Professional Documents
Culture Documents
150
F.F.L F.F.L GENERAL DETAILS :
300 N.G.L 300 N.G.L
#8 @ 175c/c [H]
#10 @ 200c/c [V]
#8 @ 175c/c [H]
#10 @ 200c/c [V]
#8 @ 175c/c [H]
#10 @ 200c/c [V]
#8 @ 175c/c [H]
#10 @ 200c/c [V]
#8 @ 175c/c [H]
#10 @ 200c/c [V]
N S #8 @ 175c/c [H]
#10 @ 200c/c [V]
2250
2250
O
1. ALL DRAWING SHOULD BE READ ALONG WITH THE ARCHITECTURAL
500
HAUNCH [230x230]
500
T I 500 DRAWINGS.
A
#8 @ 150c/c
#8 @ 150c/c #10 @ 200c/c #10 @ 200c/c 2. GRADE OF CONCRETE MIX SHALL BE M 20 (1: 112 :3) CONFORMING TO
bothways bothways
500
500
200
200
bothways
#10 @ 200c/c
bothways
#10 @ 200c/c
5440
Section - AB
P.c.c.
S
P.c.c.I 6640
Section - EF
STRICTLY CONFIRM TO I.S.456 - 2000.
4. REINFORCEMENT SHALL BE Fe 500 CONFORMING TO I.S.1786-1985.
Z - FOR FOOTING 50 MM
150
300
100
2250
MAINTAINED IN THE POSITION SHOWN IN THE DRAWING
500 500
#10 @ 200c/c (CROSS SECTION) BY PROVING PROPER COVER
bothways
BLOCKS, SPACERS AND SUPPORTING BARS.
500
7. THE COVER BLOCKS SHOULD BE PREPARED BY M20 CONCRETE MIX.
200
bothways
4440 6640
#10 @ 200c/c
T
P.c.c.
Section - CD
L
8. QUALITY & QUANTITY OF CONSTRUCTION IS SUPERVISED
1250 2500
V
9. ALL DIMENSION ARE IN " mm & m " UNLESS OTHERWISE SPECIFIED.
D
230
F
230 230
#16 - 2 x 8set #16 - 2 x 8set #16 - 2 x 8set #16 - 2 x 8set
S P
230
500
0.15L
750 750
E M
1000
0.3L
T
0.15L
0.3L
A
230
#10 @ 150c/c
Y S #10 @ 150c/c
0.3L
MEE Main Feed Water Tank
S
2500 x 4100 x 2450+100FB 0.15L 0.15L 0.15L 0.15L
1250 x 3950 x 2450+100FB
O
#10 @ 150c/c 0.3L 0.3L 0.3L 0.3L
Condensate Water Tank
5640
A B #8 @ 175c/c #8 @ 175c/c
R
#10 @ 150c/c
(UG Tank)
I
3950
V
0.3L
E N REV REV
0.15L
0.3L
NO DATE
ADFD Feed Water Tank #10 @ 150c/c #10 @ 150c/c
750
N
CLIENT LUCAS TVS LIMITED
2500 x 850 x 2450+100FB #10 @ 150c/c
I
0.15L
750
230
PROJECT
E
#16 - 2 x 8set
JOB.NO CES/MILT/244/06-2021
H
C
E
C
[Bottom Layer] [Top Layer]
PLAN SYSTEM DOUBLE EFFECT FORCED EVAPORATOR WITH ATFD
R0 NTS 23.08.2021
SK SK NP PG PG BS
REV SCALE DATE DRAWN BY GEN. BY REVWD. BY APPD. BY ISSUED. BY