Professional Documents
Culture Documents
El Book Manual Repotenciamiento
El Book Manual Repotenciamiento
of ThyssenKrupp
Technologies
ThyssenKrupp Robins
Los Pelambres – Power Upgrade, Bechtel 25100-220-POA-MHCB-0001
TABLE OF CONTENTS
SECTION 1 GENERAL
1. INTRODUCTION
2. CONTROL PHILOSOPHY
SECTION 2 DRAWINGS
1. GENERAL ARRANGEMENT DRAWINGS
2. P&IDS
Note: This manual is being supplied as supplemental documentation to the manuals supplied for the
original contract by Krupp Canada under Bechtel P.O. #23265-M-002-AC. In case of discrepancy
between the English and Spanish Operation and Maintenance Manuals, the English version shall
take precedence.
Page 1 of 2
ThyssenKrupp Robins
A company
of ThyssenKrupp
Technologies
TABLE OF CONTENTS
VOLUME 1 ELECTRICAL
VOLUME 2 ELECTRICAL
VOLUME 3 ELECTRICAL
SECTION M MOTORS
SECTION P MEASURING INSTRUMENTS
SECTION Q HIGH POWER SWITCH-GEAR
SECTION R RESISTORS
SECTION T TRANSFORMERS
SECTION U MODULATORS, CONVERTERS
SECTION X TERMINALS, PLUG CONNECTORS, SOCKET OUTLETS
CONTROL PHILOSOPHY
Revision U2
CHILE
Submitted by:
2 SYSTEM ARCHITECTURE
3 CONTROL FUNCTIONS
3.3.1.1 Alarms
3.3.1.2 Malfunctions
3.3.1.3 Emergency Malfunctions
4 OPERATOR CONTROLS
4.1.1 Conveyors
4.1.2 Other Equipment
5 SUPERVISORY SYSTEM
6 BELT FEEDERS
7 OVERLAND CONVEYORS
8 AFD DRIVES
9 MECHANICAL BRAKE
10 REDUCERS
12 SHUTTLE
13 AUXILIARY SYSTEMS
14 PLC / NETWORKS
15 APPENDICES
This document describes the control and operation philosophy for the overland conveying
system at the Los Pelambres mine.
The overland conveying system is designed to transport primary crushed copper ore
between two stockpiles over a total distance of 12.6 km, with a total negative elevation of
1296 meters. It is designed for a maximum tonnage of 8700 tph.
All the overland conveyors are of the downhill type and operate in regenerative
conditions when their tonnage exceeds 1000-1500 tph.
All the overland conveyors are powered by variable speed drives (AFD) and are
equipped with mechanical brake systems located at their tail station The head
stations are not equipped with a drive.
All the belt feeders are designed for a maximum tonnage of 2900 tph. Each belt
feeder is powered by a variable speed hydraulic motor and is equipped with a
tramp iron magnet system to protect the conveying system from belt damages.
The shuttle currently travels over a 62 meters span. Six discharge positions are
used to form an elongated stockpile. The shuttle travel will be extended to 94
meters in the future, with additional discharge positions added as required.
Several dust suppression systems are used to control the dust emission. A mist
(water and air mix) suppression type is used at the discharge end of each belt
feeder and at the head of conveyors 120-CV-005 and 120-CV-006. A water
controlled spray system is used at the head of conveyor 120-CV-007.
A general overview of the system, together with the belt profiles and drive
configurations for conveyors 120-CV-005, 120-CV-006 and 120-CV-007, are
provided in appendix A. Additional information about the feeders and overland
conveyors can also be found in the P&ID drawings provided in appendix Q.
Conveyors 120-CV-005 and 120-CV-006 are equipped with four 2500 kW AFD
drives and one mechanical disk brake system. The brake system consists of a
central power pack, of six low speed disks with two calipers each, of two quick-
set modules located near the primary and secondary pulleys, and of one quick-
apply module located near the tertiary pulley.
Conveyor 120-CV-007 is of a similar design, but is only equipped with two AFD
drives, three low speed disks, and two quick-set modules located near the
primary and secondary pulleys. All three brake disks have two calipers each.
The AFD drives are equipped with braking–choppers, braking resistors, and UPS
to maintain their stopping capabilities in case of line failure or trips of the 23 kV
breaker. The AFD drives are designed to provide 130% of their nominal torque
for up to 30 minutes to accommodate short term motor overload without stopping
the conveyor (35 minutes for conveyor 120-CV-007). The braking-choppers and
braking resistors are designed to provide a maximum of 150% of the AFD drive
nominal torque for 80 seconds.
The AFD drives are used to accelerate and stop the conveyors under normal
conditions. They are also used to stop the conveyors in case of line failure or
trips of the 23 kV breaker.
The primary driving or retarding torque for the conveyors during running
conditions is provided by the electric motors. The conveyors require retarding
torque when loaded over 1000-1500 tph (regenerative conditions). All the energy
produced under these conditions is fed back to the main grid.
The mechanical brake systems include both digital and analog controls. Several
calipers on each system are controlled with simple on/off valves, while the
remaining calipers are controlled from an analog pressure control valve. This
combined design was selected to decrease the response time of the brake while
decreasing the peak tension in the belt in case of UPS power failure.
All the analog brake calipers on all conveyors and all the digital brake calipers on
conveyor 120-CV-007 are of a fail-safe design (spring applied, hydraulically
released). Conveyors 120-CV-005 and 120-CV-006 use a mix of fail-safe and
fail-open digital brake calipers. The brake hydraulic power packs are fitted with
redundant pumps, redundant proportional control valves, several solenoid valves,
and a two-level emergency circuit to be used in case of proportional valve failure.
The mechanical brakes are used as a backup to the AFD drives to bring the
conveyors to a controlled stop in case of AFD, motor, or UPS power failure. They
are also used to park the conveyors at the end of each stopping cycle.
Three of the four reducers on conveyors 120-CV-005 and 120-CV-006 and both
reducers on conveyor 120-CV-007 are splash lubricated. The new reducers
installed on drives 22 of conveyors 120-CV-005 and 120-CV-006 are forced
lubricated and require a dedicated lubrication system. The lubrication system is
controlled by an independent unit under PLC supervision.
The belt tension of each conveyor is controlled by a gravity take-up located at the
head station. All the conveyors are equipped with a take-up winch used to
position the counterweight.
The control system consists of three PLC’s, of several remote I/O stations
located along the conveying system route, and of three operator graphic stations
located in the crusher control room #1, the crusher control room #2, and the
concentrator control room.
The PLC’s have redundant CPU‘s. The PLC’s and the operator graphic stations
are interconnected by a redundant fiber optic network (H1/OTN network) used for
monitoring, diagnostics and operator control. .
All conveyor to conveyor interlocks are hardwired between the PLC’s to insure
fail-safe operation under any conditions.
The system can be operated from any of the operator graphic stations. The
operator station in the crusher control room #1 is connected to the mine PCS via
a Modbus link.
All the system control and monitoring functions are performed by the PLC’s. The
control and monitoring of the AFD drives are performed by Simadyn D
controllers. Several functions are shared between the PLC’s and the Simadyn D
controllers.
Each PLC is interconnected to the local AFD drives by a local Profibus network.
A second Profibus is used in each substation to connect the maintenance
workstation, the local operator interface, the remote I/O stations, and the shuttle
AFD drive (PLC 7 only) to the PLC. In addition, two RS-485 links are used in
each substation to connect the PLC to the substation monitoring relays.
The PLC’s, the brake instrumentation, and all the critical field instrumentation are
powered by UPS’s to maintain control of the system in case of AC power failure.
A general overview of the control system and of the various networks is provided
in appendix B.
All the equipment control functions are performed by three Siemens S5-155H
programmable logic controllers (PLC) and several remote I/O stations located
along the conveying system route. The PLC’s are located in the substations at
the tail end of each conveyor.
The 155H PLC’s are equipped with redundant CPU’s and are interconnected by
an industrial network (H1 network) used for monitoring, diagnostics and operator
control.
All conveyor to conveyor interlocks are hardwired between the PLC’s to insure
fail-safe operation under any conditions.
The H1 network information is carried between the substations and the operator
control rooms over a redundant fiber optic network (OTN network). The OTN
network is transparent to the PLC’s.
The control and monitoring of the AFD drives and their related equipment are
performed by Simadyn D controllers. One Simadyn D controller is used for each
drive.
Two local Profibus networks are used at each drive station. The first network is
used to interconnect the AFD drives and the PLC. The second network is used to
connect the PLC to its remote I/O modules, the maintenance workstation, and
the local operator interface terminal.
Two local RS-485 links are also used in each substation. The first link is used to
connect the 23 kV monitoring relay to the PLC. The second link is used to
connect the 400V monitoring relay to the PLC. Both links are used for monitoring
purposes only.
Under normal conditions, the system is operated from one of the three operator
graphic stations located in the crusher control rooms #1 and #2 and in the
concentrator control room. All the graphic stations run the same supervisory
software.
The supervisory software was developed with the Siemens WIN-CC graphics
interface software running under Windows NT.
The operator graphic stations communicate with the PLC’s via the H1/OTN
network. All the operator graphic stations have monitoring and control
capabilities. The control functions of each station are protected with multi-level
passwords. In addition, the operator station in the crusher control room #1 is
connected to the mine PCS via a Modbus link.
Several control modes are available for the overland conveyors and each major
component. The equipment control mode is selected from the maintenance
workstation (OP37) and from several local switch panels (see section 4.1).
Access to the various modes from the maintenance workstation is passwords
protected.
The local-automatic mode provides the ability to maintain system operation and
production in case of supervisory system failure. In local-automatic mode, the
complete system is operated from the maintenance workstations located at the
drive stations. Only fully interlocked automatic equipment starts and stops are
available in this mode. A complete description of this mode is provided in section
4.2.2.
The reduced-speed mode is only available for conveyors. It provides the ability
to run each conveyor at medium speed (50%). This mode is provided to allow a
fully loaded conveyor to be emptied when the downstream conveyor is limited in
tonnage by a drive failure. This mode can only be entered if the conveyor is
stopped, but can be selected from both the local-automatic and local-manual
modes. When selected from the local-automatic mode, the conveyor to conveyor
interlocks are kept active. The feeders are disabled whenever any conveyor is
operated in this mode. A complete description of this mode is provided in section
4.2.3.
The local-manual mode provides the ability to run each conveyor and major
component independently for maintenance purpose. In this mode, each conveyor
or major component is operated from push-button panels located in the field. All
internal equipment interlocks are maintained in this mode. However, most
external interlocks are disabled. The feeders are disabled whenever any
conveyor is operated in this mode. A complete description of this mode is
provided in section 4.2.4.
The local-creep mode is only available for conveyors. In this mode, each
conveyor can be operated at low speed (10%) in forward or reverse direction
from push-button panels located in the field. This mode is provided for
maintenance purpose and is otherwise similar to the local-manual mode. This
mode can only be entered if the conveyor is stopped and is only available when
the conveyor is empty. The feeders are disabled whenever any conveyor is
operated in this mode. A complete description of this mode is provided in section
4.2.5.
The locked mode is only available for the conveyors. In this mode, the conveyor
drives are prevented from starting and the brake is prevented from releasing. The
locked mode is selected from the BCS switch at the tail of each conveyor. A
complete description of this mode is provided in section 4.2.6.
The disabled mode is only available for the take-up winches, the shuttle, the
feeders and the feeder’s magnet systems. In this mode, all motors are prevented
from starting. The disabled mode is selected from the equipment mode selector
switch. A complete description of this mode is provided for each equipment in its
respective section.
All the equipment control and monitoring functions are performed by these controllers.
The control and monitoring of the AFD drives are performed by the Simadyn D
controllers. In addition, the AFD controllers control and monitor all the equipment related
to the drives, including the 23 kV incoming feeders, 3.15 kV breakers, braking-choppers,
drive fans, drive auxiliaries, and motors.
The PLC’s control and monitor all the remaining equipment, including the mechanical
brakes. They also handle the AFD drives sequencing and monitor the AFD drives activity.
The closed loop speed and load sharing control of the AFD drives are shared between
the PLC’s and the Simadyn D controller.
The PLC commands and the AFD drive status and alarms are exchanged via the
Profibus networks.
The PLC software has been developed to control, monitor, and report on the
equipment as follows:
A more detailed description of the control logic used for each component is
provided in sections 6 to 12.
• Monitor the PLC 5 H1, OTN, and Profibus networks for normal
operating conditions.
• Monitor the PLC 5 modules, 110 VDC power supply, and UPS for
normal operating conditions.
• Monitor the PLC 6 H1, OTN, and Profibus networks for normal
operating conditions.
• Monitor the PLC 6 modules, 110 VDC power supply, and UPS for
normal operating conditions.
• Monitor the PLC 7 H1, OTN, and Profibus networks for normal
operating conditions.
• Monitor the PLC 7 modules, 110 VDC power supply, and UPS for
normal operating conditions.
All the digital inputs are filtered through timers to minimize noise and
switch bouncing problems.
All the analog inputs are filtered through a first order digital filter to
minimize noise problems.
All the analog inputs are scaled to engineering units to simplify operator
monitoring of the process.
If an analog signal is found invalid, the faulty input is disabled and the
fault reported to the operator graphic stations. Disabled inputs are
ignored by the control logic and alternate options are used if available.
All the analog set points and timing values used in the software are
independently adjustable by changing the constants stored in the PLC’s.
All the control logic has been developed using structured programming
techniques.
The structure developed for the project is shown in the PLC block
diagrams provided in appendix C.
• Generate the speed ramps used during the drive acceleration and
deceleration
• Report its operating and fault status to the PLC via the Profibus
network
A more detailed description of the control logic used for the AFD drives is
provided in section 8.
• Provide each AFD drive with a speed setpoint via the Profibus
network according to the conveyor operating mode and state
• Provide the AFD drive with several loop modifier setpoints via the
Profibus network to control the drive load sharing and close the
integral portion of the drive speed loop
A more detailed description of the control logic used for the interface with
the AFD drives is provided in sections 7 and 8.
Both the PLC’s and the AFD drives perform equipment monitoring and alarm
handling functions.
The AFD drives monitor the drives and all the drive related equipment, including
the 23 kV incoming feeders, 3.15 kV breakers, braking-choppers, drive fans,
drive auxiliaries, and motors.
The PLC’s monitor all the remaining equipment, monitor the AFD drives for
reported faults, and check the overall AFD drive activity.
The AFD drives status and alarms are reported to the PLC’s via the Profibus
networks.
The health of the Profibus networks is constantly monitored by the PLC’s, but not
by the AFD drives which cannot detect a Profibus failure. Consequently, several
hard-wired interlocks are used between the PLC’s and the AFD drives to enable
safe shutdown of the conveyors in case of drive Profibus network failure.
In all modes of operation, the PLC’s constantly monitor all the equipment
for alarm conditions. The alarms are classified into several levels
depending on their severity. Three categories and eight levels of alarms
are used on this project.
• Alarms
• Malfunctions
• Emergency malfunctions
A typical list of alarms defined for the PLC’s, together with their level, is
provided in appendix D.
3.3.1.1 Alarms
A1 Alarm level 1
This is the lowest level of alarm. The PLC does not take
any action.
A2 Alarm level 2
SP Start Permissive
M1 Malfunction level 1
M2 Malfunction level 2
M3 Malfunction level 3
M4 Malfunction level 4
M5 Malfunction level 5
In all modes of operation, the AFD drives constantly monitor all drive-
related equipment for alarm conditions. The alarms are classified into
several levels depending on their severity.
All detected alarms are coded and sent to the PLC via the Profibus
networks.
The alarms are classified into three levels depending on their severity.
The following levels of alarms are used:
A1 Alarms
M2 Trips
M3 Emergency Trips
A typical list of alarms defined for the AFD drives, together with their
level and locations, is provided in appendix E. A table showing the
protection levels for the AFD drives is provided in appendix F.
Most PLC alarms can be remotely reset from the operator graphic
stations. However, selected alarms cannot be remotely cleared and
require a local reset from the field or from one of the maintenance
workstations located at the drive stations.
The following alarms and malfunctions have to be reset from one of the
maintenance workstations:
• Belt rip
• Belt alignment
• Blocked chute
• Most brake faults
• Most drive faults
The system is normally operated from one of the three operator graphic stations located
in the crusher control rooms #1 and #2 and in the concentrator control room. All the
operator graphic stations have monitoring and control capabilities. The control functions
of each station are protected with multi-level passwords.
The supervisory system allows remote automated control of all the conveyors and
feeders, and provides visual indication of all equipment status and alarm condition.
Furthermore, advanced help and diagnostic information is available through the use of a
separate interactive help file system working in conjunction with the supervisory system
(advanced help feature).
The supervisory system was developed using the Siemens WIN-CC graphics interface
software. The advanced help features were developed in a separate software package
and linked to WIN-CC through custom written DLL files (Window executable file).
All the equipment control functions are performed by the PLC’s. The operator graphic
stations are only used to input the operator commands, to report on the system status
and alarms, and to generate the system start and stop sequences.
Each drive station is equipped with a Siemens OP37 maintenance workstation and a
small Siemens OP7 operator interface for local control and status information. Several
push button panels are located in the field for local and manual control of the equipment.
Several control modes are available depending upon the equipment. The mode selection
for all equipment and the modes of operation for the conveyors are described in the
following paragraphs. The modes of operation for all other equipment are described in
their respective sections.
The control mode is selected from the maintenance workstation (OP37) and from
several local control switches. Access to the various modes from the
maintenance workstation is passwords protected.
The status of the mode selection switches and the current operating mode for all
equipment is indicated on the operator graphic stations and the maintenance
workstations (OP37).
4.1.1 Conveyors
Each overland conveyor is equipped with two local control panels located
at the head and the tail of the conveyor, and with one lockable three-
position Belt Control Switch (BCS).
The BCS is also mounted at the tail of the conveyor and has the
following positions:
• I - Interlocked
• NI - Not Interlocked
• O - Locked out
The tail control panel is fitted with a three-position creep selector switch
(normal/tail-creep/head-creep) and a two-position direction selector
In addition, the brake systems and take-up winches are equipped with a
three-position mode selector switch (MSS) with the following positions:
• R - Remote
• L - Local
• O - Off
All the control switches described above are used for software mode
selection only and are not hardwired to the equipment. The mode of
operation for each component is selected by the PLC according the
following combinations:
Overland Conveyors:
Brake Systems:
All the belt feeders, all the feeders’ magnet systems, and the shuttle are
equipped with a three or four position mode selector switch (MSS) with
the following positions:
• R - Remote
• L - Local
• O - Off
Shuttle:
Belt Feeders:
Feeder Magnets:
The dust suppression systems are also equipped with a local mode
selector switch. However, this switch is hardwired and independent of
the PLC. Consequently, no local or manual modes of operation are
defined in the PLC for the dust suppression systems, and the local
selector switch is used for monitoring only.
• Remote-automatic mode
• Local-automatic mode
• Reduced-speed mode
The local-manual mode can only be entered when the conveyor is stopped.
However, this mode can be exited with the conveyor running.
Mode changes to and from the reduced-speed mode, the local-creep mode, the
various maintenance modes, and the locked mode are only accepted when the
conveyor is stopped. Furthermore, the local-creep mode and the brake
maintenance mode can only be entered after an empty-stop sequence has been
completed, or after an empty conveyor override command has been received
from the operator. The conveyor cannot be started in the locked mode or in any
of the maintenance modes.
In addition, in order to avoid being locked into the local-automatic mode, the
remote-automatic mode is automatically entered upon detection by the PLC of a
communication failure with the maintenance workstations (OP37) while in local-
automatic mode.
Only fully interlocked automatic equipment starts and stops are available
to the operator.
• System pre-start
• System start
• System empty-stop
• System sequence-stop
• System immediate stop
• Alarms/malfunction reset
• System Pre-Start
• System Start
• System Sequence-Stop
• System Immediate-Stop
• Conveyor pre-start
• Conveyor start
• Conveyor stop
• AFD drive disable
• AFD drive enable
Only fully interlocked automatic equipment starts and stops are available
in this mode. Conveyors to conveyor interlocks are maintained in this
mode through hardwired PLC to PLC interlocks (see section 7.4).
This mode can be entered from both the local-automatic and local-
manual modes. When selected from the local-automatic mode, the
conveyor to conveyor interlocks are kept active.
• Conveyor pre-start
• Conveyor start
• Conveyor stop
Each overland conveyor is equipped with two local control panels located
at the head and the tail of the conveyor. The local-manual mode provides
control of each conveyor from the local control panel located at its tail
drive station.
This mode provides the ability to run each conveyor independently and
should be used for maintenance purposes and to help during
commissioning of the conveyors.
All internal conveyor interlocks are maintained in this mode. However, all
conveyors to conveyor interlocks are disabled.
This mode can only be selected when the conveyor is stopped. However,
it can be exited at any time.
In addition to the mode select switches, the following local switches are
available on the tail control panel.
• Sound horns
• Start conveyor
• Stop Conveyor
Pushing the Horn button turns on the conveyor horns for 10 seconds and
initiates a conveyor pre-start sequence.
Pushing the start button when the conveyor is ready initiates a start
sequence. If the conveyor is not ready, a conveyor pre-start sequence is
initiated.
Pushing the stop switch immediately stops the conveyor with the AFD
drives.
Note that in the local-manual mode the conveyor can only be started
from the tail panel, but can be stopped from both the head and the tail
panels. This is true in all modes of operation.
The local-creep mode provides the ability to run each conveyor at low
speed in forward or reverse direction for maintenance purpose.
Each overland conveyor is equipped with two local control panels located
at the head and the tail of the conveyor. The tail control panel is fitted
with a three-position creep selector switch with the following positions:
• Normal speed
• Creep - Tail
• Creep - Head
The local-creep mode can only be entered from the local-manual mode,
and can only be entered or exited when the conveyor is stopped.
This mode is otherwise similar to the local-manual mode and offers the
same control options with the addition of the following controls:
Pushing the start button when the conveyor is ready starts the conveyor
in the selected direction at a preset creep speed (10%).
The locked mode provides the ability to immobilize each conveyor. This
mode is selected from the BCS switch located at the conveyor tail
stations.
Switching the BCS switch to the locked position with the conveyor
running results in an immediate shutdown of the conveyor using the AFD
drives.
In the locked mode, the AFD drives and the conveyor are prevented from
starting, and the brake is blocked against releasing.
It also provides more detailed diagnostic information on the AFD drives, PLC
equipment, and PLC networks.
All local operator resets are logged by the supervisory system. The typical alarm
list provided in appendix D indicates the alarms that require a local reset from a
maintenance workstation.
Each conveyor drive station is equipped with a Siemens OP7 operator interface
terminal. This terminal provides basic status and group alarm information for
local indication at each drive station. The following information is shown:
• Group malfunctions (brake fault, AFD drive fault, shuttle fault, etc.)
• Basic brake and AFD drive status (applied/released, ready/fault, etc.)
• Basic analog data (drive kW, conveyor speed, belt tension, etc.)
• Selected individual alarms (belt rip, pull cord, blocked chute, etc.)
The OP7 operator interface terminals are used for monitoring only and are not
programmed with any reset or control capabilities.
The typical alarm list provided in appendix D indicates which alarms or groups of
alarms are shown on the OP7 terminals.
Full indication of system status and alarms for each conveyor, each feeder and
the shuttle is available on the overview graphics screen. All the operator
commands required to operate the system in remote-automatic mode are also
accessible from the overview screen.
Full indication of status and alarms for each individual component is available on
subsequent graphics screens. Furthermore, the graphics screens provide visual
indication of the physical state of all critical I/O points.
• System overview
• Conveyor overviews (1 per conveyor)
• Conveyor AFD drives overviews
• Conveyor AFD drives (1 per drive)
• Conveyor brake (2 per brake system)
• Conveyor miscellaneous (5 per conveyor)
• Belt feeders (2 per feeder)
• Auxiliary systems
• Substations (1 per substation)
• Alarm log
• Real Time trending (1 for the system and 1 per conveyor)
• Historical trending
All defined alarms are shown with an individual graphical icon and a short
associated text.
The operator graphic stations maintain a historical log of all events and alarms
reported to the system in the last 48 hours. The alarms and events are logged in
the order of occurrence.
The log should be printed continuously, and is logged to the hard disk. The
historical log files are automatically saved to disk every 48 hours (48 hours
cycle).
The operator has the option to save the files for permanent storage using normal
Windows commands outside the WIN-CC environment.
• Equipment start/stop
• Control mode changes
• AFD drive enabling/disabling
• Alarm resets (remote and local)
• Alarms/malfunctions
Several real time trend screens are available for the system and for each
conveyor. These screens show real time trends of the last 10 minutes of
operation for the most critical analog registers.
The real time trend screens can be setup to show any logged analog register.
They have been initially setup to show the following variables:
Overview trends:
Conveyor trends:
The operator has the option to save the files for permanent storage using normal
Windows commands outside the WIN-CC environment.
The files are not automatically erased by the system, and the operator should
occasionally clean up the hard disk to avoid a disk overflow.
A trend review screen provides the ability to review all recorded analog variables.
It is possible to review up to eight variables at the same time, and the screen has
zoom, pan, and print capabilities.
• AFD drive power (each drive and total power for each conveyor)
• AFD drive speed reference (1 per conveyor)
• Conveyor speed (1 per conveyor)
• Mechanical brake pressure (1 per conveyor)
• Load cells (2 per conveyor)
• Belt tension (calculated, 1 per conveyor)
• Take-up counterweight position (1 per conveyor)
• Tonnage (2 weight scales)
• Shuttle position
• Feeder speed (1 per feeder)
• Motor RTD temperatures (all)
• Reducers RTD temperatures (all)
• Pulley bearing RTD temperatures (all)
• Drive vibration
Several accumulated registers are used to keep track of various functions. These
registers are updated by the PLC’s and are shown on the operator screens.
The advanced help features were developed in a separate software package and
linked to WIN-CC through custom written Windows executable files (DLL files).
Several levels of help are available, from simple tool-tips to advanced interactive
trouble shooting screens.
All the belt feeders are designed for a maximum tonnage of 2900 tph.
All the belt feeders are powered by a variable speed hydraulic motor and are equipped
with an oil cooler and a tramp iron magnet system to protect the conveying system from
belt damages.
The tramp iron magnets are motorized and can be moved between the feeder discharge
chutes and their tramp iron discharge bin.
Each belt feeder is fitted with a stockpile low level switch. This switch is used to
prevent feeder start when the stockpile is low to avoid damage to the feeder belt.
The feeders can only be started if conveyor 120-CV-005 is running at full speed
in remote-auto or local-auto mode.
A feeder can only be started if its magnet is located at the feeder chute position.
Each feeder is equipped with one latching emergency stop switch located next to
its hydraulic power pack. This switch is hardwired to the feeder pump contactor.
In addition, each feeder is equipped with one latching emergency stop switch
located next to its magnet carriage. This switch is only connected to the PLC (not
hardwired).
Actuation of any of these switches stops the selected feeder and its magnet
positioning motor, but not the magnet flux. The remaining feeders are not
stopped.
The feeders are automatically stopped when a high stockpile level is detected.
This interlock is also hardwired between the PLC’s.
The maximum number of active feeders, the feeder speed setpoints, and the
feeder system tonnage setpoint are also interlocked to the number of working
weight scales, the number of active AFD drives, and the operating mode of the
feeders.
Several control modes have been defined for the belt feeders. The control mode
is selected from the maintenance workstation (OP37) and from two selector
Each feeder is equipped with a mode selector switch (MSS) located on the
feeder panel. The MSS switch is used for software mode selection only and is
not hardwired to the equipment. It is also used as a speed selector switch to
select the source of the speed setpoint (PLC or local potentiometer).
When the mode selector switch is turned to the local-PLC position, the speed
control input from PLC 5 is enabled. When the mode selector switch is turned to
the local-panel position, the panel speed control potentiometer is enabled and
the speed control input from PLC 5 is disabled.
The operating mode for each feeder is selected by PLC 5 according the following
combinations:
In this mode the feeders are operated from the central operator control
room. Only fully interlocked automatic feeder starts and stops are
available in this mode.
The number of active feeders and the operator setpoints are limited by
PLC 5 based on operating conditions as described below.
• Tonnage control
• Fixed speed control
In both control modes, all the running feeders are operated at the
same speed and the automatic speed setback is active.
Both weight scales are fitted with a reset input to enable remote
reset of faults by the operator.
This mode provides the ability to run each feeder independently and
should be used for maintenance purposes and to help during
commissioning of the feeders.
A pump start command also turns on the warning horns and beacons for
10 seconds.
Depending upon the position of the mode selector switch, the feeder
speed can be adjusted from the speed-increase/speed-decrease
switches (PLC) or the potentiometer (Pot) located on the feeder panel.
Note that the cooler fans can be jogged in all modes of operation.
This mode only applies to the feeder itself. The feeder magnet system is
not disabled when the feeder is set to the disabled mode, the automatic
magnet cleaning sequence is still enabled, and the magnet system can
still be switched to the maintenance mode.
When the automatic setback is activated in speed control mode, the total feeder
speed (accumulated for all operating feeders) is instantly decreased by 70%. In
tonnage control mode, the tonnage setpoint is instantly decreased by 2000 tph.
The setback remains active as long as the overload condition is detected, and for
5 minutes after the condition has returned to normal.
• Very high belt tension (over 110% of nominal tension for 10 seconds,
150 tons on conveyor 120-CV-007, 290 tons on conveyors 120-CV-005
and 120-CV-006)
• Very high negative AFD drive torque (over 130% of nominal regenerative
torque for 10 seconds)
• High sustained negative AFD drive torque (over 100% of nominal
regenerative torque for 30 minutes)
• Very high negative belt slip on any drive pulley (over 10% for 5 seconds)
• Very high tonnage (over 110% of allowable tonnage for 10 seconds,
conveyor 120-CV-005 only)
When an overload condition is detected on any conveyor, the belt feeders and all
the upstream conveyors are automatically stopped. The overloaded conveyor is
not stopped. This interlock is hardwired between the PLC’s.
All the belt feeders are equipped with a tramp iron magnet system to protect the
conveying system from belt damages.
A feeder can only be started if its magnet is located at the feeder chute
position, is in the automatic mode, and is not in a fault condition.
The following control modes have been defined for the magnet systems.
If a feeder magnet has not been cleaned for more than the
maximum time, an alarm is displayed on the screen. If the
operator does not stop the feeders within the next 1 hour, the
feeder is automatically stopped and a fault is latched.
This mode can be entered at any time, even when the feeder is
operating. Switching a feeder magnet to the disabled mode will
not stop the corresponding feeder until an automatic cleaning
sequence is required.
This section provides a description of the control algorithm presently defined for the
overland conveyors.
All the overland conveyors are fitted with variable speed drives (AFD). The AFD
drives are fitted with braking-choppers, resistor banks, and UPS to maintain their
regenerative capabilities in case of 23 kV line failure or trips of the 23 kV breaker.
The AFD drives are designed to provide 130% of their nominal torque for up to
30 minutes to accommodate short term motor overload without stopping the
conveyor (35 minutes for conveyor 120-CV-007). The braking-choppers and
resistors are designed to provide a maximum of 150% of the AFD drive nominal
torque for 80 seconds.
The AFD drives are used to accelerate and stop the conveyors under normal
conditions. They are also used to stop the conveyors in case of line failure or trip
of the 23 kV breaker.
The primary driving or retarding torque for the conveyors during running
conditions is provided by the electric motors. The conveyors require retarding
torque when loaded over 1000-1500 tph (regenerative conditions). All the energy
produced under these conditions is fed back to the main grid.
The overland conveyors are also fitted with low speed, mechanical disk brake
systems mounted on their two drive pulleys and on one bend pulley at their tail
station. The disks are installed on the low speed side of the motor reducers (drive
pulleys) or directly on the pulley shaft (bend pulleys).
The mechanical brake systems include both digital and analog controls. Several
calipers on each system are controlled with simple on/off valves, while the
remaining calipers are controlled from an analog pressure control valve. This
combined design was selected to decrease the response time of the brake while
decreasing the peak tension in the belt in case of UPS power failure.
All the analog brake calipers on all conveyors and all the digital brake calipers on
conveyor 120-CV-007 are of a fail-safe design (spring applied, hydraulically
released). Conveyors 120-CV-005 and 120-CV-006 use a mix of fail-safe and
fail-open digital brake calipers. This was done to decrease the peak tension in
the belt in case of UPS power failure while providing back-up braking capacity
under PLC control.
Each drive station is equipped with one latching stop switch at each motor
location. These switches are not hardwired to the motor contactors. Actuation of
any of these switches results in an immediate shutdown of the conveyor using
the AFD drives (level 2). In addition, each drive station is equipped with one
latching emergency stop switch located at the mechanical brake hydraulic panel.
This switch is hardwired to the conveyor emergency circuit. Actuation of this
switch results in the immediate shutdown of the conveyor using the mechanical
brake emergency circuit (level 4).
Each AFD drive container and each high voltage container is equipped with two
latching emergency switches located inside and outside the container next to the
main door. Those emergency switches are hardwired to the main 23 kV breaker.
Actuating one of those switches results in an immediate shutdown of the
corresponding conveyor using the AFD drives and the braking-choppers (level 2).
Pull cords are located along the complete conveyor route. Pull cord switches are
grouped in zones and are equipped with beacons used to locate tripped pull
cords. All the pull cords on each conveyor are wired in series to a master circuit.
