Professional Documents
Culture Documents
2020-
2021
SCE5381
Project Management
PROPOSED DESIGN AND CONSTRUCTION OF COMPREHENSIVE RESIDENTIAL DEVELOPMENT PROJECT IN TUEN MUN
FONG PAK HEI (200019629)
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
Content
1 Background.............................................................................................................................2
2.1 Organization in the Construction Industry...........................................................................3
2.2 responsibility of different parties.........................................................................................4
2.2.1 The Client......................................................................................................................4
2.2.2 Consultants....................................................................................................................4
The consultants will assist the owner in developing a design schedule. The schedule should
prioritise work according to the needs of the owner and it should develop with extensive
input from all consultants which will have a key role in the design process.........................4
2.2.3 Construction Contractor................................................................................................4
2.3 Leadership style...................................................................................................................4
2.4 Management Mode...............................................................................................................5
2.5 Span of control.....................................................................................................................5
3.1 Resource changes.................................................................................................................5
4 Overcome constraints in resources..........................................................................................7
4 Conclusion...............................................................................................................................7
5 Main task.................................................................................................................................8
List of figure
Figure 1......................................................................................................................................2
Figure 2......................................................................................................................................2
Figure 3......................................................................................................................................2
Figure 4......................................................................................................................................3
Figure 5......................................................................................................................................6
List of table
Table 1......................................................................................................................................11
Table 2......................................................................................................................................13
1
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
1 Background
This building project aims to construct four residential blocks (30 storeys), two podium
levels, a ground floor landscaped area and a 15m wide waterfront promenade. The site is
approximated to be 30800 meter square. The surrounding elements near the site include
residential areas, secondary schools, a power plant and industrial buildings.
2
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
As our construction projects are large in scale, many different construction processes need to
be carried out simultaneously. Moreover, the organisation and resources of our company are
limited. Functional organisations are suitable for large company organisations with four
different types of project members in each functional organisation; project organisations are
also suitable for large companies with four functional members in each organisation. We
have therefore chosen matrix organisations, which combine the advantages of functional and
departmental organisations. The matrix organisation is suitable for small companies because
the system enables the best use of resources. Matrix organisations can bring together
knowledge from different backgrounds and training into problem solving teams to improve
the quality of decision making and problem solving.
When using matrix organisations, problems can occur when a person does not report to
multiple bosses and receives instructions from multiple managers. Matrix organisations are
difficult and costly to manage because their structure does not have a clearly defined
hierarchy of authority and responsibility.
3
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
1
https://www.dlapiperrealworld.com/law/index.html?t=construction&s=forms-of-contract-procurement-
methods&q=parties-to-a-construction-or-engineering-contract
2
https://www.pinterest.com/pin/662873638884921041/
4
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
3
https://ascelibrary.org/doi/pdf/10.1061/%28ASCE%291532-6748%282003%293%3A1%2856%29
4
https://core.ac.uk/download/pdf/54198899.pdf
5
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
6
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
income in order to set the furthest possible range of acquisition at each stage. Gradual cost
reduction is the objective of the agreement and the client but should not conflict with the
natural safety objectives of the task.
The assessment department should not later ignore the unavoidable support costs that are
essential for the organisation to reach its full capacity. The costs of maintenance, heating,
lighting and cleaning will affect the true financial estimate of the structure used. The cost of a
three-year period of work should therefore be 1 / (1 + 4. 5%) ^ 3 = 0.876.
5
https://www.constructiontuts.com/life-cycle-costing/
7
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
Fourthly, where there are insufficient resources to complete a project, it is important to ensure
that the resource management plan is as comprehensive and detailed as possible. This means
identifying the full and complete resource requirements, calculating and estimating the
amount of each resource required, and meeting the planned deadline. This means that if you
do not have enough resources to complete the project, you should prepare all the people,
equipment and materials needed to complete the project well in advance.
Once the list is complete, we should prepare a schedule of the resources required to complete
the project. It is important to know how long each resource will take to prepare so that you
can understand their impact on the project. This will allow us to know how much and how
often certain specific resources will be required each day, so that we can change the daily
requirements of the resources and thus prepare them in advance in case there is a shortage of
resources when we are ready to start the project. Add to this the need to identify assumptions
and constraints associated with resources. Therefore preparing a good resource management
plan in advance will not change the number of resources you have, but it will expand the
scope of resources to maximise their use to meet the needs of the project.
4 Conclusion
In the organisation and refinement phase of a management assumption, this establishes a
good leadership style and a management framework that reduces differences and builds
consistent values towards the goal. At the same time, it can be seen that an initial survey and
management framework can increase adaptability, flexibility and staff efficiency. The above
conditions should also be taken into account as they are important for controlling the cost,
time and quality of the project schedule.
8
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
5 Main task
1.) Site design and surveying.
2.) Site preparation.
3.) Site clearance.
4.) Hualing of heavy equipment.
5.) Temporary work.
6.) Site Excavation.
7.) Foundation work.
8.) Prepare suitable place for placing the power distributor.
9.) Refill the excavation.
10.) Prepare for tower crane.
11.) site preparation for A2.
12.) form the column preparation work (formwork, steel fixing).
13.) Receive building materials.
14.) Fabricate precast concrete blocks (seal with cement mortar).
15.) Installation of lift.
16.) Installing building service.
17.) Building the green roof.
18.) Fitting out / decoration.
19.) Landscape engineering.
21.) Installing Vertical Green wall along TUEN HING ROAD.
22.) Complect the Project.
9
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
10
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
11
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
19-22 S Q2 Landscape 5 43 48 62 14
engineering
12
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
13
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
Duration
Description (week) ES EF LF Float
Site design and surveying 1 0 1 1 0
Site preparation 1 1 2 2 0
Site clearance 2 2 4 4 0
Hualing of heavy equipment 1 4 5 5 0
Temporary work 1 5 6 6 0
Site Excavation 2 6 8 8 0
Site Excavation 2 6 8 14 6
Foundation work 7 8 15 15 0
Prepare suitable place for placing the power
distributor 1 8 9 15 6
Refill the excavation 1 15 16 16 0
Prepare for mobile crane 1 16 17 17 0
Prepare for mobile crane 1 16 17 18 1
Prepare for mobile crane 1 16 17 18 1
site preparation for A3 (Four residential building
block and Two stories podium) 1 17 18 18 0
form the column preparation work (formwork,
steel fixing) 1 18 19 19 0
Receive building materials 1 17 18 19 1
Fabricate precast concrete blocks (seal with
cement mortar) 20 19 39 39 0
Fabricate precast concrete blocks (seal with
cement mortar) 20 19 39 40 1
Fabricate precast concrete blocks (seal with
cement mortar) 20 19 39 46 7
Installation of lift 1 39 40 40 0
Installation of lift 1 39 40 46 6
Installing building service 9 40 49 49 0
Building the green roof 3 40 43 49 6
Building the green roof 3 40 43 57 14
Building the green roof 3 40 43 59 16
Building the green roof 3 40 43 57 14
Fitting out / decoration 13 49 62 62 0
Landscape engineering 5 43 48 62 14
Road Engineering 3 43 48 62 14
Installing Vertical Green wall along TUEN HING
ROAD 5 43 48 62 14
Minimum
time = 62 weeks
Table 2
14
Technological and Higher Institute of Hong Kong SCE5381 - Project Management
6 Reference
ConstructionTuts, 2019, Life Cycle Costing in Construction, [online] Available at:
<https://www.pinterest.com/pin/662873638884921041/> [Accessed 27 March 2021].
Method Statement HQ, Construction Project Job Descriptions and Organization Chart
<https://www.constructiontuts.com/life-cycle-costing/> [Accessed 27 March 2021].
DLA PIPER, Parties to a construction or engineering contract, [online] Available at:
<https://www.dlapiperrealworld.com/law/index.html?t=construction&s=forms-of-contract-
procurement-methods&q=parties-to-a-construction-or-engineering-contract >[Accessed 27
March 2021].
Leader Manage, 2003, The construction Manager as a Leader, [online] Available at:
<https://ascelibrary.org/doi/pdf/10.1061/%28ASCE%291532-
6748%282003%293%3A1%2856%29 >[Accessed 27 March 2021].
Authentic Leadership. International Journal of Project Management, Vol. 26 pp., 1986,
Leadership styles of construction project leaders – A theoretical perspective [online]
Available at: <https://core.ac.uk/download/pdf/54198899.pdf >[Accessed 27 March 2021].
15