You are on page 1of 5

QA Quality Assurance

Standardizing PV System Documentation


and Verification
I nternational concern regarding
the safety and quality of PV system
installations is growing. Incorrectly
practices for system integrators and
O&M providers. Since these entities
are already performing many of the
System data. Minimum system data
requirements outlined in IEC 62446
include basic nameplate information
installed or commissioned systems can tasks described in the standard, the and details that you would expect to
create a fire hazard or even increase the effort and cost to harmonize internal find on the cover page of a PV plan set
risk of electrocution. practices with those outlined will be or a system commissioning package.
Consider the well-documented relatively small. Anyone engaged in the Nameplate data requirements include
“thermal event” that occurred in preparation of documents and stan- rated system power and the manufac-
Bakersfield, California, on April 5, 2009 dards for projects going out to bid will turers, models and quantities of PV
(see “The Bakersfield Fire,” February/ likely find the requirements outlined in modules and inverters. Cover page data
March 2011, SolarPro magazine). It IEC 62446 useful and relevant to their requirements include contact informa-
is generally accepted that an unde- work as well. tion for the customer, system designer
tected fault-to-ground was present in and system installer, plus relevant
a grounded current-carrying source- IEC 62446 project dates.
circuit conductor at this site, and that This international standard was Wiring diagram. According to IEC
this first fault set the stage for the published in March 2009. It is formally 62446, system documentation for a grid-
eventual fire. A subsequent analysis of entitled Grid-Connected Photovoltaic connected PV system shall include at
utility-owned and -operated rooftop Systems—Minimum Requirements for minimum a single-line wiring diagram.
PV systems in North Carolina revealed System Documentation, Commissioning A list of subsections outlines the specific
the presence of undetected ground Tests and Inspection. The emphasis on information that needs to be included in
faults in approximately 10% of the documentation is interesting to note. the notes or tables associated with the
systems surveyed. In effect, system documentation is the wiring diagram.
Proper commissioning procedures evidence used to demonstrate that Annotations to the single-line dia-
are among the best defences against appropriate precautions and tests have gram must include general information
fire or electrocution hazards. While been undertaken prior to handing over about the quantity and type of modules,
guidelines and best practices for PV a PV system to the property owner. as well as specific details about the
system commissioning in North Amer- The standard is organized into two source-circuit and subarray makeup.
ica are patchwork at best, in 2009 the parts: system documentation require- IEC 62446 also requires information
International Electrochemical Com- ments and system verification about the location and type of balance of
mission (IEC) published an interna- requirements, which include inspection system components. Details need to be
tional standard, IEC 62446, that defines and testing. provided regarding conductor sizes and
minimum requirements for document- overcurrent protection device ratings.
ing, commissioning and inspecting System Documentation In addition to equipment ground-
grid-connected PV systems. System documentation require- ing details, in particular module frame
In this article I provide an overview ments are laid out in Clause 4, which grounding, any connection to an exist-
of IEC 62446, which can be purchased describes the minimum documenta- ing lightning protection system needs to
in its entirety from the IEC website tion that should be provided for the be identified, as do the locations, types
(iec.ch) for approximately $150. In addi- benefit of the customer, inspector or and ratings of ac or dc surge protection
tion to the general content outlined maintenance technician following devices. IEC 62446 also details minimum
here, the standard includes informative the installation of a grid-connected information requirements regarding the
appendices with model certificates, PV system. These requirements are existing ac electrical system.
reports and procedures. organized into six categories: system Datasheets. Per IEC 62446, mod-
While compliance with IEC 62446 data, wiring diagram, datasheets, ule and inverter datasheets must be
is not mandatory in North America at mechanical design information, O&M provided in the system documentation
this time, the standard clearly provides information, and test results and com- at a minimum requirement. An informa-
a set of internationally recognized best missioning data. tional note clarifies: C O N T I N U E D O N P A G E 1 6

14 S O L A R PR O | February/March 2012
At AE Solar Energy, we leverage over 30 years
of power conversion heritage to bring you the
most innovative line of PV string inverters available.
High performance, wireless system monitoring,
and an elegant design - backed by the industry’s
best customer experience.

We’re not just another solar energy company.


