start
## Resource Skills Duration
Date
Primary resource to work with Understanding
Deloitte team to capture of future vision
required functionality and for POLARIS
configuration for operations
implementation of financial
and accounting functionality
Role No Start
## Resource Skills Duration
Date
recommend mapping and
transformation updates
17 Interface Tester Work with the integration team Web user 1 In place Full-time
to develop understanding of the interface design
interface design Salesforce
Develop test scenarios for experience
interfaces
Work with integration partner
to execute test scenarios
Report test results
18 System Config/ Write test scenarios based on Testing 5 In place Full-time
Functional Testers user stories experience
Undertake functional testing of Knowledge of
the application DOL processes
Contribute to the reporting of desirable
test results
19 User Acceptance Run through User Acceptance Knowledge of 10- May 1 – Full-time
Testing – Release Test scripts and report results business 20 May 31,
2 processes, 2020
detailed
oriented,
adaptable to
technology
20 Organizational Plans and manages the OCM Project 1 In place Full time
Readiness activities associated with Management,
manager POLARIS familiar with
OCM activities
21 OCM Analysts Undertake OCM and Experts in OCM 2 In place Full-time
communications activities tools and
associated with POLARIS processes
22 Training Work with Deloitte Training Experienced 1 In place Full-time
Coordinator Lead to develop training plan technical trainer
Plan and manage the execution Understanding
of end user training of DOL
Participate in training materials processes is
development desirable
Training
leadership
experience
23 Trainers – Release Participate in training materials Technical 5 February 1, Full-time
2 development training 2020 –
Deliver end user training experience September
30, 2020
24 Command Center Create command center Command 1 April 1 – Full-time
Lead logistics and make sure center September
processes are set up, ensure experience 30, 2020
command center staffed during
stabilization, and report out on
command center results
Role No Start
## Resource Skills Duration
Date
25 External QA Provide oversight to project to Expert Quality 1 In place Full-time
ensure proper project Assurance
management processes are in services
place and followed.
26 Administrative Assist with office Administrative 1 In place Full-time
Assistant administrative duties for experience and
project team. skills
Where a key staff member is to be removed from the project due to Extenuating Circumstances, the
Contractor will notify DOL. Contractor will identify a replacement resource for the role within 10 business
days of notification to DOL or 20 business days prior to the scheduled departure of the key staff member,
whichever is later.
Key staff replacements will have qualifications and experience similar to the original key staff member
and will have the skills and experience necessary to complete the key staff assignment. DOL shall have
the right to review the resume of all proposed replacement resource for key staff members and to conduct
an interview of the resource on site in Olympia Washington or via video conference, and check
references. DOL shall have the right to accept or reject the proposed replacement resource.
The staff onboarding process will evolve over time. It is documented in the DOL POLARIS SharePoint
repository and can be accessed at:
https://projects.sp.dol.wa.gov/PWA/POLARIS/_layouts/15/start.aspx#/Shared%20Documents/Form
s/AllItems.aspx?RootFolder=%2FPWA%2FPOLARIS%2FShared%20Documents%2FResource%20
Management&FolderCTID=0x01200000F423678A77A541AC56382671F813CB&View=%7BC78B7C0
4%2D1DBF%2D41D9%2D91AA%2D4ABA463C2D31%7D
At a high level, Deloitte will notify DOL of the need for access and or a workstation 2 weeks in advance of
the need.
The majority of Deloitte’s staff will be in either the Business Analysts or Remote Staff category. A very
small number of staff will have the Developer role (generally those associated with data conversion).
Reporting on Resources
Ensuring the project is adequately resourced is a key project performance metric and is reported as part
of the monthly status report. If resources are not available as planned in the resource management plan
and the delay creates new risks of preventing project from delivering on-time, the status report will reflect
“yellow.” If resources are not available as planned in the resource management plan and the delay is
causing delays in project delivery, status report will reflect “red” for resources.
