Professional Documents
Culture Documents
DISCIPLINE: ARCHITECTURE
Contents
1. Purpose
2.Scope
3. References
4.Definitions
5. Responsibilities
6.Resources
7. Safety
8.Procedure
9. Attachments
The purpose of this Method Statement is to describe the HSE and quality control
Procedure to be followed during the BLOCK Works for Construction and operate phase-1 green
Riyadh nursery project.
2- SCOPE:
The scope of this Method Statement is to define all the procedures and inspections to be
followed during BLOCK WORKS on this Project, in compliance with the project specifications
and standards procedures.
3- REFERENCES:
a. Profile Survey
b. Royal Commission for Riyadh City Project requirements
c. Royal Commission for Riyadh City HSE Management Plan
d. MAG Project Quality Plan
e. Approved drawings
f. Applicable quality control documents from sub-contractor
g. ASTM-C90,ASTM-C33, ASTM-C331,ASTM-C 129,ASTM-C 270,ASTM-C150,ASTM-
C207,ASTM-C-144 & ASTM-C404,ASTM-C-476
h. Material submittal
4- DEFINITIONS:
MAG and ADVACON :Al Majal Al Arabi Group and advanced Concept of contracting
ITP : Inspection & Test Plan
PPE : Personal Protective equipment
QA/QC : Quality Assurance/Quality Control
ASTM : American Society for testing and materials
HSE : Health, Safety and Environment
RCRC : Royal commissioning for Riyadh city.
5- RESPONSIBILITIES
Ensures that the content of this method statement is understood and implemented at all
times.
Coordinate with the site engineer to ensure that the necessary resources to implement
the approved Method Statement have been allocated to the task.
Determine all the requirements needed in order to comply with safety standards and
regulations as require.
The progressing works are carried out according to the planned program and all the
equipment’s required to execute the works are available as per the project planning
and are in good condition
Co-ordinate with the Consultant, Project Manager, Site Engineer, Safety Engineer, and
sub-contractor for the safe and proper execution of the work.
5.2 QA/QC Engineer.
All inspection and testing as identified in ITP will be conducted, QC check sheets as
indicated in the ITP will be completed.
Will ensure that the site block work activities are conducted according to the approved
Method Statement and project contract documents.
Shall be responsible of the implementation of this procedure.
Will ensure that the materials being delivered and used are in accordance with the project
specifications and approved material submittal.
Shall be responsible for the inspection, preparation of all documents and compiling them
for the inclusion in the final documentation packaged.
The HSE manager is responsible for reviewing this procedure to ensure that systems of
work is in place/considered in each phase of activities.
He also has the overall responsibility of ensuring, through the safety supervisors/officers
that the works in the field are performed safely and in compliance with all applicable
quality standards stipulations and procedures of Royal Commissioning of Riyadh City.
The HSE manager reports and coordinates all HSE matters with Royal Commissioning of
Riyadh city HSE team along with the functional responsibility to the project manager.
Ensure proper welfare arrangements for all manpower and staff
Will ensure that all the activities related to the specified task are being followed safely and
all workers are wearing PPE.
Identify and take measure control the risks associated with the hazard.
Ensure that the site is maintained clean and tidy.
Inspect all the site activities and train the persons to prevent accidents and its proper
reporting to the project manager and the client.
Ensure all required documents (ITP, approved MS, RA, checklists, 3rd party certificates,
etc.) are available and up to date.
Ensure all staff and workforce involve in the job are aware about the emergency plan
Shall coordinate directly with the project/site engineer in regards to advisement of safety
issues and problems.
Report any violations to HSE manager in order to take corrective action.
Ensure that the site is maintained clean and tidy.
It will be ensured at all time that BLOCK works shall be carried out under the control of
competent works supervisor. Assigned supervisor shall have extensive experience block
works undertaken
Shall explain the Method Statement for his subordinates and responsible for executing the
works in accordance with the method statement.
To ascertain that the work is being carried out as per the instructions of site engineer and
in conformance with the approved drawings & specs.
Also to instruct workers to eliminate hazards and encourage safety actions or Initiatives.
Ensure all materials/ equipment’s to be used is available prior to start of work
Co-ordinate with the QC engineer for the tests to be carried out and initiate for the
inspection for the finished works.
Ensure that the site is maintained clean safe and tidy
5.6 Foreman
Carrying out the work and the proper distribution of all the available resources in
coordination with the site engineer on a daily basis.
Daily reports of the works achieved and coordinate for the future planning with the Site
engineer.
Incorporate all the QC and HSE requirements as requested by the concerned Engineer.
Met with any type of unforeseen incidents or requirements and reporting to the site
engineer immediately.
Reports directly to site engineer.
It will be ensured at all time that surveying works shall be carried out under the control of
competent surveyor.
To ascertain that the work is being carried out as per the instructions of site surveying
engineer and in conformance with the Plot Co-ordinate of Phase-1 green Riyadh Nursery
project provided by Royal Commissioning for Riyadh City.
Social distancing means consciously increasing the physical space between yourself and
Others.
These are measures you take to limit the spread of COVID - 19.
