Professional Documents
Culture Documents
CONSTRUCTION
PROJECT INCEPTION
LESSON OUTCOMES (LO)
At the end of this module, students should be able to:
Understand and explain the works and procedures
in construction project inception:
i. Pre-Tendering Phase.
ii. Tendering Phase.
iii. Awarding of Contract.
INCEPTION PHASE DIVIDED INTO CONCEPTUAL
(PHASE 1) AND PLANNING (PHASE 2)
awang295@sarawak.uitm.edu.my
awang295@sarawak.uitm.edu.my
Associate drawings
Pre-tendering
phase
General flowchart of
Pre-Tendering Phase
Needs and Objectives of the Project
DETAIL EXPLANATION IN TOPIC 6
awang295@sarawak.uitm.edu.my
Conceptual Drawings
Based on RFP, the architect shall produce the conceptual drawings for
consultant engineers to work on detail engineering and design.
The building illustration by architect shows the overall views of the
project including elevations, views and cut-sections of the building.
Planning Execution
Planning execution includes tasks as follow:
i. Management and Coordination
ii. Design
iii. Construction
‒ Supervision
‒ Method of Construction
‒ Approval from Authorities
awang295@sarawak.uitm.edu.my
Planning Execution
Management and Coordination
A representative on behalf of Client responsible to coordinate the
activities of those engaged in the design on construction of the project
and also lies between the management.
Preferably an architect or civil engineer.
Employer decide either to delivered the project by Turnkey Contract or
Traditional Contract.
awang295@sarawak.uitm.edu.my
Planning Execution
Design
Execute based on type of Project Delivery System implemented as
follow:
– Use-in house technical team – Turnkey contract
– Employ consultants – Traditional Contract
Two main phases of engineering and design:
– Preliminary
– Detail
awang295@sarawak.uitm.edu.my
Planning Execution
Design: Preliminary Engineering and Design
Emphasize on architectural concepts, evaluation of technological process
alternatives, size and capacity decisions and comparative economic studies.
The steps evolve directly from the concept and feasibility stage, and it is
sometimes difficult to see where one leaves off and the other begins.
In heavy construction, engineers are responsible for the preliminary design,
but they often need substantial input from geologist, hydrologist, and
increasingly from ecologist and other professionals in the natural sciences.
In construction industry, it involves input and output decisions, choices
awang295@sarawak.uitm.edu.my
awang295@sarawak.uitm.edu.my
Planning Execution
Construction: Authorities Approval
Before commencement of any construction, all the design and construction
method adopted must first receive the approval from the local and federal
authorities: i.e. all designs must comply with the building-laws of the following
authorities;
Municipality / City Council.
JPBD (Jabatan Perancangan Bandar raya).
JKR (Jabatan Kerja Raya).
JBA (Jabatan Bekalan Air).
JPS (Jabatan Pengairan dan Saliran).
JAS (Jabatan Alam Sekitar).
JPP (Jabatan Perparitan dan Pembetungan) – IWK.
TNB (Tenaga Nasional Berhad).
Telekom.
Public Health Department.
Fire Fighting Department.
Factory Act for Machinery Department.
awang295@sarawak.uitm.edu.my
Feasibility Study (FS) and Site Investigation (SI)
WILL BE COVERED IN DETAIL IN TOPIC 6 ON SITE SELECTION
FS reveal on objective, business and technical point of view in order to help
Client to make decisions on planning and execution of the project.
SI is a detail investigation based on FS and emphasize more on the
economical and technical factor in order to help Client minimize the cost
within design and safety optimizations .
awang295@sarawak.uitm.edu.my
Preliminary Drawing
Initial plans for projects prepared by the designer or architects and
engineers firm during the early planning or promotional stage of the
building development.
These drawings are NOT intended to be used for construction, but they are
used for exploring design concepts, material selection, preliminary cost
estimates, approval by the customer, and as a basis for the preparation of
finished working drawings.
awang295@sarawak.uitm.edu.my
awang295@sarawak.uitm.edu.my
TENDERING PHASE
General flowchart of
Tendering Phase
awang295@sarawak.uitm.edu.my
Tender Document and Tender Drawings
TENDER DRAWINGS
Design drawing that need to be used for tendering stage and should be
attached with tender document.
Consists of architectural, structural, mechanical and sanitary, and
M&E services drawings.
TABLE TENDER DOCUMENT (TTD)
TTD is a drawing showing all particular details of layout drawing such
as type of material, sizes of structures (foundation, column, beam slab
and trusses), fitting services and etc.
Available in a paper A3 size and imprint with the words “Table Tender
Document”.
awang295@sarawak.uitm.edu.my
Contractor Considerations Bid/Not To Bid
for the tenders
Contractors need to be realistic about their ability to prepare
proposals and the probability of winning the contract.
In order to offer the client with competitive price and service, the
factors as follow shall be recognized:
Extension of Reputation
Capability
Competitiveness/
Competition
Client funds
Factors whether to bid or
not to bid for the project
Risks Proposed
Resources
Mission
awang295@sarawak.uitm.edu.my
Contractor Considerations Bid/Not To Bid
for the tenders
Competitiveness/Competition
To seek out whom are the other contractors bidding for the project.
To find out whether these contractors have a competitive advantage
through earlier projects or assignment or having affiliation with the
customer.
Risks
To identify risks on the project viability and success.
To ascertain the uncertainties and technological barrier.