This circuit is monitored by the PLC at each substation. The individual status of
each zone is also monitored by the PLC on the remote I/O modules located
along each conveyor. The information from the remote modules is used for
diagnostics only. This was done to allow continuous operation in case of remote
I/O module fault.
Three of the four drives on conveyors 120-CV-005 and 120-CV-006 (drives 11,
22 and 21) and both drives on conveyor 120-CV-007 are fitted with Keller
reducers. These reducers are splash lubricated and do not require a dedicated
lubrication system. They were initially installed without oil cooling systems, but
were retrofitted with coolers at a later date. The reducer cooling systems are
controlled by independent controllers and are not under PLC supervision.
One drive on conveyors 120-CV-005 and 120-CV-006 (drive 22) is fitted with a
Flender reducer. These reducers are forced lubricated and require a dedicated
lubrication system. These lubrication systems are controlled by independent units
provided by Flender but are supervised and monitored by the PLC.
The belt tension of each conveyor is controlled by a gravity take-up located at the
head station. All the conveyors are equipped with a take-up winch. On the two
longer conveyors (120-CV-005 and 120-CV-006), the winch is controlled by the
PLC to position the counterweight prior to start-up and to maintain its position
within a given range while the conveyor is running. This was done to reduce the
required counterweight travel and minimize manual adjustments due to splice
stretching and temperature fluctuations.
One beacon and one horn are located at each substation. The horn is turned on
for 1 minute whenever a conveyor malfunction has been latched. The beacon is
turned on whenever an alarm or a malfunction has been latched.
All the conveyors are started following a 40 seconds S-shaped ramp with the
AFD drives. The mechanical brakes are used to hold the conveyors until the full
AFD drives torque is developed.
Under normal conditions, all the conveyors are stopped on a curved ramp using
the AFD drives regenerating into the main grid (if required). In case of line failure,
all the conveyors are stopped on the same curved ramp using the AFD drives
and the braking-choppers.
In order to ensure that the conveyor discharge chutes remain clear of material,
the conveyors are stopped with increasing time ramps from the head to the tail of
the system.
The stopping time for each conveyor is shown in the following table:
In the event of multiple AFD drives or motors failure, the conveyor is stopped on
a linear ramp with the mechanical brake using proportional control (level 3).
Combined braking using the AFD drives and the mechanical brake
simultaneously is not permitted.
In the event of failure of the mechanical brake emergency control, the conveyor
is stopped with the mechanical brake using a second emergency hydraulic circuit
that applies maximum brake torque instantly (level 5).
The normal conveyor stopping time is not maintained during emergency stops.
The control logic was developed to follow the design criteria established during
the dynamic analysis for each conveyor. The various ramps used for starting and
stopping the conveyors are shown in appendix J.
The overland conveyor system is designed for a maximum tonnage of 8700 tph.
Any conveyor can be operated with one AFD drive disabled. Under these
conditions, the maximum allowable tonnage is reduced as follows:
Maximum Tonnage
Number of Motors 120-CV-005 120-CV-006 120-CV-007
4 Motors 8700 8700 NA
3 Motors 7200 7200 NA
2 Motors NA NA 8700
1 Motor NA NA 5200
The AFD drives are designed to provide 130% of their nominal torque for up to
30 minutes to accommodate short term overloads. This margin is sufficient to
keep conveyors 120-CV-005 and 120-CV-006 running in case of single drive
failure under any load conditions until the conveyor load has been reduced by the
tonnage limit.
Furthermore, since the complete conveying route would be loaded at full tonnage
under these conditions, a special procedure is required to empty the conveying
system before the feeders could be re-started with the new tonnage limit. After
starting conveyor 120-CV-007, both conveyor 120-CV-006 and conveyor 120-
CV-005 should be switched to the reduced-speed mode, started in sequence,
and kept running at reduced speed until they are empty. Both conveyors should
then be stopped and switched back to the remote-automatic mode before
normally starting the system.
Several tables showing the torque/tonnage relation and the tonnage limitations
under various conditions are provided in appendix K.
Conveyor 120-CV-005 is equipped with two weight scales located near its
loading station. The weight scales are used to control the feeder’s speed and to
prevent material overload of the conveyors. All control and tonnage detection is
done using the highest of the two weight scales readings.
In addition, each conveyor is equipped with two load cells mounted on the
primary drive pulley supports. The load cell readings are combined with the
motor torque information from the AFD drives to estimate the high side belt
tension. The details of the calculation used are provided in appendix L. Note that
the belt tension can only be calculated while the conveyor is moving and the AFD
drives actives. In order to avoid displaying inaccurate values on the operator
screen, the belt tension register is automatically reset to zero when the conveyor
is stopped, or when the mechanical brake is applied.
The setback remains active as long as the overload condition is detected, and for
5 minutes after the condition has returned to normal.
• Very high belt tension (over 110% of nominal tension for 10 seconds,
150 tons on conveyor 120-CV-007, 290 tons on conveyors 120-CV-005
and 120-CV-006)
• Very high negative AFD drive torque (over 130% of nominal regenerative
torque for 10 seconds)
• High sustained negative AFD drive torque (over 100% of nominal
regenerative torque for 30 minutes)
• Very high negative belt slip on any drive pulley (over 10% for 5 seconds)
• Very high tonnage (over 110% of allowable tonnage for 10 seconds,
conveyor 120-CV-005 only)
When an overload condition is detected on any conveyor, the belt feeders and all
the upstream conveyors are automatically stopped. The overloaded conveyor is
not stopped. This interlock is hardwired between the PLC’s.
When a low total conveyor drive torque is detected for more than a few seconds,
the PLC automatically offsets the torque setpoint of each drive. The torque
setpoint of the drives on the primary pulley is increased, while the torque setpoint
of the drives on the secondary pulley is decreased. The drive offsets are
calculated to maintain the total conveyor drive torque, while making sure that no
drive is operated with less than 5 % torque (powering or regenerative).
The offset remains active as long as the zero torque condition is detected, and
for 1 minute after the total drive torque has increased sufficiently.
Several hardwired interlocks are used to insure fail-safe operation of the overland
conveying system.
Eight hardwired interlocks are used between each PLC to insure fail-safe
operation.
The interlocks consist of six digital outputs and two digital inputs on each
downstream PLC connected to corresponding I/O’s on each upstream
PLC.
This signal is normally high and is turned off when the downstream
conveyor initiates a level 4 stop (mechanical brake emergency stop). The
input is used to initiate a level 4 stop on the upstream conveyor in order
to minimize the chances of plugged chute at the transfer station. The
input is used in all modes. This input is fail safe (normally high) to insure
that a level 4 stop is initiated on the upstream conveyor in case of UPS
or power failure on the downstream conveyor PLC.
This signal is normally high and is turned off when the downstream
conveyor is in the reduced-speed mode. When this input is low, the
feeders are disabled and the upstream conveyor is only enabled to start
if it is in the reduced-speed mode.
This signal is normally high and is turned off if one AFD drive has been
disabled on conveyor 120-CV-006 (level 2 tonnage limit). The input is
used by PLC 5 to limit the feeder’s tonnage and speed setpoints in both
remote-automatic and local-automatic modes.
This signal is normally high and is turned off when a system level fault is
detected in the upstream PLC. Currently, the only system level fault
defined is the harmonic filter fault in PLC 5. The input is used as a run
permissive on the downstream conveyor in all modes.
This signal is normally low and is turned on when the upstream conveyor
chute is clear of material. This information is used by the downstream
conveyor to detect when the conveyor is empty. This feature was added
to enable the operator to enter the brake maintenance and the local-
The PLC and the AFD drives are interconnected by a local Profibus
network at each substation. This network is a critical part of the AFD
drives operation because the normal drive control is performed over the
Profibus network, and because part of the closed loop speed and load-
sharing control of the drives is done in the PLC.
The Profibus networks are constantly monitored by their master PLC, but
not by the AFD drives which cannot detect a Profibus failure.
The interlocks consist of two PLC outputs and one PLC input for each
drive, and the corresponding I/O’s on the Simadyn controller.
This signal indicates that the drive is no longer able to control the
motor (major drive fault). Upon detection of a loss of control fault by
any active drive, the PLC immediately initiates a disabling sequence
of the faulty drive, provided that all the other drives are operational
and that the load on the conveyor would not result in overloading of
the remaining drives.
All the hardwired interlocks between the PLC and the AFD drives are fail-
safe (normally high).
The PLC outputs are always used to stop the conveyor in case of
multiple drive Profibus failure, or when an AFD drive does not respond to
its normal stop commands. In both cases, the PLC first tries to stop the
AFD drives using the normal-stop outputs. If the conveyor speed does
When a Profibus failure is detected on a single drive, the PLC trips the
faulty drive using its E-stop output but the conveyor is not stopped
provided that all the other drives are operational and that the load on the
conveyor would not result in overloading of the remaining drives.
The AFD drive E-stop inputs are also directly controlled from the
hardwired emergency circuit to insure that the AFD drives are tripped
when the emergency circuit is activated (see following paragraph).
All the conveyors can be operated with one AFD drive disabled. The drives can
be temporarily disabled from the operator graphic stations, or permanently
disabled from the maintenance workstation. All the AFD drive enable and disable
commands are password protected.
The AFD drive enable/disable function is provided for maintenance purpose only
and is limited to one disabled AFD drive per conveyor at any time.
It is possible to disable an AFD drive on a running conveyor, provided that all the
other drives are operational and that the load on the conveyor would not result in
The system will automatically disable any AFD drive that fails on a running
conveyor (including single drive Profibus failure) provided that all the other drives
are operational and that the load on the conveyor would not result in overloading
of the remaining drives.
The AFD drives are designed to provide 130% of their nominal torque for up to
30 minutes to accommodate short term motor overloads without stopping the
conveyor (35 minutes for conveyor 120-CV-007).
In order to limit potential light loading damages to the drive reducer, a conveyor
can only be operated with a remotely disabled drive for a maximum of 30
minutes. Note that this is usually a more limiting constraint than the AFD torque
limits.
When an AFD drive is temporarily disabled, the PLC verifies that the drive is
inactive. Except for enable/disable and active faults, all alarms and faults
detected on a disabled AFD drive are ignored by the control logic. However, the
corresponding reducer is still monitored. All drive faults and Profibus faults are
still reported to the operator graphic stations and the maintenance workstations
(OP37).
Upon receipt of a pre-start command from the operator, the brake hydraulic
pump is started, the temperature of all the brake disks is checked, the AFD
drives trip command is released, a pre-start command is sent to each enabled
AFD drive, and all the conveyors warning horns are turned on for 10 seconds
The brake hydraulic pump stays on until the active accumulator on the main
hydraulic power pack is fully charged. This also charges the spring accumulator
on the quick apply module. As soon as the accumulator is charged, and provided
that the temperature of all the brake disks is below the start permissive limit, a
brake ready flag is set in the PLC. This stage can take as long as 30 seconds if
the accumulator was fully discharged. The brake pump is then controlled to
maintain the active accumulator pressure on the main brake hydraulic power
pack.
Upon receipt of the pre-start command from the PLC, each AFD drive closes its
3.15 kV circuit breaker, starts its cooling fans, and starts its DC links pre-
excitation. This stage can take as long as 90 seconds if the 3.15 kV breaker was
open. The AFD drive then sends a “ready for operation” signal back to the PLC.
When all the enabled AFD drives, the brake system, and the take-up are ready, a
conveyor ready indication is shown on the operator screen.
Upon receipt of a start command, and provided that the conveyor is ready to
start, the conveyor warning horns are turned on. If a start command is received
by a conveyor in remote-automatic, local-automatic, or reduced-speed mode
while the downstream conveyor run permissive interlock input is low, a conveyor
interlock fault is latched and the start sequence is aborted.
After a 10 seconds delay, a start command is sent to all the enabled AFD drives.
Upon receipt of the start command from the PLC, each AFD drive enables its
motor side inverter. This stage usually takes about 10 seconds. When its motor
excitation is fully built-up, the AFD drive sends a “ready for torque control” signal
back to the PLC.
When all the enabled AFD drives are ready, the PLC sends the starting torque
preset to the drives. The starting torque preset value is stored during running
conditions.
After confirmations that all the enabled AFD drives are engaged, the fail-safe
digital calipers are immediately released and the proportional calipers are
released over 5 seconds (the fail-open calipers are normally released). When the
mechanical brake is fully released the AFD speed reference is increased to the
selected speed setpoint.
Each AFD drive then accelerates to the selected speed setpoint on an internal S-
shaped ramp. Each AFD drive generates its own speed ramp. The drives internal
speed ramps are continuously sent back to the PLC for monitoring purpose.
The ramp duration varies with the speed setpoint, with a maximum of 40 seconds
for a full speed start. The various ramps used for starting the conveyors are
shown in appendix J.
When the conveyor speed reaches 1.5%, the warning horns are turned off.
When the AFD drives speed ramp reaches the selected speed setpoint, the
running state is entered.
The conveyor velocity is constantly monitored by the PLC during the starting
sequence. The conveyor is immediately stopped if any of the following conditions
is detected:
• the velocity of the conveyor differs from the PLC speed ramp by
more than 10% of nominal speed for more than 5 seconds (AFD
ramp underspeed and AFD ramp overspeed faults)
During the starting, running, and creep states, and during part of the stopping
state, the PLC constantly monitors the total AFD drive torque. The total torque
value is delayed through a 3 seconds filter (to guaranty a valid reading in case of
drive trip) and stored.
The stored torque value is used to calculate the mechanical brake torque that
would be required to stop the conveyor. This value is used at the beginning of the
stopping cycle to preset the mechanical brake pressure in case of level 3 stop.
The last value of the running torque is also constantly stored during the running
and creep states. This value is used to preset the AFD drive torque at the
beginning of the starting cycle.
Four different types of stopping control (levels 2 to 5) have been defined to stop
the conveyors depending on the conditions of the stop.
This is the normal stopping mode. It is used for all shutdowns if the AFD
drives and motors are available. Note that this includes conveyor
shutdowns in case of 23 kV line failure.
When the brake is fully applied, the AFD drives start command is
released.
The brake hydraulic pump is then stopped, the brake emergency valve is
opened, the remaining fail-safe digital calipers are applied, the fail-open
digital calipers are applied for a short time to exercise them, and the
conveyor enters the stopped state.
• the velocity of the conveyor differs from the AFD speed ramp by
more than 10% of nominal speed for more than 5 seconds (AFD
ramp underspeed and AFD ramp overspeed faults)
This braking mode is only entered if the AFD drives or the motors are not
available to stop the conveyor.
After a short time delay, the AFD drives start command is released. If a
Profibus failure has been detected, or if selected AFD faults have been
latched, the hardwired AFD E-stop outputs are also turned off.
When the conveyor speed reaches 0.5%, or after the nominal stopping
time has elapsed, the proportional calipers are fully applied with the
pressure control valve.
When the conveyor reaches a complete stop, the brake hydraulic pump
is stopped, the brake emergency valve is opened, the remaining fail-safe
digital calipers are applied, the fail-open digital calipers are applied for a
short time to exercise them, and the conveyor enters the stopped state.
• the velocity of the conveyor differs from the PLC speed ramp by
more than 10% of nominal speed for more than 5 seconds (stop
ramp fault)
• The velocity of the conveyor remains over 105% for more than 5
seconds (sustained overspeed condition level 1)
After a short time delay, the AFD drives start command is released. If a
Profibus failure has been detected, or if selected AFD faults have been
latched, the hardwired AFD E-stop outputs are also turned off.
The conveyor velocity and the brake pressure are constantly monitored
by the PLC during the stopping sequence. A level 5 fault is immediately
latched and the conveyor is stopped with the mechanical brake using the
pressure dump circuit if any of the following conditions is detected:
• The velocity of the conveyor remains over 105% for more than
10 seconds (sustained overspeed condition level 2)
This results in the fast application of all the available brake torque.
15 minutes after entering the stopped state, the AFD pre-start command is
removed, thus opening the 3.15 kV breakers and stopping the drive cooling fans.
This delay is reduced to 1 minute in case of UPS line voltage failure to save
battery power.
Please refer to the appendix O for the drive control loop diagrams.
All the AFD drive closed loop controls operate simultaneously through the
individual digital SIMADYN controls. A master and slave arrangement is
therefore not necessary. The “Pre-start”, "Start" and "Release Speed" commands
are generated and transmitted from the PLC of the conveyor station.
When a pre-start command is received by a drive, the drive gets ready for
operation (auxiliary drives on and line side inverter on), When the drive is ready,
the “drive ready for operation” signal is sent back to the PLC.
The PLC then sends a start command to the drive. When the start command is
received, the drive enables the motor side inverter and builds-up the motor
excitation. When the drive is ready, the “drive ready for torque control” signal is
sent back to the PLC.
The PLC then sends the torque pre-control setpoint (“WML”) to the drive. When
the torque pre-control setpoint is received, the drive slowly increases its actual
torque on a linear ramp. When the actual torque reaches the reference value, the
“drive engaged” signal is sent back to the PLC.
The PLC then releases the brake. When the brake is fully released, the PLC
sends the “release speed” command and the speed setpoint to the drive.
The drive then accelerates along a 40 seconds S-ramp generated by its internal
ramp-function generator with jerk limiter.
This procedure takes place automatically after the start command and the speed
setpoint have been received from the PLC.
The PLC can stop further motor acceleration at any speed by sending a speed
setpoint of "0" and removing the “release speed” command. In this case, the
drive automatically reduces its speed along the new ramp generated by the
internal S-ramp-function generator.
The drives can be operated in forward and reverse direction at creep speed
(approximately 0.5 m/s).
At the moment of power failure, the drive can be in one of the following operating
modes:
In the event of a power failure, the DC-link voltage increases due to the line
not being receptive to receive active power. When the DC-link voltage
reaches the chopper braking setpoint value, the conveyor will be stopped
dynamically via the chopper braking.
In the event of a power failure, the DC-link voltage decreases due to the line
not providing energy to the drive. The drive trips and the conveyor will be
stopped by the mechanical brake system.
In the event of a power failure, the line frequency is not maintained. The line
frequency is monitored. When this frequency drifts out of the allowable set
frequency range, the conveyor is stopped with the mechanical brake
When the chopper braking has been triggered the following steps are initiated:
• Further operation of the motor side inverter continues until the maximum
operating time of the chopper has been reached (80 seconds)
• 2 sec before the maximum operating time of the chopper has been
reached, a signal “chopper operation is about at the end” is send to the
PLC. The PLC then applies the mechanical brake. After the brake has
been applied, the drive and the chopper are switched off by the PLC by
removing the start command
• Start level
The Chopper control is activated at a voltage level higher than 4700 Volts.
This level is only reached when the power supply is disturbed. The DC-link
voltage is controlled to a level of 4300 V.
This start level (4700 V) is called trigger level in the text that follows.
The DC-link trigger setpoint for the chopper controller is 4350 V.
• Chopper logic
After the chopper control has been triggered, a memory flag is set. This
prevents the chopper being triggered for a 90 second period. The reason for
this delay is to avoid a triggered chopper dissipating braking energy into a
preheated braking resistor.
• Temperature supervision
The braking resistor is protected with two temperature switches, one above each
resistor stack. Both switches are installed to protect the resistor against high
temperature. The temperature switch is adjusted at 250°C. This is the estimated
air temperature at the sensor location when the resistor element temperature is
550°C.
In the event of an inverter failure, the PLC checks whether continuing operation
is allowed. As each drive can provide 130% of the nominal torque for 30 minutes
(35 minutes for conveyor 120-CV-007), the PLC confirms continuation of
operation, if the load does not exceed this value for each motor. Otherwise the
system is automatically shut down by the mechanical braking system. In addition
to this, the defective inverter is disconnected from the supply system. The control
system memorises with which drive motors and inverters the drive is still in
operation.
The feeding of the conveyor system is reduced to a point where the torque of all
motors is reduced to nominal torque within 35 minutes.
The AFD converters of the drives require forced air cooling; therefore each AFD
is equipped with 6 cooling fans (3 per inverter) on the SIMOVERT ML converter,
and one (1) on the braking chopper. The operation of the fans is monitored with
two air pressure switches per inverter and one air pressure switch per chopper.
• One fan fails on one or both inverters Æ the controller sends an alarm to the
PLC; a restart is disabled.
• Two fans fail on one or both inverters Æ the drive trips, the conveyor is
stopped with the mechanical brake.
• The chopper fan fails during regenerative operation Æ the controller sends
an alarm to the PLC and the chopper braking is disabled. In the event that a
power failure follows, the AFD trips and the conveyor is stopped with the
mechanical brake. A restart is disabled.
• The chopper fan fails during chopper braking Æ the drive trips, the conveyor
is stopped with the mechanical brake.
It is possible to select and de-select drives during operation ("on the fly"). This
can be done, if:
• An alarm is sent from the AFD, which does not require an immediate
shut down.
• The conditions for de-selecting a drive are the same as shown in the
paragraph "Drive-failure".
To reduce jerks in the conveyor belt, the switching of the torque is done smoothly
in a time of approximately 5 to 10 seconds.
Conveyors 120-CV-005 and 120-CV-006 are equipped with two drive pulleys,
AT1 and AT2. Each of these drive pulleys is driven by two 2,500 kW drive
motors. As the conveyor system operates in a steep downhill mode, the drives
are located at the tail end of the conveyors. The head station is not equipped with
a drive. A relatively low, practically constant belt tension (100 kN) is applied to
the conveyor belt by a gravity tensioning weight, connected to the conveyor belt
via a series of return pulleys. The position of the gravity take-up weight changes
in vertical direction as the load on the conveyor belt changes, as well as during
acceleration and braking operation.
Contrary to most industrial drives which normally can be modeled with single
mass or dual mass loads, a drive for a conveyor belt has a closed loop control
circuit in which continuously distributed masses and springs are present. A drive
for a dual mass load has a sinusoidal characteristic with a fixed system
frequency response after an induced speed step change. This is, however, not
the case for a conveyor belt system, where initially unexpected speed step
fluctuations occur which, only after some time, gradually change to a sinusoidal
characteristic with a characteristic constant frequency. Results from simulation
models show that the duration of the period for these oscillations is
approximately 9 seconds due to the extreme length of these conveyors at 6000
meters. When this 6-km conveyor belt is loaded at full capacity, a speed or
These difficult parameters in the closed loop control circuit of this system, which
can easily oscillate with low damping capability, lead to a control concept in
which torque step functions and bumps must be eliminated. The motor drive
torque, needed to accelerate the conveyor, must be applied on a linear ramp. In
addition to this, the speed setpoint value must be applied with a curve into the
linear acceleration phase as well as with a curve into the constant speed phase.
The soft – ramp generator (S-HLG) is included in the design concept for this
purpose. This ramp generator (S-HLG) converts an incoming stepped speed
setpoint change value into a speed setpoint value with curved characteristic v*.
This setpoint value v*, ensures that the acceleration, “amax,”, as well as the jerk,
“rmax”, are limited and will not exceed a predetermined maximum value. (the jerk,
“r max”, is the first derivative of the acceleration value). The jerk time, defined as
the time ramp in which the torque increases, is defined as the quotient of “amax”
and “rmax”. (“amax” / “rmax”). The acceleration can be adjusted independently for
acceleration and deceleration. (In this case 40 seconds starting time and a
braking time of 76 / 78 / 80 seconds).
The ramp generator S-HLG is equipped with two outputs, which are realized
through integrators:
• The output v*, which corresponds exactly with the input value after the
system oscillations have stabilized.
• The output for the acceleration value a*, which is required for the
generation of the acceleration torque.
The diameters of the drive pulleys will decrease as time passes due to wear. The
drive motor rpm therefore needs to be increased in order to maintain a constant
speed of the conveyor belt. A conveyor belt speed correction circuit serves to
meet this requirement. The output of the S-HLG is connected to a multiplier that
in turn receives an input from the conveyor belt speed correction circuit. This
signal is compiled as a set point from the output value of the S-HLG and actual
value of the conveyor speed, which is derived from an encoder driven by a non-
driven conveyor pulley. The controller for this purpose is an integrating controller
(realized in the S5 PLC) with a long integration time, in order to delay / eliminate
smaller fluctuations. This controller is designed with a limitation value set at a few
percentage points of the nominal value. In connection with the addition of the
value 1, a small adjustment range of the belt speed correction circuit is achieved.
The integrated value of this controller is stored before stopping the conveyor,
which ensures that this value will not change during braking or after the conveyor
has stopped. The integrator is released only after the conveyor rated speed is
reached again after a subsequent start.
Each drive is equipped with a closed loop speed controller, however, the speed
controller of both drive motors on one pulley are in identical operating modes. For
example, the input (setpoint) value to the controller for the drive pulley AT1, is
“WN01” and the actual speed value “XNP1”, which is derived from the mean
average value of the actual speeds of the drive motors M11 and M12. The actual
values for the drive motor speeds are generated by digital encoders on the main
drive motors. This mean average actual value generation has the advantage of
stabilizing the closed loop control circuit in the event that the individual main drive
motors oscillate with respect to each other.
With this gain a static speed control in the range of 10 to 5% is achieved which
contributes to equal load sharing on both drive pulleys.
Simultaneously, this integrator is utilized for advance load control. Similarly to the
conveyor speed correction control, the value of the advance load control is stored
before the conveyor stop command is released. This stored load value is now
available to the control systems before a restart command of the conveyor is
released. Contrary to other large drives in industry, the conveyor load conditions
do not change significantly during stopping of this conveyor.
The load sharing on both drive pulleys can be different due to differences in the
diameters of the drive pulleys. The load sharing controller processes the
difference of the output values of the speed controllers in an integrating
Minimal speed differentials between the two drive pulleys can also occur due to
the elasticity slip of the belt as it wraps around the drive pulleys. Also these
differences in speed are corrected by the load sharing closed loop control circuits
The three torque set points which are derived from the speed controllers, from
the advance load control and from the advance acceleration control, are added
together and limited. The torque limitation for the drive motors is herewith
achieved in a simplified way. For this system the limitation is adjusted to 1.5
times the nominal value. From this point on the setpoint is connected to a ramp
generator with a short ramp time (approximately .5 to 1 second). This measure
will ensure that hard torque jerks / bumps on the drive motors are avoided due to
any possible irregularities in the closed loop controller circuits.
The bottom closed loop control circuit is the torque closed loop control circuit,
with which an arbitrary torque set point M* can be converted into a corresponding
motor torque independent of the motor speed. As both motors which are driving
one drive pulley, receive the same torque set point M*, both motors also apply
exactly the same torque to the pulley.
The danger that both drive motors will start oscillating with respect to each other
exists with the drive configuration (motors coupled to the drive pulley via angle
gear reducers, as used on this these conveyors). This is particularly the case
when the play in the gear reducers is more significant.
A differential speed filter has been included in the design to prevent these
oscillations. The difference between the two motor speed signals is connected to
the torque set points of each motor via a variable gain-inverting controller. This
insures that oscillations of this nature are filtered.
During operation of the conveyor system Los Pelambres it can occur that the
torque delivered by the motors connected to the drive pulleys, as demanded by
the control system, hovers around the value zero for extended periods of time
under certain load conditions. Operation under these “zero demand torque”
conditions can cause greasing problems as well as the tooth surfaces of the
gearwheels to knock against each other in alternate forward and reverse
directions during minor fluctuations of the demand torque. This operation can
In order to avoid this unfavorable operation, a control circuit has been developed
which ensures that the drives / gear reducers can not be operated under these
conditions.
A suitable circuit design has the feature that a relatively fast transition from a
negative to a positive torque value, and vice versa, is achieved on a unit drive
(ATR1, ATR2), during a conveyor torque demand, ( Manf ), transition. It is ensured
that a unit drive can not operate at zero torque for any extended period of time.
As also in the forgoing solution, the unit drive torque’s on the drive pulleys ATR1
and ATR2, have the same sense of direction for a conveyor drive demand torque,
(Manf) above a given minimum demand torque, (delta Manf).
When the conveyor demand torque, “Manf”, approaches the zero line by a value
“delta Manf”, an additional torque, delta “Mversp”, is added to the current drive
torque on ATR1 such that the resultant torque will cross the zero line.
Simultaneously, a torque “delta Mversp” of the same magnitude but with opposite
sense of direction is added to the torque on ATR2. These two torque additions, to
ATR1 and ATR2 respectively, herewith cancel each other on the current
conveyor torque ( Manf ). The application of the torque addition “delta Mversp” is not
realized as a step function, but is applied on a ramp via a ramp generator, (with a
ramp time of approximately 5 seconds), in order to avoid oscillations in the
system.
It is important that the comparator circuits, which detect the conveyor demand
torque, “Manf”, approaching the zero torque line, have a hysteresis. This
hysteresis prevents frequent switching of this control during minimal demand
torque variation transients. The load torque (load integrator) is used as the
“conveyor demand torque” value “Manf”. The zero torque suppression, counter
torque control system, is released only during stationary operation. This means
that only after the conveyor has accelerated to rated speed, and after the closed
loop control system for the load sharing has stabilized, is the zero torque
suppression control released.
Should the zero torque situation occur during startup of the conveyor drive, this
zero torque condition is allowed.
All the overland conveyors are fitted with low speed, mechanical, disk brake systems
The mechanical brakes are used as a backup to the AFD drives to bring the conveyors to
a controlled stop in case of AFD, motor, or UPS power failure, or whenever a malfunction
of level 3, 4 or 5 is detected. They are also used to park the conveyors at the end of each
stopping cycle.
Each brake system consists of a central power pack, of several low speed disks with two
calipers per disk, and of several hydraulic modules. The brake disks are mounted on the
conveyor drive pulleys and on one bend pulley at the conveyor tail stations.
Conveyors 120-CV-005 and 120-CV-006 are equipped with six low speed disks (two on
each drive pulley and two on the bend pulley), with two quick-set modules located near
the primary and secondary drive pulleys, and with one quick-apply module located near
the tertiary bend pulley.
Conveyor 120-CV-007 is of a similar design, but is only equipped with three low-speed
disks (one on each pulley) and with two quick-set modules located near the primary and
secondary drive pulleys.
The brake systems include both digital and analog controls. Several calipers on each
system are controlled with simple on/off valves (digital calipers), while the remaining
calipers are controlled from a proportional pressure control valve (proportional calipers).
This combined design was selected to decrease the response time of the brake while
decreasing the peak tension in the belt in case of UPS power failure.
Conveyors 120-CV-005 and 120-CV-006 are equipped with one proportional caliper and
one digital caliper on each disk. All the proportional calipers are of a fail-safe design
(spring applied, hydraulically released). All the digital calipers on the primary and
secondary drive pulleys disks are also of a fail-safe design. The digital calipers on the
tertiary bend pulley disks are of a fail-open design (pressure applied). This was done to
decrease the peak tension in the belt in case of UPS power failure while providing back-
up braking capacity under PLC control.
Conveyor 120-CV-007 is equipped with one proportional caliper and one digital caliper on
the primary and secondary drive pulleys disks, and with two proportional calipers on the
tertiary bend pulley disk. All the calipers are of a fail-safe design.
In the event of failure of the brake proportional control circuit, or whenever the
conveyor emergency circuit is tripped, the proportional calipers are applied with
an emergency circuit that provides a preset torque control independent of the
PLC (level 4).
All the available brake torque is applied during an emergency brake stop
on conveyor 120-CV-007.
All the energy produced by the mechanical brake during a conveyor stop
is dissipated in the brake discs. Consequently, the brake discs can
become very hot. This is especially true following emergency stops from
high overspeed.
To prevent a conveyor start when the discs are too hot without imposing
unnecessary restriction on the minimum time between conveyor starts,
each brake disk is equipped with an infrared temperature detector.
The temperature of all the discs is checked prior to every conveyor start,
and the start sequence is blocked if the temperature of any disc is above
the start permissive limit.
The following controls are provided from the hydraulic cabinet panels:
The following controls are provided from each quick-set and quick-apply
module:
The mechanical brake system used on all the conveyors consist of several low
speed steel disks fitted with two calipers each, of one central hydraulic power
pack, and of several quick-set and quick-apply modules located close to the
brake disks.
The brake disks are mounted on the conveyor drive pulleys and on one bend
pulley at the conveyor tail stations. The disks are installed on the low speed side
The brake calipers are of the clamshell design and use a dual spring/piston
assembly per caliper. Both fail-safe and fail-open calipers are used.
On fail-safe calipers, the braking force is obtained from springs that push the
brake pads against the disk. The caliper is released by applying hydraulic
pressure to the piston, therefore decreasing the clamping force. When fully
released, the pistons retract and the pads lift free of the disk.
The hydraulic power packs provide the working pressure for all calipers, and
include the proportional control and emergency components for the proportional
calipers.
The control components for the fail-safe digital calipers are located in the quick-
set modules. One quick-set module is used for each pulley fitted with fail-safe
calipers (primary and secondary drive pulleys on all conveyors).
The control components for the fail-open digital calipers are located in the quick-
apply modules. One quick-apply module is used for each pulley fitted with fail-
open calipers (tertiary bend pulley on conveyors 120-CV-005 and 120-CV-006).
A single hydraulic power pack is used for each conveyor. Each power pack is
composed of one large cabinet located close to the conveyor tail station. The
electrical components are located inside a smaller electrical enclosure mounted
to the side of the hydraulic cabinet.
All the hydraulic components in each power pack are mounted on two manifolds
inside the main cabinet. The pressure generation and the proportional control
components are mounted on one hydraulic manifold. The quickset components,
the emergency components, and the dump components are mounted on a
separate manifold.
The active pump is selected by the PLC based on alarm conditions and
operator commands. If a pump failure is detected while the conveyor is
running, the PLC automatically switches to the remaining pump. If both
pumps are faulty, a dual pump fault is latched and the conveyor is
stopped using the AFD drives.
Pressure relief valve PRB is used to protect the pumps from excessive
pressure.
The filter assembly is equipped with two filters. The active filter is
selected with manual valve MVF.
Pressure switches PS1A and PS1B are used to control the active pump
in order to maintain the corresponding accumulator pressure. The
accumulators are sized to minimize pump cycling and to provide enough
fluid reserve to complete a full controlled stop in case of pump or AC
power failure.
Several check valves are used to direct the flow and isolate the various
part of the circuit. Each digital caliper set and the proportional calipers
are similarly isolated from each other. Consequently, a catastrophic loss
of pressure at any caliper, or on the main accumulator, would not result
in a loss of pressure at all calipers.
This category includes the main and the standby pressure control
components for the proportional calipers as well as several common
The main components include the main pressure control valve and its
associated pressure regulator, isolation valves SV1A and SV2A, and full
release valve SV3A.
The standby components include the standby pressure control valve and
its associated pressure regulator, isolation valves SV1B and SV2B, and
full release valve SV3B.
Solenoid valve SV3A (or SV3B) is used to bypass the pressure control
valve and apply the accumulator pressure directly to the proportional
caliper line during running conditions. This insures full release of the
brake calipers and minimizes the duty on the pressure control valves.
Solenoid valves SV1A and SV2A (or SV1B/SV2B) are used to isolate the
pressure control valve from the proportional caliper line during full
release and emergency conditions.
Pressure transducer PT1 is used by the PLC to confirm the action of the
pressure control valve and to check the pressure decay during
emergency braking.
This category includes solenoid valve SVE2 and pressure relief valve
SQV2.
This category includes solenoid valve SVE1, pressure relief valve SQV1,
the emergency accumulator and the emergency orifices. Valve SVE1 is
normally open and is connected to the conveyor emergency circuit
The proportional calipers then discharge very fast into the emergency
circuit, bringing the pressure down to approximately 50%. After this initial
drop in pressure, the emergency accumulator discharges slowly trough
the emergency orifices, bringing the proportional calipers pressure to
zero in about 10 seconds.
Two emergency orifices are used. The first one is a fixed orifice with a
bleed time of approximately 20 seconds. The second orifice is adjustable
and should be set for a combined bleed time of 10 seconds. This was
done to avoid the possibility of accidental closure of the adjustable
orifice, which would result in the loss of the emergency circuit.
The design preset pressure ramp for the emergency circuit is shown in
appendix N.
The proportional calipers then discharge very fast into the dump circuit,
bringing their pressure down to zero in less than 1 second.
All the control components for the fail-safe digital calipers are mounted
on manifolds located inside the quick-set modules. One quick-set module
is used for the primary drive pulley and one for the secondary drive
pulley on all conveyors. The modules are located next to the pulley.
Solenoid valves SVSP1 and SVSP2 are used to release the hydraulic
pressure on the caliper and apply the brake. Two valves are used for
redundancy.
All the control components for the fail-open digital calipers are mounted
on manifolds located inside the quick-apply modules. One quick-apply
module is used on conveyors 120-CV-005 and 120-CV-006. It is located
next to the tertiary bend pulley.
The control components for each quick-apply module includes one check
valve (CVB1), one spring accumulator (ACQA), three solenoid valves
(SVB1, SVB2, and SVB3), and one pressure switch (PSQA).
When the pump is started on the main hydraulic power pack, the spring
accumulator ACQA is automatically charged through check valve CVB1.
This check valve insures that accumulator ACQA stays pressurized even
in case of UPS power or main pack pump failure.
Solenoid valves SVB1 and SVB2 are used to apply the hydraulic
pressure from accumulator ACQA on the calipers and apply the brake.
Two valves are used for redundancy.
Solenoid valve SVB3 is normally open. All the other solenoid valves are
normally closed. None of the solenoid valves are connected to the
conveyor emergency circuit.
In the original system configuration, conveyors 120-CV-005 and 120-CV-006 were only
equipped with three drives each. These drives, as well as both drives on conveyor 120-
CV-007, are fitted with Keller reducers.
An additional drive was installed on conveyors 120-CV-005 and 120-CV-006 during the
system upgrade performed in 2006. The new drives are fitted with Flender reducers.
The Keller and Flender reducers differ in several ways, the most important one being the
type of lubrication used. The Keller units are splash lubricated while the Flender units are
forced lubricated.
In addition, the Keller unit has a reduction ratio of 22.423 and the Flender units have a
reduction ratio of 22.432. While the difference amounts only to 0.04%, it is large enough
to require compensation in the drive control logic to enable proper load sharing between
the drives on the same shaft. This compensation is performed in the drive control block of
the PLC.
The following paragraphs provide a basic description of the control logic required for each
type of reducer.
All the reducers are equipped with digital vibration sensors, analog oil
temperature sensors, analog bearing temperature sensors, and digital oil level
sensors. These sensors are monitored by the PLC’s.
The vibration sensors are used for monitoring only and do not result in a
conveyor shutdown when triggered.
All the temperature sensors are monitored for high and very high levels.
Detection of a very high temperature condition on any sensor results in an
immediate shutdown of the conveyor using the AFD drives (level 2).
The Keller reducers are splash lubricated and do not require a dedicated
lubrication system.
The reducers were initially installed without oil cooling systems, but were
retrofitted with coolers at a later date. The reducer cooling systems are controlled
by independent controllers and are not under PLC supervision.
The Flender reducers are forced lubricated and are equipped with dedicated
lubrication systems. Each lubrication system includes a hydraulic power pack, a
hydraulic pump, a heat exchanger, and a fan. In addition, each reducer is
equipped with an oil heater.
The lubrication system is automatically stopped by the PLC a short time after the
conveyor reaches a complete stop. If the reducer oil temperature is high at the
time of the shutdown, the lubrication system is kept on to enable the oil cooler to
operate. The lubrication system is automatically stopped by the PLC when the oil
temperature has returned to normal.
The reducer oil temperature is monitored by the PLC using both the temperature
sensor connected to the PLC and the feedback received from the lubrication
system controller via the Profibus link.
The belt tension of each conveyor is controlled by a gravity take-up located at the head
station. All the conveyors are equipped with a take-up winch used to position the
counterweight.
Each take-up system is equipped with one electric winch. The winch motor is
fitted with an internal brake. The winch is used to position the counterweight.
The take-up carriage and the take-up counterweight are equipped with over-
travel position switches. These switches are connected to the PLC and are not
hardwired to the winch motors.
All the take-up systems are equipped with a latching emergency stop switch. This
switch is hardwired to the winch motor contactor. Actuation of this switch stops
the winch motor and initiates a conveyor shutdown using the AFD drives.
Several control modes have been defined for the take-up winch. The control
mode is selected from a mode selector switch (MSS) located in the field.
The MSS switch is used for software mode selection only and is not hardwired to
the equipment. The operating mode for the take-up winch is selected by the PLC
according the following combinations:
When the conveyor is running, the PLC controls the winch to maintain
the counterweight position within a preset operating range.
The local-manual mode provides control of the winch from push buttons
located in the field.
This mode provides the ability to position the counterweight from the field
while the conveyor is running. All interlocks are kept active.
• Move counterweight up
• Move counterweight down
The maintenance mode also provides manual control of the winch from
push buttons located in the field.
This mode provides the ability to move the counterweight to any position
for maintenance purposes. This mode can only be entered if the
conveyor is stopped and conveyor starts are prevented in this mode.
All interlocks are disabled in this mode except the over-travel position
switches.
This mode provides the ability to disable the winch motion for operational
purposes.
The conveyor can be still operated with the winch disabled as long as the
counterweight position is within its operating range.
The shuttle motion is controlled by an AFD drive with a maximum speed of 10 meters per
minute. The shuttle position is monitored with an absolute encoder.
The shuttle position is continuously variable under load, but the discharge positions are
limited due to interference with structural beams. The shuttle can be moved over the
structural beams while material is flowing, but cannot be parked over them.
The shuttle currently travels over a 62 meters span. Six discharge positions are used to
form an elongated stockpile. The shuttle travel will be extended to 94 meters in the future,
with additional discharge positions added as required.
Shuttle motor faults and shuttle jam alarms do not result in a conveyor shutdown
if the shuttle is located in a valid position.
The shuttle is equipped with two digital stockpile level switches used for blocked
chute detection. A high stockpile level detected by one of these switch results in
an immediate shutdown of the overland conveyor system.
The shuttle is also equipped with two analog stockpile level sensors. These
sensors are located on the shuttle carriage. The two sensors are constantly
compared to each other and the higher of the two reading is always used for
control. An alarm is latched whenever the two readings differ by more than 10%
for more than 10 seconds, and the belt feeders are automatically stopped if both
sensors are found defective.
The stockpile level sensors are monitored in all modes of operation. The high
level setpoint is adjusted to provide enough room on the stockpile to empty the
conveyor system. When a stockpile full alarm is latched, a warning is displayed
on the operator screens and the belt feeders are automatically stopped.
The stockpile to belt feeders interlocks are done trough a hardwired interlock
between PLC 7 and PLC 5 (relayed by PLC 6).
The shuttle is equipped with several latching emergency stop switches and
several pull cord switches. These switches are hardwired to the shuttle motor
contactor. Actuation of any of these switches stops the shuttle motion and the
conveyor system.
Several control modes have been defined for the shuttle. The control mode is
selected from the maintenance workstation (OP37) and from a mode selector
switch (MSS) located in the field. Access to the various modes from the
maintenance workstation is passwords protected.
The MSS switch is used for software mode selection only and is not hardwired to
the equipment. The operating mode for the shuttle is selected by the PLC
according the following combinations:
The operator can remotely select the shuttle position control mode,
enable and disable the shuttle automatic motion, and enter the position
control parameters. In addition, several local operator commands are
available from the shuttle field control panel. These commands are
described in chapter 11.2.3 (local-manual mode).
• Fixed position
• Automatic motion between selected positions
In the automatic mode, the shuttle is operated between two end positions
selected by the operator. The shuttle remains in the first position for a
preset time (initially 5 minutes). It is then automatically moved from
position to position at the same preset time interval. When the last
position has been reached, the shuttle is automatically moved back to
the first position and the cycle is started again. If a high stockpile level is
Before any automatic shuttle motion, the shuttle warning horn and
beacon are turned on for 5 seconds. They are then kept on until the new
position has been reached.
The local-manual mode provides control of the shuttle from push buttons
located in the field.
This mode provides the ability to position the shuttle from the field while
keeping all interlocks active.
Shuttle motion can be resumed by first pushing the local reset button,
then pushing the forward or the reverse push button. In both automatic
modes, only the push button pointing toward the active operator position
setpoint is enabled.
The shuttle warning horn and beacon are turned on for 5 seconds before
any shuttle motion. They are then kept on until the new position has
been reached.
The maintenance mode provides manual control of the shuttle from push
buttons located in the field.
This mode provides the ability to move the shuttle to any location and
should be used for maintenance purposes and to help during
commissioning of the shuttle.
All internal shuttle interlocks are maintained in this mode. However, all
external interlocks are disabled.
In this mode, the shuttle can be positioned at any location between the
end-of-travel position switches. The shuttle warning horn and beacon are
turned on for 5 seconds before the shuttle motion is initiated. They are
then kept on as long as the shuttle is moving.
This mode provides the ability to disable the shuttle motion for
operational purposes.
The conveying system can be still operated when the shuttle is disabled
as long as the shuttle is located in a valid position.
Two different kinds of dust suppression systems are used in the conveying
system:
One fogger system is used at each conveyor loading station (feeder area and
transfer stations), and one spray water system is used at conveyor 120-CV-007
discharge station (shuttle area).
The dust suppression systems are constantly monitored by the PLC. Abnormal
conditions are alarmed and displayed on the operator screens. Dust suppression
alarms do not result in conveyors shutdown.
Each fogger system is composed of one common power station, one air
compressor, and several local fogger stations (one per belt feeder and
one per transfer station).
The PLC controls the air compressors. The power station controls the
flow of water and air to all the fogger stations. Each station is equipped
with several control relays (heater, water flow and airflow), and several
monitoring devices (low air pressure and low water pressure).
Each fogger station controls its own spray. Fogger stations are equipped
with several control relays (water flow, airflow, and purge control) and
one mode selector switch. The fogger mode selector switch is hardwired
and independent of the PLC.
The foggers are normally operated in remote mode. In this mode, the
PLC automatically turns on each fogger spray when the corresponding
feeder/conveyor is in operation.
The spray system is normally operated in remote mode. In this mode, the
PLC automatically enables the spray system when conveyor 120-CV-007
is running, and adjusts the water flow based on the amount of ore
detected on the conveyor.
Several air conditioning units are used at each substation to cool the
AFD drive containers. Due to the large amount of heat dissipated by the
AFD drives, these air conditioning units are critical to the operation of the
system. Consequently, several standby units are also installed.
All the air conditioning units are constantly powered. However, only the
units required for operation are enabled.
In case of UPS line voltage failure, all the air conditioning units are
disabled one minute after the conveyor has reached a complete stop.
This is done to save battery power on the UPS.
All the air conditioning units are continuously monitored by the PLC.
The following tables show the number of units available, the number of
units required, and the number of standby units at each substation:
120-CV-005 AC Units
AFD House Available Units Required Units Standby Units
House 1 3 2 1
House 2 3 2 1
120-CV-006 AC Units
AFD House Available Units Required Units Standby Units
House 1 1 1
1 (Shared)
House 2 1 1
120-CV-007 AC Units
AFD House Available Units Required Units Standby Units
House 1 2 1 1
The standby units are automatically enabled by the PLC in case of failure
of one of the normal units.
When two units fail at the same time, the corresponding conveyor is
immediately stopped with the AFD drives (level 2).
The standby unit for conveyor 120-CV-006 is shared between the two
houses. A gate is used to direct the airflow into the required house. The
Each AFD drive container and each high voltage container is equipped
with a fire detection system.
When a fire is detected in one of the AFD drive containers or in the high
voltage container, the main 23 kV breaker is immediately tripped, the
AFD drives are tripped, and the corresponding conveyor is stopped with
the mechanical brake (level 3).
Each AFD drive container and each high voltage container is equipped
with two latching emergency switches located inside and outside the
container next to the main door.
Each 155H PLC is equipped with two 948R CPU’s in a switched configuration.
This configuration offers central controller redundancy.
The two CPU are designated master and standby. All the I/O information is under
control of the master CPU, but is available to the standby CPU through the use of
special registers. All information used, received and issued from the master CPU
is therefore the same in the standby CPU. The transfer from master to standby
CPU is synchronized with the CPU’s scans. This synchronization procedure
ensures bumpless switching from master to standby controller at all times:
The PLC automatically switches from the master to the standby controller in the
following instances:
Full indication of the CPU’s status and alarm condition for each PLC is available
on the operator graphics screens.
The health of each local I/O module is constantly monitored by the PLC.
Full indication of each local I/O rack alarm condition is available on the operator
graphics screens.
Two local Profibus networks are used at each drive station. The first network is
used to connect the AFD drives Simadyn controllers to the PLC. The second
network is used to connect the PLC to the maintenance workstation, the local
operator interface terminal, and the remote I/O modules located in the drive
station and along the conveyor.
The Profibus network is a high speed field bus designed for cyclic communication
where I/O modules are distant from the PLC. It operates under a master slave
protocol similar to an RS-485 network and uses differential voltage signals over
single twisted pair wiring for high transmission rates and high noise immunity.
The Profibus port’s Baud rate is selectable from 9.6 kbit/s to 12 Mbit/s. A
maximum of 32 masters and 126 slaves can be configured on each Profibus
network.
16 remote I/O modules are used for PLC 5, 15 for PLC 6, and 5 for PLC 7. In all
the Profibus networks, the PLC is configured as the master and all the other
nodes as slaves.
All the Profibus network functions are controlled by the Profibus communication
processor. All the Profibus network configuration, programming, and diagnostic is
done by this processor independently of the PLC. Several diagnostic functions
are built in the communication processor and are available to the PLC. The
overview diagnostic function is used to check the status of the slave stations. The
master diagnostic function provides the status of the master station.
When a Profibus failure is detected on a single drive, the PLC trips the faulty
drive using its E-stop output but the conveyor is not stopped provided that all the
other drives are operational and that the load on the conveyor would not result in
overloading of the remaining drives.
14.4 H1 Network
All the PLC’s and operator graphic stations are interconnected by an H1 network.
The H1 network information is carried between the substations and the operator
control rooms over a redundant fiber optic network (OTN network). The OTN
network is transparent to the PLC’s.
The H1/OTN network is only used for monitoring, diagnostics and operator
control. All conveyor to conveyor interlocks are hardwired between the PLC’s to
insure fail-safe operation under any conditions.
Six short Ethernet H1 connections are used in the network. The first three are
used to connect the PLC’s to the main OTN network. The other three are used to
connect the operator stations to the OTN network.
The H1 network is used for monitoring, diagnostics and operator control only and
does not carry critical interlocking information. All critical interlocks are hardwired
between each PLC. This was done to enable safe operation of the complete
system in case of graphic station or network failure. A failure of the H1/OTN
network does not result in a conveyor shutdown.
Full indication of each H1 link status and alarm condition is available on the
operator graphics screens.
5 OTN nodes are used in this project. Each node consists of a modular card
structure mounted in a rack. Various interface cards are used at each node for
the following equipment:
H1 network
RS-485 network (Modbus)
Video connection
Telephone connection
RS-232 communication
The OTN network is independent of the PLC’s and of the H1 network, and no
direct OTN status or diagnostic information is available to the PLC’s or the
operator stations. However, critical OTN failures are brought to the operator’s
attention through the failure of the corresponding H1 station.
Two local RS-485 links are used in each substation. The first link is used to
connect the 23 kV monitoring relays to the PLC. The second link is used to
connect the 400V monitoring relays to the PLC. Those links are used for
monitoring purposes only.
Each PLC is equipped with a CP544 RS-485 communication card plugged in the
PLC rack. The CP544 communication processor is used for fast point-to-point
connections to programmable controller or equipment from other manufacturer
using standard protocols. All the RS-485 network functions are controlled by the
communication processor on the CP544 card. All the network configuration,
programming, and diagnostic for the RS-485 networks is done on this card
independently of the PLC. However, basic network diagnostics are available in
the PLC.
Each card has two independent communication ports. Each port’s Baud rate is
selectable from 300 bits/s to 76,800 bits/s. The first port is connected to the 23
kV power meter. The second port is connected to the 400 V power meter. Both
ports are set up as Masters.
• Amps
• Volts
The operator station in the crusher control room #1 is connected to the mine PCS
via an RS-485 link using the Modbus protocol. This link is only used for alarm
and status monitoring by the PCS system.
The operator station communicates to the PCS using the station’s RS-232 port
and an RS-232 to RS-485 converter. The operator station computer is set up as
a Slave and the PCS as a Master. All information available to the operator station
is also available to the PCS. This link is not monitored by the operator stations.
To PCS
REV
U1
CHK
JLC
SHEET : 1/1
MATERIAL FLOW AND CONTROL
AREA 120 LAYOUT:
DWG: LSP-OVERVIEW-R4.VSD
CRUSHER CONCENTRATOR
COMM. ROOM COMM. ROOM
B B B
A A A
P5 P6 P7
JOB: 194
FE-008
LOS PELAMBRES PROJECT
FE-007
FE-006 TAIL STATION TAIL STATION TAIL STATION
GENERAL LAYOUT
FE-005
CV-005 (5,905 m, -536 m)
PHASE 2
- Ethernet Hub
- AFD Drive ( Simadyn D)
- Fiber Pair
- Power Meter 4700 (23KV, 400V)
- Modbus
- Maintenance Workstation (OP 37)
- RS-485
This drawing is the property of Conveyor Dynamics Inc. It is loaned upon the express condition that it shall not be copied or reproduced in any manner, that it shall not be submitted to others for examination without
the consent of Conveyor Dynamics Inc., that it shall not be used in any other way detrimental to the interests of Conveyor Dynamics Inc. and that it shall be returned to Conveyor Dynamics Inc. upon demand.
Coarse Ore Conveyor 120-CV-005
50
-50
-100
-150
-200
-250
-300
-350
-400
-450
-500
This drawing is the property of Conveyor Dynamics Inc. It is loaned upon the express condition that it shall not be copied or reproduced in any manner, that it shall not be submitted to others for examination without the
-550
0 1000 2000 3000 4000 5000 6000
Station (m)
consent of Conveyor Dynamics Inc., that it shall not be used in any other way detrimental to the interests of Conveyor Dynamics Inc. and that it shall be returned to Conveyor Dynamics Inc. upon demand.
120-CV-005 Profile
Primary
Head
Secondary
120-CV-005 Geometry
2500 kW 2500 kW
DATE REV CHK DWG: LSP-APP-A-LAYOUT-R6.VSD KRUPP - SIEMENS CONVEYOR DYNAMICS, INC
03/01/06 U1 JLC LOS PELAMBRES PROJECT
CONVEYOR 120-CV-005 LAYOUT
PHASE 2
SHEET: 1/3 JOB: 194 GENERAL LAYOUT
To AFD Drive To AFD Drive
To AFD Drive To AFD Drive
Reducer Motor 12 Reducer Motor 22
To PLC
To Weight Scale 2 To PLC
Disk 12 Disk 32 (120-CV-005 Only) Disk 22 To PLC To PLC
This drawing is the property of Conveyor Dynamics Inc. It is loaned upon the express condition that it shall not be copied or reproduced in any manner, that it shall not be submitted to others for examination without the
Pulley Pulley Pulley
consent of Conveyor Dynamics Inc., that it shall not be used in any other way detrimental to the interests of Conveyor Dynamics Inc. and that it shall be returned to Conveyor Dynamics Inc. upon demand.
Disk 11 Disk 31 To Weight Scale 1 Disk 21
(120-CV-005 Only)
Reducer Motor 11 Reducer Motor 21
To AFD Drive To AFD Drive
To AFD Drive To AFD Drive
To PLC
To PLC To PLC To PLC
Legend
DATE REV CHK DWG: LSP-SPD-SENSORS-R4.VSD KRUPP - SIEMENS CONVEYOR DYNAMICS, INC
03/01/06 U1 JLC CONVEYOR SPEED LOS PELAMBRES PROJECT
SENSORS LOCATIONS PHASE 2
SHEET: 1/1 JOB: 194 GENERAL LAYOUT
Primary Tertiary Secondary
SD SP PD SP SD SP
This drawing is the property of Conveyor Dynamics Inc. It is loaned upon the express condition that it shall not be copied or reproduced in any manner, that it shall not be submitted to others for examination without the
consent of Conveyor Dynamics Inc., that it shall not be used in any other way detrimental to the interests of Conveyor Dynamics Inc. and that it shall be returned to Conveyor Dynamics Inc. upon demand.
SD SP PD SP SD SP
120-CV-005
SD SP PD SP SD SP
SD SP PD SP SD SP
120-CV-006
SD SP SP SP SD SP
120-CV-007
DATE REV CHK DWG: LSP-BRK-PAD-R4.VSD KRUPP - SIEMENS CONVEYOR DYNAMICS, INC
03/01/06 U1 JLC LOS PELAMBRES PROJECT
CONVEYOR BRAKE PAD LAYOUT
PHASE 2
SHEET: 1/1 JOB: 194 GENERAL LAYOUT
03/01/06
DATE
BRAKE HYDRAULICS
REV
Watchdog
U1
This drawing is the property of Conveyor Dynamics Inc. It is loaned upon the express condition that it shall not be copied or reproduced in any manner, that it shall not be submitted to others for examination without the
Relay
Emergency Valve
CHK
(Main Manifold)
(1 Hz Pulse) Delay
consent of Conveyor Dynamics Inc., that it shall not be used in any other way detrimental to the interests of Conveyor Dynamics Inc. and that it shall be returned to Conveyor Dynamics Inc. upon demand.
SHEET: 1/1
EMERGENCY CIRCUIT
DWG: LSP-EM-CIRCUIT-R5.VSD
SVE1
To PLC Input
KRUPP - SIEMENS
AFD Drive 12
(CV-005/006)
E-Stop Input
AFD Drive 21
Note:
E-Stop Input
AFD Drive 22
Solenoid valves for tertiary
digital brake calipers on CV-
CONVEYOR DYNAMICS, INC
(CV-005/006)
005 and CV-006 are not
E-Stop Input connected to the emergency
circuit and should be powered
directly from the UPS
Legend
Normally Open
Solenoid Valve
RESET O
A
F O W A P
L
S I P I U
A
E E N T 7
NOTES
R T
T L 3 O
M I S D
P D 7 C All alarms and malfunctions are displayed
DESCRIPTION O
M E
C R I
L E C on both the OP 37 and the WIN-CC stations
I E S
E R
N S P
V All Setpoints and Timer preset as of July 2000
T E L
E
T A
L Y
AREA INTERLOCKS
DOWNSTREAM TONNAGE LIMIT LEVEL 2 INTERLOCK A2 0.3 X X INDICATES DISABLED DRIVE ON CV-05/06, TRIGGERS TONNAGE LIMIT 2 (5200TPH)
HORN BREAKER START PERMISSIVE ALARM SP 0.3 X X X HORN BREAKER OFF OR TRIPPED
HORN BREAKER INTERLOCK M2 NA X X X START COMMAND RECEIVED WITH HORN BREAKER OFF OR TRIPPED
CONVEYOR INTERLOCKS
DOWNSTREAM RUN PERMISSIVE INTERLOCK M2 0.3 X X X
SHUTTLE/STOCKPILE INTERLOCK M2 NA X X X CONCENTRATOR STOCKPILE LEVEL HIHI OR SHUTTLE OUT OF POSITION, CV-07 ONLY
MODE INTERLOCK M2 NA X X X
BELT FEEDERS
INTERLOCKS
CLEANING REQUIRED ALARM A1 7 HR X
LOCAL STOP SWITCH SEQUENCE INTERLOCK M2 NA X X X MAGNET SYSTEM LOCAL STOP SWITCH ACTIVATED DURING CLEANING SEQUENCE
DRIVE
MODULE CONTROL MALF M2 2 X X NO ENABLED SIGNAL FROM JUPITER CARD
DRIVE - HYDRAULIC
CHARGE PRESSURE LO SWITCH ALARM A1 NO X
DRIVE - PUMP
GROUND FAULT A1 NO X
CONTACTOR MALF M2 2 X X
OVERLOAD MALF M2 2 X
DRIVE - COOLER
GROUND FAULT A1 NO X
DRIVE - TANK
LEVEL LO SWITCH ALARM A1 NO X
BELTLINE - MISC
ALIGNMENT ALARM A1 2 X
ALIGNMENT MALF M2 2 X
MAGNET E-STOP SWITCH MALF M2 0.3 X X STOPS FEEDER AND MAGNET CARRIAGE MOTION
BELTLINE - SPEED
BELT SPEED TACHOMETER INVALID ALARM A2 3 / 28 MA 0.5 X DISABLES BELT SPEED TACHOMETER INPUT
DRIVE SPEED TACHOMETER INVALID ALARM A2 3 / 28 MA 0.5 X DISABLES DRIVE SPEED TACHOMETER INPUT
CONTACTOR FORWARD ALARM A2 2 X X STOPS CARRIAGE FORWARD MOTION (TOWARD CONVEYOR POSITION)
CONTACTOR REVERSE ALARM A2 2 X X STOPS CARRIAGE REVERSE MOTION (TOWARD BIN POSITION)
CONTACTOR MALF - CV-05 CONVEYOR INTERLOCK M2 10 X X STOPS MAGNET FIELD, FEEDER AND CONVEYOR CV-05
DC RECTIFIER CURRENT MALF - CV-05 CONVEYOR INTERLOCK M2 10 X STOPS MAGNET FIELD, FEEDER AND CONVEYOR CV-05
OVERTRAVEL CONVEYOR POSITION SWITCH ALARM A2 1 X STOPS CARRIAGE FORWARD MOTION (TOWARD CONVEYOR POSITION)
OVERTRAVEL BIN POSITION SWITCH ALARM A2 1 X STOPS CARRIAGE REVERSE MOTION (TOWARD BIN POSITION)
POSITION FAULT M2 2 X
CONVEYORS
AFD DRIVES
DRIVE FAULT A2 NA X
ENGAGED ALARM A2 10 X
TOTAL TORQUE HI REGEN ALARM A2 -300% 10 X -200% FOR CV-07, TRIGGERS BELT FEEDERS SPEED SETBACK ON CV-05
TOTAL TORQUE HIHI REGEN MALF M1 -420% 10 X X -280% FOR CV-07, TRIGGERS UPSTREAM CONVEYOR SHUTDOWN
AFD RAMP UNDERSPEED MALF M3 10% UNDER 5 X X RAMP UNDERSPEED DURING START OR LEVEL 2 STOP
AFD RAMP OVERSPEED MALF M3 10% OVER 5 X X RAMP OVERSPEED DURING START OR LEVEL 2 STOP
BRAKE RAMP OVERSPEED MALF M4 10% OVER 5 X X RAMP OVERSPEED DURING LEVEL 3 STOP
BRAKE SYSTEM
PANEL E-STOP SWITCH MALF M4 0.3 X X ON BRAKE PANEL
BRAKE - HYDRAULIC
FILTER CLOGED ALARM (EACH FILTER) A1 2 X FROM DIFFERENTIAL PRESSURE SWITCH
OVERLOAD / CONTROL VOLTAGE ALARM A2 2 X STOPS PUMP MOTOR AND TRIGGER PUMP SWITCHOVER
DISCHARGE PRESSURE LO ALARM A2 30 X STOPS PUMP MOTOR AND TRIGGER PUMP SWITCHOVER
CONTROL PRESSURE LOLO MALF M2 400 PSI UNDER 3 X WITH RESPECT TO TARGET PRESSURE
CONTROL PRESSURE HIHI MALF M2 400 PSI OVER 3 X WITH RESPECT TO TARGET PRESSURE
EMERGENCY PRESSURE HIHI MALF M5 400 PSI OVER 4 X WITH RESPECT TO DESIGN PRESET RAMP
TEMPERATURE SIGNAL INVALID ALARM A2 3 / 28 MA 0.5 X DISABLES BRAKE DISC TEMPERATURE INPUT
OIL TEMPERATURE SIGNAL INVALID ALARM A2 -25 / 250 DEG C 0.5 X DISABLES OIL TEMPERATURE INPUT
BEARING TEMPERATURE SIGNAL INVALID ALARM (EACH SENSOR) A2 -25 / 250 DEG C 0.5 X DISABLES BEARING TEMPERATURE INPUT
OIL TEMPERATURE SIGNAL INVALID ALARM A2 -25 / 250 DEG C 0.5 X DISABLES OIL TEMPERATURE INPUT
BEARING TEMPERATURE SIGNAL INVALID ALARM (EACH SENSOR) A2 -25 / 250 DEG C 0.5 X DISABLES BEARING TEMPERATURE INPUT
LUBRICATION SYSTEM RUNNING MALF M2 1/10 X 10 SEC TIMER FOR INITIAL TURN-ON DELAY, 1 SEC TIMER FOR FAULT WHILE RUNNING
PULLEY BEARING TEMPERATURE SIGNAL INVALID ALARM (EACH SIDE) A2 -25 / 250 DEG C 0.5 X DISABLES BEARING TEMPERATURE INPUT
BELTLINE - PULLCORDS
PULLCORD FEEDER MONITORING ALARM A1 0.3 X
BELTLINE - ALIGNMENT
ALIGNMENT ALARM (EACH ALIGNMENT SWITCH) A1 4 X
HEALTHY MALF M2 1 X X
BELTLINE - MISC
HORN / BEACON BREAKER FAULT (EACH SECTION) SP 2 X X X
IMMEDIATE STOP SWITCH MALF (EACH DRIVE AND CONVEYOR HEAD) M2 0.3 X X X
NEGATIVE SLIP HI ALARM (EACH PULLEY) A2 -1.50% 5 X TRIGGERS BELT FEEDERS SPEED SETBACK ( CV-05 ONLY)
NEGATIVE SLIP HIHI MALF (EACH PULLEY) M1 -10% 5 X TRIGGERS UPSTREAM CONVEYOR SHUTDOWN
UNDERSPEED MALF M3 10% UNDER 1 X X WITH RESPECT TO SPEED SETPOINT, WITH CONVEYOR IN RUNNING STATE
WITH RESPECT TO SPEED SETPOINT M3 5% OVER 1 X X X WITH RESPECT TO SPEED SETPOINT, WITH CONVEYOR IN RUNNING STATE
HI OVERSPEED MALF M4 20% OVER 1 X X WITH RESPECT TO SPEED SETPOINT, WITH CONVEYOR IN RUNNING STATE
SUSTAINED OVERSPEED LEVEL1 MALF M4 5 % OVER 5 X X WITH RESPECT TO SPEED SETPOINT, WITH CONVEYOR IN RUNNING STATE
SUSTAINED OVERSPEED LEVEL2 MALF M5 5 % OVER 10 X X WITH RESPECT TO SPEED SETPOINT, WITH CONVEYOR IN RUNNING STATE
TAKE UP - CARRIAGE
POSITION LO SWITCH ALARM A1 NO X
TAKE UP - COUNTERWEIGHT
POSITION LO SWITCH ALARM A1 NO X
POSITION LOLO SWITCH MALF M2 0.2 X STOPS FORWARD MOTION (DOWN) AND CONVEYOR
POSITION HIHI SWITCH MALF M2 0.2 X STOPS REVERSE MOTION (UP) AND CONVEYOR
SIGNAL INVALID ALARM A2 3 / 28 MA 0.5 X DISABLES WEIGHT SCALE INPUT AND TRIGGERS TONNAGE LIMIT 2 (5200TPH)
SIGNAL INVALID ALARM (EACH LOAD CELL) A2 3 / 28 MA 0.5 X DISABLES LOAD CELL INPUT
BELT TENSION HI ALARM A2 260 T X 135 T FOR CV-07, TRIGGERS BELT FEEDERS SPEED SETBACK ON CV-05
BELT TENSION HIHI MALF M1 290 T 10 X 150 T FOR CV-07, TRIGGERS UPSTREAM CONVEYOR SHUTDOWN
10
SHUTTLE/STOCKPILE
CONTACTOR MALF M3 1 X X
DRIVE FAULT M3 NA X
READY MALF M3 8 X
RUNNING MALF M3 8 X
BRAKE SYSTEM
INSULATION MONITORING ALARM A1 NO X
CONTACTOR MALF M3 3 X X
CARRIAGE
POS LO MALF - END OF TRAVEL REVERSE SWITCH A2 NO X X STOPS REVERSE MOTION (TOWARD CONVEYOR)
POS HI MALF - END OF TRAVEL FORWARD SWITCH A2 NO X X STOPS FORWARD MOTION (TOWARD STOCKPILE)
MISC
CONTROL PANEL INSULATION MONITORING ALARM A1 NO X
PULLCORD MALF (EACH PULLCORD) M3 0.3 X X STOPS SHUTTLE MOTOR AND TRIGGERS UPSTREAM CONVEYOR SHUTDOWN
E-STOP SWITCH - CONVEYOR INTERLOCK (EACH SWITCH) M3 0.3 X X STOPS SHUTTLE MOTOR AND TRIGGERS UPSTREAM CONVEYOR SHUTDOWN
STOCKPILE
LEVEL DIFF HI ALARM A1 10% 4 X
LEVEL SIGNAL INVALID ALARM (EACH SENSOR) A2 3 / 28 MA 0.5 X DISABLES CORRESPONDING STOCKPILE LEVEL INPUT
AREA AUXILIARIES
SUBST - 23KV
23 KV BREAKER - TRIP COIL MONITORING ALARM A1 0.3 X
H.V HOUSE FIRE DETECTED MALF M3 0.3 X TRIPS 23KV BREAKER (SOFTWARE TRIP)
SUBST - 400V
23 KV POWER LBS FUSE BLOWN ALARM A1 2 X
SUBST - MCC
E1 MAIN BREAKER TRIPPED ALARM A1 0.3 X
SUBST - MISC
UTILITY PANEL GROUND FAULT A1 NO X
UNIT FAULT ALARM (EACH COOLING UNIT) A2 2 X DISABLES COOLER AND TRIGGERS SWITCHOVER TO STANDBY UNIT
MATERIAL LEVEL SIGNAL INVALID ALARM A2 3 / 28 MA 0.5 X DISABLES MATERIAL LEVEL TRANSDUCER INPUT, CV-07 ONLY
AUX - MISC
SUPPLY FAN FILTER PRESSURE HI ALARM (EACH FAN) A1 NO X
PLC - WATCHDOG
SYSTEM BYPASS ALARM A1 NO X
SYSTEM FAULT M4 1 X
CALCULATIONS: CEMA X DIN OTHER NEW ELECT. MOTOR POWER: 4 X 2500 kw (S)
ALLOWABLE BELT SAG 1 % (B) RUNNING TENSION: 2520 kN (S)
MINIMUM EDGE DISTANCE: 180 mm (B) ACCEL. TENSION: 2040 kN (S)
METHOD OF ACCEL. CONTROL: AFD (B) BRAKE RATING: kw (S) 3220 kN (S)
ACCELERATION TIME: 40 sec (S) DRIVE WRAP ANGLE: 170+180 deg (S)
COASTING TIME: N/A sec (S) DRIVE FRICTION FACTOR:
COASTING DISTANCE: N/A m (S) RUNNING: 0.35 (S)
BRAKING TIME (LEVEL 1): 80 sec (S) DECEL: 0.25 - 0.35 (S)
BRAKING DISTANCE: 240 m (S) COUNTER WEIGHT: 200 kN (S)
STARTING TORQUE: 100% N-m (S) TAKEUP DISPLACEMENT: m (S)
BRAKEAWAY TORQUE: 130% N-m (S) ORIGINAL CAPACITY: (S)
DRIVE EFFICIENCY: 95 % (S) ELECT. MOTOR POWER: 3 x 2500 kw (S)
4 feed points
1
Drop: 3 Drive pulley
536.42
6
m 2
Gravity Hydraulic adjustment
Drive pulley
5 4 for maintenance
Take-Up
NOTES
All dimensions are in meters
Max. Loading Angle: 10°
Max. Conveyor Angle: 15°
DRIVE TRAIN: CV-005D (only) TYPE: X ELECTRIC MOTOR WITH GEAR REDUCER
HYDRAULIC MOTOR
GEAR REDUCER SPECIFIED BY BECHTEL SUPPLIER DATA
DESIGN CODE AGMA 6010-E
MANUFACTURER FLENDER
MODEL NO.
