LAPORAN

PROGRESS HARIAN SEKSI 3A


DK 82 S/D DK 88
UPDATE TGL 30 APRIL 2021
VOLUME RENCANA VOLUME REALISASI
NO URAIAN PEKERJAAN LOKASI DK HARGA SATUAN 3 3

M TITIK JUMLAH HARGA M TITIK JUMLAH HARGA
1 Borrow Material AB Subgrade #29 82 Rp 336,615 100 - Rp 33,661,500 - - - Tunggu Pend. Material
2 Trapezoidal Ditch Subgrade #29 82 Rp 2,385,707 5 - Rp 11,928,536 - - - Cont. Install Rebar & F/W
3 GCS 3% Cemented Subgrade #29 82 Rp 417,000 105 - Rp 43,785,000 - - - Cont. Layering Testing
4 Borrow Material AB Subgrade #30A 83 Rp 336,615 95 - Rp 31,978,425 - - - Tunggu Pend. Material
5 PC CFG Subgrade #30B 83 Rp 1,721,471 5 10 Rp 17,214,713 13 20 Rp 34,429,427
6 Slope Protection Subgrade #30B 83 Rp 1,850,766 10.5 - Rp 19,433,043 31 - Rp 57,373,746
7 PC CFG Subgrade #32A 85 Rp 1,721,471 5 10 Rp 17,214,713 - - - Cont. Gali Plattofrm
8 CFG Subgrade #32A 85 Rp 5,381,542 10 20 Rp 107,630,840 24 7 Rp 37,670,794
9 Slope Protection Subgrade #32A 85 Rp 1,850,766 10.5 - Rp 19,433,043 24 - Rp 44,418,384
10 Well Graded Gravel Subgrade #32A 85 Rp 377,958 95 - Rp 35,906,010 93.4 - Rp 35,301,277
11 Slope Protection Subgrade #33B 87 Rp 1,850,766 10.5 - Rp 19,433,043 - - - Cont. Install F/W
12 Secant Pile RW Box Traffic BP21 Subgrade #33B 87 Rp 95,166,297 30 1 Rp 95,166,297 30 1 Rp 95,166,297
13 Borrow Material AB Subgrade #33B 87 Rp 336,615 95 - Rp 31,978,425 - - - Cont. Layering Testing
14 Bored Pile RW BP49 (Sisi Kiri) Subgrade #34 88 Rp 95,166,297 55 1 Rp 95,166,297 57 1 Rp 95,166,297
JUMLAH TOTAL 341.5 42 Rp 579,929,886 179 29 Rp 399,526,222
RENCANA TARGET PRODUKSI PERIODE BULAN APRIL 2021 Rp 22,572,775,180 100%
KUMULATIF REALISASI S/D SAAT INI Rp 11,103,992,145 49.192%
DEVIASI Rp 11,468,783,035 50.808%

LAPORAN CUACA
00.00 - 06.00 = CERAH
08.00 - 12.00 = CERAH
12.00 - 14.00 = CERAH
14.00 - 16.00 = HUJAN
16.00 - 18.00 = HUJAN
18.00 - 21.00 = HUJAN RINGAN
21.00 - 24.00 = CERAH