To ascertain whether research and development need to be carried out
on the feasibility of the project.
Mission
To access whether the project is in line with the company business
mission and core areas.
awang295@sarawak.uitm.edu.my
Contractor Considerations Bid/Not To Bid for the tenders
Extension of Capabilities
To decide whether the proposed project will provide the contractor
with an opportunity to enhance its expertise and capabilities.
Reputation
To decide whether the organization has a good reputation and
relationships with the customer, such as established close rapport and
good successful records on past projects with the customers.
Review past documents on how many times the contractor bid for the
same organizations and was unsuccessful.
Client Funds
To find out about the clients funds and financial credibility for the
project.
Proposed Resources
To ascertain whether the contractor has the right amount and quality
of resources to bid for the project.
awang295@sarawak.uitm.edu.my
Contractor Considerations Bid/Not To Bid
for the tenders
IMPORTANT OF HAVING SITE VISIT
NO CLAIMS CAN BE MADE DUE TO ADVERSE SITE CONDITION THUS
CONTRACTORS MUST CHECK FOR THE FOLLOWING POINTS:
Access to Site
Ground
Condition Availability
of Services
Factors whether to bid or
not to bid for the project
Environment
Local Labor
Accommodation
for Staff Local Suppliers
awang295@sarawak.uitm.edu.my
Contractor Considerations Bid/Not To Bid
for the tenders
IMPORTANT OF HAVING SITE VISIT
awang295@sarawak.uitm.edu.my
Scrutiny the Tenders
After opening the tenders, the tenders should be scrutinized. Tender Report
Things that need to be checked: Structures
List of all tenders received along with detail of the Earnest The 1st report is the tabular statement of
Money (Tender Deposit). tenders which consists of:
It should be checked that the contractors duly signs every • Name of tenderer, class and status
necessary pages in Tender Document. • Tender Sum (before correction of any
The address of the contractor should be clear and complete. arithmetical error)
Verification of the contract conditions should be done. • Construction period (time of completion)
Whether the contract condition is original or alteration has
been done.
Rates are written in words as well as figure or not. Both
should be the same. When different, then the lower should be
considered. The 2nd report, same as 1st report,
The calculation and amount stated by contractor (arithmetic except for:
error) should be carefully checked. • Name of the contractor not listed
• The list of tender will be listed in
*After proper scrutiny: ascending price order
The comparative statement of all the tenders should be • The lowest tender will be at the top,
prepared the highest tender price will be at the
Signed by all persons present at the time of opening tenders bottom of the list
awang295@sarawak.uitm.edu.my
Tender Evaluation Process
Coordinated by tender committee and contract department and lead by a secretary.
Secretary responsible to coordinate all parties on date, time and place of opening
tenders.
A tender committee comprise of the technical committee that looks into the
specifications, construction method, resources and etc., while commercial committee
will looks into the price and costing aspects of the project.
Stages involve in tender evaluation are as shown below:
Financial
Standardization
Standing
EVALUATION TENDER
(Based on
awang295@sarawak.uitm.edu.my
Technical
capability Warranties
Performance
Capacity Experience
Standards
Awarding of Contract
General flowchart for awarding of contract
Awarding Phase
Recommending tenders
awang295@sarawak.uitm.edu.my
Awarding of Contract
Recommending Tenders
Open tender committee will recommend a few (say, 3) short-listed tenders, but only
one contractor will be awarded with the contract except for a mega project. The
important criteria recommendations in selecting contractor are as follow;
Financial
Background
Paid-up
Tender Sum Capital
Factors when considering
contractor for the project
Construction
Equipment Period
Technical Knowledge
& Experience
awang295@sarawak.uitm.edu.my
Awarding of Contract
Recommending Tenders
Tender Sum
Wherever possible the lowest tender sum shall be recommended. BQ in tender allow
checking the cost of each item. Some contractor will quote higher price for the early stage
job i.e: preliminaries, site clearing and foundation. As contractors are being paid as they
constructed will allow them to collect great profit margin up to sub-structure work and then
abandon the project.
Paid-Up Capital
Paid-Up Capital concern with the possibility of bankruptcy. To enable recovery from
bankruptcy is based on the assets and Paid-Up Capital. Depending on the project size,
contractor should have reasonable Paid-Up Capital to decease possibility of bankruptcy.
awang295@sarawak.uitm.edu.my
Awarding of Contract
Recommending Tenders
Construction Period
Wherever possible contractors offer the shortest construction period should be accepted,
but shortest construction period normally does not align with the tender sum and may
avoiding SOP.
Equipment
Contractor possess the equipment shall run the job better than if they were rented. Some
equipment may be hard to rent during peak season.
awang295@sarawak.uitm.edu.my
Awarding of Contract
Recommending Tenders
Other factors:
Contractor’s qualification
Construction method
Contractor’s previous project track record
Contractor’s office and site management skill
Knowledge about surrounding (environment aspects)
Integrity background
Insurance and warranty
Performance (workmanship)
awang295@sarawak.uitm.edu.my
Awarding of Contract
awang295@sarawak.uitm.edu.my
Awarding of Contract
awang295@sarawak.uitm.edu.my
awang295@sarawak.uitm.edu.my
summary
Construction project inception involve several phases
as follow:
Pre-Tender Phase
• Conceptual drawings (normally prepare by an architect)
• Preliminary drawings (various amendment)
Tendering Phase
• Tender Drawings