REDUCER TYPE: PARALLEL SHAFT
X RIGHT ANGLE TRIPLE REDUCTION
SHAFT MOUNTED (up to 40 kw or 150 mm dia. shaft)
REDUCER MOUNTING SHAFT MOUNTED "V" BELT DRIVE
DIRECTLY CONNECTED SHAFT MOUNTED
X COMMON BASE PLATE
CHAIN DRIVE IS NOT ACCEPTABLE.
REDUCER DESIGN FACTORS MINIMUM SERVICE RATINGS:
SHALL BE APPLIED OVER THE MECHANICAL: 1.5
NAME PLATE KW OF THE THERMAL: 1.0
MOTOR. DURABILITY: 2.0 (pitting)
STRENGTH: 3.0 (teeth)
INPUT SHAFT DIA. 180 mm
OUTPUT SHAFT DIA. OD FLANGE 1200 mm
INPUT SPEED: 1020 RPM
OUTPUT SPEED: 45.47 RPM
HOUSING CAST IRON GGG40
BEARING TYPE
BEARING L-10G LIFE: 80,000 hrs min. for continuous brake loading. 80,000 hrs
BEARING SEAL (at nominal speed)
ACCESSORIES: X FILLER PLUG Provision for Installatioin
X DRAIN PLUG or forced lubrication &
X OIL LEVEL INDICATOR oil cooler in future.
X BREATHER Internal piping is installed
X HEATER WITH LOW & HIGH TEMP. SWITCHES
LUBRICATION: SPLASH
X FORCED
OPERATING TEMPERATURE: As per discussions 70 °C MAX. °C
COOLING METHOD DRIVE FAN NONE DR. FAN
X "FLENDER" AIR-OIL EXTERNAL HEAT EXCH. X HEAT EXCHANGER
OUTSIDE DIMENSIONS/WEIGHT kg
METHOD OF SOFT START HYDRAULIC CPLG. W/CONST.FILLING
REQUIRED WITH DRIVES & DELAY CHAMBER
AT 60 KW (75 HP) OR HIGHER. HYDRAULIC CPLG.-SCOOP TYPE
REQUIRED FOR CONVEYORS WITH WOUND ROTOR MOTOR (ALTERNATE)
CONCAVE VERTICAL CURVES X FREQUENCY CONTROL
ACCELERATING TENSION D.C. MOTOR
SHALL NOT EXCEED 150 %
OF RATED BELT TENSION.
NOTES
06/28/06
V-BELTS:
QTY:
SIZE:
MOTOR SHEAVE P.D.
DRIVEN SHEAVE P.D.
HOLDBACK:
MANUFACTURER:
TYPE AND MODEL NO.:
TORQUE RATING:
HYDRAULIC COUPLING:
MANUFACTURER:
TYPE:
MODEL NO.
RATING:
TAKE-UP:
TYPE:
TRAVEL:
WINCH TAKE-UP
GRAVITY TU WEIGHT:
LOCATION- WINCH TU
LOCATION- GRVTY TU
FLYWHEEL: YES NO
LOCATION:
SIZE:
TYPE OF FABRIC
NO OF PLIES
BREAKER ON FACE
FABRIC BELT BREAKER THICKNESS
TEMPERATURE RATING :
COEFF. OF THERMAL EXPANSION ( HR ):
FILL MATERIAL:
FRICTION RATING BETWEEN PLIES:
CORD DIA. :
CABLE BREAKING STRENGTH:
CABLE SPACING:
STEEL CORD MODULUS OF ELASTICITY AT RATED TENSION:
PULL-OUT STRENGTH OF CABLE :
> 10,000 cycles
ADHESION BETWEEN COVER AND BONDING RUBBER:
IMPACT RESISTANCE: PHOENIX TEST RIG
THICKNESS: TOP:
BOTTOM :
COVER MINIMUM TENSILE STRENGTH:
RMA GRADE:
TOLERANCE: PLUS:
MINUS:
REPAIRS CARCASS:
COVER:
QUANTITY REQUIRED:(S)
LOAD RATING:
SPACING: (S)
* IMPACT ZONE:
* UNDER SKIRTBRD: (S)
GENERAL:
DISTANCE FROM
HEAD OR TAIL PULLEY
ROLL DIA.
SHELL THICKNESS:(S)
SHAFT DIA (S).
BEARING DIA.(S)
BEARING TYPE: (S)
BEARING L-10 LIFE(S)
SEAL TYPE:(B)
MULTI - LABYRINTH
SEALED FOR LIFE
CEMA NO./DIN
END SHIELD:(B)
ADJUSTABLE TROUGHING
ANGLES:(B)
INCREMENT:
(B) START/STOP CONTROL SW. (B) PULLEY GUARD (B) DUAL BELT SCRAPER
(B) ZERO SPEED SWITCH (B) CPLG. GUARD
TYPE (S): (B) RETURN BELT V PLOW
(B) BELT ALIGNMENT SWITCH. (B) BELT RIP PROTECTION (B) V PLOW AT TU PULLEY
(B) EMERG. PULL CORD SWITCH (B) PLUG CHUTE DETECTOR (B) BRAKE
1 SIDE 2 SIDES (B) BELT SEAL
(B) PRE-START HORN (B) FEED/DISCH. CHUTE
mm mm mm mm mm mm mm mm mm mm A B mm kg Hours
1
2
3
4
5
6
f b e
a
F
d1 d2
d3
D
Fillet radii shall not be less than 25 % of the minor shaft dia.
Fillet radii shall be two times the difference in diameters, that is: R = 2 x (D - d)
NOTES
INDICATOR RUNOUT:
BEFORE LAGGING:
AFTER LAGGING:
LAGGING: DRIVE PULLEYS:
HARDNESS (SHORE A)
THICKNESS
LAGGING- OTHER PULLEYS:
HARDNESS(SHORE A)
THICKNESS:
HUB LOCKING DEVICE: TYPE
TYPE
MAKE/MODEL NO:
END DISCS: TYPE:
THICKNESS:
ALLOWABLE STRESS:
MATERIAL:
SHAFTS:
SERVICE FACTOR
BENDING MOMENT:
TORSIONAL MOMENT
SLOPE
LINER MATERIAL:
FEED AND TRANSFER THICKNESS: mm
CHUTES TOTAL WEIGHT: kg
MATERIAL:
THICKNESS: mm
TOTAL WEIGHT: kg
FEED /TRANSFER CHUTE WIDTH
For 900 mm and smaller belts
For 1000 mm and wider belts
TOTAL WEIGHT:
SKIRTBOARDS: LENGTH m
THICKNESS mm
SKIRTBOARD MATERIAL
LINERS: THICKNESS
TOTAL WEIGHT:
SEALING STRIPS
DUST ENCLOSURE MATERIAL
AT FEED AREA THICKNESS
NUMBER OF PACKAGES:
NOTES
CALCULATIONS: CEMA X DIN OTHER NEW ELECT. MOTOR POWER: 4 X 2500 kw (S)
ALLOWABLE BELT SAG 1 % (B) RUNNING TENSION: 2520 kN (S)
MINIMUM EDGE DISTANCE: 180 mm (B) ACCEL. TENSION: 2040 kN (S)
METHOD OF ACCEL. CONTROL: AFD (B) BRAKE RATING: kw (S) 3220 kN (S)
ACCELERATION TIME: N/A sec (S) DRIVE WRAP ANGLE: 170+180 deg (S)
COASTING TIME: N/A sec (S) DRIVE FRICTION FACTOR:
COASTING DISTANCE: 120 m (S) RUNNING: 0.35 (S)
BRAKING TIME (LEVEL 1): 80 sec (S) DECEL: 0.25 - 0.35 (S)
BRAKING DISTANCE: 240 m (S) COUNTER WEIGHT: 200 kN (S)
STARTING TORQUE: 100% N-m (S) TAKEUP DISPLACEMENT: m (S)
BRAKEAWAY TORQUE: 130% N-m (S) ORIGINAL CAPACITY: (S)
DRIVE EFFICIENCY: 95 % (S) ELECT. MOTOR POWER: 3 x 2500 kw (S)
Drop
526.62m 6
4
(2) Secondary Hydraulic adjustment
5 Drive Pulley for maintenance
Gravity
take up
Length 5,280.82
NOTES
All dimensions are in meters
Max. Loading Angle: 10°
Max. Conveyor Angle: 15°
DRIVE TRAIN: CV-006D (only) TYPE: X ELECTRIC MOTOR WITH GEAR REDUCER
HYDRAULIC MOTOR
GEAR REDUCER SPECIFIED BY BECHTEL SUPPLIER DATA
DESIGN CODE AGMA 6010-E
MANUFACTURER FLENDER
MODEL NO.
REDUCER TYPE: PARALLEL SHAFT
X RIGHT ANGLE TRIPLE REDUCTION
SHAFT MOUNTED (up to 40 kw or 150 mm dia. shaft)
REDUCER MOUNTING SHAFT MOUNTED "V" BELT DRIVE
DIRECTLY CONNECTED SHAFT MOUNTED
X COMMON BASE PLATE
CHAIN DRIVE IS NOT ACCEPTABLE.
REDUCER DESIGN FACTORS MINIMUM SERVICE RATINGS:
SHALL BE APPLIED OVER THE MECHANICAL: 1.5
NAME PLATE KW OF THE THERMAL: 1.0
MOTOR. DURABILITY: 2.0 (pitting)
STRENGTH: 3.0 (teeth)
INPUT SHAFT DIA. 180 mm
OUTPUT SHAFT DIA. OD FLANGE 1200 mm
INPUT SPEED: 1020 RPM
OUTPUT SPEED: 45.47 RPM
HOUSING CAST IRON GGG40
BEARING TYPE
BEARING L-10G LIFE: 80,000 hrs min. for continuous brake loading. 80,000 hrs
BEARING SEAL (at nominal speed)
ACCESSORIES: X FILLER PLUG Provision for Installatioin
X DRAIN PLUG or forced lubrication &
X OIL LEVEL INDICATOR oil cooler in future.
X BREATHER Internal piping is installed
X HEATER WITH LOW & HIGH TEMP. SWITCHES
LUBRICATION: SPLASH
X FORCED
OPERATING TEMPERATURE: As per discussions 70 °C MAX. °C
COOLING METHOD DRIVE FAN NONE DR. FAN
X FLENDER AIR-OIL EXTERNAL HEAT EXCH. X HEAT EXCHANGER
OUTSIDE DIMENSIONS/WEIGHT 4680 x 1760 x 2126 mm (length x width x height) 29,370 kg
METHOD OF SOFT START HYDRAULIC CPLG. W/CONST.FILLING
REQUIRED WITH DRIVES & DELAY CHAMBER
AT 60 KW (75 HP) OR HIGHER. HYDRAULIC CPLG.-SCOOP TYPE
REQUIRED FOR CONVEYORS WITH WOUND ROTOR MOTOR (ALTERNATE)
CONCAVE VERTICAL CURVES X FREQUENCY CONTROL
ACCELERATING TENSION D.C. MOTOR
SHALL NOT EXCEED 150 %
OF RATED BELT TENSION.
NOTES
06/28/06
V-BELTS:
QTY:
SIZE:
MOTOR SHEAVE P.D.
DRIVEN SHEAVE P.D.
HOLDBACK:
MANUFACTURER:
TYPE AND MODEL NO.:
TORQUE RATING:
HYDRAULIC COUPLING:
MANUFACTURER:
TYPE:
MODEL NO.
RATING:
TAKE-UP:
TYPE:
TRAVEL:
WINCH TAKE-UP
GRAVITY TU WEIGHT:
LOCATION- WINCH TU
LOCATION- GRVTY TU
FLYWHEEL: YES X NO
LOCATION: HIGH SPEED COUPLING
SIZE:
TYPE OF FABRIC
NO OF PLIES
BREAKER ON FACE
FABRIC BELT BREAKER THICKNESS
TEMPERATURE RATING :
COEFF. OF THERMAL EXPANSION ( HR ):
FILL MATERIAL:
FRICTION RATING BETWEEN PLIES:
CORD DIA. :
CABLE BREAKING STRENGTH:
CABLE SPACING:
STEEL CORD MODULUS OF ELASTICITY AT RATED TENSION:
PULL-OUT STRENGTH OF CABLE :
> 10,000 cycles
ADHESION BETWEEN COVER AND BONDING RUBBER:
IMPACT RESISTANCE: PHOENIX TEST RIG
THICKNESS: TOP:
BOTTOM :
COVER MINIMUM TENSILE STRENGTH:
RMA GRADE:
TOLERANCE: PLUS:
MINUS:
REPAIRS CARCASS:
COVER:
6.17.05
QUANTITY REQUIRED:(S)
LOAD RATING:
SPACING: (S)
* IMPACT ZONE:
* UNDER SKIRTBRD: (S)
GENERAL:
DISTANCE FROM
HEAD OR TAIL PULLEY
ROLL DIA.
SHELL THICKNESS:(S)
SHAFT DIA (S).
BEARING DIA.(S)
BEARING TYPE: (S)
BEARING L-10 LIFE(S)
SEAL TYPE:(B)
MULTI - LABYRINTH
SEALED FOR LIFE
CEMA NO./DIN
END SHIELD:(B)
ADJUSTABLE TROUGHING
ANGLES:(B)
INCREMENT:
(B) START/STOP CONTROL SW. (B) PULLEY GUARD (B) DUAL BELT SCRAPER
(B) ZERO SPEED SWITCH (B) CPLG. GUARD
TYPE (S): (B) RETURN BELT V PLOW
(B) BELT ALIGNMENT SWITCH. (B) BELT RIP PROTECTION (B) V PLOW AT TU PULLEY
(B) EMERG. PULL CORD SWITCH (B) PLUG CHUTE DETECTOR (B) BRAKE
1 SIDE 2 SIDES (B) BELT SEAL
(B) PRE-START HORN (B) FEED/DISCH. CHUTE
mm mm mm mm mm mm mm mm mm mm A B mm kg Hours
1
2
3
4
5
6
f b e
a
F
d1 d2
d3
D
Fillet radii shall not be less than 25 % of the minor shaft dia.
Fillet radii shall be two times the difference in diameters, that is: R = 2 x (D - d)
NOTES
1 6.17.05
Enter S (STANDARD PULLEY) or E (ENGINEERED PULLEY) in column "B".
INDICATOR RUNOUT:
BEFORE LAGGING:
AFTER LAGGING:
LAGGING: DRIVE PULLEYS:
HARDNESS (SHORE A)
THICKNESS
LAGGING- OTHER PULLEYS:
HARDNESS(SHORE A)
THICKNESS:
HUB LOCKING DEVICE: TYPE
TYPE
MAKE/MODEL NO:
END DISCS: TYPE:
THICKNESS:
ALLOWABLE STRESS:
MATERIAL:
SHAFTS:
SERVICE FACTOR
BENDING MOMENT:
TORSIONAL MOMENT
SLOPE
6.17.05
LINER MATERIAL:
FEED AND TRANSFER THICKNESS: mm
CHUTES TOTAL WEIGHT: kg
MATERIAL:
THICKNESS: mm
TOTAL WEIGHT: kg
FEED /TRANSFER CHUTE WIDTH
For 900 mm and smaller belts
For 1000 mm and wider belts
TOTAL WEIGHT:
SKIRTBOARDS: LENGTH m
THICKNESS mm
SKIRTBOARD MATERIAL
LINERS: THICKNESS
TOTAL WEIGHT:
SEALING STRIPS
DUST ENCLOSURE MATERIAL
AT FEED AREA THICKNESS
NUMBER OF PACKAGES:
NOTES
2 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\2. Lpla0314.dwg
2 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\3. Lple322A1.dwg
1 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\4. Lple323A1.dwg
1 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\5. Lple3261.dwg
1 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\6. Lple3271.dwg
1 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\7. Lple3281.dwg
1 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\8. Lple329A1.dwg
1 of 2
C:\Docs y Planos\OM Manual\vol 1 english mechanical\Section 2 (Drawings)\9. Lple330A1.dwg
1 of 2
Documentation
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
Order.-No. 316047
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
Installation:
Ambient temperature : -12 ... +34 °C
Space : big hall
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
BA 3600 EN 08.98
Flexible RUPEX couplings,
type RWN, RWS and RWB, RBS
RWN
RWS
RWB
RBS
1. Technical data 4
1.1 Validity of the nominal torques TKN 4
1.2 Types RWN and RWS 4
1.3 Types RWB and RBS 6
2. General notes 7
2.1 General 7
3. Safety notes 8
3.1 Safety notes 8
3.1.1 Notes and symbols in the operating instructions 8
5. Technical description 10
5.1 General description 10
6. Assembly 11
6.1 Notes on fitting the finished bore, the axial securing, the set screws, the balancing 11
6.1.1 Finished bore 11
6.1.1.1 Keyway 12
6.1.2 Axial securing 12
6.1.3 Set screws 12
6.1.4 Balancing 13
6.2 General installation notes 13
6.3 Mounting the coupling parts 14
6.4 Aligning 14
6.5 Possible misalignments 15
6.5.1 Axial misalignment 15
6.5.2 Angular misalignment 15
6.5.3 Radial misalignment 15
6.6 Assignments of the tightening torques 16
7. Startup 16
7.1 Measures before startup 16
8. Operation 17
8.1 General operating data 17
BA 3600 EN 08.98
10. Maintenance and repair 18
10.1 General 18
10.2 Change of wear parts 18
BA 3600 EN 08.98
1. Technical data
w1 u
S1 S1
1 P u 2 1 P u 2
l l l l
da
da
d2
d2
d2
d2
D1
D1
D1
D1
Size 105 - 360 Size 400
u u
S1 S1
1 P u 2 1 P u 2
l l l l
da
da
d2
d2
d2
d2
D1
D1
D1
D1
v v v v
BA 3600 EN 08.98
Nominal Speed Bore Weight 2)
torque
TKN nmax from to da l v P S1 w1 u RWN RWS
Size
1) RWN RWS RWN RWS Part 1 Part 2 Part 1 Part 2
D1/2 D1 D2 D1 D2 d1 d2
Nm 1/min 1/min mm mm mm mm mm mm mm mm mm mm mm mm mm mm kg kg kg kg
105 200 5000 5000 10 32 38 32 38 105 53 59 45 30 2... 4 12 13 0.8 1 0.9 1.1
125 350 5000 5000 14 40 48 40 48 125 65 68 50 35 2... 4 15 16 1.4 1.5 1.5 1.6
144 500 4900 5000 18 45 55 50 60 144 76 84 55 35 2... 4 15 16 1.9 2.6 2.1 2.8
162 750 4300 5000 22 50 60 55 65 162 85 92 60 40 2... 5 18 20 2.8 3.9 3 4.2
178 950 3800 4900 24 60 70 780 75 178 102 108 70 40 2... 5 18 20 4.1 5.6 4.4 6.1
198 1300 3400 4600 28 70 80 80 85 198 120 128 80 40 2... 5 18 20 5.9 7 6.4 7.6
228 2200 3000 4400 28 80 90 85 95 228 129 140 90 50 2... 5 24 26 7.3 11.5 7.9 12.5
252 2750 2700 4200 38 90 100 100 110 252 150 160 100 50 2... 5 24 26 10.5 15.5 11.5 16.5
285 4300 2400 3900 48 100 110 110 120 285 164 175 110 60 3... 6 30 32 16 23 17.5 25
320 5500 2100 3500 55 110 120 125 130 320 180 192 125 60 3... 6 30 32 23 30 25 32
360 7800 1900 3100 65 120 130 135 140 360 200 210 140 75 3... 6 42 42 32 46 35 50
400 12500 1700 2800 75 140 140 150 150 400 230 230 160 75 3... 6 42 53 53 57 57
450 18500 1500 2500 85 160 160 170 170 450 260 260 180 90 4... 7 52 78 78 84 84
500 25000 1350 2200 95 180 180 190 190 500 290 290 200 90 4... 7 52 99 99 105 105
100 140 140 165 165 250 250 140 140 150 150
560 39000 1200 2000 > 140 180 180 200 200 560 300 300 220 70 120 4... 8 68 145 145 155 155
> 180 200 200 210 210 320 320 145 145 155 155
100 140 140 165 165 250 250 175 175 190 190
630 52000 1050 1800 > 140 180 180 200 200 630 300 300 240 80 120 4... 8 68 185 185 200 200
> 180 220 220 235 246 355 355 200 200 215 215
110 160 160 190 190 290 290 255 255 275 275
710 84000 950 1600 > 160 200 200 220 220 710 330 330 260 80 140 5... 9 80 260 260 280 280
> 200 240 240 250 250 385 385 270 270 290 290
125 180 180 210 210 320 320 330 330 360 360
800 110000 850 1400 > 180 220 220 240 240 800 360 360 290 90 140 5... 9 80 350 350 380 380
> 220 260 260 280 280 420 420 360 360 390 390
140 180 180 210 210 320 320 450 450 490 490
> 180 220 220 240 240 360 360 450 450 490 490
900 150000 750 1250 900 320 100 160 5...10 90
> 220 260 260 280 280 425 425 480 480 520 520
> 260 290 290 310 310 465 465 510 510 550 550
150 200 200 230 230 355 355 560 560 610 610
> 200 240 240 260 260 395 395 580 580 630 630
1000 195000 680 1100 1000 350 110 160 5...10 90
> 240 280 280 300 300 460 460 630 630 680 680
> 280 320 320 340 340 515 515 660 660 710 710
160 200 200 240 240 360 360 730 730 790 790
> 200 250 250 270 270 410 410 750 750 810 810
1120 270000 600 1000 1120 380 120 180 6...11 100
> 250 300 300 330 330 495 495 800 800 870 870
> 300 350 350 370 370 560 560 840 840 910 910
180 230 230 270 270 410 410 920 920 1000 1000
> 230 280 280 300 300 460 460 950 950 1050 1050
1250 345000 550 900 1250 420 130 180 6...11 100
> 280 330 330 360 360 540 540 1000 1000 1050 1050
> 330 380 380 400 400 610 610 1100 1100 1150 1150
200 260 260 310 310 465 465 1400 1400 1500 1500
> 260 320 320 350 350 525 525 1450 1450 1550 1550
1400 530000 490 800 1400 480 145 210 6...12 120
> 320 380 380 410 410 620 620 1550 1550 1650 1650
> 380 440 440 460 460 700 700 1650 1650 1750 1750
260 320 320 370 370 565 565 1900 1900 2050 2050
> 320 380 380 410 410 625 625 1950 1950 2100 2100
1600 750000 430 700 1600 540 165 210 6...12 120
> 380 440 440 480 380 720 720 2050 2050 2200 2200
> 440 480 480 510 510 770 770 2150 2150 2300 2300
320 380 380 440 440 660 660 2750 2750 3000 3000
> 380 440 440 480 480 720 720 2800 2800 3050 3050
1800 975000 380 600 1800 600 185 240 8...16 140
> 440 500 500 540 540 820 820 3000 3000 3250 3250
> 500 540 540 580 580 870 870 3150 3150 3400 3400
380 440 440 500 500 760 760 3400 3400 3700 3700
> 440 500 500 540 540 820 820 3500 3500 3800 3800
2000 1300000 340 550 2000 660 200 240 8...16 140
> 500 560 560 610 610 920 920 3700 3700 4000 4000
> 560 600 600 640 640 960 960 3800 3800 4100 4100
Table 1.1: Torques TKN, speeds nmax, weights and sizes of type RWN and RWS
BA 3600 EN 08.98
1.3 Types RWB and RBS
S1 b1
P u
Part 1 Part 3
D1
D3
2
d3
1
l
a
d
d
BA 3600 EN 08.98
2. General notes
2.1 General
These Operating Instructions constitute part of the coupling shipment and should be kept in the
immediate vicinity of the coupling at all times.
Only a precise knowledge of the Operating Instructions will ensure trouble-free operation of the
coupling. It is therefore in the interest of our customer that the operating instructions are read,
understood and observed in all respects by the persons responsible for handling, installation and
operation.
Note: We accept no liability for any damage or malfunction resulting from non-observance
of the operating instructions.
The ”coupling” dealt with in these operating instructions was developed for stationary use in general
engineering.
The coupling is only designed for the field of application as specified in Section 1 ”Technical data”.
Operating conditions which differ from the stated will require fresh contractual agreements.
The coupling described here is in accordance with the state of the art at the time of these operating
instructions go into print.
In the interest of further development, we reserve the right to introduce modifications which, while
retaining the essential features, can be regarded as desirable to increase its efficiency and safety.
The copyright of these Operating Instructions remains the property of FLENDER AG.
These operating instructions may not be duplicated in part or whole, utilized for the purpose of publicity
or communicated to third parties without our expressed consent.
Please contact our works listed below in respect of all technical queries.
FLENDER AG
D 46393 Bocholt
Telephone: 02871/92-2800
Telefax: 02871/92-2801
or one of our service branches which are listed in Section 11 ”Stocking spare parts, service facility
addresses”.
BA 3600 EN 08.98
3. Safety notes
S The coupling is constructed in accordance with the state of the art and is reliable in the condition as
shipped. Unauthorized modifications which impair its reliability are not permissible. This also applies
to guards which are fitted as protection against accidental contact.
S The coupling may only be used and operated within the scope of the condition specified in the contract
of performance and supply.
S The customer should ensure that the persons entrusted with installation, operation, care and
maintenance as well as repair have read and understood the operating instructions and observe them
in all respects in order to:
– prevent hazard to life and limb of the user and third parties
S The relevant regulations concerning industrial safety and pollution control should be observed during
handling, installation, operation as well as care and maintenance.
S The coupling may only be operated, serviced and repaired by authorized, trained and properly
instructed personnel.
S All work should be carried out with care with the safety aspect in mind.
S All work on the coupling may only be carried out when it is stationary.
The coupling must be secured to prevent accidental start up (e.g. by locking the key switch or by
removing the fuses and the power supply). A notice should be displayed at the switch-on point stating
that work is in progress on the coupling.
S The drive unit should be shut off at once if changes in the coupling are detected during operation, such
as e.g. changed running noises.
S The coupling must be protected by means of suitable guards to prevent accidental contact.
S During installation of the coupling in units or systems, the manufacturer of the units or systems is
obliged to incorporate the requirements, notes and descriptions contained in these operating
instructions in his own operating instructions.
Instructions in the operating instructions which concern operating safety are emphasized as follows:
This symbol draws attention tosafety measures which must be observed to prevent
personal injury.
This symbol draws attention to safety measures which must be observed to prevent
Caution! damage to the coupling.
Note: This note draws attention to general operating notes which should be especially
observed.
BA 3600 EN 08.98
4. Handling and storage
The scope of the shipment is listed in the shipping documents. They should be checked for
completeness on receipt. Any shipping damage and/or missing parts should be reported in writing at
once. After consulting FLENDER an expert is to be called in.
4.2 Handling
The packing of the coupling will differ depending on method of shipment and size. The packing, unless
otherwise agreed contractually, complies with HPE Packing Guidelines.
The symbols shown on the packing should be noted. Their meaning is as follows:
bild-transport
4.3 Storage
The coupling is delivered in a preserved state and can be stored at a covered dry place up to 6 months.
If the coupling shall be stored for a longer period of time, an appropriate long-term preservation is
necessary (consultation with FLENDER required).
Before cleaning the coupling parts and applying the long-term preservation,
Caution! the buffers are to be removed.
4.3.2.1 General
Properly stored buffers keep their characteristics for up to 5 years. Unfavourable storage conditions and
improper treatment of the buffers result in a negative change of the physical characteristics. These
changes can be caused by the effects of e.g. ozone, extreme temperatures, light, moisture or solvents.
The storage room should be dry and dust-free. The buffers must not be stored together with chemicals,
solvents, fuels, acids, etc. Furthermore, they should be protected against light, especially against direct
sun light and strong artificial light with a high ultra-violet percentage.
The storage romms must not contain any ozone-producing devices like e.g.
Caution! fluorescent light sources, mercury-vapour lamps, electric high-voltage
devices. Damp storage rooms are unsuitable. Make sure that no condensation
develops. The relative humidity of air is most favourable below 65 %.
BA 3600 EN 08.98
5. Technical description
1 2 1 3
P
6 5 4 8 10
The RUPEX coupling type RWN and RWS consists of two coupling parts and the pins with the flexible
plastic buffers required for torque transmission. In the RWN version, the hub parts (1 and 2) are of grey
cast iron. In the RWS version, they are of steel.
