On
Instant Concrete Road Repair Solution
Submitted
In partial fulfillment for the Degree of
Bachelor of Technology
in
Civil Engineering
by
Chirag Parashar
(19EJCCE027)
Submitted To:
Dr. Krishan Kumar Saini
Head of Department
Civil Department
JAIPUR ENGINEERING COLLEGE AND RESEARCH CENTRE
RAJASTHAN TECHNICAL UNIVERSITY
DECEMEMBER 2022
CANDIDATE’S DECLARATION
I have not submitted the matter presented in this report anywhere for
the award of any degree.
Chirag parashar
(19EJCCE027)
Jaipur Engineering College & Research Centre Department of Civil Engineering
Session-2022-23
CERTIFICATE
Dated:
Chirag parashar
19EJCCE027
ABSTRACT:
U-BOOT BETON
2. MUSHROOM SLAB
Advantages compared with tradition play on cement systems those and
light weight training or fully faceted to win slabs the traditional clay cement or
polystyrene floor slabs. The traditional clay cement or polystyrene floor slabs
normally consists of mono directional beings that discharge stresses on to the
main beings from these two pillars and finally the foundations the full plate
floor slabs instead are made from monolithic reinforced concrete casts in which
the structure is able to bi directionally transmit loads directly to the by using U-
boot and lighter slab structure is obtained capable of splitting the stresses in any
direction transferring them directly to the penance to simplify the concept we
could imagine a series of double teams of alongside the other and arranged as a
premise all stresses will be concentrated close to pillars where the suitable full
section gets left in this way floor slabs with mushroom like files for the repose
in modern people specificity being that the mushroom is embedded in the floor.
MUSHROOM SLAB
the sandwich type superimposing two or more base elements allows the
implementation of load releasing elements of various heights according to the
plan things out the floor slack also the chronicle elevator feet placed at the four
corners can be of different heights determining a different distance from the
casting deck plate and as a result the different thickness of the internals
slapping the remarkable versatility and flexibility of the U-boot beton
construction system can satisfy any design the map since 2001 millions of U-
boot have been deployed in the implementation of worksin various countries
throughout the world works f various dimensions types and complexity often
born of the pencil stroke and genius of famous designers.
U-boot permits to build big spans slabs or slabs supporting high loads without
beams. Light and easy to pose, the draftsman can change the geometrical
parameters of the slab, in order to suit any kind of situation .U-boot is used in
all applications that require a plate structural solution ,along with concrete-
savings and therefore weight-savings.
5. POSING:
The U-boot system particularly fits structures that need significant open
spaces, like bureaus,industrial and commercial buildings, and civil constructions
as well. The system also allows a more irregular distribution of pillars, since
beams are not necessary
CONNECTION BRIDGE:
SPACER JOINT
7. CLOSING PLATE:
The reinforcement pose is to be completed by disposing the upper bending steel
bars in two directions, the shear and punching reinforcement, where necessary.
Due to the floating pressure exerted on U-boots, the concrete should be cast in
two different phases: the first casting has to fill a thickness equal to the feet
height
.
The final phase has to be done when the first concrete layer starts to set and
becomes semi-solid. Casting proceeds each time from the previous starting
point. While the casting proceeds, the concrete sets. Finally the casting has to be
levelled up in a traditional way (picture 6). The U-boot system execution time
will be accelerated by using new deck technologies which permit to disassemble
within 2-4 days, or using the carpet reinforcement system, in order to reduce the
steel bars posing time up to 4-6 times.
U-boot slabs do not need beams between pillars, a perimeter edge beam is
enough. The orthogonal grid of beams transfers all stresses directly on pillars;
around which it is enough to leave a massive area, called mushroom pillar,
which is thick as the slab and variable in function of shear stresses.
U-boot lightened slab scheme: the lack of connection beams between pillars
Among foundation different typologies, raft foundation is surely one of the most
known and used, considering its evident technical advantages: high stiffness due
to its static bidirectional behaviour, and thus load partition capacity on the
ground; it also permits to absorb stresses coming from the building, with
differential subsidences close to zero; easy and quick to carry out. If stresses
increase or the ground bearing capacity decreases, the structure may require a
thick raft foundation.
This means having more concrete and more pressure on the ground; and
therefore higher building costs. U-boot beton is a formwork made of recycled
polypropylene, purposely designed to build lightened plate slabs and raft
foundations. Once drowned into concrete, it creates an alveolar structure with
two slabs of different thickness, joined by an orthogonal grid of beams of
variable width, therefore building an ideal light structure for raft foundations.
Statically, it can be seen as a grid of I beams which means having a rationalized
masses distribution for the purpose of inertia, in order to get high stiffness with
a minimum quantity of concrete. This perfect combination of lightness and
stiffness permits, in particular cases, to avoid using foundation piles.
U-Boot Betonis used to create slabs with large span or that are able to
support large loads without beams. Light and quick and easy to position, thanks
to their modularity the designer can vary the geometric parameters as needed to
adapt to all situations with great architectural freedom.
9. INSTALLATION
1. The entire surface of the slab to be cast on site is shuttered with wood
deckings (or similar systems), then the lower reinforcement concrete bars are
positioned in two mutually perpendicular directions according to the design and
the lattice for the upper reinforcement concrete is arranged.
2. The U-Boot Beton® formworks are positioned using the lateral spacers joints
to place them at the desired centre distance that will determine the beam width.
Thanks to the conic elevator foot, theU-Boot Beton® formworks will be lifted
from the surface, making it possible for the lower slab to be formed. If double
or triple elements are used, these elements must first be assembled, which will
be supplied on distinct pallets in the yard.
floatation of the formworks: an initial layer will be cast to fill a thickness equal
to the height of the elevator foot. Casting will continue for this first portion of
the slab until the concrete starts to set and become semi fluid.
5. Once suitably set, the casting can be restarted from the starting point,
completely burying the U-Boot Beton. The casting is then levelled and
smoothed in a traditional manner.
AFTER COMPLETION
6. Once the structure has hardened, the formwork can be removed. The surface
is smooth in correspondence of the soffit
10. ADVANTAGES
FLEXIBLE:
Spans up to 20 m, Absence of beams between pillars, Reduction of pillars
number, Possible use with prefabricated slabs, No lifting and movement devices
required, ideal for restructuring, Possible creation of monodirectional slabs
thanks to the “bridge” accessory
ANTISEISMIC :
Reduced seismic mass, Less dimensional limitations of elements , Double
inferior and superior slab
OPEN SPACES :
More spacious rooms , Bigger architectural freedom , Easier change of use
ECONOMIC:
Less concrete incidence, thickness being equal , Less steel incidence , Usable
height saving on each floor, since avoiding beams being out of the slab
thickness enables a higher number of floors, height being equal (tower
buildings) , Rapidity and easiness of pose (unique twophased casting) ,
Possibility of big spans, load being equal , Possibility of high bearing capacity,
spans being equal , Economical transport and easy stocking, since it is
stackable, Ready to smooth once the deck is taken off, the intrados is a plane
surface which do not require false ceilings at an aesthetical level , If a false
ceiling is necessary, pose is made more rapidly
SAFE:
Significant fire resistance (certification REI 180; concrete cover 3cm) ,
Sound insulation
CONCLUSION: