Professional Documents
Culture Documents
Capital Budgeting
CAPITAL BUDGETING
Capital Budgeting: The total process of generating, evaluating, selecting and following
up on capital expenditure alternatives.
Capital Expenditure: An outlay made by a firm for a fixed or an intangible asset from
which benefits are expected to be received over a period greater than a year.
Independent Projects: Capital expenditure alternatives that compete with each other, but
in such a way that the acceptance of one project does not eliminate the other projects
from further consideration.
Mutually Exclusive Projects: A group of capital budgeting projects that compete with
one another in such a way that the acceptance of one eliminates all other in the group
from further consideration.
Ranking Approach: Evaluating the relative attractiveness of capital projects on the basis
of some predetermined criterion.
Present Value: The value of a future sum or stream of dollars discounted at a specified
rate. The process of finding present value is actually the inverse of the compounding
process.
Future value: The value of a single sum or an annuity compounded at a given interest
rate for a specified time period.
4. Risky Investment.
1. Accept-Reject Decision
2. Mutually Exclusive Projects Decision
5. Expansion of business
5. Dsicounting rate
6. Techniques of evaluation
*Average investment
= Original Investment – Salvage value + Salvage value
2
PBP = Investment
Cash flow after tax
PBP = A + NCO - C
D
Where, A = Year in which the accumulated cash flows are nearer to NCO
NCO = Net Cash Outlay
C = Accumulated cash outlay of the year ‘A’
D = Cash flow of the succeeding year of the year ‘A’
Formula : NPV
n CFt Sn Wn
NPV = t 1 t
COo
(1 K ) (1 K )n
n CFt
Or, NPV = t 1 COo
(1 K ) t
Or, NPV = PV of NCB – PV of NCO
Here,
NPV = Net Present Value
CFt= Cash flow at different time period.
Sn= Salvage value at N year.
Wn= Working capital structure
Coo= Initial cash out flow
K = Cost of capital.
n CFt Sn Wn n COt
NPV = t 1 t 1
(1 K ) t (1 K ) n (1 K ) t
Or, NPV = PV of NCB – PV of NCO
Here,
Cot= Cash out flow at different times.
FORMULA : IRR
IRR = A + × (B-A)
Where, IRR = Internal Rate of Return
A = Lower Discount Rate.
B = Higher Discount Rate.
C = NPV of Lower Discount Rate.
D = NPV of Higher Discount Rate
ILLUSTRATION (NPV)
ABC co. has two projects for consideration
If the tax rate is 40% and the discount rate is 12%, which of the two projects will be
accepted ?
SOLUTION:
Depreciation = = = 9,000.
Year CFBT Dep. EBT Tax 40% EAT CFAT Factor 12% PV
1 10,000 9,000 1,000 400 600 9,600 .892 8,563
2 15,000 9,000 6,000 2,400 3,600 12,600 .797 10,042
3 12,000 9,000 3,000 1,200 1,800 10,800 .712 7,690
4 20,000 9,000 11,000 4,400 6,600 15,600 .635 9,906
5 10,000 9,000 1,000 400 600 9,600 .567 5,443
S.V 5,000 --- 5,000 --- 5,000 5,000 .567 2,835
44,479
Depreciation = = 9,500
Year CFBT Dep. EBT Tax 40% EAT CFAT Factor 12% PV
1 12,000 9,500 2,500 1,000 1,500 11,000 .892 9,812
2 10,000 9,500 500 200 300 9,800 .797 7,811
3 15,000 9,500 5,500 2,200 3,300 12,800 .712 9,101
4 25,000 9,500 15,500 15,500 9,300 18,800 .635 11,938
5 9,500 9,500 0 0 0 9,500 .567 5,387
44,049
FORMULA : IRR
IRR = A + × (B-A)
Where, IRR = Internal Rate of Return
A = Lower Discount Rate.
B = Higher Discount Rate.
C = NPV of Lower Discount Rate.
D = NPV of Higher Discount Rate
ILLUSTRATION: (IRR)
The cost of a 3 year project is estimated as tk. 20,000. The estimated inflows for three
years have been estimated as tk. 8,000 per year. If the cost of capital is 7% whether
investment in the project is worthy or not?
Calculation of IRR
Year CFAT Factor 7% PV Factor 10% PV
1-3 8,000 2,624 20,992 2,486 19,888
Less : NCO 20,000 20,000
992 -112
IRR = A + × (B-A)
= 7% + (10-7)%
= 7% + × 3%
= 7% + 2.695%
= 9.695%
Nishat Enterprise wants to buy a machine costing tk. 1,50,000 for an expected life of
5 years. The projected net profit after tax is follows:
Years Net Profit After Tax
1 Tk. 20,000
2 Tk. 18,000
3 Tk. 15,000
4 Tk.17,000
5 Tk. 15,000
Illustration 2 : NPV