We’re empowering the industry.
advanced-energy.com/solarnow
QA
“The provision of datasheets for other
significant system components should
4.6 O&M Information
also be considered.” Operation and maintenance information shall be provided and shall include, at a

C o py r ig h t © 20 0 9 I E C , Ge n e v a , S w it z e rl a nd
Mechanical design. A datasheet for minimum, the following items:
the array mounting system needs to a) Procedures for verifying correct system operation.
be provided, at a minimum. Where b) A checklist of what to do in case of a system failure.
applicable, structural engineering docu- c) Emergency shutdown and isolation procedures.
ments, soil testing results and so forth d) Maintenance and cleaning recommendations (if any).
can also be provided. e) Considerations for any future building works related to the PV array
O&M information. Meeting the (for example, roof works).
requirements found in subsection 4.6 f) Warranty documentation for PV modules and inverters—to include starting
of IEC 62446 (see sidebar) is inherently date of warranty and period of warranty.
more subjective than other system g) Documentation on any applicable workmanship or weather-tightness
documentation requirements. Proper warranties.
documentation of system O&M infor-
mation depends upon the audience and
may involve a significant investment personnel are expected to take on the results of the verification tests out-
in time and resources on the project routine maintenance activities for the lined in Clause 5 of the standard.
back end. While basic O&M templates PV system.
can be developed for residential and Test results and commissioning data. System Verification
commercial clients, templates for IEC 62446 requires that copies of test The requirements laid out in Clause
commercial projects invariably require results and commissioning data be 5 apply to both initial and periodic
more customization. This is especially included in the documentation pack- verification of a grid-connected PV
true when a facility’s maintenance age. At a minimum, this must include system. Initial verification takes place

Solar Power Management


TM

More than Monitoring TM

If your current platform only monitors solar power performance, then it’s
just part of the solution.
Solar Power ManagementTM combines comprehensive performance
monitoring, system alarming, and trouble ticket management with the
support of a staffed 24/7/365 National Operations Center.
Trust your Solar PV system performance and ROI to a Fortune 500
company that has been providing monitoring and management services
to over 30,000 multi-industry sites for more than 12 years.
1.888.313.5274 www.arguson.com

ArgusON
16 S O L A R PR O | February/March 2012
upon completion of a knowledgeable regarding PV systems
new installation, as well and the electrical equipment used
as whenever “additions in their construction, and trained to
or alterations to exiting avoid all associated hazards.
installations” are made. System verification is achieved
Periodic verification is through inspection, followed by testing.
intended to ensure that These steps must be documented in a
“the installation and all verification report.
its constituent compo- Inspection. The requirements found
nents remain in a satis- in this subsection are intended to be
factory condition for use.” completed “prior to energizing the sys-
It is worth noting tem.” Inspection activities are broken
Co u r te s y Se a w a rd S o la r

that IEC 62446 requires into four subcategories: dc system,


that a “skilled person, overvoltage and shock, ac system,
competent in verifica- and labeling and identification. While
tion” perform initial or IEC 62446 includes a fair amount of
periodic verification. detail regarding inspection require-
Section 690.4(E) of the ments, companies should defer to the
PV installation test IEC 62446 describes a variety National Electrical Code NEC and the local AHJ when setting
of techniques for shorting a string during testing similarly requires that a internal quality-assurance and quality-
and taking measurements using clip-on ammeters. qualified person install control standards.
However, the use of dedicated PV test instruments, PV systems. By exten- Testing. Testing of PV systems
like this Seaward Solar PV100 tester, simplifies the sion, persons verifying should be conducted in accordance
process, making it quicker and safer for technicians. PV systems should be with NFPA 70E, Electrical Safety in the

ALLIED
FOR YOUR Ultraguard ® resists yellowing,
changes in gloss, and discoloration*.

NEEDS YOUR PROTECTION IN


SOLAR POWER
With fiberglass-reinforced enclosures from Allied Moulded
Products, you’ll get outstanding protection from the elements
even while you are harnessing their power. Made with our exclusive
Ultraguard ® formulation that withstands the harshest extremes
in temperature and UV radiation—it’s the right solution in any
environment. Now backed by the industry’s most comprehensive
warranty, other alternatives simply don’t compare.