1. Keep at least 1 to 2 meters
2. Stay away from a sick person
3. Call MOH online services
4. Stay at home when u sick
6- RESOURCES
1) Blockwork –SANCO-GRP-07-NU002-MAG-CIV-MAT-00017
2) Block work and plaster accessories-ISAM KABBANI- GRP-07-NU002-MAG-CIV-MAT-
00014
6.5 Equipment
1) Project Engineer
2) Site Engineer
3) Foreman.
4) Charge hands
5) Land Surveyors
6) Mechanic
7) Electrician
8) Skilled labors
9) Unskilled labors
10) Vehicles & Machine Operators
7- SAFETY PRECAUTIONS:
1) Task specific safety briefing / tool box talk has been conducted by HSE dept. prior to
start of work activity.
2) Safety officer and direct supervisor will ensure that PPE are worn by site personnel
at all times during this activity.
3) Safety officer shall ensure that all workers and workplaces are safe by continuous
monitoring and providing safety instructions.
4) All personnel must adhere to the safety rules and regulations at the site.
5) Hazard identification and control measures has been implemented.
6) Only approved scaffolds should be used
7) Proper housekeeping is done on a daily basis.
8) Safety warning signs, lights and notices shall be displayed as needed on site
locations.
9) Excavations / Permits shall comply as per HSE plan.
10) It will be ensured that the equipment used at site shall be maintained and relevant
certification (including operator training certification and / or licenses) shall be
Submitted.
11) Housekeeping shall be given prime importance and carried out on a regular basis.
Prevention of entry by personnel into restricted areas, and a high regard for the
environment and natural resources shall be adhered to at all times
12) Experienced banksman will be assigned for machinery operation.
8- PROCEDURES / METHOD
9. ATTACHMENTS:
HERA
ITP
CHECK LIST
Contractor Signature:
Discipline Engineer: QA/ QC HSE MEP Project Manager:
MAG
The Engineer:
A- Approved B- Approved with Comments C- Revise and Resubmit
D- Rejected
Comments:
Distribution:
Client Engineer Contractor
Client: Consultant: Contractor: Form No. 3-QC-03.0
Page 1
Form No: 3-QC-35.0 CLIENT: CONSULTANT: CONTRACTOR:
Page 1 of 1
Contractor: Project Management Consultant Client: Royal Commission for Riyadh City
Al Majal Al Arabi Group Company Dorsch holding GmbH KSA
(MAG) and ADVACON Consortium
DISCIPLINE: CIVIL
RISK ASSESMENT MATRIX CONTROL
SHEET
PROJECT: CONSTRUCTION AND OPERATE PHASE-1 GREEN RIYADH NURSERY, RCRC, KSA
RISK ASSESSMENT
ACTIVITY: CMU Block/Plaster work Ref: HIRA/ME/00
RISK RESIDUAL RISK
CONTROL MEASURES
SN. HAZARD HARM/HAZARD LX
LXS L M H L M H
S
MAG will Implement permit-to-work system
4
9M for activity to be carried out,
L
Task will be briefed by MAG supervisor and
Dust Exposure
record will be maintained.
Site / work Slip, Trip
Limit the working time of the workers
1 preparation Defective Equipment or 3x3
exposed to adverse environmental condition.
Supervisor
Machinery
Site staff and workers must be competent to
High speed vehicles
execute the job.
Site traffic speed limit must be followed
Site access routes must be clearly defined.
Allocate adequate resources
(personnel and equipment) for
continuous housekeeping.
Train employees on housekeeping.
Ensure an appropriate housekeeping
level at all times. 4L
2 Poor Fire Ensure instant and regular waste Supervisor
Housekeeping Slips/Trips/Falls 3x4 12M removal from site.
Ill-health Provide proper welfare facilities such
Environmental Pollution as toilets, rest area, hand wash, and
drinking water to the employees.
Maintain an adequate housekeeping
12PROJECT: CONSTRUCTION AND OPERATE PHASE-1 GREEN RIYADH NURSERY, RCRC, KSA
PROJECT: CONSTRUCTION AND OPERATE PHASE-1 GREEN RIYADH NURSERY, RCRC, KSA
PROJECT: CONSTRUCTION AND OPERATE PHASE-1 GREEN RIYADH NURSERY, RCRC, KSA
emergency
Proper transportation, use, handling and
disposal of hazardous substances
Uncontrolled waste (spill/contamination) must be observed
generation & strictly
improper handling Ensure Proper dust suppression method
&Disposal Leaks / and determine the frequency of work to
Environmental spills of hazardous be done by water tankers 2
1 3x4 12 Supervisor
Hazards (Air, liquid Declare the whole site as “No Burning” L
2 M
Ground, Water, dust zone for all types of waste materials
Dust, Noise) suppression Ensure engineering / Administrative
measures Air controls for operatives working around
Pollution noisy areas / machines above the
Ill-health workplace exposure limit for 8 hour
work.
ASSESSED SHEIK MOHAMMED BIN SALAM
REV. 0
BY(NAME): SIGNATURE:
No: 0
REVIEWED
REV.
BY(NAME):
SIGNATURE: DATE:
APPROVED
BY(NAME):
SIGNATURE: