LAPORAN

PROGRESS HARIAN SEKSI 3A


DK 82 S/D DK 88
UPDATE TGL 24 MEI 2021
VOLUME RENCANA VOLUME REALISASI
NO URAIAN PEKERJAAN LOKASI DK HARGA SATUAN 3 3

M TITIK JUMLAH HARGA M TITIK JUMLAH HARGA
1 GCS 3% Cemented Subgrade #29 82 Rp 417,000 105 - Rp 43,785,000 - - - Cont. Persiapan Layering
2 Trapezoidal Ditch Subgrade #29 82 Rp 2,385,707 5 - Rp 11,928,536 - - - Cont. Install Rebar & F/W
3 Borrow Material AB Subgrade #29 82 Rp 336,615 300 - Rp 100,984,500 289 - Rp 97,281,735
4 Borrow Material AB Subgrade #30A 83 Rp 336,615 95 - Rp 31,978,425 - - - Cont Pemadatan
5 PC CFG Subgrade #30B 83 Rp 1,721,471 5 2 Rp 3,442,943 - - - Cont. Install Rebar & F/W
6 Gali Buang Subgrade #30C 84 Rp 20,820 1000 - Rp 20,820,000 - - - Standby
7 Trapezoidal Ditch Subgrade #32A 85 Rp 2,385,707 5 - Rp 11,928,536 - - - Cont. Rebar
8 Borrow Material C Subgrade #32A 85 Rp 235,814 300 - Rp 70,744,200 180 - Rp 42,446,520
9 Footing Gravity RW Subgrade #32B 86 Rp 1,344,662 9 - Rp 12,101,958 - - -
10 Dinding BPRW Subgrade #33B 87 - 15 - - 15 - -
11 Capping Beam BPRW Subgrade #33B 87 - 9 - - 9 - - Seg. 3 Kiri 87+950
12 Borrow Material AB Subgrade #33B 87 Rp 336,615 95 - Rp 31,978,425 - - - Cont. Pemadatan
13 PC CFG Subgrade #33B 87 Rp 1,721,471 5 2 Rp 3,442,943 - - - Cont. Install Rebar & F/W
14 Slope Protection Subgrade #33B 87 Rp 1,850,766 10.5 - Rp 19,433,043 21 - Rp 38,866,086
15 Bored Pile RW BP37 (Sisi Kiri) Subgrade #34 88 Rp 95,166,297 55 1 Rp 95,166,297 57 1 Rp 95,166,297
. 523.5 5 Rp 457,734,806 78 1 Rp 273,760,638
RENCANA TARGET PRODUKSI PERIODE BULAN MEI 2021 Rp 18,405,445,450 100%
KUMULATIF REALISASI S/D SAAT INI Rp 5,904,040,797 32.078%
DEVIASI Rp 12,501,404,653 67.922%

LAPORAN CUACA
00.00 - 06.00 = CERAH
08.00 - 12.00 = CERAH
12.00 - 14.00 = CERAH
14.00 - 16.00 = CERAH
16.00 - 18.00 = HUJAN
18.00 - 21.00 = HUJAN
21.00 - 24.00 = HUJAN