Procurement Status

Cut off: 28-Sep-21


Project Completion Date 30-Apr-22
MCCH - Mainwali Actual % Complete
Lead Time
Forecasted Finish
(Months)

Biomedical Procurement 4% 13-Jul-22 (1.77)

Package-1 Medical Gas Pipeline System 26% 24-Mar-22 0.90

Package-2 CSSD Equipment 31% 18-Mar-22 1.03

Package-3 Laundry Equipment 46% 01-Mar-22 1.47

Package-4 Radiology Equipment 46% 01-Mar-22 1.47

Package-5 Anaesthesia 13% 11-May-22 (0.27)

Package-6 OT Tables 0% 07-Jun-22 (0.90)

Package-7 Electrosugrical 0% 06-Jun-22 (0.87)

Package-8 Defibrillators 0% 07-Jun-22 (0.90)

Package-9 ECG Machines 0% 07-Jun-22 (0.90)

Package-10 Monitoring 6% 13-Jul-22 (1.77)

Package-11 ICU Ventilators 6% 13-Jul-22 (1.77)

Package-12 Medical Furniture (Imported) 6% 13-Jul-22 (1.77)

Package-13 OT Equipment 0% 06-Jun-22 (0.87)

Package-14 Suction Machines 0% 07-Jun-22 (0.90)

Package-15 Ambulance 0% 20-Jun-22 (1.20)

Package-16 BiPAP 0% 20-Jun-22 (1.20)

Package-17 General Equipment (Nursing School) 0% 20-Jun-22 (1.20)

Package-18 Simulators & Manikin 0% 20-Jun-22 (1.20)

Package- 19 Dental 0% 06-Jun-22 (0.87)

Package- 20 Endoscopy (Flexible) 0% 20-Jun-22 (1.20)

Package-21 Endoscopy (Rigid) 0% 20-Jun-22 (1.20)

Package-22 Gynae Equipment 0% 20-Jun-22 (1.20)

Package-23 ICU Equipment 0% 06-Jun-22 (0.87)

Package-24 Laboratory (Blood Bank) 0% 20-Jun-22 (1.20)

Package-25 Laboratory (Centrifuges) 0% 20-Jun-22 (1.20)

Package-26 Laboratory (Chemical Pathology) 0% 20-Jun-22 (1.20)

Package-27 Laboratory (Chemistry) 0% 20-Jun-22 (1.20)

Package-28 Laboratory (General Items) 0% 20-Jun-22 (1.20)

Package-29 Laboratory (Hematology) 0% 20-Jun-22 (1.20)

Package-30 Laboratory (Histopathology) 0% 20-Jun-22 (1.20)

Package-31 Laboratory (Microbiology) 0% 20-Jun-22 (1.20)

Package-32 Laboratory (Microscopes) 0% 20-Jun-22 (1.20)

Package-33 Morutary 0% 20-Jun-22 (1.20)

Package-34 Neonatal Equipment 0% 20-Jun-22 (1.20)

Package-35 Operating Microscope 0% 20-Jun-22 (1.20)

Package-36 Physiotherapy 0% 20-Jun-22 (1.20)

Package-37 Refrigeration (Imported) 0% 20-Jun-22 (1.20)

Package-38 Kitchen 0% 06-Jun-22 (0.87)

Package-39 General Medical Equipment 0% 20-Jun-22 (1.20)

Package-40 Biomedical Workshop Equipment 0% 20-Jun-22 (1.20)

Package-41 Medical Furniture (Local) 0% 20-Jun-22 (1.20)

Package-42 Holloware 0% 20-Jun-22 (1.20)

Package-43 Refrigeration (Local) 0% 20-Jun-22 (1.20)

Package-44 Waste Management 0% 20-Jun-22 (1.20)

Package-45 Instruments 0% 20-Jun-22 (1.20)

Package-46 General Furniture (P&D) 0% 20-Jun-22 (1.20)

Package-47 General Items (P&D) 0% 20-Jun-22 (1.20)

Package-48 IT 0% 20-Jun-22 (1.20)