Professional Documents
Culture Documents
B 3 days 2 days 50 50
C 2 days 3 days 30 20
D 1 day 1 day 20 30
E 2 days 4 days 25 25
1
Question Two [25 Marks]
a) Briefly define the meaning of Project Network Analysis and further explain the three
commonly used techniques. (7 Marks)
b) Given the following activities, draw a Ghant chart including Hammocks and Milestones,
assuming works are to begin on 14th April, 2018. Further, draw a Revised Ghant Chart
indicating the progress of the Project as of today 5th May, 2018. ( 8 Marks)
No. Activities Duration (Days)
1.1 Civil
1.1.1 Excavation 3
1.1.2 Setting out 1
1.1.3 Dig Foundation 2
1.1.4 Throw concrete 5
1.1.5 Walling 8
1.1.6 Roofing 5
2
1.2 Plumbing
1.2.1 Piping 4
1.2.2 Sewerage 4
1.3 Electrical
1.3.1 Wiring 3
1.3.2 Appliances 5
1.4 Fitting Windows 3
c) With the use of an illustration, explain the Matrix organization Structure. (5 Marks)
d) You are the project manager on the Construction of a 3-Stoyed Structure in Kampala,
explain at least four coordination devices you can use to reduce the need for coordination.
(7 Marks)
i) Compute the critical path of the above logical Network diagram (10 Marks)
b) Define the following terms as used in Project Network Analysis
i) Earliest Start Time
ii) Latest Start Time
iii) Earliest Finish Time
iv) Latest Finish Time
v) Event slack (5 Marks)
c)
3
d) Find the critical path and calculate the slack time for the following network (10 Marks)
END