5 Schedule Management
Consistent, high-quality schedule management processes allow PMs to understand the current situation,
forecast the future, accurately assess the impact of changes, prioritize team efforts, and effectively
communicate both internally and externally. Project team coordination requires a structured process to
confirm that the team develops, baselines, maintains, and reports status against the project Work Plan. A
key to building and maintaining a good Work Plan that will accurately model the project is to keep the
Work Plan as simple, yet realistic, as possible.
Task owners will provide updated status on the Look Ahead Document that is circulated weekly.
Tasks that have not started will be reported as not started.
Tasks that have started and are less than 5 days in duration will be reported as 50% complete.
Tasks that are more than 5 days in duration will be reported as 20% complete once they are
started until they are complete.
Tasks can be marked 100% complete when they are fully complete
Task status will be collected weekly from Task owners and be updated in the project schedule. The
PMO staff will then calculate a schedule variance based on the percent complete against expected
percent complete at that point in the project.
5.2.3 Refine and Revise
Should it be determined that more detail or refinement is required in the schedule as the project moves
forward, a Rolling Wave style planning process will be scheduled to make those changes. During the
Rolling Wave planning activities, the PM and Team Leads will refine and revise the schedule. The PM will
initiate the process with a phase planning meeting, including the PM leads of the various work-streams,
and the PMO scheduler (if possible). During this meeting, the PM will describe the scope of the plan
refinement activity and the process for refining the schedule. The group will discuss the major activities for
the team to refine and determine the approach. The various leads of the work-streams will create a
concise written summary of the major activities in the next phase for which their team is responsible. The
summaries will include the following for each major activity:
The overall approach
Frequency of Updates
The project schedule shall be updated weekly after the first baseline is created. Results of the update
will be communicated as part of status reporting. More substantive updates may occur to the project as
part of Rolling Wave updates as often as once every two to three months depending on the needs.
Small changes to the schedule (addition of small numbers of tasks or adjustment of dependencies) may
occur as often as weekly as required to address schedule adjustments and in reaction to task schedule
slippages or other issues.
Communication Approach
This Communication Management Plan documents the protocol for the Project team to communicate
internally and with the POLARIS stakeholders with the objective to structure communication in an
effective way and to define high level responsibilities for communications. The Communication
Management Plan documents the information needs, activities and methods needed to facilitate timely
and appropriate generation, dissemination, and disposition of project information.
This plan is intended as a starting point to establish the minimum expectations for communications.
Additional methods and opportunities will be sought and employed as appropriate.
Status Report
The project management team will generate two status reports. The first, a weekly report will be
generated by the Deloitte Project Management team but will incorporate status from both the Deloitte and
DOL staff working on the various threads of work. It is relatively detailed and reports on the individual
threads of work. It is intended for the core project leadership team to communicate status of the project
execution and keep the on the ground project leadership appraised of status on the ground.
The second, a monthly status report will be generated by the DOL Project Manager with support from
Deloitte and will report on the high-level status of the project meant for an executive audience (primarily
the Steering Committee).
6.2.1 Weekly Status Report
The weekly status report is structured as a power point deck with a slide for each thread of activity
currently underway (i.e. functional, conversion, integration, OCM), a dashboard and a link to the
Deliverable tracker. The report dashboard that reports overall status of the project as well as the
performance metrics from the development sprints.
Select risk and issues that need to be discussed on a weekly basis are also brought forward in the weekly
status report.
6.2.2 Monthly Status Report
The monthly status report is structured as a narrative document. It reports the project status at a higher
level intended for the steering committee and other executive audiences. The monthly status report
includes:
Dashboard showing key performance indicators
High level description of the status by major thread of activity
Performance against milestones
Extract of key risks and issues from the respective trackers
feedback on the deliverable within the time period documented in the Deliverable Log. For standard
deliverables (non-payment milestones), upon completion, the reviewer will document deliverable sign-off
by noting approval in the file and sending an email to the Deloitte Deputy PM and Deloitte PMO Analyst.
For deliverables that are tied to a milestone payment, approval is provided by hand-written signature in a
deliverable approval form.
Once a deliverable is signed off, the DOL and Deloitte project manager(s) will archive the approved
deliverable (along with the completed Deliverable Sign-off Form) in POLARIS SharePoint site, and any
additional changes to the deliverable will need an approved change request.
