Signature &
Date
Client
Description Reviewed By Approval By Stamp
Name
Designation
Signature &
Date
The scope of the work is to make a proper barrier for the building from termite
attack by doing Anti-termite Treatment (vertically and horizontally) with the use
of approved Anti-termite Material for proposed warehouse facilities at duqm for
M/s Port of Duqm company S.A.O.C.
.References:
RESOURCES:
2
J213-MS for Antitermite Treatment
A) MATERIALS
IMIDACLOPRID 30.5% SC
Potable water
Water tank
List of Machineries:
Hose with Spray Nozzle
Pump Spray machine
Wheel barrow
Hand tools
Safety equipment’s ( Face Mask, Hand glows, Safety goggle etc.,)
B)MANPOWER
Responsibilities:
A) PROJECT MANAGER
Overall responsibility for all activities.
The management and coordination of project specification of CIVIL & MEP
and associated technical data, obtaining necessary approvals and ensuring
the distribution and availability of required in formats, documents where it
is needed.
Selection, sourcing and scheduling of all materials, obtaining necessary
approvals to procure and ensure availability of materials at site within the
planned time frame.
Monitoring of project in terms of cost and time, liaison with the client, and
obtaining approvals where ever necessary to reallocate or provide
additional resources.
Preparation of working program in terms of labor, plant / machineries and
time allocated.
3
J213-MS for Antitermite Treatment
B) CONSTRUCTION MANAGER
Assess manpower equipment and other resources required to achieve
milestone / target dates pertaining to their respective areas and inform
project manager team
Coordinate with sub ordinate staff and execute the work as per planned
schedules in conformance with applicable specifications.
Shall ensure that all activity are carried out as per the lay down procedures
Arrange the required Materials on time to site
Coordinate with Head office for required Manpower and Machinery
arrangements
C) PROJECT/SITE ENGINEER
D) QA/QC ENGINEER
Prepare and get approval of the Method statement based on spec and
drawing requirements
Approved Method Statement procedure communicate to Engineers and
training to be given the procedure to be followed.
Raised Inspection to be checked at site and make readiness to carryout
Consultant inspection.
Any consultant Comments /Rejection to be communicate to Execution
team and Get approval for Re inspection.
Responsible for maintenance of all records and other inspection testing
documents
E) SAFETY ENGINEER
4
J213-MS for Antitermite Treatment
Responsible to visit site frequently and inspect the construction activities,
equipment, and facilities to determine HSE compliance.
Responsible for productive equipment if any illness happen at the time of
waterproofing on site
Toolbox talk is conducted prior to the start of the work in accordance of
procedure.
Maintaining all HSE records updated and in traceable manner.
Conducting on the job training to the workers on safe work equipment at
site.
Proper lighting arrangements shall be provided & checked periodically.
Timely report incidents/accidents to the project manager.
F) S/C TECHNICIAN
Ensure the Chemical Mixing and application as per approved Procedure
Apply the chemical to meet the requirement of area to be applied.
Ensure the Safety requirements are fullfiled to self and surrounding
workers.
Proper Inspection and Worksheet Sign off From Engineer.
WORK PROCEDURE
A) Preliminary Activities
The area of Anti termite treatment to be highlighted in RFI and get
approved by Engineer prior to start the work.
The work will be properly coordinate with the approved Anti-termite
contractor on how the process will be done as per the project
specifications.
Coordinate and confirmation of people site access and the water source
accessibility on site.
B) Preconstruction Activities
The soil shall be leveled and compacted if in case bottom of the blinding
before treatment should start.
All construction related tests shall be approved by the Engineer prior to
treatment.
C) Construction Activities
5
J213-MS for Antitermite Treatment
The tank to use the Mixed Chemical and water to be clean condition from
the approved anti-termite contractor.
The ratio of mixing of water is 400 litre of water per 1 litre of
IMIDACLOPRID.30.5% SC
Chemical will only be mixed on as needed basis, with the quantities being
mixed sufficient for filling the pump.
Approved anti-termite contractor’s staff mixing chemical shall fitted with
PPE which includes safety shoes, fluorescent vest, company cover all, hard
hat, long rubber gloves, mouth and nose mask, and safety goggles.
Approved anti-termite contractor staff will apply the anti-termite chemicals
using high pressure guns and wands. The guns will be focused downward
prior to release of the chemical agent.
Application will be done with the spray oriented in a down-wind direction.
After anti-termite treatment done concrete should be poured over the
1000 gauge polythene sheet within 24 hours of chemical applied.
As a general precaution chemically treated areas should not be treated
upon barefooted nor disturbed by any mechanical means, such as re
levelling, digging or earth filling as this will break the chemical barrier. In
case such situation arises, the area has to be treated again to restore the
chemical barrier.
Application on Different area of structure as per the Manufacturer written
Method Statement as attached.
6
J213-MS for Antitermite Treatment