Professional Documents
Culture Documents
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
CT222-M
CONSTRUCTION PROJECT MANAGEMENT
WRITTEN REPORT
DESIGN PHASE
Submitted By:
Bustamante, Gerimae
De Vera, Arman
Gacis, Gian
Medina, Klarise Joy
Oquin, Jervin
BETCT – 2 EF
Submitted To:
Prof. Charlene F. Ricopuerto
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
CONTENTS
DESIGN PHASE………………………………………………………………………………...1
RISK MANAGEMENT………………………………………………………………………….3
CONSTRUCTION CONTRACTS……………………………………………………………..8
DESIGN PHASE
The process for completing the design and construction of a building is often divided into
notional stages or phases.
1. CONCEPT DESIGN
➢ Concept design generally takes place after feasibility studies and options
appraisals have been carried out and a project brief has been prepared.
➢ Whilst these phases may include the preparation of drawings and other
studies, they are generally not considered to involve design.
➢ The concept design represents the design team's initial response to the
project brief and articulates the broad outlines of function and form.
2. DETAIL DESIGN
➢ Concept design is followed by detailed design or developed design during
which all the main components of the building and how they fit together are
described.
➢ By the end of the detailed design process, the design should be
dimensionally correct and coordinated.
3. TECHNICAL DESIGN
➢ This includes project activities that take place after the detailed design has
been completed, but before the construction contract is tendered or
construction begins.
➢ By the end of the stage the architectural, structural, and mechanical services
design and specifications should describe all the main components of the
building and how they fit together, any performance specified work should
be defined and there should be sufficient information for applications for
statutory approval to be completed.
In the design phase, one or more designs are developed, with which the project result
can apparently be achieved. The project supervisors use these designs to choose the
definitive design that will be produced in the project.
RESPONSIBILITIES:
a. Owner – The owner may participate in the Preliminary Design Review.
b. Project Manager – The Project Manager is responsible and accountable
for the successful execution of the Design Phase. The Project Manager is
responsible for leading the team that accomplishes the phase activities and
deliverables.
c. Integrated Project Team – are responsible for accomplishing assigned
tasks as directed by the Project Manager.
1|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
2|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
RISK MANAGEMENT
➢ Risk management in construction is designed to plan, monitor, and control those
measures needed to prevent exposure to risk.
➢ To do this it is necessary to identify the hazard, assess the extent of the risk,
provide measures to control the risk and manage any residual risks.
RISK ASSESSMENT
Risk assessments are carried out in a controlled and thorough way following a set
process. Risk assessments for health and safety risks are a statutory requirement under
the management of Health and Safety at Work Regulations and a typical assessment
might follow these steps:
1. Identify the hazard.
2. Identify who or what might be harmed.
3. Evaluate the risks arising from the hazard.
4. Determine the control measures.
5. Evaluate the remaining risks.
6. Record the findings of the risk assessment.
7. Make contingency plans for the residual risks.
8. Review and revision.
Client risks are around cost time and quality. Risk management considerations for
the client may include:
• Feasibility risk - the decision to go ahead backed up by a robust business
case, considering options and presenting the preferred solution.
• Design risk - deciding the level of control to keep over design and therefore
the level of risk that remains with the client in terms of design.
• Funding risk - ensuring funds are available to pay the contractor and
avoiding the risk of contractor insolvency.
• Commercial risk - the impact on income and profits if the new asset
(building) is not delivered to time, cost or quality.
2. CONTRACTOR RISK
For contractors, the biggest risk is around the tender stage when commitments are
made to a price and a timescale. Margins can be lost if the bill of quantities is not accurate.
Subcontractors may not stand by their quotes and work may be more expensive than
estimated if the choice of construction method turns out not to be suitable.
3. HEALTH AND SAFETY RISKS
A health and safety plan are required for all but the smallest of projects and it is an
important means of communication throughout the project.
3|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
3. GENERAL CONDITIONS
➢ This contract document will define the obligations and rights on how to execute
the project.
➢ Overhead costs, what to claim and your rights must be included in this portion
of the contract.
4. SPECIAL CONDITIONS
➢ This is usually an extension of the contract and to the general conditions.
➢ This part must specify specific conditions and clauses to each project or job.
➢ Pay special attention to specific instructions and requirements on how to
perform the work.
5. BILL OF QUANTITIES
➢ This is formed by the list of diverse trades, and materials included that form
part of the construction.
➢ Sometimes this document is not required by the contracting officer.
6. DRAWINGS
➢ All set of drawings that form part of the job to be performed.
➢ These drawings are usually the latest drawings and must be received by the
contractor prior to the date of commencement.
➢ It must include all drawings from consultants and will constitute the entire
project being contracted.
4|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
5|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
CONSTRUCTION DRAWINGS
➢ Construction drawing is the general term used for drawings that form part of the
production information that is incorporated into tender documentation and then
the contract documents for the construction works.
➢ This means they have legal significance and form part of the agreement between
the employer and the contractor.
➢ The main purpose of construction drawings is to provide a graphic representation
of what is to be built. Construction drawings should be concise and coordinated
to avoid, wherever possible, ambiguity and confusion. Delays and
misunderstandings can be minimized by properly coordinating the drawings.