Due to the iterative nature of the development on the POLARIS project, the following Deliverables will not
require a change request if changes are introduced during the development phase (before the start of
SIT):
Deployment Plan **
High Level Application Design *
Solution Architecture *
Interface Agreement, Specification, and Mapping Document *
Integration Design Document *
Data Dictionary *
Data Conversion Plan
Data Conversion Mapping Source to Staging
Data Conversion Mapping Staging to Salesforce
Test Plan
Initial signed-off versions of the above Deliverables will serve as a baseline version. Changes to these
Deliverables can happen throughout the development phase to reflect design decisions. Documents
marked with a single asterisk * will be updated throughout the project to reflect design changes. No
formal resubmission will be conducted. The Deployment Plan, marked with two asterisks ** will be
submitted for a second review during User Acceptance Test. This updated version will reflect the
updated deployment activities that would be required to deploy a new environment during production
operations. The balance of the deliverables are working documents are will only be updated should a
significant deviation be required in the process during the period of applicability of the deliverable.
Formal Review: Formal reviews represent the most structured review type and are used as development
step for critical designs or deliverables with cross-team impact. They often follow a walkthrough or offline
review for the same deliverable.
The formal review takes place as a scheduled, facilitated meeting between two or more reviewers, after
previously providing the deliverable and review criteria in advance of the meeting to all review
participants. Formal reviews are not meant to be conducted as walkthroughs. Reviewers must come
prepared to share their findings from their individual preparation review with the other reviewers. There
may even be a kickoff or preparation meeting with the reviewers before the formal review session. The
consensus review defects are documented in one feedback document and/or marked up copy of the
deliverable and agreed-upon changes must be implemented and verified before the formal review is
considered complete.
Walkthrough Review: Walkthrough reviews are an effective deliverable review type for medium-risk
deliverables or deliverables that may be hard to understand (for example, complex technical design
documentation).
The format of this walkthrough review is a face-to-face meeting where the authors of the deliverable walk
a reviewer group through the deliverable. The reviewer group should include at least two individuals, with
at least one subject matter expert. The review defects are documented in one deliverable feedback
record and agreed-upon changes are resolved and verified in the deliverable before the walkthrough is
considered complete.
Offline Review: Offline reviews are performed by someone other than the deliverable author in a
distributed or asynchronous manner (that is, not a face-to-face meeting or live teleconference).
Each offline reviewer uses the Deliverable Feedback Form (DFF) and the corresponding Deliverable
Expectation Document to evaluate the deliverable, identify defects, and document feedback. The DFF is
provided to the deliverable author for resolution. The owner of the deliverable review assignment will
verify that all defects are resolved before the deliverable review can be considered complete.
No
No
Risks Log
Legend
Inputs / Supporting
Task Outputs Step Output Procedure Decision
Field Description
Title Brief, high-level description of the risk
Owner Project team member responsible for ensuring that the risk is properly
analyzed and addressed
Assigned To Project team member responsible to develop and implement the risk
response plan
Status Status of the risk as it flows through the process
Category Identifies the type of risk. Options (definitions are provided in section 8.3
Risk/Issue Types):
Contract
External
Financial
Functional
Quality
Organization
Performance
Project Management
Resource
Schedule
Scope
Technical
General
Due Date Date when the mitigation plan is due
Probability Likelihood of the risk occurring Options:
1 – Low
3 – Medium
5 – High
Trigger Description Description of outcomes or results that indicate the risk has occurred
Trigger Condition that triggers the contingency plan
Options:
Date – date of occurrence
Exposure over threshold – risk probability exceeds acceptable level
Tasks not completed – assigned work was not done
Other
Once the issue record is created, cross-reference the new issue ID in the old risk record before
closing the risk record.
If the risk has not been realized, continue monitoring it throughout the project, for as long as the
risk is active.
After each risk review meeting, the DOL project manager has the following responsibilities:
• Validate Risk Log is updated with changes and additions
• Archive any approved risk response plans
• Communicate the updated risk records
Project
Management
Plan
4. Manage
3. Change
1. Create Issue 2. Resolve Issue Yes Change
Request?
