Professional Documents
Culture Documents
An incident occurred relating to the failure of a cooling water circulating pump f or one of the two
ammonia plants with the capacity of1,350 MT/d in KRIBHCO. Since March 1986, its startup in the
plant had consistently performed well at the capacity of over 110% until the incident of February
1992.
T
here are eight cooling water recirculating
pumps for KRIBHCO's ammonia plants, out of noise started coming from the gearbox, and the pump
which six turbine-driven ones have been in rotor bearing temperature was quite high at 77°C as
continuous service since 1986 without any problem. opposed to the normal temperature of 55°C. The plant
The design specification of the pumps are provided in operator promptly reported the matter to Mechanical
Table 1. Maintenance, which advised continued running of the
pump following a checkup of the pump while running.
Failure of Pump and Gearbox Two days later, the pump was stopped at 9:15 a.m. to
attend to the tachometer which was not showing cor-
One of the turbine-driven pumps (No. 2101-JB-2) rect rpm. The pump was restarted the same day at 4:30
intended for circulating cooling water to the p.m. and was put on full load at 5:10 p.m. at 5,700
Ammonia plant II broke down on March 20, 1992. rpm under the abnormal sound condition which was
The pump was in continuous operation until February not considered serious. At 6:00 p.m., however, a low
20, 1992 when it was stopped for overhauling of the cooling water pressure alarm appeared in the
turbine by vendor specialist, M/S. Triveni Ammonia Plant-II Control Room which promptly
Engineering, under a preventive maintenance program informed the cooling tower area field operator. Almost
which included inspection of the turbine rotor, gear simultaneously, a low C.W. pressure alarm appeared in
box, bearings, main and auxiliary oil pumps, and trip the cooling water tower field panel. The operator and
devices. shift engineer who immediately rushed to the pump
The overhauling of turbine was carried out from found that the gearbox and the pump bearing housings
Efficiency: 90%
KW Absorbed: 620
Manufacturer of the Drive Turbine: M/S. Triveni Eng. The pump and gearbox were dismantled on March
Works, India 22 and several parts were found damaged.
Figure 5b. Completely womoiit portion of pinion teeth gearbox bearing and other parts.
During the reassembly of gearbox and turbine, the The following measures have been incorporated to
overspeed trip device was found defective. The worn- further improve the built-in safety of the pump:
out drive wheel on the Woodward governor was also (1) A single channel vibration monitor with an alarm
replaced. The governor was tested before assembly. strip and a velocity sensor, made by IRD mechanaly-
The test run for turbine was done independently for sis, was installed to measure and monitor the vibration
the overspeed trip. of the turbine.
(2) A thrust wear trip supplied by Triveni
Sequence of Events Leading To Failure Engineering Works was installed in a turbine consist-
ing of a nozzle, a nozzleblock, a thrust wear trip relay,
From the investigation results, it is seen that the a pressure gauge, and a pressure switch. This system
pump shaft was of proper design and there was no trips the turbine at a high thrust. The thrust is sensed in
material abnormality. The failure most likely occurred terms of oil backpressure as shown in Figures 9a and
due to malfunction of the overspeed trip device and 9b. The pressure switch is used as an alarm of back-
governor of the turbine. After overhauling of the tur- pressure of oil before tripping the turbine, i.e., the
bine, the pump was restarted on March 13, 1992 but alarm is set at 2.0 kg/cm* and trip relay actuators are
five days later abnormal sound was noticed from the set at 2.6 kg/cm* of oil backpressure.
gearbox. Also, the tachometer was not indicating prop- (3) The constant level oiler tube was increased from
er speed. 1/4 in. (6.35 mm) to 3/8 in. (9.53 mm) size to avoid
It may be inferred that abnormal sound from the chances of clogging.
gearbox was due to running of the unit at a higher (4) The level of vigilance by field operator has been
speed than normal. It is likely that due to operation at further improved.
higher speed for about two days during which time (5) After every major overhauling of the turbine, it
the turbine was stopped for checking and recalibration has become mandatory to run an overspeed trip test
l —'AlUMJ
COHT4CT l
REF. DESCRIPTION
TUBBIHE COVH. EH1> BRG.
ÏUBBDIB EXHAUST EHP HBO.
PINION SHAFT* BBCk VJS3SSX END.
ronoN SHAFT BBC. ALTESHATOK BID.
GEAE WHKB. SHUT BHQ. TUHBWB BID.
O&IH 1BQBEL SHAfT BRQ. AI3KBN£lYffi £ND.
ILiraOUIDR BBC. DBIVXH BID.
U.TXBMUOR BBS. IK» DSOVHC DB).
VffiRATION MONTTER
DISC