To learn more, visit alliedmoulded.com.


*Results confirmed by independent lab tests of leading enclosure manufacturers.

© 2011 Allied Moulded Products, Inc.

222 North Union Street (419) 636.4217


Bryan, Ohio 43506 (419) 636.2450 FAX

solarprofessional.com | S O L A R P R O 17
QA
Workplace, published by the National While IEC 62446 does not specify the intent is to simply verify that the
Fire Protection Association. To miti- the order of the tests, there is logic installation is correct by comparing
gate electrical hazards, workers must behind the order that it recommends. expected Voc and Isc results to mea-
employ personal protective equipment For example, if equipment is properly sured values. Ideally, the results of
commensurate with the electrical bonded to earth, then it is inherently all of the source-circuit measure-
energy present, follow proper proce- safer to work around in the event of ments should be within 5% of one
dures and use appropriate tools. a fault; and if polarity tests are not another. To make this comparison
IEC 62446 requires that the ac cir- completed before functional tests are with confidence, you must have
cuits be tested first, then the following performed, then equipment may be stable irradiance conditions. For best
six dc circuit tests be performed, prefer- damaged at start-up due to reverse results, the measurements should be
ably in this order: polarity or overvoltage. normalized using an irradiance meter
Note that in the event that a test reading. (See “PV System Commis-
1. Test continuity of equipment- indicates a fault, the standard requires sioning,” October/November 2009,
grounding conductors and that all previous tests be repeated SolarPro magazine.)
system-grounding conductors after the fault is rectified. This is Verification reports. Once the PV
(if applicable). because the fault may have influenced system is inspected and tested, IEC
2. Test polarity of all dc cables and earlier test results. 62446 requires that a verification
check for correct cable identifica- The subsections related to the report be prepared. The report must
tion and connection. specific dc circuit tests provide instruc- summarize the system information
3. Test open-circuit voltage [Voc] tions on how to perform the verifica- and also provide relevant names and
for each PV source circuit. tion tests, as well as how to interpret addresses. Each circuit that has been
4. Test short-circuit current [Isc] the results. For example, IEC 62446 inspected and tested must be listed.
for each PV source circuit. describes two short-circuit test pro- A record of each inspection must be
5. Test functionality of major cedures, the results of which can be provided, as well as a record of the
system components (switchgear, measured using either an in-line or a individual test results for each cir-
controls, inverters), including clamp-on ammeter. Similarly, two test cuit. The recommended interval until
inverter anti-islanding. methods are provided for the PV array the next periodic verification must
6. Test the insulation resistance of insulation test, as well as a recom- be identified. Lastly, signatures are
the dc circuit conductors. mended procedure and a table for required for the person(s) responsible
interpreting the results (see Table 1). for the current round of inspection,
The methods for performing these The two PV source-circuit tests testing and reporting.
tests are generally familiar to all electri- are not intended to measure array —Rod Taylor / Seaward Solar / Tampa, FL /
cians. However, difficulties may arise performance, which means that I-V seawardsolar.com
if the technician is unaware of the curve traces are not required. Instead,
extent to which PV circuits need to be
segmented and isolated for these tests
to be performed properly. Therefore, it Minimum Values of Insulation Resistance
is important that anyone performing Courtesy International Electrochemical Commission
these tests be specifically qualified with Minimum
regard to PV systems. System Test insulation
Combinations of standard electrical voltage voltage resistance
Test method (Voc x 1.25) (V) (MΩ)
test equipment can be used to complete
the required tests, such as a megohm <120 250 0.5
Test method 1: Separate tests to array positive and
meter paired with either a digital mul- array negative
120–500 500 1
timeter or a clamp meter. Increasingly, >500 1,000 1
specialized test equipment is available <120 250 0.5
for PV applications. For example, the Test method 2: Array positive and negative shorted
120–500 500 1
PV100 solar installation test kit from together
>500 1,000 1
Seaward Solar includes everything
needed to test to IEC 62446: a continuity Table 1 Insulation resistance test results are satisfactory, according to the test
and insulation resistance tester, a digital methods and procedure outlined in IEC 62446, if they are not less than the values
multimeter and a dc current clamp. shown here.

18 S O L A R PR O | February/March 2012

You might also like