Requests
No
5. Close Issue
Issues Log
Legend
Inputs / Supporting
Task Outputs Step Output Procedure Decision
Field Description
Action/Issue Designate whether the item is an Action or an Issue
Action/Issue Status Status of the issue as it flows through the process. Options:
New – recently created
In-progress – currently working on the item
Blocked – unable to proceed
On-hold – delay action on the item
Closed – complete
Title Brief, high-level description of the issue
Release Impacting? Release that is affected by the issue. Options:
Release 1
Release 2
Both
Category Identifies the type of issue. Options (definitions are provided in section 8.3
Risk/Issue Types):
Contract
External
Financial
Functional
Quality
Organization
Performance
Project Management
Resource
Schedule
Scope
Technical
General
Description Details on what the issue is, what’s causing the issue, the impacts, and the
resolution actions. The resolution actions include:
Resolution approach
Whether a change request (CR) needs to be created to close the issue
Other closure criteria
Priority A subjective assignment of the significance of the issue used by the project
manager for prioritization and status reporting. The priority issue ratings for the
project are as follows:
Critical - the issue resolution actions must be defined and executed
immediately (Severity Level 1)
High - the issue resolution actions must be defined and executed as
soon as possible (Severity Level 2)
Medium - the issue resolution actions can be developed any time
before the next risk and issue review meeting (Severity Level 3)
Low – the appropriate issue resolution actions will be determined at
the next risk and issue review meeting (Severity Level 4)
Assigned To Project team member responsible for addressing the issue and developing a
resolution plan
Due Date Date when resolution is required to be complete
Related Identify any other related issues or actions
Issues/Actions
Related Risk ID ID for risk associated with issue
Comments Free text field to provide additional information
The DOL and Deloitte project managers review and validate “New” issue records from the project team,
canceling issues entries that are not valid. The project managers will then confirm or re-assign valid
issues to the appropriate project team member(s) (issue owners) for detailed analysis and resolution
planning.
The assigned team member(s) will confirm or define the following fields for an issue record after
completing the necessary due diligence and analysis on the issue. Where appropriate (e.g., for “Critical”
or “High” priority issue), the project managers should review and approve the proposed issue resolution.
Implement the resolution actions to close the issue. Determine whether the resolution actions
require a Change Request (see next step).
Document the resolution results.
If the issue cannot be resolved, escalate the issue.
Risk/Issue Types
The following risk and issue types will be used to categorize identified risks in the Risk Log, and issues in
the Issue Log respectively.
9 Project Organization
The project organization is documented in an integrated organization chart in SharePoint. It can be
accessed at:
https://projects.sp.dol.wa.gov/PWA/POLARIS/_layouts/15/start.aspx#/Shared%20Documents/Form
s/AllItems.aspx?RootFolder=%2FPWA%2FPOLARIS%2FShared%20Documents%2FProject%20Go
vernance&FolderCTID=0x01200000F423678A77A541AC56382671F813CB&View=%7BC78B7C04%2
D1DBF%2D41D9%2D91AA%2D4ABA463C2D31%7D
Titled: Integrated Org Chart
10 Deliverables Log
Project deliverables are outlined in the table below along with the primary review and approval
assignments and the review durations expected.
Deliverables Log
About Deloitte
Deloitte provides audit, tax, consulting, and financial advisory services to public and private
clients spanning multiple industries. With a globally connected network of member firms in
140 countries, Deloitte brings world-class capabilities and deep local expertise to help
clients succeed wherever they operate. Deloitte's 200,000 professionals are committed to
becoming the standard of excellence.
Usage Statement
This publication is for internal distribution and use only among personnel of Deloitte Touche
Tohmatsu Limited, its member firms, and its and their affiliates. Deloitte Touche Tohmatsu
Limited, its member firms, and its and their affiliates shall not be responsible for any loss
whatsoever sustained by any person who relies on this publication.
If you will be using this template to prepare document for delivery external to Deloitte, you
are required to add the appropriate member firm disclaimer statement.