Professional Documents
Culture Documents
COURSEWORK 01
1(a) State the two main aims of setting out and briefly describe the three basic principles on
which setting out operations should be based in order that these aims can be achieved.
Answer,
1. Once setting out begins it must proceed quickly with little or no delay in order that the works
can proceed smoothly and the cost can be minimized. It must always be remembered that the
contractor’s main commercial purpose is to make a profit – therefore setting out needs to be done
efficiently.
2. The various elements of the scheme must be correct in all three dimensions both relatively
and absolutely, that is each must be its correct size, in its correct plan position and correct
reduced level
The three basic principles on which setting out operations should be based in order that above
aims can be achieved are,
Points of known position must be established within or near the site from which the
design points can be set out in their correct plan positions. This involves horizontal
control techniques.
Points of known elevation relative to an agreed datum are required within or near the site
from which the design points can be set out at their correct reduced levels which involves
vertical control technique
Accurate methods must be adopted to establish design points from the horizontal and
vertical control which involves positioning techniques.
(b) Discuss the various different types of plans and drawings that may be required when
undertaking setting out operations.
The various different types of plans and drawings that may be required when undertaking setting
out operations are as bellow,
Architectural plan which consists of plan layouts of the building at different levels,
sectionals elevations with vertical reference levels and all of these drawings are drawn to
scale to be installed in the actual positions as shown on the site layout.
Structural plans-These form the most important parts of the building since the most
important structural members such as columns and foundation footings are well identified
by the grid lines as indicated on the structural plan layouts.
Survey plans and profile drawings. These identify the contour levels at different locations
on the proposed site layout; hence they form a basis for reference on exact levels to fix
the building levels.
(c) With the aid of illustrations, discuss the various types of horizontal control grids that can be used
during surveying and setting out operations.
A control grid enables points to be set over a large area. Several different grids can be used
in setting out
-Survey grid: is drawn on the survey plan from the original traverse or network. The grid
points have known easting and northing related either to some arbitrary origin or to the
national grid.
-Site grid: is used by the designer. It is usually related in some way to the survey grid and
should, if possible, actually be the survey grid, the advantage of this being that if the original
control stations have been permanently marked then the design points will be on the same
coordinate system and setting out is greatly simplified.
-The structural grid is established around a particular building or structure which contains
much detail such as columns, which cannot be set out with sufficient accuracy from the grid site.
-The secondary grid is established inside the structure from the structural grid when it is no
longer possible to use the structural grid to establish internal features of the building – as the
vision becomes obscured.
(d) Discuss the roles of temporary and transferred bench marks in surveying and setting
out operations. Include illustrations showing examples of TBMs and state the accuracies to
which they should be established.
The positions of TBMs should be fixed during the initial reconnaissance so that their
construction can be completed in good time and they can be allowed to settle before leveling
them in. In practice, 20mm diameter steel bolts and 100mm long, driven into existing steps,
ledges, footpaths etc are ideal.
If TBM are constructed at ground level on site, a design to that shown below should be
used.
There should never be more that 80m between TBMs on site and the accuracy of leveling should
be within the following limits: Site TBM relative to the MBM ± 0.005m Spot levels on soft
surfaces relative to a TMB ± 0.010m Spot levels on hard surfaces relative to a TBM ± 0.005m
(e) With the aid of illustrations, discuss the use of offset pegs in setting out operations.
Whether used in the form of a baseline or a grid, the horizontal control points are used to
establish design points on the proposed structure.
Once excavations for foundations begin, the corner pegs will be lost. To avoid these extra
pegs called offset pegs are used.
(f) With the aid of illustrations, briefly discuss how the following should be undertaken
Setting out column position
Solution,
E F G H
RL1 RL4 RL7 RL10
HC
RL3 RL6 RL9 RL12
GL
Theodolite TBM
RL11
RL8
RL5
50)
lope(1:1
RL2
id to s
Pipe la
60m 60m 60m
Let; Let;
RL1=Reduced Level of the stake at point E RL3=Reduced Level of the site rail at point E
RL4=Reduced Level of the stake at point F RL6=Reduced Level of the site rail at point F
RL7=Reduced Level of the stake at point G RL9=Reduced Level of the site rail at point G
RL10=Reduced Level of the stake at point H RL12=Reduced Level of the site rail at point H
Let;
RL2=Reduced Level of the bottom of trench at point E Note;
RL5=Reduced Level of the bottom of trench at point F Height of the Traveller = 2.0m
RL8=Reduced Level of the bottom of trench at point G
RL11=Reduced Level of the bottom of trench at point H
GL Cover level
97.53
Theodolite TBM
RL4
Existing RL3
MH RL2
RL1 (1:200)
to slope
Pipe laid
80m 66m 52m
RL1=97.53-1.87=95.66m.
Height of traveller=3.0m
=Height of site rail at the existing manhole-The level of the cover of the existing manhole.
Height of site rail required above the top of the peg at Manhole A;
Also,RL2=RL1+0.4=95.66+0.4=96.06m
Height of site rail at Manhole A-The level of the peg at Manhole A=(99.06-98.13m)=0.93m
Height of site rail required above the top of the peg at Manhole B;
Also,RL3=RL2+0.33=96.39m
Height of site rail at Manhole A-The level of the peg at Manhole A=(99.39-98.23m)=1.16m
Height of site rail required above the top of the peg at Manhole C;
Also,RL4=RL3+0.26=96.39+0.26=96.65m
Height of site rail at Manhole A-The level of the peg at Manhole A=(99.65-98.68m)=0.97m