Professional Documents
Culture Documents
PROPOSAL ESTIMATING
Based on a conceptual design and design
study specification
APPROVED ESTIMATING
Proposal estimates was modified due to client’s
view
PRE-TENDER ESTIMATING
A refinement of the approved estimates based
on the definitive design work using the
information provided in the tender documents
At this stage the estimator should reflect the
total capital cost of the project and all the
charges and fees and allowances or
contingency for the clients risk
POST CONTRACT ESTIMATING
A further refinement of the pre tender
estimates
ACHIEVED COST
Actual cost of the job in order to review
performance and provide data for
future project
The five common estimating techniques are
summarized as follows
Global – a simple estimating techniques
which based on existence of data from
similar project
Factorial - a technique used widely on
process plants where the key components
can be easily identified and priced and all
other works are calculated as factors of
these components
Man hour – works is estimated in total man
hours and cost in conjunction with plant
and material costs
Unit rate - based on bill of quantities, where
the quantities if work are defined and
measured in accordance with standard
method of measurement
Operational - based on all the constituents
operations necessary to construct the work
and estimating the labour, plant and
material cost together with the overheads
The price of an item of work is made up of
the following components:
Solution:
Total labour time involved=1.5 hrs + 1.5 hrs=3.0 hrs
1 day = 8 hours working
Given, labour cost = RM 50 per day
= RM 50/8 hrs
= RM 6.25 per hour
Data given:
Labour time involved in excavating 1 m³ of soft soil = 8.0 hrs
Labour time involved in cart-away 1 m³ of soft soil = 2.0 hrs
Solution:
Total labour time involved = 8.0 hrs + 2.0 hrs = 10.0 hrs
1 day = 8 hours working
Given, labour cost = RM 60 per day
= RM 60/8 hrs
= RM 7.5 per hour
Data given:
Solution:
1m³ of H/C delivered to site = RM20.00
Cost of 1 m2 of 0.2 m thick H/C – RM20 x 1 x 1 x 0.2 = RM4.00
Allowing for 20% consolidation – RM4 x (20/100) = RM0.80
Total material cost for 1 m2 of H/C = RM4.80
Cement = RM 15/bag
Sand = RM 8/m³
Aggregate = RM 20/m³
Skilled labour = RM 50/person/day
Unskilled labour = RM 20/person/day
Diesel = RM 2.00/liter
Lubricating oil = RM 10.00/liter
10/7 Mixer :
- Cost of mixer = RM 15,000.00
- Interest rate = 10% per annum
- Installment period = 5 years
- Life span of mixer = 5 years
Assume repair & maintenance = 2% per years
Assume cost of transportation to site = 1% per year
Assume mixer can work = 200 days/year & 8 hours/ day
Allow = 15% profit margin
Allow = 50% shrinkage for concrete(7m³ of 1:2:4 mat)
Output of mixer per hour = 2.5 m³/hour
= RM 144.50
Therefore, cost 1 m2 of 0.25 m thick concrete slab of 1:2:4 mix inclusive 15% profit margin
= [ RM 144.5 x 1 m x 1 m x 0.25 m ]
= RM 36.20
Compute the cost of 1 m2 of half (1/2) brick wall
based on the data given below:
DATA:
Cost of engineering brick RM0.80
Size Brick 215mm x 65mm
Bed & Joint thickness 10mm
Unskilled labour RM50.00
Skilled labour RM100.00
Cement RM15/bag
Sand RM10/m3
Cost of mixing 1 m3 mortar RM23.20
Allow 15% profit
Any
Thank You… Questions????