Professional Documents
Culture Documents
1|Page
Indian Institute of Technology-Madras
The reason for this shift in project delivery method can be attributed to that of the many advantages of
EPC contracts, namely:
Contractor is at Single point responsibility – Client need not coordinate between designers, architects
and other contractors.
Higher efficiency – Both designers and construction contractor work under the same team thus
eliminating chances of disputes.
Lower risk on Client – Contractor bears most of the risk as he holds the prime responsibility of the
project
Fast Track approach – The separate design bid and construction phases in a traditional approach can
be minimized and a lot of time can be saved if project is properly planned.
Fast track construction approach:
Completing the project as early as possible is of utmost importance to the client. The returns of the investment
on the project is solely dependent on the timely completion of the project. Clients these days do not mind
spending a little more money on the project provided that the project can be completed well ahead of schedule.
Construction primarily involves three phases namely Engineering (Design), Procurement and Construction.
The fast track construction approach aims at compressing the project timeline by overlapping the design and
construction phase, as in based on the preliminary designs and drawings the construction is executed in sites.
Engineering Engineering
Procurement Procurement
Construction Construction
2|Page