➢ This document is a complete package outlining all the information needed to have
your project constructed just as you envision it. This document is used in
conjunction with outside consultants who provide information relating to
engineering requirements including:
a. Architectural
b. Structural
c. Electrical
d. Communications
e. Mechanical
All working drawings are completed with the following information:
• Key Plan or Site Plan
• Demolition Plan (if applicable)
• Furniture Plan
• Partition Plan
• Reflected Ceiling Plan
• Power/Communications/Electrical Plan
• Finishes Plan
Construction Details:
• Sections
• Elevations
• Specifications
• Door and Hardware Schedules
• General Notes and Specifications
CONSTRUCTION SPECIFICATIONS
➢ Specifications will detail the materials, standards, techniques, and so on required
to carry out the works.
➢ Construction drawings provide the graphical representation, indicating the
arrangement of components, detailing, dimensions and so on.
➢ They may sometimes contain some of the information set out in specifications, but
this should be avoided if possible, by referring to specifications rather than
duplicating information.
6|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
7|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
CONSTRUCTION CONTRACT
2. CONTRACT PRICE
➢ The type of contract price that has been awarded and the total amount of
money being contracted are detailed, as well as possible additions or
deductions to the contract and how they will be released.
3. PAYMENT BASIS
➢ This describes the money that will be paid to the contractor, whether on a
weekly, monthly, or milestone basis.
➢ This section should also specify what percentage of money should be
retained on every application for payment.
➢ It will also define when the payment is due, the penalty for late payments,
whether interest is accrued, and any other payment and invoicing terms.
4. SCHEDULE OR CALENDAR
➢ The total number of days or how the project schedule will be divided, it
should describe either calendar days or business days and can be
presented as a Gantt Chart, bar chart, CPM, or another method.
5. DOCUMENTS LIST
➢ A list of all contract documents forms this part of the contract agreement.
Drawings, exhibits, specs, and supplemental conditions can be part of this
list.
6. CONSTRUCTION SCOPE
➢ The scope normally can be measured or quantifiable and is a description of
all construction activities that will form part of the project.
8|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
8. CONTRACT LAWS
➢ Any applicable legal requirements, including governing laws, liens
requirements, claims procedures, arbitration procedures, insurance,
substantial completion requirements, final completion, and liquidated
damages are detailed.
➢ This may also include procedures for how to terminate or suspend the work
and the agreement with the contractor.
➢ Once the contract is finalized, it should be signed by both parties before any
work begins. By signing, both parties indicate that they agree to the project
terms.
➢ If either party breaks the terms of the agreement, the contract should outline
procedures for how the dispute can be addressed, including legal action.
9|Page
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
4. Unit Price
➢ requires the contractor to fix a price on each unit of work. The work,
therefore, is broken down into parts.
Advantage: This type of contract includes the flexibility in adjusting the scope and the
fact that it is not necessary to know the complete design.
Disadvantage: This type of contract includes the unknown cost to complete the entire
project and a potentially inaccurate determination by the contractor of the quantities
needed.
3. Cost-Plus Contracts
➢ used when the purchaser of an engineering project agrees to pay for the labor,
materials and an additional amount for the contractor overhead for some profit.
4. Incentive Contracts
➢ are like compensation contracts, where engineers are paid based on
performance, budget, quality, and schedule for a specific project.
10 | P a g e
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
For Periodic Report, the summarized result can be logged in one of the following periods:
• Hourly
• Daily
• Weekly
• Monthly
• Quarterly
• Yearly
11 | P a g e
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
REQUIREMENTS:
PERIODIC STATUS REPORT
➢ must be followed while preparing both a progress report and an exposure
data summary (DID). Person Task Orders may have additional reporting
provisions.
➢ The papers must be printed on 8.5 x 11-inch plain bond paper or letterhead
from the company.
➢ Multiple sites can be mentioned on the same website, but each location
must be listed separately on the form.
MONTHLY PERIODIC STATUS REPORT
➢ It should have additionally includes a Munitions Response Monthly
Progress Summary Report covering all individual Task Orders shall provide
as indicated below.
➢ The projects/task orders shall be grouped and reported by types indicating
both a work category and technology used by a Roman numeral and Arabic
letter, as best described using the following:
WORK CATEGORY
I: Surface removal only
II: Sampling effort only (detection and confirmation)
III: Geophysical mapping effort only (no confirmation)
IV: Subsurface removal
V: Construction Support
TECHNOLOGY TYPE
A. Geophysical Instrument w/analog readout
B. Geophysical Instrument w/digital recorder
C. Geophysical Instrument w/digital navigation system
D. Geophysical Instrument w/multi-sensor system
E. Visual Only
NOTE: The required column for Acres Sampled will include the total number of acres on
which all of the planned sample grids/transects have been completed (all data collected).
Do not indicate the total grid/transect area of the sample grids/transects that are
completed.
COST/SCHEDULE/PROGRESS DATA
a. Costs (for cost-type contracts/Task Orders only)
➢ In spreadsheet format, indicate total hours and funds authorized by contract
line item number (CLIN).
12 | P a g e
Technological University of the Philippines
Manila
College of Industrial Technology
Bachelor of Engineering Technology
Major in Construction Engineering Technology (BET-CT)
➢ Separate labor, materials, and travel. Indicate the Task Order modification
number (if applicable) under which the funds are authorized.
➢ For each CLIN, show the current month/week and cumulative expenditures
in both dollars and hours (for labor).
➢ Indicate balance, and percentage of total remaining for hours and dollars.
Expenditures shall be reported as accrued/incurred, and do not necessarily
have to be paid.
➢ Notes shall be used to explain pertinent facts that are not apparent within
the spreadsheet.
13 | P a g e