The RUPEX coupling type RWB and RBS consists of a coupling part and a brake drum, with the pins
and flexible plastic buffers required for torque transmission. In the RWB version, the hub part (1) and
the brake drum (3) are of grey cast iron. In the RBS version, they are of steel.
Up to size 360, the ground steel pins are attached to the buffers only in the coupling part (2) (RWN and
RWS) or the brake drum (3) (RWB and RBS). From size 400 they are attached alternately in the coupling
parts (1 and 2). In the assembled state, the buffers engage the buffer bores of the counterpart.
The flexible plastic buffers of buna N have a hardness of 80 Shore. Buffers of differing material quality
and/or hardness are available within limits. With regard to the availability of these special buffers and
the extent to which the properties of the coupling are affected, please consult FLENDER.
BA 3600 EN 08.98
6. Assembly
6.1 Notes on fitting the finished bore, the axial securing, the set screws, the balancing
6.1.1 Finished bore
S Remove buffers.
S Remove the anti-corrosion agent from coupling parts
When fitting the finished bore, align the parts carefully. For the permissible radial and axial excentricity
see DIN ISO 286 degree of fundamental tolerance IT8. The location of the parts ( ) is to be carried
out on the marked surfaces.
The maximum permissible boring diameters (see Section 1.) are designed for
Caution! driving connections without tightening according to DIN 6885/1 and must not
be exceeded in any case.
If other shaft hub connections (e.g. splined hub profile, tapered or graded bore, driving connection with
tightening, etc.) shall be fitted instead of the intended driving connections, FLENDER is to be consulted.
Non-observance of these notes may lead to the drifting of coupling.
There is a danger to life due to broken pieces flying around!
d1
A A
d1
D1
D1
3.2 3.2
IT8 A
IT8 A
Part 1 / Part 2 / Part 1/2 Part 3
In case of drive by means of parallel keys, the following fit pairings are prescripted for the bores:
Bore
Fit selection above to Shaft tolerances Boring tolerances
mm mm
25 k6
Shaft tolerance to FLENDER
25 100 m6 H7
standard
100 n6
50 k6
Shaft tolerance to DIN 748/1 H7
50 m6
50 K7
h6
Unified system shaft 50 M7
all h8 N7
Table 6.1: Fit pairings
BA 3600 EN 08.98
6.1.1.1 Keyway
The keyways have to be designed according to the existing parallel keys. For keyways, the tolerance
field of the hub keyway width ISO JS 9 is to be observed.
For more difficult operating conditions, as it is the case for e.g. reversing operation of operation with
impulses, the tolerance filed of the hub keyway width ISO P9 is prescribed.
Caution! The keyways are to be set and centered between the buffer bores.
BA 3600 EN 08.98
Size 105 125 144 162 178 198 228 252 285 320 360 400 450
Distance dimension e1 15 20 25 25 35 40 40 50 55 60 70 80 80
Size 500 560 630 710 800 900 1000 1120 1250 1400 1600 1800 2000
Distance dimension e1 90 100 110 130 115 160 175 160 200 240 250 300 330
Break drum 200 x 75 250 x 95 315 x 118 400 x 150 500 x 190 630 x 236 710 x 265
Distance dimension e3 12 12 25 30 50 75 90
Tabelle 6.3: Distance dimensions of the set screws
Generally, the set screws are to be arranged on the keyway. This does not apply
Caution! to coupling parts 1+2 of sizes 105 and 125 where the set screw should be
arranged by 180° shifted to the keyway.
6.1.4 Balancing
Prebored couplings resp. prebored coupling parts are shipped unbalanced. For these parts et is
recommended to balance them depeding on the application case after finish boring (see also DIN 740,
VDI guideline 2060).
Balancing is usually carried out by material cutting through boring. In order ro restrict the material
quantity to be cut to a minium, the biggest possible balancing radius is to be selected.
For parts 1/2, cutting has to be carried out between the bores without
Caution! through-boring of the bottom. For part 32, the break surface must not be
damaged under any circumstances.
Finished bored couplings or coupling parts are balanced according to the instructions of the ording
party.
Balancing bore
The installation has to be carried out with utmost care by trained personnel.
Already during the planning phase it is to be observed that sufficient room is to be provided for the
installation and later inspection and maintenance work.
Before starting the installation a sufficient number of hoists must be provided for.
BA 3600 EN 08.98
6.3 Mounting the coupling parts
Before starting the assembly, clean the shaft ends, the brake drum and the coupling parts carefully.
Before cleaning the coupling parts with solvents, remove the buffers.
Observe the manufactuer’s instructions on handling the solvents.
The coupling parts and the brake drum are to be fitted by means of suitable
Caution! devices in order to prevent damage to the shaft bearing arrangement by the
axial fitting force.
Make sure that suitable hoists are used.
If it shall be possible to exchange the buffers or to move the coupled machines, the dimension P should
be taken into consideration during assembly according to 6.6.
Tightening of the set screws only by means of a hexgon socket head wrench
Caution! according to DIN 911, without an extension pipe.
The assembly process is made easier by heating the coupling parts and the brake drum (3) (to max.
+150 °C). If using temperatures greater than +80 °C, the buffers/bolts must be removed from the
coupling parts before heating them.
After mounting the coupling parts or the brake drum, replace the buffers (if removed beforehand).
Tighten the nuts (7) and bolts (11) using a torque wrench (for correct torques, see section 6.6). Secure
bolts (11) with a few spots of adhesive (e.g. Loctite, type 242). Coupling parts which have been
previously heated must be allowed to cool to a temperature of less than 80 °C.
BA 3600 EN 08.98
6.5 Possible misalignments
S1max S1max
D Kr
DKa
D Kw
S1min S1min
Misalignments of the coupling parts may result from an inexact alignment during the assembly but also
from the operation of the plant (expansion due to heat, bending of the shaft, machine frame to soft, etc.).
Speed n [1/min]
figure 6.4
Angular and radial misalignments may occur at the same time. The sum of both
Caution! misalignments must not exceed the max. permissible value of the angular or
radial misalignment.
(Kw + Kr)existing ≤ DKw x Sn or DKr x Sn
BA 3600 EN 08.98
6.6 Assignments of the tightening torques
7. Startup
Before startup, check the tightening of the set screws, the alignment and the distance dimension S1 and
correct if necessary and check all screw connections for the prescribed tightening torques (see Section
1. and Section 6.). Finally, the coupling guard to prevent accidental contact is to be fixed.
BA 3600 EN 08.98
8. Operation
– sudden shaking.
If irregularities are detected during operation, the drive assembly should be set
Caution! off immediately. The cause of the malfunction should be determined with the
aid of the Troubleshooting Table (Section 9.).
The Troubleshooting Table lists possible malfunctions, their causes and
suggestions for remedying them.
If the cause cannot be determined or there is no facility for repair with suitable
equipment, we recommend calling in one of our service fitters (see Section 11.).
9.1 General
In case of a complex plant, all other components have always to be included in the troubleshooting.
The coupling has to run with low noise and without shaking in all operating phases. Any deviating
behaviour is to be regarded as malfunction and should be repaired immediately.
Before maintenance work, repairs or other work, the operator should make sure
that the whole drive train is stationary. Especially the drive motors are to be
secured against accidental start up.
Futhermore, we refer to the relevant regulations on the prevention of accidents
at the place of installation.
Sudden change of the noise Change of alignment Shut down the plant
level and/or sudden shaking
possibly repair the reason for
the change of alignment
(e.g. fasten loose foundation bolts)
BA 3600 EN 08.98
10. Maintenance and repair
10.1 General
The circumferential backlash between the two coupling parts should be checked according to the
maintenance intervals, however, at least once a year. As far as an increased backlash of the coupling
is not detrimental to the operation of the coupling, the elastic buffers may remain in use until a defined
wear limit is reached before they should be changed. For evaluating the wear, in Table 10.1, the
permissible circumferential backlash is listed, which is converted to the chord dimension DSV on the
outer coupling diameter. In order to determine the dimension DSV, a coupling part is turned until stop
without torque and a mark is made on the coupling part (see figure 10.1). By turning the coupling part
in the opposite direction of rotation until stop, the marks move apart. The distance between the marks
is the chord dimension DSV. If the dimension DSV exceeds the value listed in Table 10.1, the buffers
should be changed.
figure 10.1 D SV
125 162 228 285 360 450 560 710 900 1120 1400 1800
Size 105
144 198 252 320 400 500 630 800 1000 1250 1600 2000
DSV 3.0 3.5 4.0 4.5 6.0 7.0 8.5 10.0 12.0 13.5 15.0 18.0 20.0
Table 10.1: Wear mark
Only use original RUPEX buffers as spare buffers, in order to guarantee a perfect transmission of the
torque and a trouble-free function.
Note: Changing the buffers is possible without moving the coupled machines.
Up to coupling size 400, the bolts with the plastic buffers can be removed through the buffer holes after
releasing and removing the nuts, and up to coupling size 450, after releasing and removing the hexagon
bolts and end plates.
After renewing the plastic buffers, assemble the unit in the opposite sequence. Secure the nuts or bolts
with adhesive (e.g. Loctite 242).
Carefully observe the instructions of Section 6. ”Installation” and Section 7. ”Start up” for the
re-installation.
BA 3600 EN 08.98
11. Spare parts stock, service facility addresses
Maintaining a stock of the most essential spare and wear parts is an important prerequisite for the
permanent service ability of the coupling.
– Description / Size (the size designation corresponds to the outer diameter da in mm)
– Quantity
We would expressly draw attention to the fact that spare parts and accessories
Caution! not supplied by us have not been tested or approved by us either. Fitting and/or
use of such products can therefore under certain circumstances adversely
affect structurally specified properties of the coupling and will thus impair
active and/or passive safety. No form of reliability or warranty will be assumed
by FLENDER for damage occasioned by use of non-original spare parts and
accessories.
Please note that production and supply specifications frequently exist for components and we will
always offer spare parts in accordance with the state of the art and in accordance with the latest legal
requirements.
When ordering spare parts or requesting a service fitter, please contact FLENDER AG first of all.
FLENDER Germany
A. FRIEDR. FLENDER AG
46393 Bocholt - Tel.: (0 28 71) 92-0 - Fax: (0 28 71) 92 25 96
E-mail: contact@flender.com S www.flender.com
Shipping address: Alfred - Flender - Strasse 77 - 46395 Bocholt
LOHER GMBH
94095 Ruhstorf - Tel.: (0 85 31) 3 90 - Fax: (0 85 31) 3 94 37
E-mail: info@loher.de S www.loher.de
Shipping address: Hans-Loher-Strasse 32 - 94099 Ruhstorf
BA 3600 EN 08.98
Germany
A. FRIEDR. FLENDER AG
46393 BOCHOLT - TEL.: (0 28 71) 92 - 0 - FAX: (0 28 71) 92 25 96
SHIPPING ADDRESS: ALFRED - FLENDER - STRASSE 77 - 46395 BOCHOLT
––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
E-mail: contact@flender.com S www.flender.com
––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
VERTRIEBSZENTRUM BOCHOLT 46393 Bocholt
Alfred-Flender-Strasse 77, 46395 Bocholt
Tel.: (0 28 71) 92 - 0
Fax: (0 28 71) 92 - 14 35
E-mail: vz.bocholt@flender.com
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________
BA 3600 EN 08.98
FLENDER International (2003-12-01)
BA 3600 EN 08.98
SERBIA-MONTENEGRO SALES OFFICES: USA
ALBANIA / MACEDONIA Flender Brasil Ltda. Flender Corporation
A. Friedr. Flender AG Rua James Watt, 142 950 Tollgate Road
Branch Office conj. 142 - Brooklin Novo P.O. Box 1449, Elgin, IL. 60123
c/o G.P.Inzenjering d.o.o. 04576 - 050, São Paulo - SP Phone: +1 (0) 8 47 - 9 31 19 90
III Bulevar 54 / 19 Phone: +55 (0) 11 - 55 05 99 33 Fax: +1 (0) 8 47 - 9 31 07 11
11070 Novi Beograd Fax: +55 (0) 11 - 55 05 30 10 E-mail: flender@flenderusa.com
Phone: +381 (0) 11 - 60 44 73 E-mail: flesao@uol.com.br www.flenderusa.com
Fax: +381 (0) 11 - 3 11 67 91 Flender Corporation
E-mail: flender@eunet.yu Flender Brasil Ltda. Service Centers West
Rua Campos Salles, 1095 4234 Foster Ave.
sala 04 - Centro 14015 - 110, Bakersfield, CA. 93308
Ribeirão Preto - SP
AFRICA Phone: +55 (0) 16 - 6 35 15 90
Phone: +1 (0) 6 61 - 3 25 44 78
Fax: +1 (0) 6 61 - 3 25 44 70
Fax: +55 (0) 16 - 6 35 11 05 E-mail: flender1@lightspeed.net
NORTH AFRICAN COUNTRIES E-mail: flender.ribpreto@uol.com.br
Please refer to Flender s.a.r.l. VENEZUELA
3, rue Jean Monnet - B.P. 5 F. H. Transmisiones S.A.
78996 Elancourt Cedex CANADA Urbanización Buena Vista
Phone: +33 (0) 1 - 30 66 39 00 Flender Power Transmission Inc. Calle Johan Schafer o Segunda Calle
Fax: +33 (0) 1 - 30 66 35 13 215 Shields Court, Units 4 - 6 Municipio Sucre, Petare
E-mail: sales@flender.fr Markham, Ontario L3R 8V2 Caracas
Phone: +1 (0) 9 05 - 3 05 10 21 Phone: +58 (0) 2 - 21 52 61
Fax: +1 (0) 9 05 - 3 05 10 23 Fax: +58 (0) 2 - 21 18 38
EGYPT E-mail: flender@ca.inter.net E-mail: fhtransm@telcel.net.ve
Sons of Farid Hassanen www.flenderpti.com www.fhtransmisiones.com
81 Matbaa Ahlia Street
Boulac 11221, Cairo SALES OFFICE: ASIA
Phone: +20 (0) 2 - 5 75 15 44 Flender Power Transmission Inc.
Fax: +20 (0) 2 - 5 75 17 02 34992 Bemina Court BANGLADESH / SRI LANKA
E-mail: hussein@sonfarid.com Abbotsford - Vancouver Please refer to Flender Limited
B.C. V3G 1C2 No. 2 St. George’s Gate Road
Phone: +1 (0) 6 04 - 8 59 66 75 5th Floor, Hastings
SOUTH AFRICA Fax: +1 (0) 6 04 - 8 59 68 78 Kolkata - 700 022
Flender Power Transmission (Pty.) Ltd. E-mail: tvickers@rapidnet.net Phone: +91 (0) 33 - 2 23 05 45
Cnr. Furnace St & Quality Rd. Fax: +91 (0) 33 - 2 23 18 57
P.O. Box 131, Isando 1600 E-mail: flender@flenderindia.com
Johannesburg CHILE / ARGENTINA / BOLIVIA
Phone: +27 (0) 11 - 5 71 20 00 ECUADOR / PARAGUAY / URUGUAY PEOPLE’S REPUBLIC OF CHINA
Fax: +27 (0) 11 - 3 92 24 34 Flender Cono Sur Limitada Flender Power Transmission
E-mail: sales@flender.co.za Avda. Galvarino Gallardo 1534 (Tianjin) Co. Ltd.
www.flender.co.za Providencia, Santiago ShuangHu Rd.- Shuangchen Rd. West
Phone: +56 (0) 2 - 2 35 32 49 Beichen Economic Development
SALES OFFICES: Area (BEDA)
Flender Power Transmission (Pty.) Ltd. Fax: +56 (0) 2 - 2 64 20 25
E-mail: flender@flender.cl Tianjin 300400
Unit 3 Marconi Park Phone: +86 (0) 22 - 26 97 20 63
9 Marconi Crescent, Montague Gardens www.flender.cl
Fax: +86 (0) 22 - 26 97 20 61
P.O. Box 37291 E-mail: flender@flendertj.com
Chempet 7442, Cape Town www.flendertj.com
Phone: +27 (0) 21 - 5 51 50 03 COLOMBIA
Fax: +27 (0) 21 - 5 52 38 24 A.G.P. Representaciones Ltda. Flender Power Transmission
E-mail: sales@flender.co.za Flender Liaison Office Colombia (Tianjin) Co. Ltd.
Av Boyaca No 23A Beijing Office
Flender Power Transmission (Pty.) Ltd. 50 Bodega UA 7-1, Bogotá C-415, Lufthansa Center
Unit 3 Goshawk Park Phone: +57 (0) 1 - 5 70 63 53 50 Liangmaqiao Road, Chaoyang District
Falcon Industrial Estate Fax: +57 (0) 1 - 5 70 73 35 Beijing 100016
P.O. Box 1608 E-mail: aguerrero@agp.com.co Phone: +86 (0) 10 - 64 62 21 51
New Germany 3620, Durban www.agp.com.co Fax: +86 (0) 10 - 64 62 21 43
Phone: +27 (0) 31 - 7 05 38 92 E-mail: beijing@flenderprc.com.cn
Fax: +27 (0) 31 - 7 05 38 72 Flender Power Transmission
E-mail: sales@flender.co.za MEXICO (Tianjin) Co. Ltd.
Flender Power Transmission (Pty.) Ltd. Flender de Mexico S.A. de C.V. Shanghai Office
9 Industrial Crescent, Ext. 25 17, Pte, 713 Centro 1101-1102 Harbour Ring Plaza
P.O. Box 17609, Witbank 1035 72000 Puebla 18 Xizang Zhong Rd.
Phone: +27 (0) 13 - 6 92 34 38 Phone: +52 (0) 2 22 - 2 37 19 00 Shanghai 200 001
Fax: +27 (0) 13 - 6 92 34 52 Fax: +52 (0) 2 22 - 2 37 11 33 Phone: +86 (0) 21 - 53 85 31 48
E-mail: sales@flender.co.za E-mail: szugasti@flendermexico.com Fax: +86 (0) 21 - 53 85 31 46
www.flendermexico.com E-mail: shanghai@flenderprc.com.cn
Flender Power Transmission (Pty.) Ltd. Flender Power Transmission
Unit 14 King Fisher Park, Alton SALES OFFICES: (Tianjin) Co. Ltd.
Cnr. Ceramic Curve & Alumina Allee Flender de Mexico S.A. de C.V. Wuhan Office
P.O. Box 101995 Lago Nargis No. 38 Rm. 1503, Jianyin Building,
Meerensee 3901, Richards Bay Col. Granada, 709 Jianshedadao
Phone: +27 (0) 35 - 7 51 15 63 11520 Mexico, D.F. Wuhan 430 015
Fax: +27 (0) 35 - 7 51 15 64 Phone: +52 (0) 55 - 52 54 30 37 Phone: +86 (0) 27 - 85 48 67 15
E-mail: sales@flender.co.za Fax: +52 (0) 55 - 55 31 69 39 Fax: +86 (0) 27 - 85 48 68 36
E-mail: info@flendermexico.com E-mail: wuhan@flenderprc.com.cn
Flender de Mexico S.A. de C.V. Flender Power Transmission
AMERICA Ave. San Pedro No. 231-5 (Tianjin) Co. Ltd.
Col. Miravalle Guangzhou Office
64660 Monterrey, N.L. Rm. 2802, Guangzhou International
ARGENTINA Electronics Tower
Chilicote S.A. Phone: +52 (0) 81 - 83 63 82 82
Fax: +52 (0) 81 - 83 63 82 83 403 Huanshi Rd. East
Avda. Julio A. Roca 546
E-mail: info@flendermexico.com Guangzhou 510 095
C 1067 ABN Buenos Aires
Phone: +86 (0) 20 - 87 32 60 42
Phone: +54 (0) 11 - 43 31 66 10 Fax: +86 (0) 20 - 87 32 60 45
Fax: +54 (0) 11 - 43 31 42 78 E-mail: guangzhou@flenderprc.com.cn
E-mail: chilicote@chilicote.com.ar PERU
Potencia Industrial E.I.R.L. Flender Power Transmission
Calle Victor González Olaechea N° 110 (Tianjin) Co. Ltd.
BRASIL Urb. La Aurora - Miraflores, Chengdu Office
Flender Brasil Ltda. P.O.Box: Av. 2 de Mayo N° 679 G-6 / F Guoxin Mansion,
Rua Quatorze, 60 - Cidade Industrial Of.108-Miraflores 77 Xiyu Street
32211 - 970, Contagem - MG Casilla N° 392, Lima 18 Chengdu 610 015
Phone: +55 (0) 31 - 33 69 21 00 Phone: +51 (0) 1 - 2 42 84 68 Phone: +86 (0) 28 - 86 19 83 72
Fax: +55 (0) 31 - 33 69 21 66 Fax: +51 (0) 1 - 2 42 08 62 Fax: +86 (0) 28 - 86 19 88 10
E-mail: vendas@flenderbrasil.com E-mail: cesarzam@chavin.rcp.net.pe E-mail: chengdu@flenderprc.com.cn
BA 3600 EN 08.98
Flender Power Transmission ISRAEL SINGAPORE
(Tianjin) Co. Ltd. Greenshpon Engineering Works Ltd. Flender Singapore Pte. Ltd.
Shenyang Office Haamelim Street 20 13 A, Tech Park Crescent
Rm. 2-163, Tower I, City Plaza Shenyan P.O. Box 10108, 26110 Haifa Singapore 637843
206 Nanjing Street (N), Heping District Phone: +972 (0) 4 - 8 72 11 87 Phone: +65 (0) - 68 97 94 66
Shenyang 110 001 Fax: +972 (0) 4 - 8 72 62 31 Fax: +65 (0) - 68 97 94 11
Phone: +86 (0) 24 - 23 34 20 48 E-mail: sales@greenshpon.com E-mail: flender@singnet.com.sg
Fax: +86 (0) 24 - 23 34 20 46 www.greenshpon.com www.flender.com.sg
E-mail: shenyang@flenderprc.com.cn
JAPAN SYRIA
Flender Power Transmission Flender Japan Co., Ltd. Misrabi Co & Trading
(Tianjin) Co. Ltd. WBG Marive East 21F Mezzeh Autostrade Transportation
Xi’an Office Nakasa 2 - 6 Building 4/A, 5th Floor
Rm. 302, Shaanzi Zhong Da Mihama-ku, Chiba-shi P.O. Box 12450, Damascus
International Mansion Chiba 261-7121 Phone: +963 (0) 11 - 6 11 67 94
30 Southern Rd. Phone: +81 (0) 43 - 2 13 39 30 Fax: +963 (0) 11 - 6 11 09 08
Xi’an 710 002 Fax: +81 (0) 43 - 2 13 39 55 E-mail: ismael.misrabi@gmx.net
Phone: +86 (0) 29 - 7 20 32 68 E-mail: contact@flender-japan.com
Fax: +86 (0) 29 - 7 20 32 04
E-mail: xian@flenderprc.com.cn TAIWAN
KOREA A. Friedr. Flender AG
Flender Ltd. Taiwan Branch Company
INDIA 7th Fl. Dorim Bldg. 1F, No. 5, Lane 240
Flender Limited 1823 Bangbae-Dong, Seocho-Ku, Nan Yang Street, Hsichih
Head Office: Seoul 137-060 Taipei Hsien 221
No. 2 St. George’s Gate Road Phone: +82 (0) 2 - 34 78 63 37 Phone: +886 (0) 2 - 26 93 24 41
5th Floor, Hastings Fax: +82 (0) 2 - 34 78 63 45 Fax: +886 (0) 2 - 26 94 36 11
Kolkata - 700 022 E-mail: flender@unitel.co.kr E-mail: flender_tw@flender.com.tw
Phone: +91 (0) 33 - 22 23 05 45
Fax: +91 (0) 33 - 22 23 08 30 KUWAIT THAILAND
E-mail: flender@flenderindia.com South Gulf Company Flender Singapore Pte. Ltd.
Al-Reqai, Plot 1, Block 96 Representative Office
Flender Limited P.O. Box 26229, Safat 13123 23/F M Thai Tower, All Seasons Place
Industrial Growth Centre Phone: +965 (0) - 4 88 39 15 87 Wireless Road, Phatumwan
Rakhajungle, Nimpura Fax: +965 (0) - 4 88 39 14 Bangkok 10330
Kharagpur - 721 302 E-mail: adelameen@hotmail.com Phone: +66 (0) 2 - 6 27 91 09
Phone: +91 (0) 3222 - 23 33 07 Fax: +66 (0) 2 - 6 27 90 01
Fax: +91 (0) 3222 - 23 33 64 LEBANON E-mail: christian.beckers@flender.th.com
E-mail: works@flenderindia.com Gabriel Acar & Fils s.a.r.l.
Dahr-el-Jamal VIETNAM
SALES OFFICES: Zone Industrielle, Sin-el-Fil Flender Singapore Pte. Ltd.
Flender Limited B.P. 80484, Beyrouth Representative Office
Eastern Regional Sales Office Phone: +961 (0) 1 - 49 82 72 Suite 6/6A, 16F Saigon Tower
No. 2 St. George’s Gate Road Fax: +961 (0) 1 - 49 49 71 29 Le Duan Street, District 1
5th Floor, Hastings E-mail: gacar@beirut.com Ho Chi Minh City, Vietnam
Kolkata - 700 022
Phone: +84 (0) 8 - 8 23 62 97
Phone: +91 (0) 33 - 22 23 05 45
MALAYSIA Fax: +84 (0) 8 - 8 23 62 88
Fax: +91 (0) 33 - 22 23 08 30 E-mail: flender@hcm.vnn.vn
Flender Singapore Pte. Ltd.
E-mail: ero@flenderindia.com
Representative Office
Flender Limited 37 A - 2, Jalan PJU 1/39
Western Regional Sales Office Dataran Prima AUSTRALIA
Plot No. 23, Sector 19 - C 47301 Petaling Jaya
Vashi, Navi Mumbai - 400 705 Selangor Darul Ehsan
Phone: +91 (0) 22 - 27 65 72 27 Phone: +60 (0) 3 - 78 80 42 63
Fax: +60 (0) 3 - 78 80 42 73 Flender (Australia) Pty. Ltd.
Fax: +91 (0) 22 - 27 65 72 28 9 Nello Place, P.O. Box 6047
E-mail: wro@flenderindia.com E-mail: flender@tm.net.my
Wetherill Park
Flender Limited N.S.W. 2164, Sydney
PAKISTAN Phone: +61 (0) 2 - 97 56 23 22
Southern Regional Sales Office Please refer to
41 Nelson Manickam Road Fax: +61 (0) 2 - 97 56 48 92, 97 56 14 92
A. Friedr. Flender AG
Aminjikarai, E-mail: sales@flender.com.au
46393 Bocholt
Chennai - 600 029 www.flender.com.au
Phone: +49 (0) 28 71 - 92 22 59
Phone: +91 (0) 44 - 23 74 39 21 Fax: +49 (0) 28 71 - 92 15 16 SALES OFFICES:
Fax: +91 (0) 44 - 23 74 39 19 E-mail: ludger.wittag@flender.com Flender (Australia) Pty. Ltd.
E-mail: sro@flenderindia.com Suite 3, 261 Centre Rd.
PHILIPPINES Bentleigh, VIC 3204 Melbourne
Flender Limited Phone: +61 (0) 3 - 95 57 08 11
Northern Regional Sales Office Flender Singapore Pte. Ltd.
Representative Office Fax: +61 (0) 3 - 95 57 08 22
209-A, Masjid Moth, 2nd Floor E-mail: sales@flender.com.au
(Behind South Extension II) 28/F, Unit 2814
New Delhi - 110 049 The Enterprise Centre Flender (Australia) Pty. Ltd.
Phone: +91 (0) 11 - 26 25 02 21 6766 Ayala Avenue corner Suite 5, 1407 Logan Rd.
Fax: +91 (0) 11 - 26 25 63 72 Paeso de Roxas, Makati City Mt. Gravatt
E-mail: nro@flenderindia.com Phone: +63 (0) 2 - 8 49 39 93 QLD 4122, Brisbane
Fax: +63 (0) 2 - 8 49 39 17 Phone: +61 (0) 7 - 34 22 23 89
E-mail: roman@flender.com.ph Fax: +61 (0) 7 - 34 22 24 03
INDONESIA E-mail: sales@flender.com.au
Flender Singapore Pte. Ltd. BAHRAIN / IRAQ / JORDAN / LYBIA Flender (Australia) Pty. Ltd.
Representative Office OMAN / QATAR / U.A.E. / YEMEN
Please refer to A. Friedr. Flender AG Suite 2 403 Great Eastern Highway
Perkantoran Puri Niaga II W.A. 6104, Redcliffe - Perth
Jalan Puri Kencana Blok J1 Middle East Sales Office
IMES Sanayi Sitesi Phone: +61 (0) 8 - 94 77 41 66
No. 2i, Kembangan Fax: +61 (0) 8 - 94 77 65 11
Jakarta Barat 11610 E Blok 502, Sokak No. 22
81260 Dudullu - Istanbul E-mail: sales@flender.com.au
Phone: +62 (0) 21 - 5 82 86 24
Fax: +62 (0) 21 - 5 82 86 23 Phone: +90 (0) 2 16 - 4 99 66 23
Fax: +90 (0) 2 16 - 3 64 59 13 NEW ZEALAND
E-mail: bobwall@cbn.net.id Please refer to Flender (Australia) Pty. Ltd.
E-mail: meso@flendertr.com
9 Nello Place, P.O. Box 6047
IRAN SAUDI ARABIA Wetherill Park
Cimaghand Co. Ltd. South Gulf Co. N.S.W. 2164, Sydney
P.O. Box 15745-493 Al-Khobar, Dahran Str. Phone: +61 (0) 2 - 97 56 23 22
No. 13, 16th East Street Middle East Trade Center Fax: +61 (0) 2 - 97 56 48 92
Beyhaghi Ave., Argentina Sq. 3rd floor, Flat # 23 E-mail: sales@flender.com.au
Tehran 15156 P.O. Box 20434 31952 Al-Khobar
Phone: +98 (0) 21 - 8 73 02 14 Phone: +966 (0) 3 - 8 87 53 32
Fax: +98 (0) 21 - 8 73 39 70 Fax: +966 (0) 3 - 8 87 53 31
E-mail: info@cimaghand.com E-mail: adelameen@hotmail.com
BA 3600 EN 08.98
12. Declaration by the manufacturer
This Manufacturer’s Declaration takes into account all the unified standards (inasmuch as
they apply to our products) published by the European Commission in the Official Journal of
the European Community.
Bocholt, 1998-08-24
Signature (person responible for products)
BA 3600 EN 08.98
Bauart RWS Seite
Stückliste (SL) Type Page
Parts list Größe 710,0 1/1
Size
Übersetzung
ratio
Bei Korrespondenz bitte angeben
Please quote in correspondence SL 4214492-020 DE/EN
Hierzu gehört Zeichnungs-Nr.
Please refer to DWG No. 6106880
Teil-Nr. Menge Benennung Zeichnungs-Nr. Material-Nr. Gw(kg)
Part No. No. off Description Drawings No. Ident no. Weight
Die mit * gekennzeichneten Teile gehören zu einer Baugruppe (G). Die Baugruppe ist nur komplett auszutauschen.
The parts marked with * belong to a subassembly (G). The subassemblymust be replaced complete.
BA 5010 EN 06.03
Gear Unit Types
H.SH, H.VH, H.HH, H.DH, H.KH, H.FH, H.HM, H.DM, H.KM, H.FM, H.PH
B.SH, B.VH, B.HH, B.DH, B.KH, B.FH, B.HM, B.DM, B.KM, B.FM
Sizes 3 to 26
H.SH B.SH
H.VH B.VH
H.HH
H.DH B.HH
H.KH B.DH
H.PH B.KH
H.FH B.FH
H.HM B.HM
H.DM B.DM
H.KM B.KM
H.FM B.FM
1. Technical data 5
1.1 General technical data 5
1.1.1 Weights 6
1.1.2 Measuring-surface sound-pressure level 7
1.1.2.1 Measuring-surface sound-pressure level for bevel-helical gear units (B...) with fan 7
1.1.2.2 Measuring-surface sound-pressure level for bevel-helical gear units (B...) without fan 8
1.1.2.3 Measuring-surface sound-pressure level for helical gear units (H...) with fan 9
1.1.2.4 Measuring-surface sound-pressure level for helical gear units (H...) without fan 10
2. General notes 11
2.1 Introduction 11
2.2 Copyright 11
3. Safety notes 11
3.1 Proper use 11
3.2 Obligations of the user 12
3.3 Environmental protection 12
3.4 Special dangers 13
3.5 Warnings and symbols used in these Instructions 13
5. Technical description 16
5.1 General description 16
5.2 Output designs 17
5.3 Housing 17
5.4 Toothed components 19
5.5 Lubrication 19
5.5.1 Dip lubrication 19
5.5.2 Pressure lubrication through add-on oil supply system 20
5.6 Shaft bearings 20
5.7 Shaft seals 21
5.7.1 Radial shaft sealing rings 21
5.7.2 Labyrinth seals 21
5.7.3 Taconite seals 21
5.8 Backstop 23
5.9 Cooling 24
5.9.1 Fan 24
5.9.2 Cooling coil 25
5.9.3 Add-on air oil-cooling units 26
5.9.4 Add-on water oil-cooling units 27
5.10 Heating element 28
5.11 Oil-temperature measurement 29
5.12 Oil-level monitoring system 29
5.13 Bearing monitoring system 30
5.14 Speed transmitter 30
BA 5010 EN 06.03
6. Assembly 31
6.1 General information on installation 31
6.2 Installation of gear unit on housing base 31
6.2.1 Foundation 31
6.2.2 Description of installation work 32
6.2.2.1 Aligning surfaces, aligning thread 33
6.2.2.2 Mounting on a foundation frame 33
6.2.2.3 Mounting on a concrete foundation by means of stone bolts or foundation blocks 34
6.2.2.4 Mounting on a concrete foundation by means of anchor bolts 35
6.3 Couplings 37
6.4 Assembly of a shaft-mounting gear unit with hollow shaft and parallel keyway 39
6.4.1 Preparatory work 39
6.4.2 Assembly 39
6.4.2.1 Fitting 40
6.4.2.2 Axial fastening 40
6.4.3 Dismantling 41
6.5 Shaft-mounting gear unit with hollow shaft and internal spline to DIN 5480 43
6.5.1 Preparatory work 43
6.5.2 Assembly 43
6.5.2.1 Fitting 44
6.5.2.2 Axial fastening 44
6.5.3 Dismantling 45
6.6 Shaft-mounting gear unit with hollow shaft and shrink disk 47
6.6.1 Assembly 47
6.6.1.1 Fitting 47
6.6.1.2 Axial fastening 48
6.6.2 Shrink disk, type HSD 48
6.6.2.1 Assembly of shrink disk 48
6.6.2.2 Demounting and remounting the shrink disk 49
6.6.2.3 Cleaning and greasing the shrink disk 50
6.6.3 Dismantling 50
6.7 Shaft-mounting gear unit with flanged shaft 52
6.8 Shaft mounting gear unit with block flange 53
6.9 Mounting the torque arm for gear housing 54
6.9.1 Attaching the torque arm 54
6.10 Mounting supports for gear-unit swing bases 55
6.10.1 Attaching the support 55
6.11 Gear unit with cooling coil 56
6.12 Gear unit with add-on components 56
6.13 Gear unit with air oil-cooler 56
6.14 Gear unit with water oil-cooler 56
6.15 Gear units with heating element 56
6.16 Gear units with oil-temperature measurement 56
6.17 Gear units with oil-level monitoring 56
6.18 Gear units with speed transmitter 56
6.19 Final work 56
BA 5010 EN 06.03
7. Start-up 57
7.1 Procedure before start-up 57
7.1.1 Removal of preservative agent 57
7.1.2 Charging with lubricant 58
7.1.2.1 Oil quantities 59
7.2 Start-up 60
7.2.1 Oil level 60
7.2.2 Gear unit with cooling coil or external oil cooling or oil supply system 60
7.2.3 Gear unit with backstop 60
7.2.4 Checking procedure 60
7.3 Removal from service 60
7.3.1 Interior preservation during longer disuse 61
7.3.1.1 Interior preservation with gear oil 61
7.3.1.2 Interior preservation with preservative agent 61
7.3.1.3 Interior preservation procedure 61
7.3.2 Exterior preservation 62
7.3.2.1 Exterior preservation procedure 62
8. Operation 62
BA 5010 EN 06.03
1. Technical data
The most important technical data are shown on the rating plate. These data and the contractual
agreements between FLENDER and the customer for the gear unit determine the limits of its correct
use.
1
2
3
4 5
6 7
8 9 10
11
12
e.g. *)
B 3 S H 13
Size . . . . . . . . . . . . . . . . . 3 ... 26
Installation . . . . . . . . . . . H = horizontal
M= horizontal design without base
(from size 13)
Type of output shaft . . . S = solid shaft
V = solid shaft, reinforced
H = hollow shaft with parallel keyway
D = hollow shaft for shrink disk
K = hollow shaft with internal-spline
to DIN 5480
F = flanged shaft
P = Design of paper processing machine
Number of stages . . . . . 1, 2, 3 or 4
Gear-unit type . . . . . . . . H = Helical gear unit
B = Bevel-helical gear unit
( 2, 3 or 4 stages only)
Data on weights and measuring-surface sound-pressure levels of the various gear types are given in
items 1.1.1 and 1.1.2.
For further technical data, refer to the drawings in the gear-unit documentation.
BA 5010 EN 06.03
1.1.1 Weights
H2.H 115 190 300 355 505 590 830 960 1335 1615 2000 2570
H3.H – – 320 365 540 625 875 1020 1400 1675 2295 2625
B2.H 140 235 360 410 615 700 1000 1155 1640 1910 2450 2825
B3.H 130 210 325 380 550 635 890 1020 1455 1730 2380 2750
B4.H – – 335 385 555 655 890 1025 1485 1750 2395 2735
H2.H 3430 3655 4650 5125 6600 7500 8900 9600 11600 13000 15500 17200
H2.M 3240 3465 4420 4870 6300 7200 8400 9200 11000 12300 14700 16200
H3.H 3475 3875 4560 5030 6700 8100 9100 9800 11500 13400 16100 17600
H3.M 3260 3625 4250 4740 6200 7600 8500 9300 10600 12500 15200 16500
H4.H 3635 3965 4680 5185 6800 8200 9200 9900 11600 13500 16100 17600
H4.M 3440 3740 4445 4915 6300 7700 8600 9400 10700 12600 15200 16500
B3.H 3730 3955 4990 5495 7000 8100 9200 9900 11500 13400 16000 17500
B3.M 3540 3765 4760 5240 6500 7600 8600 9400 10600 12500 15100 16400
B4.H 3630 3985 4695 5200 6800 8200 9200 9900 11600 13500 16100 17600
B4.M 3435 3765 4460 4930 6300 7700 8600 9400 10700 12600 15200 16500
Table 1.1: Weights (approx. values only)
Note: All weights are for gear unit without oil filling or add-ons. For the exact weights, refer
to the drawings in the gear-unit documentation.
BA 5010 EN 06.03
1.1.2 Measuring-surface sound-pressure level
The measuring-surface sound-pressure level for the gear unit at a distance of 1 metre can be found in
tables 1.1.2.1 to 1.1.2.4.
The measurement is carried out to DIN 45635 Parts 1 and 23, using the sound-intensity method.
The workplace of the operating personnel is defined as the area on the measuring-surface at a distance
of 1 metre in the vicinity of which persons may be present.
The sound-pressure level applies to the warmed-up gear unit at input speed n1 and output power P2
stated on the rating plate. If several figures are given, the highest speed and power values apply.
The measuring surface sound-pressure level does not include add-on lubricating units.
If repeat measurements on site do not produce conclusive results with regard to measuring technology,
the measurement obtained on the FLENDER test bench will apply.
The sound-pressure levels stated in the table were obtained by statistical calculation by our Quality
Control Dept. The gear unit can be statistically expected to comply with these sound-pressure levels.
1.1.2.1 Measuring-surface sound-pressure level for bevel-helical gear units (B...) with fan
Measuring-surface sound-pressure level LpA in dB(A) for bevel-helical gear units with fan
n1 Gear-unit size
Type iN 1/min 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
5 1500 73 76 79 81 83 84 85 87 88 89 91 92 94 – – – – – – – – – – –
. 1000 67 71 73 74 77 78 79 80 82 83 84 85 87 89 90 – – – – – – – – –
8 750 61 64 66 67 70 71 72 73 75 76 77 78 81 82 83 85 – – – – – – – –
9 1500 70 73 75 76 78 81 82 83 84 85 86 87 88 90 – – – – – – – – – –
B2 . 1000 63 67 68 70 73 74 75 77 79 80 81 82 83 84 86 87 – – – – – – – –
14 750 1) 61 62 64 66 67 68 70 72 73 74 75 77 78 79 80 – – – – – – – –
16 1500 67 71 74 76 78 79 80 81 83 84 87 88 89 90 – – – – – – – – – –
. 1000 60 64 67 68 70 72 73 74 78 79 80 81 82 83 84 84 – – – – – – – –
22.4 750 1) 1) 61 63 65 67 68 69 71 72 73 73 74 74 75 76 – – – – – – – –
12.5 1500 69 72 75 77 79 80 81 82 83 85 88 89 90 91 93 93 93 93 95 95 – – – –
. 1000 62 65 68 69 71 72 73 74 77 78 80 82 83 83 84 85 86 86 88 88 89 90 91 –
31.5 750 1) 1) 63 64 66 68 69 70 71 73 74 75 76 77 78 78 79 79 81 81 82 84 85 85
35.5 1500 67 69 72 73 74 75 77 79 82 84 86 87 88 89 90 91 92 92 93 93 – – – –
B3 . 1000 1) 63 65 66 67 69 71 72 73 75 77 78 79 80 81 82 83 84 85 86 86 87 88 89
56 750 1) 1) 1) 1) 62 64 65 67 69 70 71 72 73 74 75 76 77 78 79 79 80 81 82 82
63 1500 66 68 70 71 73 74 76 78 81 83 85 86 87 88 89 90 91 91 92 92 – – – –
. 1000 1) 61 63 64 66 68 69 71 73 75 77 78 79 80 81 81 82 82 83 84 84 85 86 86
90 750 1) 1) 1) 1) 61 63 64 66 67 68 70 71 72 73 74 75 75 76 77 77 78 79 79 80
BA 5010 EN 06.03
1.1.2.2 Measuring-surface sound-pressure level for bevel-helical gear units (B...) without fan
Measuring-surface sound-pressure level LpA in dB(A) for bevel-helical gear units without fan
n1 Gear-unit size
Type iN 1/min 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
5 1500 72 75 78 80 82 83 84 86 87 88 89 90 93 – – – – – – – – – – –
. 1000 66 70 72 73 76 77 78 79 81 82 83 84 86 88 89 – – – – – – – – –
8 750 1) 63 65 66 69 71 72 73 74 75 77 78 80 82 83 84 – – – – – – – –
9 1500 67 71 74 75 77 79 80 81 83 84 85 86 87 89 – – – – – – – – – –
B2 . 1000 61 65 67 69 72 73 74 76 77 78 80 81 82 83 85 86 – – – – – – – –
14 750 1) 1) 60 63 65 66 67 69 71 72 73 74 76 77 78 79 – – – – – – – –
16 1500 63 66 69 71 72 74 75 77 78 80 81 82 85 85 – – – – – – – – – –
. 1000 1) 61 63 65 67 68 69 71 72 74 75 77 79 80 81 81 – – – – – – – –
22.4 750 1) 1) 1) 1) 60 62 63 64 66 67 68 70 72 73 74 75 – – – – – – – –
12.5 1500 65 68 71 74 75 76 77 79 81 83 84 85 86 87 87 88 89 90 91 92 – – – –
. 1000 1) 63 66 68 69 70 72 73 75 77 78 80 80 81 82 82 84 85 86 86 88 89 90 –
31.5 750 1) 1) 1) 61 62 64 65 66 68 71 71 73 73 74 75 75 77 78 79 79 81 82 83 84
35.5 1500 60 65 67 70 71 71 72 74 77 79 80 81 82 83 83 84 86 86 88 88 – – – –
B3 . 1000 1) 1) 62 65 65 66 66 69 71 73 75 76 76 77 77 78 80 81 82 83 84 85 86 87
56 750 1) 1) 1) 1) 1) 1) 1) 62 65 67 68 69 70 70 71 72 74 74 75 76 78 80 80 80
63 1500 1) 61 64 70 67 68 68 70 73 75 76 78 78 79 79 80 82 83 84 84 – – – –
. 1000 1) 1) 1) 63 62 62 62 65 68 70 71 72 73 73 74 75 76 77 78 79 81 81 83 83
90 750 1) 1) 1) 1) 1) 1) 1) 1) 61 63 64 65 66 67 67 68 70 70 72 72 74 75 76 76
80 1500 – – 64 65 67 68 70 72 75 76 77 79 80 81 82 83 84 85 86 86 87 88 87 89
. 1000 – – 1) 1) 61 63 64 67 69 70 72 73 74 75 76 77 78 79 80 80 81 82 82 83
125 750 – – 1) 1) 1) 1) 1) 1) 62 64 65 66 68 68 69 71 71 72 73 74 74 75 75 76
140 1500 – – 60 61 63 65 66 68 71 72 73 75 76 77 78 79 80 81 82 82 83 84 85 86
B4 . 1000 – – 1) 1) 1) 1) 61 63 65 67 68 69 71 71 72 74 75 75 76 77 78 78 79 80
224 750 – – 1) 1) 1) 1) 1) 1) 1) 1) 61 62 64 65 66 67 68 69 69 70 71 72 73 73
250 1500 – – 1) 1) 1) 62 63 65 67 69 70 71 73 73 75 76 77 77 78 79 80 80 81 82
. 1000 – – 1) 1) 1) 1) 1) 1) 62 63 64 66 67 68 69 70 71 72 73 73 74 75 76 77
400 750 – – 1) 1) 1) 1) 1) 1) 1) 1) 1) 1) 1) 61 62 63 64 65 66 66 67 68 69 70
1) LpA 60 dB(A)
BA 5010 EN 06.03
1.1.2.3 Measuring-surface sound-pressure level for helical gear units (H...) with fan
Measuring-surface sound-pressure level LpA in dB(A) for helical gear units with fan
n1 Gear-unit size
Type iN 1/min 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
1.25 1500 76 – 81 – 84 – 87 – 91 – – – – – – – – – – – – – – –
. 1000 71 – 76 – 79 – 81 – 83 – 85 – – – – – – – – – – – – –
2 750 67 – 72 – 75 – 78 – 80 – 82 – 85 – – – – – – – – – – –
2.24 1500 73 – 79 – 82 – 84 – 89 – 90 – – – – – – – – – – – – –
H1 . 1000 68 – 74 – 77 – 79 – 82 – 84 – 87 – – – – – – – – – – –
3.55 750 64 – 70 – 72 – 75 – 78 – 80 – 83 – 84 – – – – – – – – –
4 1500 70 – 77 – 81 – 83 – 86 – 89 – 93 – – – – – – – – – – –
. 1000 65 – 71 – 75 – 77 – 80 – 82 – 84 – 85 – 87 – – – – – – –
5.6 750 61 – 68 – 71 – 72 – 75 – 77 – 79 – 81 – 83 – – – – – – –
6.3 1500 – 75 76 77 80 81 82 84 85 86 88 90 92 94 96 96 – – – – – – – –
. 1000 – 69 71 72 74 75 77 79 80 81 83 84 85 86 87 88 88 89 90 – – – – –
10 750 – 66 68 69 70 72 73 75 76 77 79 80 81 82 83 83 84 84 85 85 86 – – –
11.2 1500 – 73 75 77 79 80 81 82 85 88 90 91 92 93 95 95 – – – – – – – –
H2 . 1000 – 68 69 70 72 73 75 77 79 80 82 83 84 85 85 86 86 87 87 87 88 88 – –
16 750 – 64 66 67 69 70 71 73 74 76 78 79 79 80 81 81 82 82 83 83 83 84 84 85
18 1500 – 71 73 75 77 78 80 82 84 86 87 90 91 92 93 94 94 95 95 95 – – – –
. 1000 – 65 67 68 71 72 73 75 77 78 80 81 82 83 83 84 85 85 86 86 86 87 87 87
28 750 – 62 64 65 67 68 69 71 73 74 75 77 78 79 79 80 80 81 81 81 82 82 82 83
22.4 1500 – – 71 72 75 75 77 77 80 80 81 81 84 84 84 85 – – – – – – – –
. 1000 – – 65 66 69 70 71 72 74 75 75 75 78 78 78 79 – – – – – – – –
35.5 750 – – 62 62 66 67 67 68 70 70 71 72 74 74 75 76 – – – – – – – –
40 1500 – – 70 71 73 74 76 76 79 79 80 80 83 82 83 83 – – – – – – – –
H3 . 1000 – – 64 65 67 68 69 70 73 73 73 74 77 77 77 77 – – – – – – – –
63 750 – – 62 62 63 64 65 66 69 69 69 70 72 73 73 73 – – – – – – – –
71 1500 – – 70 70 72 72 75 75 78 78 78 78 82 82 82 82 – – – – – – – –
. 1000 – – 64 64 65 66 68 69 71 72 72 72 75 75 75 76 – – – – – – – –
112 750 – – 61 61 62 62 64 65 67 67 68 68 71 71 71 72 – – – – – – – –
1) LpA 60 dB(A)
BA 5010 EN 06.03
1.1.2.4 Measuring-surface sound-pressure level for helical gear units (H...) without fan
Measuring-surface sound-pressure level LpA in dB(A) for helical gear units without fan
n1 Gear-unit size
Type iN 1/min 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
1.25 1500 73 – 77 – 79 – 81 – 83 – – – – – – – – – – – – – – –
. 1000 69 – 72 – 75 – 76 – 78 – 80 – – – – – – – – – – – – –
2 750 65 – 69 – 71 – 73 – 75 – 77 – 79 – – – – – – – – – – –
2.24 1500 70 – 75 – 77 – 79 – 81 – 83 – – – – – – – – – – – – –
H1 . 1000 66 – 70 – 72 – 74 – 76 – 78 – 80 – – – – – – – – – – –
3.55 750 62 – 67 – 68 – 71 – 73 – 75 – 77 – 79 – – – – – – – – –
4 1500 67 – 72 – 74 – 76 – 78 – 79 – 82 – – – – – – – – – – –
. 1000 1) – 67 – 70 – 71 – 73 – 75 – 77 – 79 – 81 – – – – – – –
5.6 750 1) – 63 – 66 – 67 – 70 – 71 – 74 – 76 – 78 – – – – – – –
6.3 1500 – 71 74 75 76 77 79 79 80 81 81 82 84 85 85 86 – – – – – – – –
. 1000 – 66 69 70 71 72 74 74 75 76 76 77 80 80 80 81 83 83 84 – – – – –
10 750 – 63 66 67 67 69 70 71 72 73 73 74 76 77 77 78 80 80 81 81 81 – – –
11.2 1500 – 69 72 73 74 75 77 77 78 79 79 80 82 83 83 84 – – – – – – – –
H2 . 1000 – 64 67 68 69 70 72 72 73 74 74 75 77 78 78 79 81 81 82 82 83 83 – –
16 750 – 61 64 65 66 67 69 69 70 71 71 72 74 75 75 76 77 78 79 79 79 80 81 81
18 1500 – 66 69 70 71 72 74 74 75 76 77 78 80 80 81 82 83 84 84 85 – – – –
. 1000 – 61 64 65 66 68 69 69 70 71 72 73 75 75 76 77 78 79 79 80 80 81 81 82
28 750 – 1) 61 62 63 64 66 66 67 68 69 70 72 72 73 73 75 75 76 76 77 77 78 78
22.4 1500 – – 68 69 73 74 74 75 77 77 78 79 81 81 82 83 83 84 85 86 86 87 – –
. 1000 – – 63 65 68 69 69 71 72 73 73 74 76 77 77 78 79 79 81 81 81 82 83 83
35.5 750 – – 60 61 65 66 65 67 69 69 70 71 73 73 74 75 75 76 77 78 78 79 79 80
35.5 1500 – – 65 67 70 71 71 73 74 75 76 76 78 79 79 80 81 81 83 83 84 84 – –
H3 . 1000 – – 1) 62 65 66 66 68 69 70 71 72 73 74 75 75 76 77 78 78 79 79 80 80
63 750 – – 1) 1) 62 63 63 65 66 67 67 68 70 71 71 72 73 73 75 75 76 76 77 77
71 1500 – – 62 64 67 68 68 70 71 72 73 74 76 76 77 78 78 79 80 81 81 82 82 83
. 1000 – – 1) 1) 62 63 63 65 66 67 68 69 71 71 72 73 73 74 75 76 76 77 77 78
112 750 – – 1) 1) 1) 1) 1) 62 63 64 65 66 68 68 69 70 70 71 72 72 73 73 74 75
100 1500 – – – – 66 67 68 69 70 71 72 73 75 75 76 76 77 78 78 78 79 80 81 81
. 1000 – – – – 62 63 63 64 65 66 67 68 70 70 71 72 72 73 73 74 74 76 76 77
140 750 – – – – 1) 1) 1) 61 62 63 64 64 66 67 68 68 69 69 70 70 71 72 73 73
160 1500 – – – – 64 65 66 66 68 68 69 70 72 73 73 74 74 75 75 76 76 78 78 79
H4 . 1000 – – – – 1) 60 61 62 63 64 64 65 67 68 68 69 70 70 71 71 72 73 74 74
250 750 – – – – 1) 1) 1) 1) 60 61 61 62 64 64 65 66 66 67 67 68 68 70 70 71
280 1500 – – – – 61 62 63 64 65 66 67 67 69 70 70 71 72 72 73 73 74 75 76 76
. 1000 – – – – 1) 1) 1) 1) 60 61 62 63 64 65 66 66 67 68 68 68 69 70 71 72
450 750 – – – – 1) 1) 1) 1) 1) 1) 1) 1) 61 62 62 63 64 64 55 65 65 67 68 68
1) LpA 60 dB(A)
BA 5010 EN 06.03
2. General notes
2.1 Introduction
These Operating Instructions (BA) are an integral part of the gear unit supplied and must be kept in its
vicinity for reference at all times.
The ”FLENDER gear unit” described in these Operating Instructions (BA) has been developed for
stationary use in general engineering applications. Possible areas of use for gear units of this type are
(e.g.) sewage treatment, excavators, chemical industry, iron and steel industry, conveyor systems,
crane systems, foodstuffs industry, paper machinery, cableways, cement industry, etc.
The gear unit is designed only for the application described in section 1, ”Technical data”.
The gear unit described in these Instructions reflects the state of technical development at the time
these Instructions went to print.
In the interest of technical progress we reserve the right to make changes to the individual assemblies
and accessories which we regard as necessary to preserve their essential characteristics and improve
their efficiency and safety.
2.2 Copyright
Internet: www.flender.com
or to one of our customer-service addresses. A list of our customer-service addresses is given in
section 11, ”Spare parts, customer-service addresses”.
3. Safety notes
S The gear unit has been manufactured in accordance with the state of the art and is delivered in a
condition for safe and reliable use. Any changes on the part of the user are not permitted. This applies
equally to safety features designed to prevent accidental contact.
S The gear unit must be used and operated strictly in accordance with the conditions laid down in the
contract governing performance and supply agreed by FLENDER and the customer.
BA 5010 EN 06.03
3.2 Obligations of the user
S The operator must ensure that all persons involved in installation, operation, maintenance and repair
have read and understood these Operating Instructions and comply with them at all times in order
to:
and
S During transport, assembly, installation, dismantling, operation and maintenance of the unit, the
relevant safety and environmental regulations must be complied with at all times.
S The gear unit should be operated, maintained or repaired by authorised, trained and qualified
personnel.
S The gear unit must not be cleaned using high-pressure cleaning equipment.
S All work must be carried out with great care and with due regard to safety.
S All work on the gear unit must be carried out only when it is not in operation.
The drive unit must be secured against being switched on accidentally (e.g. by locking the key switch
or removing the fuses from the power supply). A notice should be attached to the start switch stating
clearly that work is in progress.
S If any changes are noticed during operation (e.g. overheating or unusual noises), the drive assembly
must be switched off immediately.
S Rotating drive components such as couplings, gearwheels, belt drives etc. must be protected against
accidental contact.
S If the gear unit is intended for installation in plant or machinery, the manufacturer of such plant or
machinery must ensure that the contents of these Instructions are incorporated in his own
instructions.
S Notices attached to the gear unit, e.g. rating plate, direction arrows etc. must always be observed.
They must be kept free from dirt and paint at all times. Missing plates must be replaced.
S Screws which have been damaged during assembly or disassembly work must be replaced with new
ones of the same strength class and type.
S Spare parts should always be obtained from FLENDER (please refer to section 11, ”Spare parts,
customer-service addresses”.
S When changing oil, the used oil must be collected in suitable containers. Any spillage of oil must be
removed immediately.
S Used oil, preservative agent, oil-binding agents and oil-soaked cloths must be disposed of in
accordance with environmental legislation.
BA 5010 EN 06.03
3.4 Special dangers
S Depending on operating conditions, the surface of the gear unit may heat up considerably.
Danger of burns!
S Small foreign matter such as sand, dust, etc. can get into the cover plates of the rotating parts and
be thrown back by these. Eye protection must therefor be worn while the gear unit is operating.
The gear unit is not suitable for operation in locations liable to explosion. When
Caution! operating in locations liable to explosion special additional safety procedures
must be observed.
This symbol indicates safety measures which must be observed to avoid personal
injury.
This symbol indicates safety measures which must be observed to avoid damage to
Caution! the gear unit.
Note: This symbol indicates general operating instructions which are of particular
importance.
The products supplied are listed in the despatch papers. Check immediately on receipt to ensure that
all the products listed have actually been delivered. Parts damaged during transport or missing parts
must be reported in writing immediately to FLENDER AG.
Caution! If damage has occurred, the gear unit must not be put into operation.
4.2 Handling
When handling FLENDER products, use only lifting and handling equipment of
sufficient load-bearing capacity!
Observe the notes regarding load distribution on the packaging.
The gear unit is delivered in the fully assembled condition. Additional items (e.g. oil cooler, pipes and
fittings) can be delivered separately packaged.
Different forms of packaging may be used, depending on the size of the unit and method of transport.
Unless otherwise agreed, the packaging complies with the HPE Packaging Guidelines.
The symbols marked on the packaging must be observed at all times. These have the following
meanings:
bild-transport
BA 5010 EN 06.03
Transport of the gear unit must be carried out so as to avoid personal damage
Caution! and damage to the gear unit.
If, for example, the free shaft ends are knocked, this may damage the gear unit.
Note: The gear units must be transported with suitable equipment only.
During transport the gear unit should be left without oil filling and on the transport
packaging.
Use only the 4 eyes provided to attach lifting equipment to the unit.
Caution! Do not use the front threads at the shaft ends to attach eye bolts for transport.
Slinging equipment must be adequate for the weight of the gear unit.
500004-10-1
H... B...
For drive units where additional components (such as motor, attached coupling etc.) are mounted on
the gear unit an additional attachment point may be required because of the shift in the centre of gravity.
500004-10-2
500004-10-3
BA 5010 EN 06.03
500004-10-4
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
The gear unit must be stored in the position of use in a sheltered place; it must be placed on a
vibration-free, dry wooden base and covered over.
When storing the gear unit and any single components supplied with it, the preservative agent should
be left on them. It must not be damaged, otherwise there is a risk of corrosion.
If the gear unit is being stored out of doors, it must be particularly carefully
Caution! covered, and care taken that neither moisture nor foreign material can collect
on the unit (consult FLENDER).
Note: Unless otherwise agreed by contract, the gear units must not be exposed to harmful
environmental factors such as chemical products, high air pollution, air humidity, and
ambient temperatures outside the range 0 to + 20 °C.
The gear unit is provided with an internal preservative agent; the free shaft ends are painted for
protection.
The properties of the outer paint coat are as follows: Resistant to acids, weak alkalis, solvents,
atmospheric action, temperatures up to 120 °C (temporarily up to 140 °C) and to tropical conditions.
For longer periods of storage (> 6 months) we advise regular checking and, if necessary, renewal of
the internal and external preservation (see section 7, ”Start-up”).
The output shaft must be rotated at least one turn to change the position of the rolling element in the
bearings. The input shaft must not come to a standstill in the same position as before rotation.
This procedure must be repeated and documented every 6 months until start-up.
BA 5010 EN 06.03
5. Technical description
Configuration
Type
A B C D E F G H I
H1SH
H2SH H2HM
H2HH H2DM
H2DH H2KM
H2KH H2FM
H2FH H2PH
H2VH
H3SH H3HM
H3HH H3DM
H3DH H3KM
H3KH H3FM
H3FH H3VH
H4SH H4HM
H4HH H4DM
H4DH H4KM
H4KH H4FM
H4FH H4VH
B2SH B2HM
B2HH B2DM
B2DH B2KM
B2KH B2FM
B2FH B2VH
B3SH B3HM
B3HH B3DM
B3DH B3KM
B3KH B3FM
B3FH B3VH
B4SH B4HM
B4HH B4DM
B4DH B4KM
B4KH B4FM
B4FH B4VH
The gear units are characterised by a low noise level. This is achieved by helical and bevel-helical gears
with a high contact ratio and special sound-damping housings.
The good temperature characteristics of the gear unit are achieved by its high degree of efficiency, large
housing surface and performance-related cooling system.
Note: Unless otherwise agreed by contract, the gear units must not be exposed to harmful
environmental factors such as chemical products, high air pollution, air humidity, and
ambient temperatures outside the range 0 to + 20 °C.
BA 5010 EN 06.03
5.2 Output designs
500005-10-7
5.3 Housing
The housings are of cast iron. If required, they may also be of steel.
Housings up to size 12 are made in one part. The exception are types H1SH and H2PH, which have
a two-part housing similar to those of sizes 13 - 26 of the other types. The housing is rigid in design and
due to its form has excellent noise and temperature characteristics.
The housing is fitted with adequately dimensioned lifting eyes, inspection or assembly covers.
The oil level is checked by oil dipstick or by oil sight glass. An oil filler plug for filling with oil, an oil drain
plug for oil change and an air filter for aerating and ventilating the gear unit are provided.
Colour codes for ventilating, oil inlet, oil level and oil drainage:
Breather: yellow
500005-10-1
2 3 4 1 14 17
6 7 1)
10 5 5
7
9
12
13
18
11 8
H..H 12
BA 5010 EN 06.03
500005-10-2
3 14 3 1 4 15 2
17 7
10 5 5
6
9
13
12
11 16 8
H..H 13
500005-10-3
3 14 3 1 4 15 2
17 7
10 5 5
6
9
13
12
18 8
H..M 13
500005-10-4
2 3 4 1 14 17
6
9
5
5 10
13
12
18 11 8
B..H 12
BA 5010 EN 06.03
500005-10-5
3 14 3 1 4 15 2
17
7
9
5 5
10
13
12
11 16 8
B..H 13
500005-10-6
3 14 3 1 4 15 2
17
7
9
5 5
10
13
12
18 8
B..M 13
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
The toothed components of the gear unit are case-hardened. The helical gear teeth are ground;
depending on their size and transmission ratio, bevel-helical gear teeth are lapped, ground or
HPG-gear-cut. The high quality of the teeth leads to a significant noise reduction and ensures safe and
reliable running.
The gear wheels are joined to the shafts by interference fits and parallel keys. These types of joints
transmit with adequate reliability the torques generated.
5.5 Lubrication
Unless otherwise stated in the order documentation, the teeth and bearings are adequately
splash-lubricated with oil by the gearwheels. This means that the gear units require very little
maintenance.
BA 5010 EN 06.03
5.5.2 Pressure lubrication through add-on oil supply system
In non-horizontal positions, with high bearing speeds or peripheral velocities on the teeth, the splash
lubrication system may be replaced or supported by a pressure lubrication system.
The oil supply system is permanently attached to the gear unit and consists of a flange pump, a coarse
filter, a pressure-monitoring device and pipework. For gear units of sizes 13 to 26, the coarse filter is
replaced by a double change-over filter.
The direction of flow from the flange pumps is independent of the direction of rotation.
500005-10-8
3 2 2
1 1
H... 12 H... 13
500005-10-9
3 2 4 2
1 1
B... 12 B... 13
The operation and maintenance of the pump, pressure monitor, coarse filter or double change-over filter
are described in instructions included in the annex.
For technical data, refer to the order-specific equipment list.
BA 5010 EN 06.03
5.7 Shaft seals
Depending on requirements, radial shaft sealing rings, labyrinth seals or Taconite seals are mounted
at the shaft exits to prevent oil from leaking from the housing and dirt from entering it.
Radial shaft sealing rings are the standard type of seal. They are fitted preferably with an additional dust
lip to protect the actual sealing lip from external contamination.
500005-10-10
Labyrinth seals are non-contacting and avoid wear to the shaft. They therefore require no maintenance
and ensure favourable temperature characteristics. They can be used only with certain transmission
ratios and minimum speeds.
Check in the spare parts drawing and the spare parts list whether the gear unit is provided with labyrinth
seals.
500005-10-11
Taconite seals were specially developed for use in a dusty environment. The penetration of dust is
prevented by a combination of seal elements (radial shaft sealing ring, lamellar seal and
grease-charged labyrinth seal).
500005-10-12
4
BA 5010 EN 06.03
Taconite seals are divided into the following types:
500005-10-13
500005-10-14
2 4
1 1
3 2
Taconite
Application Remarks
type variant
All input shafts
“E” with or without fan
Output shaft Re-chargeable labyrinth
Type S (solid shaft)
“F” Type V (solid shaft, reinforced)
Type F (flanged shaft)
Output shaft
Type H (hollow shaft with parallel keyway) Labyrinth re-chargeable on both sides,
“F-F” Type K (hollow shaft with internal spline incl. cowl to prevent contact on gear
to DIN 5480) side facing away from output
Type D (hollow shaft for shrink disk)
Output shaft
Type H (hollow shaft with parallel keyway)
”F-H” Type K (hollow shaft with internal-spline
Re-chargeable labyrinth on output side;
to DIN 5480)
dustproof cowl on opposite side
Output shaft
“F-K” Type D (hollow shaft for shrink disk)
For re-charging the labyrinth seals with grease, the specified frequencies must be observed (see
section 10, ”Maintenance and repair”).
BA 5010 EN 06.03
5.8 Backstop
For certain requirements, the gear unit can be fitted with a mechanical backstop. This permits only the
specified direction of rotation during the operation of the unit. The direction of rotation is marked by a
corresponding arrow on the input and output side of the gear unit.
The backstop is mounted oiltight on an adapter flange on the gear unit and integrated in its oil-circulation
system.
The backstop is fitted with centrifugally operated sprags. When the gear unit is running in the specified
direction, the inner ring and the cage with the sprags also rotates while the outer ring remains stationary.
At a certain rotation speed, the sprags lift off and the backstop then operates without any wear.
500005-10-21
1
5
6
Note: The stop direction can be changed by turning the cage around. If a change in stop
direction is required, FLENDER should be consulted beforehand.
To avoid damaging the backstop or the gear unit, the motor must not be run in
Caution! the stop direction of the gear unit.
Observe the notice fixed to the gear unit.
The minimum lifting speeds must not be exceeded during operation.
Before connecting the motor, determine the direction of rotation of the three-phase current supply using
a phase-sequence indicator, and connect the motor in accordance with the pre-determined direction
of rotation.
BA 5010 EN 06.03
5.9 Cooling
Depending on requirement, the gear unit is fitted with a fan, a cooling coil, a water or air oil-cooling
system or a separate oil supply system. In the case of a separate oil supply system, the specific
instructions for this oil supply system must be observed.
5.9.1 Fan
The fan is mounted on a high-speed shaft of the gear unit and is protected from accidental contact by
a cowl. The fan sucks air through the grid on the cover and blows it along the air ducts on the side of
the gear housing. It thereby dissipates a certain amount of heat from the housing.
500005-10-15
1 1
2 2
H... B...
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
For gear units fitted with a fan, sufficient space must be allowed for air intake
Caution! when mounting the safety guards for the coupling or other components.
The correct distance is given in the dimensioned drawing in the gear-unit
documentation.
It must be ensured that the fan cover is correctly fastened. The fan cover must
be protected against damage from outside. The fan must not come into contact
with the fan cover.
The cooling effect is considerably reduced if the fan or the gear housing are dirty (see section 10,
”Maintenance and repair”).
BA 5010 EN 06.03
5.9.2 Cooling coil
The cooling coil is located in the oil sump of the gear unit and is supplied with cooling water via a
connection to be provided by the user. Either fresh water, sea water or brackish water can be used for
cooling purposes. When water is flowing through the coil, a certain amount of heat is transferred from
the oil to the water and thereby removed from the system.
500005-10-16
X X
1, 2 3 3 1 2
H... B...
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
The water can flow through the gear unit in either direction. The pressure of the
Caution! cooling water must not exceed 8 bars.
If the gear unit is being withdrawn from service for a longer period or if there
is a danger of freezing, the cooling water must be drained off. Remove any
remaining water with compressed air.
The ends of the cooling coil must never be twisted because this could destroy
the cooling coil.
The reducing bolt must not be tightened or demounted because this may result
in damage to the cooling coil.
To avoid excess pressure, the cooling-water inlet must be fitted with a flow-control device, e.g. a
pressure reducer or suitable stop valve.
H2.M – – – – – – – – – – 8 8 8 8 8 8 1) 1)
H3.H – – 4 4 4 4 4 4 8 8 8 8 8 8 8 8 1) 1)
H3.M – – – – – – – – – – 8 8 8 8 8 8 1) 1)
B2.H – 4 8 4 8 4 8 8 8 8 8 8 8 8 8 8 – –
B3.H – 4 4 4 4 4 8 8 8 8 8 8 8 8 8 8 1) 1)
B2.M – – – – – – – – – – 8 8 8 8 8 8 – –
B3.M – – – – – – – – – – 8 8 8 8 8 8 1) 1)
1) on request
BA 5010 EN 06.03
5.9.3 Add-on air oil-cooling units
For types H1.., H2.. and B2.., a cooling unit with air oil-cooler may be applied if required in the order.
This unit is permanently mounted on the gear unit and consists of a flange pump, a coarse filter, a
pressure monitor, a temperature-control valve, the actual air oil-cooler and the necessary pipework. For
gear units of sizes 13 to 26, the coarse filter is replaced by a double change-over filter.
The air oil-cooler is designed to cool the gear oil by means of air from the surrounding atmosphere.
Depending on the volume flow, the oil passes through the cooler in one or more streams and through
the current of air blown in by the fan. For cold starts, a bypass pipe with a temperature-control valve
is provided for.
The flow direction of the flange pump used is independent of the direction of rotation, if nothing is
specified in the documentation to the contrary.
500005-10-17
3 2 2 4
6
6
5
5
1 1
500005-10-18
3 2 2 4
6
6
5
5
1 1
B2.. 12 B2.. 13
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
When installing gear units with add-on air oil-cooling units, it must be ensured
Caution! that the air circulation is not obstructed.
The required minimum distance from adjacent components, walls, etc. is
indicated in the drawings in the unit documentation.
Add-on pressure monitors must be connected as shown in item 5.5.2.
Depending on the order specification and application, the flange pump may have been replaced by a
motor pump.
For operation and maintenance, always observe the operating instructions indicated in the
order-specific appendix.
For technical data, refer to the order-specific equipment list.
The cooling effect is considerably reduced if the cooler or the gear housing are dirty (see section 10,
”Maintenance and repair”).
BA 5010 EN 06.03
5.9.4 Add-on water oil-cooling units
For types H1.., H2.. and B2.., a cooling unit with water oil-cooler may be applied if required in the order.
This oil-cooling unit is permanently mounted on the gear unit and consists of a flange pump, a coarse
filter, a pressure monitor, the actual water oil-cooler and the necessary pipework. For gear units of sizes
13 to 26, the coarse filter is replaced by a double change-over filter.
The flow direction of the flange pump used is independent of the direction of rotation, if nothing is
specified in the documentation to the contrary.
5 4
3 5
6 6
1 1
500005-10-20
2 2
5 4
3 5
6 6
1 1
B2.. 12 B2.. 13
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
Depending on the order specification and application, the flange pump may have been replaced by a
motor pump.
For operation and maintenance, always observe the operating instructions indicated in the
order-specific appendix.
For technical data, refer to the order-specific equipment list.
BA 5010 EN 06.03
5.10 Heating element
At low temperatures it may be necessary to heat the gear oil before switching on the drive unit or even
during operation. In such cases one or two such heating element may be provided if required. These
convert the electrical energy into heat which is conducted to the surrounding oil. The heating elements
are located in protective tubes inside the housing, thus making it possible to replace them without
draining off the oil.
Complete immersion of the heating elements in the oil bath must be guaranteed.
The heating elements are controlled by a temperature monitor which emits a signal when maximum and
minimum temperatures are reached; the signal requires amplification.
500005-10-22
1 2 1 2 1 2 1 2
For a detailed illustration of the gear unit and the position of the add-on parts, please refer to the
drawings of the gear-unit documentation.
Never switch the heating element on unless complete immersion of the heating
Caution! elements in the oil bath is ensured. Fire hazard!
If heating elements are installed afterwards the max. heating capacity
of 0.8 W/cm2 on the outer surface of the heating elements must not be
exceeded.
For operation and maintenance, always observe the operating instructions indicated in the
order-specific appendix.
For technical data, refer to the order-specific equipment list.
BA 5010 EN 06.03
5.11 Oil-temperature measurement
Depending on the order specification, the gear unit may be fitted with a PT100 resistance thermometer
for monitoring the oil temperature in the sump. In order to measure the temperatures or temperature
differences, the PT100 resistance thermometer should be connected to a suitable instrument provided
by the customer. The thermometer has a connection head (protection type IP54) for the wiring. A
two-conductor circuit is fitted by the manufacturer. However, the customer may fit his own three- or
four-conductor circuit if required.
Note: A certain level of oil is necessary for reliable temperature measurement. For this
reason, the resistance thermometer is not suitable for use with labyrinth seals.
500005-10-23
1 1 1 1
For a detailed illustration of the gear unit and the position of the add-on parts, please refer to the
drawings of the gear-unit documentation.
For operation and maintenance, always observe the operating instructions indicated in the
order-specific appendix.
For technical data, refer to the order-specific equipment list.
Depending on the order specification, the gear unit may be fitted with an oil-level monitor in the form
of a level limit switch. This monitoring is designed as a standstill monitoring (gear unit stop) and checks
the level of the oil before the unit is started up. When the signal ”oil level too low” is given, it should be
wired in such a way that the drive motor cannot start and an alarm is given. During operation, any signal
should be bridged.
500005-10-25
For a detailed illustration of the gear unit and the position of the add-on parts, please refer to the
drawings of the gear-unit documentation.
For operation and maintenance, always observe the operating instructions indicated in the
order-specific appendix.
For technical data, refer to the order-specific equipment list.
If an oil-level monitoring device is in use, it is very important that the gear unit is in a horizontal position.
BA 5010 EN 06.03
5.13 Bearing monitoring system
Depending on the order, the gear unit may be prepared for bearing monitoring by fitting measuring
nipples. These nipples are intended for attachment of the shock-pulse sensors with rapid-action
coupling and are located in the vicinity of the bearings to be monitored.
500005-10-26
X X ”X”
SW17
X 500005-10-27
X X ”X”
SW17
For a detailed illustration of the gear unit and the position of the add-on parts, please refer to the
drawings of the gear-unit documentation.
Depending on order specification, an incremental speed transmitter may be mounted on the second
last shaft. Wiring and evaluation instrument should be provided by the customer.
500005-10-28
A 3
”A”
2 1 3
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
For operation and maintenance, always observe the operating instructions indicated in the
order-specific appendix.
For technical data, refer to the order-specific equipment list.
BA 5010 EN 06.03
6. Assembly
Assembly and installation work must be done with great care by trained and qualified personnel. The
manufacturer cannot be held liable for damage caused by incorrect assembly and installation.
During the planning phase sufficient space must be allowed around the gear unit for later care and
maintenance work.
Adequate lifting equipment must be available before beginning the installation and assembly work.
If the gear unit is fitted with a fan, there should be sufficient space for air intake.
All the fastening points provided by the design of the unit must be used.
Caution! Screws which have been damaged during assembly or disassembly work must
be replaced with new ones of the same strength class and type.
To ensure proper lubrication, the installation position specified in the order must always be observed.
6.2.1 Foundation
The foundation must be horizontal and level; the gear unit must not be excessively stressed when
tightening the fastening screws.
It must be designed in such a way that no resonance vibrations are set up and that no vibrations are
transmitted from adjacent foundations. Steel structures on which the unit is to be mounted must be rigid.
It must be designed according to the mass and torque, taking into account the forces acting on the gear
unit.
When fastening the gear unit to concrete foundations by means of stone bolts and/or foundation blocks,
suitable recesses should be made in the foundation.
Fastening bolts or nuts must be tightened to the prescribed torque. For the correct torque, refer to item
10.2.10. Bolts of the minimum strength class 8.8 must be used.
Slide rails should be correctly aligned and embedded in the concrete foundation.
Note: For dimensions, space requirement, arrangement of supply connections (e.g. with
separate oil-cooling units), refer to the drawings in the gear-unit documentation.
BA 5010 EN 06.03
6.2.2 Description of installation work
S Remove the anti-corrosion paint on the shafts with suitable cleaning agent such as benzine.
Caution! Do not allow the cleaning agent (e.g. benzine) to contact the shaft sealing rings.
S Mount and secure input and output drive elements (e.g. coupling components) on shafts.
If these are to be heated before mounting, refer to the dimensioned drawings in the coupling
documentation for the correct joining temperatures.
Unless otherwise specified, the components may be heated inductively, with a burner or in a furnace.
Protect shaft sealing rings from damage and heating to over + 100 _C (use
Caution! heat-protective screens to protect against radiant heat.)
The components must be pushed smartly onto the shaft up to the position specified in the order-specific
dimensioned drawing.
Fit the coupling with the aid of suitable fitting equipment. Never use force or
Caution! knock the couplings into position, as this may damage the gearwheels, rolling
bearings, locking rings, etc.
When fitting the components, care must be taken that the shaft sealing rings
and shaft running surface are not damaged.
When installing the drives, make absolutely certain that the individual
components are accurately aligned in relation to each other. Inadmissibly large
errors in the alignment of the shaft ends to be connected due to angular and
axial misalignments result in premature wear and material damage.
Insufficiently rigid base frames or sub-structures can also during operation
cause a radial or axial misalignment, which cannnot be measured when the unit
is at a standstill.
Note: Gear units whose weight requires the use of lifting gear must be attached as shown
in section 4, ”Transport, handling and storage”. When add-on parts are mounted on
the gear unit, appropriate additional attachment points must be provided in
accordance with the order-specific dimensioned drawing.
BA 5010 EN 06.03
6.2.2.1 Aligning surfaces, aligning thread
Initial alignment of the gear units (sizes 3 to 12) in a horizontal direction is done by the surfaces of the
inspection or assembly cover.
500006-10-1
1 1
Gear units of sizes 13 to 26 have special alignment surfaces on the top of the housing. To facilitate
alignment of gear units of these sizes, alignment threads are provided on the housing base.
500006-10-2
1 1
1
2 2
S Using suitable lifting gear, place the gear unit on the foundation frame.
S Tighten the foundation bolts to the specified torque (see item 10.2.10). If necessary, use stops to
prevent displacement.
The gear unit must not be excessively stressed when tensioning the fastening
Caution! bolts.
The final fine alignment with the assemblies on the in- and output side must be carried out accurately
by the shaft axes, using:
S rulers
S spirit level
S dial gauge
Only then should the gear unit be fastened and the alignment checked once again.
Note: The accuracy of shaft axis alignment is an important factor in determining the life span
of shafts, bearings and couplings. If possible, the deviation should be zero. For
amongst others the special requirements for the couplings, refer to the specific
operating instructions.
BA 5010 EN 06.03
6.2.2.3 Mounting on a concrete foundation by means of stone bolts or foundation blocks
S Hook the stone bolts with washers and hexagon nuts and/or foundation blocks with washers and
fastening bolts into the foundation fastening points on the housing and tighten the hexagon nuts
and/or fastening bolts to the specified torque (see item 10.2.10) (see figure below).
bild-stein
1
2
3
4
S If applying considerable force, use stops to prevent the unit from displacement.
S Pour concrete into the recesses of the stone bolts or foundation blocks.
Note: Before pouring the concrete foundation, fill up the openings in the foundation blocks
with polystyrene.
When the concrete has set, tighten the hexagon nuts of the stone bolts or fastening
bolts to the specified torque (see Item 10.2.10).
With types H1 and H2, remove the air-conducting cowls before tightening the
foundation bolts and then bolt them back into position.
The gear unit must not be excessively stressed when tensioning the hexagon
Caution! nuts or fastening bolts.
BA 5010 EN 06.03
The final fine alignment with the assemblies on the in- and output side must be carried out accurately
by the shaft axes, using:
S rulers
S spirit level
S dial gauge
Only then should the gear unit be fastened and the alignment checked once again.
Note: The accuracy of shaft axis alignment is an important factor in determining the life span
of shafts, bearings and couplings. If possible, the deviation should be zero. For
amongst others the special requirements for the couplings, refer to the specific
operating instructions.
S Place wood under anchor bolts in such a way that the top edge is set back about 10 mm.
bild-anker-1
2
7
3
8
1
4
5
6
The carrying ropes must be attached only by the specified lifting eyes (see
Caution! Section 4, ”Handling and Storage”).
BA 5010 EN 06.03
S Pull anchor bolts up, fit washer and hexagon nut in place by giving it a few turns
The values punched into the screeds must always be observed. Alignment tolerances in relation to the
units on the input and output sides are to be in accordance with the permissible angular and longitudinal
displacements of the couplings (see Coupling Drawings).
Record alignment dimensions.
Prior to tensioning the anchor bolts, the fine-grained concrete filling must have set for at least 28 days.
S Put anchor bolts under tension by tightening the hexagon nut with your fingers. Place hydraulic
tensioning device in position.
Tension bolts alternately to a tensioning force in accordance with Table 10.2.
The tensioning pressures and the initial tensioning forces should be recorded (see also item 7.2.4).
bild-anker-2
5
4 6
2
7
3
8
1
BA 5010 EN 06.03
6.3 Couplings
Generally speaking, flexible couplings or hydraulic couplings combined with flexible couplings should
be provided for the input drive.
Note: In the case of gear units with fan, the hydraulic unit of the hydraulic coupling should
be located on the motor shaft to ensure that sufficient space is available for intake of
cooling air (see item 5.9.1).
In the case of gear unit types with solid output shaft, flexible couplings are, likewise, ordinarily used for
the output shaft.
If rigid couplings or other input or output elements which generate additional radial and/or axial forces
(e.g. gear wheels, belt pulleys, disk flywheels, hydraulic couplings) are to be used, these must be
agreed by contract.
For maintenance and operation of the couplings, refer to the specific operating instructions for the
coupling.
When installing the drives, make absolutely certain that the individual
components are accurately aligned in relation to each other. Inadmissibly large
errors in the alignment of the shaft ends to be connected due to angular and
axial misalignments result in premature wear and material damage.
Insufficiently rigid base frames or sub-structures can also during operation
cause a radial or axial misalignment, which cannnot be measured when the unit
is at a standstill.
Note: For permissible alignment errors in the case of couplings supplied by FLENDER,
please refer to the operating manuals for the couplings.
If you use couplings by other manufacturers, ask which alignment errors are
permissible, stating the radial loads occurring.
Note: The smaller the radial and angular misalignment between coupling parts on the shaft
ends to be connected, the longer the service life and the higher the reliability of the
equipment and the quieter the operation.
Misalignments of the coupling parts in relation to each other can be caused by inaccurate alignment
during assembly, but also by actual operation of the equipment (expansion due to heat, shaft deflection,
insufficiently rigid machine frames, etc.).
Possible misalignments
500005-10-29
D Ka
D Kw
D Kr
BA 5010 EN 06.03
Alignment has to be done in two axial planes arranged perpendicular to each other. This can be done
by means of a ruler (radial misalignment) and feeler gauge (angular misalignment), as shown in the
illustration. The aligning accuracy can be increased by using a dial gauge or a laser alignment system.
500005-10-30
1 3
2 3
Note: For alignment of the drive components (vertical direction), it is recommended to use
packing or foil plates underneath the mounting feet. The use of claws with set screws
on the foundation for lateral adjustment of the drive components is also
advantageous.
In the case of gear units with hollow output shafts or flange output shafts, the coupling on the output
side is not required. Gear units with hollow output shafts must be mounted on the shafts of the
customer’s machinery. Gear units with flanged output shafts must be mounted on the customer’s shaft
via a counterflange.
BA 5010 EN 06.03
6.4 Assembly of a shaft-mounting gear unit with hollow shaft and parallel keyway
The shaft end of the driven machine must be provided with a parallel key to DIN 6885 Part 1 Form A
(material C60+N or higher strength) and should have a centring means to DIN 332 Form DS (with
thread) in its end face (for connecting dimensions of the driven machine shaft, see dimensioned drawing
in the gear unit documentation).
To assist demounting (see also item 6.4.3), we recommend providing a connection for pressure oil on
the end of the driven machine shaft. For this a hole must be drilled through to the hollow shaft bore (refer
to fig. 1).
500006-10-14
3
4
1
5
2
Fig. 1
6.4.2 Assembly
S Remove the preservative agent from the hollow shaft and the machine shaft with a suitable cleaning
agent (such as benzine).
Caution! Do not allow the cleaning agent (e.g. benzine) to contact the shaft sealing rings.
S Check the hollow and machine shafts to ensure that seats and edges are not damaged. If necessary,
rework the parts with a suitable tool and clean them again.
Note: Coat with a suitable lubricant (e.g. Calypsol grease type H 443 HD88) to prevent
frictional corrosion of the contact surfaces.
BA 5010 EN 06.03
6.4.2.1 Fitting
S Fit the gear unit by means of nut and threaded spindle. The counterforce is provided by the hollow
shaft.
The hollow shaft must be exactly aligned with the machine shaft to avoid
Caution! canting.
500006-10-3
3
7
Fig. 2
Instead of the nut and threaded spindle shown in the diagram, other types of equipment such as a
hydraulic lifting equipment (type Lucas) may be used.
The hollow shaft may be pulled against a machine shaft collar only on gear
Caution! arrangements with a torque arm or if supported with gear unit swing bases,
because with a different arrangement the bearings would be excessively
stressed.
Depending on type, secure the hollow shaft axially on the machine shaft (e.g. with locking ring, end
plate, set screw etc.).
BA 5010 EN 06.03
6.4.3 Dismantling
S Remove the axial securing device from the hollow shaft.
S If frictional corrosion has occurred on the seating surfaces, inject rust-releasing or other agent (e.g.
with a pump) into the bore cavity to reach the seats in order to facilitate forcing off. The rust releaser
can be injected through a bore in the machine shaft (see fig. 1).
S Depending on the facilities available on site, the gear unit can be forced off the machine shaft using
forcing screws in an end plate (see fig. 4), a central threaded spindle or preferably a Lucas hydraulic
lifting unit.
S When the rust-releasing agent has taken effect, pull the gear unit off with the device as shown in
figs. 3 or 4.
Note: The end plate and the auxiliary plate for forcing off the gear unit are not included in
our delivery.
Each of the two end faces of the hollow shaft is provided with 2 tapped holes (for
dimensions, see fig. 5) to receive bolts for fastening the end plate to the hollow shaft.
500006-10-4
6
3
5 1
4
2
7
Fig. 3
5 1
4 2
Fig. 4
Note: The plate for forcing out is not included in our delivery.
BA 5010 EN 06.03
500006-10-15
*) *)
m
s
s
t t
Fig. 5 *) 2 threads offset 180_
Gear-unit m s t Gear-unit m s t
size mm mm size mm mm
4 95 M8 14.5 12 215 M 12 19.5
5 115 M8 14.5 13 230 M 12 19.5
6 125 M8 14.5 14 250 M 12 19.5
7 140 M 10 17 15 270 M 16 24
8 150 M 10 17 16 280 M 16 24
9 160 M 10 17 17 300 M 16 24
10 180 M 12 19.5 18 320 M 16 24
11 195 M 12 19.5 19 ... 26 on request
Table 6.1: Threaded holes on the end faces of the gear unit hollow shafts
If the counterforce is provided not only by the hollow shaft, but also by the
Caution! housing, as shown in fig. 3, the forces used must not exceed the values given
in the following table.
If the above values are exceeded, the housing, the hollow-shaft bearings or
Caution! other gear components may be irreparably damaged. Before replacing the gear
unit on the machine shaft, always check the bearings for any signs of damage.
Note: When using forcing screws or threaded spindles, the head of the thread pressing
against the driven machine should be rounded and well greased to reduce the risk of
seizing at this point.
BA 5010 EN 06.03
6.5 Shaft-mounting gear unit with hollow shaft and internal spline to DIN 5480
The shaft end of the driven machine must be designed with involute splines to DIN 5480 and should
have a centring means to DIN 332 Form DS (with thread) in its end face (for connecting dimensions of
the driven machine shaft, see dimensioned drawing in the gear unit documentation).
To facilitate demounting (see also item 6.4.3.), we recommend providing a connection for pressure oil
on the end of the driven machine shaft. Doing this a hole must be drilled through to the hollow shaft bore
(refer to fig. 6).
500006-10-16
3
4
1
5
2
Fig. 6
6.5.2 Assembly
S Remove the preservative agent from the hollow shaft and the machine shaft with a suitable cleaning
agent (such as benzine).
Caution! Do not allow the cleaning agent (e.g. benzine) to contact the shaft sealing rings.
S Check the hollow and machine shafts to ensure that seats, teeth or edges are not damaged. If
necessary, rework the parts with a suitable tool and clean them again.
Note: Coat with a suitable lubricant (e.g. Calypsol grease type H 443 HD88) to prevent
frictional corrosion of the contact surfaces.
BA 5010 EN 06.03
6.5.2.1 Fitting
S Fit the gear unit by means of nut and threaded spindle. The counterforce is provided by the hollow
shaft.
The hollow shaft must be exactly aligned with the machine shaft to avoid
Caution! canting. When fitting, ensure that the position of the teeth between the machine
shaft and hollow shaft is correct. The correct position can be determined by
turning the input shaft or by swivelling the gear unit lightly around the hollow
shaft.
500006-10-6
3
7
1
Fig. 7
The loose DU bush is pushed onto the machine shaft, fixed rigidly in position with a locating tie and then
pulled into the hollow shaft along with the machine shaft (see fig. 7).
The hollow shaft must be exactly aligned with the machine shaft to avoid
Caution! canting. When fitting, ensure that the position of the teeth between the machine
shaft and hollow shaft is correct. The correct position can be determined by
turning the input shaft or by swivelling the gear unit lightly around the hollow
shaft.
Instead of the nut and threaded spindle shown in the diagram, other types of equipment such as a
hydraulic lifting equipment (type Lucas) may be used.
The hollow shaft may be pulled against a machine shaft collar only on gear
Caution! arrangements with a torque arm or if supported with gear unit swing bases,
because with a different arrangement the bearings may be excessively
stressed.
Depending on type, secure the hollow shaft axially on the machine shaft (e.g. with locking ring, end
plate, set screw etc.).
BA 5010 EN 06.03
6.5.3 Dismantling
S If frictional corrosion has occurred on the seating surfaces, inject rust-releasing or other agent (e.g.
with a pump) into the bore cavity to reach the seats in order to facilitate forcing off. The rust releaser
can be injected through a bore in the machine shaft (see fig. 6).
S The end plate and the locking ring must first be removed.
S Depending on the facilities available on site, the gear unit can be forced off the machine shaft using
forcing screws in an end plate (see fig. 9), a central threaded spindle or preferably a Lucas hydraulic
lifting unit.
S When the rust-releasing agent has taken effect, pull the gear unit off with the device as shown in
figs. 8 or 9.
500006-10-7
6 3
1
5
4
2
7
Fig. 8
500006-10-8
5 1
4
2
Fig. 9
Note: The plate for forcing out is not included in our delivery.
BA 5010 EN 06.03
If the counterforce is provided not only by the hollow shaft, but also by the
Caution! housing, as shown in fig. 8, the forces used must not exceed the values given
in the following table.
If the above values are exceeded, the housing, the hollow-shaft bearings or
Caution! other gear components may be irreparably damaged. Before replacing the gear
unit on the machine shaft, always check the bearings for any signs of damage.
Note: When using forcing screws or threaded spindles, the head of the thread pressing
against the driven machine should be rounded and well greased to reduce the risk of
seizing at this point.
BA 5010 EN 06.03
6.6 Shaft-mounting gear unit with hollow shaft and shrink disk
The end of the driven machine shaft (material C60+N or higher strength) should have a centring means
to DIN 332 Form DS (with thread) in its end face (for connecting dimensions of the driven machine shaft,
see dimensioned drawing in the gear unit documentation).
6.6.1 Assembly
S Remove the preservative agent from the hollow shaft and the machine shaft with a suitable cleaning
agent (such as benzine).
Caution! Do not allow the cleaning agent (e.g. benzine) to contact the shaft sealing rings.
3
7
1
Fig. 10
BA 5010 EN 06.03
6.6.1.2 Axial fastening
If the shrink disk is fitted according to instructions (see item 6.6.2.1), the gear unit is fixed securely in
the axial direction. Additional fastening is not required.
Caution! It must not be dismantled before tensioning for the first time.
The bore of the hollow shaft and the machine shaft must be absolutely free of
Caution! grease in the area of the shrink disk seat.
This is essential for safe and reliable torque transmission.
Do not use contaminated solvents or dirty cloths for removing grease.
bild-schrumpf-1
W
1 B
2
3
5
4
For the exact installation height (W) of the shrink disk, refer to the dimensioned drawing (see section 1,
”Technical data”)
Note: The outer surface of the hollow shaft may be greased in the area of the shrink disk
seat.
Caution! Do not tighten the tensioning bolts until the machine shaft is installed.
The tensioning bolts must be tightened one after the other, in rotation and in several passes to the
tightening torque shown on the shrink disk.
Tighten all the tensioning bolts until the lateral surfaces of the inner and outer rings are aligned.
Note: This allows the tension condition to be checked visually. For safety the tensioning
bolts must then be tightened in 2 further passes.
BA 5010 EN 06.03
To avoid overloading the individual bolts, the maximum tensioning torque (see
Caution! table 6.4) must never be exceeded. The alignment of the front surfaces has
priority. If alignment cannot be achieved by tightening, consult FLENDER.
For safety reasons, a protective cover should be mounted above the shrink
disk.
To enable the stored energy of the outer ring during disassembly to be lowered slowly via the bolts to
be loosened, the bolts must be loosened evenly and in sequence. Initially only by a quarter turn.
Caution! Under no circumstances must the bolts be unscrewed one after the other.
If after loosening all the bolts approx. one turn the outer ring does not come free of the inner ring of its
own accord, the outer ring can be detensioned with the forcing threads by screwing some of the adjacent
fastening bolts into the them. The now loosening outer ring is braced against the remaining bolts. This
operation must be carried out until the outer ring releases of its own accord.
Remove shaft or slip hub off the shaft. Rust deposits which may have formed on the shaft must be
removed from the hub before performing this operation.
BA 5010 EN 06.03
6.6.2.3 Cleaning and greasing the shrink disk
Dismantled shrink disks do not have to be dismantled and re-greased before being re-installed.
Following cleaning, only the inner sliding surfaces of the shrink disk should be
Caution! re-greased.
Use a solid lubricant with a high MoS2-based molybdenum disulphide content and with a coefficient of
friction of m = 0.04 according to the following table.
6.6.3 Dismantling
S If frictional corrosion has occurred on the seating surfaces, inject rust-releasing or other agent (e.g.
with a pump) into the bore cavity to reach the seats. The rust releaser can be injected through a bore
in the machine shaft (see fig. 11).
S Depending on the facilities availableon site, the gear unit can be forced off the machine shaft using
forcing screws in an end plate (see fig. 12), a central threaded spindle or preferably a Lucas hydraulic
lifting unit.
S When the rust-releasing agent has taken effect, pull the gear unit off with the device as shown in
figs. 11 or 12.
500006-10-10
6
3
1
5
4
2
7
Fig. 11
BA 5010 EN 06.03
500006-10-11
5 1
4
2
Fig. 12
If the counterforce is provided not only by the hollow shaft, but also by the
Caution! housing, as shown in fig. 11, the forces used must not exceed the values given
in the following table.
If the above values are exceeded, the housing, the hollow-shaft bearings or
Caution! other gear components may be irreparably damaged. Before replacing the gear
unit on the machine shaft, always check the bearings for any signs of damage.
Note: When using forcing screws or threaded spindles, the head of the thread pressing
against the driven machine should be rounded and well greased to reduce the risk of
seizing at this point.
BA 5010 EN 06.03
6.7 Shaft-mounting gear unit with flanged shaft
The front area of the flanged shaft must be absolutely free of grease.
Caution! This is essential for safe and reliable torque transmission. Do not use
contaminated solvents or dirty cloths for removing grease.
Before tightening the tensioning bolts it must be ensured that the flange
Caution! centring means are inserted one inside the other.
Then tighten diametrically opposed tensioning bolts to full torque.
Strength class
Gear-unit size Tightening
Bolt Nut torque
DIN 931 DIN 934
BA 5010 EN 06.03
6.8 Shaft mounting gear unit with block flange
The front area of the block flange must be absolutely free of grease.
Caution! This is essential for safe and reliable torque transmission. Do not use
contaminated solvents or dirty cloths for removing grease.
500006-11-11
ØK1
Configuration 1)
Type
B C
H2..
H3..
H4..
B2..
B3..
B4..
BA 5010 EN 06.03
6.9 Mounting the torque arm for gear housing
Caution! The torque arm must be mounted stress-free on the machine side
On helical gear units with a motor bell housing the torque arm is located opposite the motor bell housing.
500006-10-12
1
S Foundation type for fastening torque arm, see item 6.2.1 ”Foundation”.
S If the customer fits a torque arm, connection to the foundation must be by means of a flexible element.
BA 5010 EN 06.03
6.10 Mounting supports for gear-unit swing bases
Caution! The support for the swing base must be mounted free of stress.
500006-10-13
2 1 2 1
4 3 5 3
S Foundation type for fastening torque arm, see item 6.2.1 ”Foundation”.
S If the customer fits a torque arm, connection to the foundation must be by means of a flexible element.
BA 5010 EN 06.03
6.11 Gear unit with cooling coil
S Before connecting the cooling coil remove the plugs from the connection bush of the cooling coil and
flush the coil well to remove any dirt.
S Install the cooling-water in- and outflow pipes (for exact position of connections, see dimensionedl
drawing).
S For the technical data to the add-on components, as stated in item 6.13 to 6.18, refer to the
order-specific equipment list.
S The electrical equipment for regulation and control must be wired in accordance with the equipment
suppliers’ instructions.
S For operation and maintenance the operating instructions provided specifically for the order and the
specifications in item 5.9.2 to 5.14 must be observed.
S Connect the indicator for double change-over filter (for gear sizes 13 only) and pressure monitor
electrically
S Before connecting the water oil-cooler remove the plugs from the water connection and flush the
water oil-cooler well to remove any dirt.
S Install the cooling-water in- and outflow pipes. For the flow direction of the cooling water and the
location of the connections please refer to the dimensioned drawing.
S Connect resistance thermometer with evaluating instrument (to be provided by customer) electrically
S After installation of the gear unit check all screw connections for tight fit.
S In addition, after tightening the fixings a check must be made to see that the alignment has not
changed.
S Check by means of the order specific equipment list as well as the associated drawings whether all
units which may have been removed for transport have been refitted.
S Rotating parts must be checked for correct seating. Contact with rotating parts is not permitted.
BA 5010 EN 06.03
7. Start-up
S Unscrew the oil drain plug or open the draining valve, allow the preservative agent or run-in oil to drain
into a suitable container and dispose of it in accordance with regulations. Any residual-oil drain plugs
should also be opened (e.g. in the case of gear units with add-on backstop). The location of the oil
draining point is marked by an appropriate symbol in the dimensioned drawing in the unit
documentation.
2
8
7
5
9
6
4
B... 12
500007-10-2
1
3
5
8
7
2
9
6
B... 13
For a detailed view of the gear unit, refer to the drawings in the gear-unit documentation.
Before start-up, replace the yellow plastic plug with a breather screw with cap
Caution! (see also notice on gear unit).
BA 5010 EN 06.03
7.1.2 Charging with lubricant
S Release the fastening bolts on the inspection or assembly cover and remove the cover (including
seal) from the housing or use the marked oil filler plug. Do not discard the seal.
S In the case of gear units with add-on backstop, release the screw plug on the backstop cover and pour
in approx. 0.5 l fresh oil of the total oil quantity via a filter (max. filter mesh 25 mm)
Using a filter (max. mesh 25 mm), fill the gear unit with fresh oil up to the MAX
Caution! mark on the oil dipstick or oil sight glass.
Remember to fill the oil pockets above the bearings and (with bevel-gear units)
at the input shaft on the inside.
Note: For the correct type of oil (of various brands) to be used, refer to the BA 7300 EN
operating instructions supplied separately.
Information on the type, quantity and viscosity of the oil is given on the rating plate on
the gear unit.
The quantity of oil indicated on the rating plate is an approximation only. The marks
on the dipstick or oil sight glass are decisive for the amount of oil to be filled in.
Note: In the case of gear units fitted with forced lubrication or an oil-cooling system, the oil
circuit must also be charged with oil. To do this, briefly start up the gear unit with
add-on pump as described in section 8.
S Check the oil level in the gear unit housing with the oil dipstick or by means of the oil sight glass.
Note: The oil level must be at the upper mark on the oil dipstick or oil sight glass.
S Place the inspection or assembly cover (including seal) on the housing and replace and tighten the
fastening bolts (see item 10.2.10).
BA 5010 EN 06.03
7.1.2.1 Oil quantities
BA 5010 EN 06.03
7.2 Start-up
7.2.1 Oil level
The oil level must be monitored by means of the oil level monitoring equipment provided. The gear unit
must be shut down or FLENDER consulted.
When the oil is cool, the level should be at the upper mark on the oil dipstick or oil sight glass. When
the oil is warm it may slightly exceed this mark. It must in no case be allowed to fall below the mark. If
necessary, top up to the correct level.
7.2.2 Gear unit with cooling coil or external oil cooling or oil supply system
For technical data, refer to the order-specific equipment list.
After starting up the external oil cooling or oil supply system for the first time the oil level must be once
more checked in accordance with item 7.2.1.
Fully open the stop valves in the coolant in- and outflow pipes.
7.2.3 Gear units with backstop
Before start-up, check whether the backstop can be turned manually in the free-wheeling direction
without exerting undue force. Observe the direction-of-rotation arrows on the housing.
To avoid damaging the backstop or the gear unit, the motor should not be run
Caution! in the stop direction of the gear unit.
Observe the notice fixed to the gear unit.
The minimum lifting speeds must not be exceeded during operation.
Before connecting the motor, determine the direction of rotation of the three-phase current supply using
a phase-sequence indicator, and connect the motor in accordance with the pre-determined direction
of rotation.
Note: The unit can be started up once the amount of oil indicated on the notice has been
poured in through the oil filler plug screw of the backstop. Always use oil of the same
type and viscosity as for the gear unit.
7.2.4 Checking procedure
The following visual checks must be conducted and recorded when starting up:
S Oil level
S Oiltightness of the oil cooling or oil supply lines
S Opening condition of the shut-off valves
S Effectiveness of the shaft seals
S Freedom of the rotating parts from contact
The tension pressures and pretensioning forces in accordance with item 6.2.2.4 must also be recorded
in this document.
Note: The document must be kept with the operating instructions.
7.3 Removal from service
S To take the gear unit out of service, first switch off the drive unit.
Secure the drive unit to prevent it from being started up unintentionally.
Attach a warning notice to the start switch!
S In the case of gear units fitted with cooling coil or water oil-coolers, close the stop valve on the water
inflow and outflow pipes. To prevent freezing, drain the water from the cooling coil or the water
oil-cooler.
S During longer periods of disuse, start the unit up briefly at intervals of approx. 3 weeks. If the gear unit
is to remain out of service for longer than six months, it must be treated with preservative agent
(see item 7.3.1).
BA 5010 EN 06.03
7.3.1 Interior preservation during longer disuse
Depending on the type of lubrication or shaft sealing, the following types of internal preservative agent
can be used.
Gear units with dip lubrication systems and contacting shaft seals can be filled with the correct type of
oil up to a point just below the breather screw.
Before longer periods of storage gear units with forced lubrication systems, oil circulation cooling or
non-contacting shaft seals should be filled with preservative agent and run without load.
up to 6 months none
For storage periods longer than 24 months, renew the preservative agent.
For storage periods over 36 months, FLENDER should be consulted before.
Table 7.3: Preservation procedure when using mineral oil or PAO-based synthetic oil
up to 6 months none
Special anti-corrosion oil
Close gear unit, replace breather screw or
TRIBOL 1390 1)
up to 36 months air filter with a yellow plug screw
(replace the original parts before start-up)
S Switch the gear unit off and drain the oil as described in section 10, ”Maintenance and repair”.
S Pour in the preservative agent specified in Table 7.3 or 7.4 through the venting hole or the opening
in the inspection or assembly cover until it reaches the top mark on the oil dipstick or oil sight glass.
S Close the venting hole or the opening in the inspection or assembly cover.
S Start the gear unit and allow it to idle for a short time.
S Unscrew the oil drain plug and allow the preservative agent to drain into a suitable container and
dispose of it according to regulations.
There is a risk of scalding from the hot preservative agent draining from the
gear unit. Wear protective gloves to avoid scalding.
Before re-starting the gear unit replace the screw plug with the breather screw
Caution! or air filter.
See also item 7.1.1.
BA 5010 EN 06.03
7.3.2 Exterior preservation
Duration of Preservative
protection agent Layer thickness Remarks
Table 7.5: External preservation of shaft ends and other bright machined surfaces
S For separation between the sealing lip of the shaft sealing ring and the preservative agent, the shaft
should be brushed with grease in way of the sealing lip
8. Operation
Observe the ”Safety instructions” in section 3, the instructions in section 9, ”Faults, causes and remedy”,
and in section 10, ”Maintenance and repair”!
Observe the ”Safety instructions” in section 3 and the instructions in section 10, ”Maintenance and
repair”!
Note: Faults and malfunctions occurring during the guarantee period and requiring repair
work on the gear unit must be carried out only by FLENDER Customer Service.
In the case of faults and malfunctions occurring after the guarantee period and whose
cause cannot be precisely identified, we advise our customers to contact our
customer service.
BA 5010 EN 06.03
FLENDER will not be bound by the terms of the guarantee or otherwise be
Caution! responsible in cases of improper use of the gear unit, modifications carried out
without FLENDER’s agreement or use of spare parts not supplied by FLENDER.
To remedy faults and malfunctions, the gear unit must always be taken out of
service.
Secure the drive unit to prevent it from being started up unintentionally.
Attach a warning notice to the start switch.
Loud noises in area of Fastening has worked loose Tighten bolts / nuts to prescribed
gear-unit fastening torque.
Replace damaged bolts / nuts.
Changes in gear noise Damage to gear teeth Contact Customer Service.
– Check all toothed components and
replace any damaged parts.
On gear units with oil-cooling Fully set valves in inflow and outflow
system: pipes.
Coolant flow too low or too high Check for free flow through water
oil-cooler.
On gear units with fan: Clean fan cowl and gear-unit housing
Suction opening in fan cowl and/or
housing badly contaminated
BA 5010 EN 06.03
Malfunctions Causes Remedy
Increased temperature at Oil level in gear-unit housing too Check oil level at room temperature
bearing points low or too high and, if necessary, top up oil
Gear unit exposed to cold air from Protect gear unit with suitable heat
machine-room ventilator: water insulation.
condensing Close air outlet or alter its direction by
structural measures.
Pressure monitor triggers Oil pressure < 0.5 bar Check oil level at room temperature
alarm and, if necessary, top up oil.
(gear units with pressurised Check oil filter, clean if necessary.
lubrication, water oil-cooler, Contact Customer Service.
air oil-cooler) – Check that oil pump is functioning
correctly
– Repair or replace oil pump
Indicator on double Double change-over filter clogged Change filter over as instructed,
change-over filter triggers remove clogged filter element and
alarm clean
Fault in oil supply system Consult operating instructions
for oil supply system
Table 9.1: Faults, causes and remedies
BA 5010 EN 06.03
10. Maintenance and repair
Observe the ”Safety instructions” in section 3 and the instructions in section 9, ”Faults, causes and
remedy”.
Maintenance and repair work must be done with care by trained and qualified personnel only.
The periods indicated in table 10.1 depend on the conditions under which the
Caution! gear unit is operated. Only average periods can therefore be stated here. These
refer to:
For operation and maintenance, always observe the instructions given in the order-specific appendix.
For technical data, refer to the order-specific equipment list.
Test oil for water content. after approx. 400 operating hours see Item 10.2.1
once per year at least
subsequent oil changes every 2 years or after max. see Item 10.2.2
10 000 operating hours 1)
Refill Taconite seals every 3 000 operating hours see Item 10.2.4
with grease. or every 6 months at least
Clean fan, fan cowl and depending on requirements or see Item 10.2.5
gear-unit housing. simultaneously with due oil change
BA 5010 EN 06.03
Measures Periods Remarks
Check tightness of after first oil change, thereafter see Item 10.2.10
fastening bolts. after every second oil change
Carry out complete inspection approx. every 2 years see Item 10.3.1
of gear unit. simultaneously with due oil change
Table 10.1: Maintenance and repair work
For detailed information on testing the oil for water-content apply to the lubricant manufacturer.
S Close the stop valves in the coolant in- and outflow pipes (gear units with cooling coil or water
oil-cooling systems)
S Drain the oil while it is still warm, i.e. immediately after shutting down the machinery.
When changing the oil, always re-fill the gear unit with the same type of oil.
Caution! Never mix different types of oil or oils made by different manufacturers. Never
mix synthetic oils with mineral-based oils or with other synthetic oils. When
changing from mineral-based oil to synthetic oil or from one type of synthetic
oil to another, flush the gear unit well with the new type of oil beforehand.
When changing the oil, the housing must be flushed with oil to remove sludge, metal particles and oil
residue. Use the same type of oil as is used for normal operation. High-viscosity oils must be heated
beforehand. Ensure that all residues have been removed before filling with fresh oil.
S Place a suitable container under the oil drain plug of the gear-unit housing
S Unscrew the oil drain plug and allow the oil to drain into the container
There is a danger of scalding from the hot oil emerging from the housing.
Wear protective gloves to avoid scalding.
Remove any oil spillage immediately with an oil-binding agent.
Note: Check the condition of the sealing ring (the sealing ring is vulcanised onto the oil drain
plug). If necessary, use a new oil drain plug.
If a layer of dust has built up, the breather screw must be cleaned, whether or not the minimum period
of 3 months has expired. To do this, the breather screw must be unscrewed, cleaned with benzine or
similar agent and dried. It can also be cleaned by blowing out with compressed air.
Caution! Foreign bodies must be prevented from entering the gear unit.
BA 5010 EN 06.03
10.2.4 Refilling Taconite seals with grease
S Inject approx. 30 g lithium-based bearing grease into each of the lubrication points of the Taconite
seal. The lubrication points are fitted with flat grease nipples type AM10x1 to DIN 3404.
S Using a stiff brush, remove any dirt adhering to the fan wheel, cowl and safety grid.
Caution! The gear unit must not be cleaned with high-pressure cleaning equipment.
It must be ensured that the fan cowl is correctly fastened. The fan must not
Caution! come into contact with the fan cover.
S Disconnect the water in- and outflow pipes from the cooling coil
If the cooling coil is dirty, heat is no longer withdrawn effectively from the gear
Caution! unit. Any dirt adhering to the inside of the coil should be removed by chemical
cleaning or the coil should replaced with a new one.
S If thick deposits have formed on the inside of the cooling coil, the cooling water (or the deposits
themselves) should be chemically analysed. These analyses are carried out by companies which
specialise in chemical cleaning. They also supply the special cleaning agents required.
Note: Before using these cleaning agents, ensure that they will not damage the coil
materials (contact FLENDER). Observe the manufacturer’s instructions at all times.
Avoid burns when working with corrosive cleaning agents. Always observe the
manufacturers’ instructions for safety and use.
S Seriously contaminated cooling coils must be replaced. Consult our Customer Service.
BA 5010 EN 06.03
10.2.8 Checking water oil-cooler
S Close the stop valves in the coolant in- and outflow pipes
S Always top up with the same type of oil as already used in the gear unit (see also item 10.2.2).
S Close the stop valves in the coolant in- and outflow pipes (gear units with cooling coil or water
oil-cooling system)
All other bolts on the gear unit should be checked for tightening torques according to the following table:
Tightening torque
Thread size (with µ = 0.14)
Note: Damaged bolts must be replaced with new bolts of the same type and strength class.
BA 5010 EN 06.03
10.3 Final work
The general inspection of the gear unit must be carried out by the FLENDER Customer Service, as our
engineers have the experience and training necessary to identify any components requiring
replacement.
10.4 Lubricants
The oil selected for use in the gear unit must be of the viscosity (VG class) indicated on the nameplate.
The viscosity class applies for the contractually agreed operating conditions.
Note: For the correct type of oil (of various brands) to be used, refer to the BA 7300 EN
operating instructions supplied separately.
We are familiar with the composition of these lubricants and, as far as we are currently aware, they
possess the properties with regard to load-bearing capacity, corrosion resistance, resistance to grey
staining and compatibility with seals and internal paint coats which are necessary for the type of gear
unit concerned.
We therefore advise our customers to select one of the lubricants listed in the BA 7300 EN instructions,
taking into account the VG class specified on the rating plate.
Note: To avoid misunderstandings, we should like to point out that this recommendation is
in no way intended as a guarantee of the quality of the lubricant supplied. Each
lubricant manufacturer is responsible for the quality of his own product.
If for an important reason of your own you do not wish to follow our recommendation, you assume
responsibility for the technical suitability of the lubricant used.
By stocking the most important spare and wearing parts on site you can ensure that the gear unit is
ready for use at any time.
For further information refer to the spare-parts drawing stated in the list.
Please note that spare parts and accessories not supplied by us have not been
Caution! tested or approved by us. The installation and/or use of such products may
therefore impair essential characteristics of the gear unit, thereby posing an
active or passive risk to safety. FLENDER will assume no liability or guarantee
for damage caused by spare parts and accessories not supplied by FLENDER.
Please note that certain components often have special production and supply specifications and that
we supply you with spare parts which comply fully with the current state of technical development as
well as current legislation.
BA 5010 EN 06.03
11.2 Spare-part and customer service addresses
When ordering spare parts or the services of our specialist engineers, apply first to FLENDER AG.
FLENDER Germany
A. FRIEDR. FLENDER AG
46393 Bocholt - Tel.: (0 28 71) 92-0 - Fax: (0 28 71) 92 25 96
E-mail: contact@flender.com S www.flender.com
Shipping address: Alfred - Flender - Strasse 77 - 46395 Bocholt
LOHER GMBH
94095 Ruhstorf - Tel.: (0 85 31) 3 90 - Fax: (0 85 31) 3 94 37
E-mail: info@loher.de S www.loher.de
Shipping address: Hans-Loher-Strasse 32 - 94099 Ruhstorf
BA 5010 EN 06.03
Germany
A. FRIEDR. FLENDER AG
46393 BOCHOLT - TEL.: (0 28 71) 92 - 0 - FAX: (0 28 71) 92 25 96
SHIPPING ADDRESS: ALFRED - FLENDER - STRASSE 77 - 46395 BOCHOLT
––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
E-mail: contact@flender.com S www.flender.com
––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
VERTRIEBSZENTRUM BOCHOLT 46393 Bocholt
Alfred-Flender-Strasse 77, 46395 Bocholt
Tel.: (0 28 71) 92 - 0
Fax: (0 28 71) 92 - 14 35
E-mail: vz.bocholt@flender.com
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________
___________________________________________________________________________________________________________
BA 5010 EN 06.03
FLENDER International (2003-12-01)
BA 5010 EN 06.03
SERBIA-MONTENEGRO SALES OFFICES: USA
ALBANIA / MACEDONIA Flender Brasil Ltda. Flender Corporation
A. Friedr. Flender AG Rua James Watt, 142 950 Tollgate Road
Branch Office conj. 142 - Brooklin Novo P.O. Box 1449, Elgin, IL. 60123
c/o G.P.Inzenjering d.o.o. 04576 - 050, São Paulo - SP Phone: +1 (0) 8 47 - 9 31 19 90
III Bulevar 54 / 19 Phone: +55 (0) 11 - 55 05 99 33 Fax: +1 (0) 8 47 - 9 31 07 11
11070 Novi Beograd Fax: +55 (0) 11 - 55 05 30 10 E-mail: flender@flenderusa.com
Phone: +381 (0) 11 - 60 44 73 E-mail: flesao@uol.com.br www.flenderusa.com
Fax: +381 (0) 11 - 3 11 67 91 Flender Corporation
E-mail: flender@eunet.yu Flender Brasil Ltda. Service Centers West
Rua Campos Salles, 1095 4234 Foster Ave.
sala 04 - Centro 14015 - 110, Bakersfield, CA. 93308
Ribeirão Preto - SP
AFRICA Phone: +55 (0) 16 - 6 35 15 90
Phone: +1 (0) 6 61 - 3 25 44 78
Fax: +1 (0) 6 61 - 3 25 44 70
Fax: +55 (0) 16 - 6 35 11 05 E-mail: flender1@lightspeed.net
NORTH AFRICAN COUNTRIES E-mail: flender.ribpreto@uol.com.br
Please refer to Flender s.a.r.l. VENEZUELA
3, rue Jean Monnet - B.P. 5 F. H. Transmisiones S.A.
78996 Elancourt Cedex CANADA Urbanización Buena Vista
Phone: +33 (0) 1 - 30 66 39 00 Flender Power Transmission Inc. Calle Johan Schafer o Segunda Calle
Fax: +33 (0) 1 - 30 66 35 13 215 Shields Court, Units 4 - 6 Municipio Sucre, Petare
E-mail: sales@flender.fr Markham, Ontario L3R 8V2 Caracas
Phone: +1 (0) 9 05 - 3 05 10 21 Phone: +58 (0) 2 - 21 52 61
Fax: +1 (0) 9 05 - 3 05 10 23 Fax: +58 (0) 2 - 21 18 38
EGYPT E-mail: flender@ca.inter.net E-mail: fhtransm@telcel.net.ve
Sons of Farid Hassanen www.flenderpti.com www.fhtransmisiones.com
81 Matbaa Ahlia Street
Boulac 11221, Cairo SALES OFFICE: ASIA
Phone: +20 (0) 2 - 5 75 15 44 Flender Power Transmission Inc.
Fax: +20 (0) 2 - 5 75 17 02 34992 Bemina Court BANGLADESH / SRI LANKA
E-mail: hussein@sonfarid.com Abbotsford - Vancouver Please refer to Flender Limited
B.C. V3G 1C2 No. 2 St. George’s Gate Road
Phone: +1 (0) 6 04 - 8 59 66 75 5th Floor, Hastings
SOUTH AFRICA Fax: +1 (0) 6 04 - 8 59 68 78 Kolkata - 700 022
Flender Power Transmission (Pty.) Ltd. E-mail: tvickers@rapidnet.net Phone: +91 (0) 33 - 2 23 05 45
Cnr. Furnace St & Quality Rd. Fax: +91 (0) 33 - 2 23 18 57
P.O. Box 131, Isando 1600 E-mail: flender@flenderindia.com
Johannesburg CHILE / ARGENTINA / BOLIVIA
Phone: +27 (0) 11 - 5 71 20 00 ECUADOR / PARAGUAY / URUGUAY PEOPLE’S REPUBLIC OF CHINA
Fax: +27 (0) 11 - 3 92 24 34 Flender Cono Sur Limitada Flender Power Transmission
E-mail: sales@flender.co.za Avda. Galvarino Gallardo 1534 (Tianjin) Co. Ltd.
www.flender.co.za Providencia, Santiago ShuangHu Rd.- Shuangchen Rd. West
Phone: +56 (0) 2 - 2 35 32 49 Beichen Economic Development
SALES OFFICES: Area (BEDA)
Flender Power Transmission (Pty.) Ltd. Fax: +56 (0) 2 - 2 64 20 25
E-mail: flender@flender.cl Tianjin 300400
Unit 3 Marconi Park Phone: +86 (0) 22 - 26 97 20 63
9 Marconi Crescent, Montague Gardens www.flender.cl
Fax: +86 (0) 22 - 26 97 20 61
P.O. Box 37291 E-mail: flender@flendertj.com
Chempet 7442, Cape Town www.flendertj.com
Phone: +27 (0) 21 - 5 51 50 03 COLOMBIA
Fax: +27 (0) 21 - 5 52 38 24 A.G.P. Representaciones Ltda. Flender Power Transmission
E-mail: sales@flender.co.za Flender Liaison Office Colombia (Tianjin) Co. Ltd.
Av Boyaca No 23A Beijing Office
Flender Power Transmission (Pty.) Ltd. 50 Bodega UA 7-1, Bogotá C-415, Lufthansa Center
Unit 3 Goshawk Park Phone: +57 (0) 1 - 5 70 63 53 50 Liangmaqiao Road, Chaoyang District
Falcon Industrial Estate Fax: +57 (0) 1 - 5 70 73 35 Beijing 100016
P.O. Box 1608 E-mail: aguerrero@agp.com.co Phone: +86 (0) 10 - 64 62 21 51
New Germany 3620, Durban www.agp.com.co Fax: +86 (0) 10 - 64 62 21 43
Phone: +27 (0) 31 - 7 05 38 92 E-mail: beijing@flenderprc.com.cn
Fax: +27 (0) 31 - 7 05 38 72 Flender Power Transmission
E-mail: sales@flender.co.za MEXICO (Tianjin) Co. Ltd.
Flender Power Transmission (Pty.) Ltd. Flender de Mexico S.A. de C.V. Shanghai Office
9 Industrial Crescent, Ext. 25 17, Pte, 713 Centro 1101-1102 Harbour Ring Plaza
P.O. Box 17609, Witbank 1035 72000 Puebla 18 Xizang Zhong Rd.
Phone: +27 (0) 13 - 6 92 34 38 Phone: +52 (0) 2 22 - 2 37 19 00 Shanghai 200 001
Fax: +27 (0) 13 - 6 92 34 52 Fax: +52 (0) 2 22 - 2 37 11 33 Phone: +86 (0) 21 - 53 85 31 48
E-mail: sales@flender.co.za E-mail: szugasti@flendermexico.com Fax: +86 (0) 21 - 53 85 31 46
www.flendermexico.com E-mail: shanghai@flenderprc.com.cn
Flender Power Transmission (Pty.) Ltd. Flender Power Transmission
Unit 14 King Fisher Park, Alton SALES OFFICES: (Tianjin) Co. Ltd.
Cnr. Ceramic Curve & Alumina Allee Flender de Mexico S.A. de C.V. Wuhan Office
P.O. Box 101995 Lago Nargis No. 38 Rm. 1503, Jianyin Building,
Meerensee 3901, Richards Bay Col. Granada, 709 Jianshedadao
Phone: +27 (0) 35 - 7 51 15 63 11520 Mexico, D.F. Wuhan 430 015
Fax: +27 (0) 35 - 7 51 15 64 Phone: +52 (0) 55 - 52 54 30 37 Phone: +86 (0) 27 - 85 48 67 15
E-mail: sales@flender.co.za Fax: +52 (0) 55 - 55 31 69 39 Fax: +86 (0) 27 - 85 48 68 36
E-mail: info@flendermexico.com E-mail: wuhan@flenderprc.com.cn
Flender de Mexico S.A. de C.V. Flender Power Transmission
AMERICA Ave. San Pedro No. 231-5 (Tianjin) Co. Ltd.
Col. Miravalle Guangzhou Office
64660 Monterrey, N.L. Rm. 2802, Guangzhou International
ARGENTINA Electronics Tower
Chilicote S.A. Phone: +52 (0) 81 - 83 63 82 82
Fax: +52 (0) 81 - 83 63 82 83 403 Huanshi Rd. East
Avda. Julio A. Roca 546
E-mail: info@flendermexico.com Guangzhou 510 095
C 1067 ABN Buenos Aires
Phone: +86 (0) 20 - 87 32 60 42
Phone: +54 (0) 11 - 43 31 66 10 Fax: +86 (0) 20 - 87 32 60 45
Fax: +54 (0) 11 - 43 31 42 78 E-mail: guangzhou@flenderprc.com.cn
E-mail: chilicote@chilicote.com.ar PERU
Potencia Industrial E.I.R.L. Flender Power Transmission
Calle Victor González Olaechea N° 110 (Tianjin) Co. Ltd.
BRASIL Urb. La Aurora - Miraflores, Chengdu Office
Flender Brasil Ltda. P.O.Box: Av. 2 de Mayo N° 679 G-6 / F Guoxin Mansion,
Rua Quatorze, 60 - Cidade Industrial Of.108-Miraflores 77 Xiyu Street
32211 - 970, Contagem - MG Casilla N° 392, Lima 18 Chengdu 610 015
Phone: +55 (0) 31 - 33 69 21 00 Phone: +51 (0) 1 - 2 42 84 68 Phone: +86 (0) 28 - 86 19 83 72
Fax: +55 (0) 31 - 33 69 21 66 Fax: +51 (0) 1 - 2 42 08 62 Fax: +86 (0) 28 - 86 19 88 10
E-mail: vendas@flenderbrasil.com E-mail: cesarzam@chavin.rcp.net.pe E-mail: chengdu@flenderprc.com.cn
BA 5010 EN 06.03
Flender Power Transmission ISRAEL SINGAPORE
(Tianjin) Co. Ltd. Greenshpon Engineering Works Ltd. Flender Singapore Pte. Ltd.
Shenyang Office Haamelim Street 20 13 A, Tech Park Crescent
Rm. 2-163, Tower I, City Plaza Shenyan P.O. Box 10108, 26110 Haifa Singapore 637843
206 Nanjing Street (N), Heping District Phone: +972 (0) 4 - 8 72 11 87 Phone: +65 (0) - 68 97 94 66
Shenyang 110 001 Fax: +972 (0) 4 - 8 72 62 31 Fax: +65 (0) - 68 97 94 11
Phone: +86 (0) 24 - 23 34 20 48 E-mail: sales@greenshpon.com E-mail: flender@singnet.com.sg
Fax: +86 (0) 24 - 23 34 20 46 www.greenshpon.com www.flender.com.sg
E-mail: shenyang@flenderprc.com.cn
JAPAN SYRIA
Flender Power Transmission Flender Japan Co., Ltd. Misrabi Co & Trading
(Tianjin) Co. Ltd. WBG Marive East 21F Mezzeh Autostrade Transportation
Xi’an Office Nakasa 2 - 6 Building 4/A, 5th Floor
Rm. 302, Shaanzi Zhong Da Mihama-ku, Chiba-shi P.O. Box 12450, Damascus
International Mansion Chiba 261-7121 Phone: +963 (0) 11 - 6 11 67 94
30 Southern Rd. Phone: +81 (0) 43 - 2 13 39 30 Fax: +963 (0) 11 - 6 11 09 08
Xi’an 710 002 Fax: +81 (0) 43 - 2 13 39 55 E-mail: ismael.misrabi@gmx.net
Phone: +86 (0) 29 - 7 20 32 68 E-mail: contact@flender-japan.com
Fax: +86 (0) 29 - 7 20 32 04
E-mail: xian@flenderprc.com.cn TAIWAN
KOREA A. Friedr. Flender AG
Flender Ltd. Taiwan Branch Company
INDIA 7th Fl. Dorim Bldg. 1F, No. 5, Lane 240
Flender Limited 1823 Bangbae-Dong, Seocho-Ku, Nan Yang Street, Hsichih
Head Office: Seoul 137-060 Taipei Hsien 221
No. 2 St. George’s Gate Road Phone: +82 (0) 2 - 34 78 63 37 Phone: +886 (0) 2 - 26 93 24 41
5th Floor, Hastings Fax: +82 (0) 2 - 34 78 63 45 Fax: +886 (0) 2 - 26 94 36 11
Kolkata - 700 022 E-mail: flender@unitel.co.kr E-mail: flender_tw@flender.com.tw
Phone: +91 (0) 33 - 22 23 05 45
Fax: +91 (0) 33 - 22 23 08 30 KUWAIT THAILAND
E-mail: flender@flenderindia.com South Gulf Company Flender Singapore Pte. Ltd.
Al-Reqai, Plot 1, Block 96 Representative Office
Flender Limited P.O. Box 26229, Safat 13123 23/F M Thai Tower, All Seasons Place
Industrial Growth Centre Phone: +965 (0) - 4 88 39 15 87 Wireless Road, Phatumwan
Rakhajungle, Nimpura Fax: +965 (0) - 4 88 39 14 Bangkok 10330
Kharagpur - 721 302 E-mail: adelameen@hotmail.com Phone: +66 (0) 2 - 6 27 91 09
Phone: +91 (0) 3222 - 23 33 07 Fax: +66 (0) 2 - 6 27 90 01
Fax: +91 (0) 3222 - 23 33 64 LEBANON E-mail: christian.beckers@flender.th.com
E-mail: works@flenderindia.com Gabriel Acar & Fils s.a.r.l.
Dahr-el-Jamal VIETNAM
SALES OFFICES: Zone Industrielle, Sin-el-Fil Flender Singapore Pte. Ltd.
Flender Limited B.P. 80484, Beyrouth Representative Office
Eastern Regional Sales Office Phone: +961 (0) 1 - 49 82 72 Suite 6/6A, 16F Saigon Tower
No. 2 St. George’s Gate Road Fax: +961 (0) 1 - 49 49 71 29 Le Duan Street, District 1
5th Floor, Hastings E-mail: gacar@beirut.com Ho Chi Minh City, Vietnam
Kolkata - 700 022
Phone: +84 (0) 8 - 8 23 62 97
Phone: +91 (0) 33 - 22 23 05 45
MALAYSIA Fax: +84 (0) 8 - 8 23 62 88
Fax: +91 (0) 33 - 22 23 08 30 E-mail: flender@hcm.vnn.vn
Flender Singapore Pte. Ltd.
E-mail: ero@flenderindia.com
Representative Office
Flender Limited 37 A - 2, Jalan PJU 1/39
Western Regional Sales Office Dataran Prima AUSTRALIA
Plot No. 23, Sector 19 - C 47301 Petaling Jaya
Vashi, Navi Mumbai - 400 705 Selangor Darul Ehsan
Phone: +91 (0) 22 - 27 65 72 27 Phone: +60 (0) 3 - 78 80 42 63
Fax: +60 (0) 3 - 78 80 42 73 Flender (Australia) Pty. Ltd.
Fax: +91 (0) 22 - 27 65 72 28 9 Nello Place, P.O. Box 6047
E-mail: wro@flenderindia.com E-mail: flender@tm.net.my
Wetherill Park
Flender Limited N.S.W. 2164, Sydney
PAKISTAN Phone: +61 (0) 2 - 97 56 23 22
Southern Regional Sales Office Please refer to
41 Nelson Manickam Road Fax: +61 (0) 2 - 97 56 48 92, 97 56 14 92
A. Friedr. Flender AG
Aminjikarai, E-mail: sales@flender.com.au
46393 Bocholt
Chennai - 600 029 www.flender.com.au
Phone: +49 (0) 28 71 - 92 22 59
Phone: +91 (0) 44 - 23 74 39 21 Fax: +49 (0) 28 71 - 92 15 16 SALES OFFICES:
Fax: +91 (0) 44 - 23 74 39 19 E-mail: ludger.wittag@flender.com Flender (Australia) Pty. Ltd.
E-mail: sro@flenderindia.com Suite 3, 261 Centre Rd.
PHILIPPINES Bentleigh, VIC 3204 Melbourne
Flender Limited Phone: +61 (0) 3 - 95 57 08 11
Northern Regional Sales Office Flender Singapore Pte. Ltd.
Representative Office Fax: +61 (0) 3 - 95 57 08 22
209-A, Masjid Moth, 2nd Floor E-mail: sales@flender.com.au
(Behind South Extension II) 28/F, Unit 2814
New Delhi - 110 049 The Enterprise Centre Flender (Australia) Pty. Ltd.
Phone: +91 (0) 11 - 26 25 02 21 6766 Ayala Avenue corner Suite 5, 1407 Logan Rd.
Fax: +91 (0) 11 - 26 25 63 72 Paeso de Roxas, Makati City Mt. Gravatt
E-mail: nro@flenderindia.com Phone: +63 (0) 2 - 8 49 39 93 QLD 4122, Brisbane
Fax: +63 (0) 2 - 8 49 39 17 Phone: +61 (0) 7 - 34 22 23 89
E-mail: roman@flender.com.ph Fax: +61 (0) 7 - 34 22 24 03
INDONESIA E-mail: sales@flender.com.au
Flender Singapore Pte. Ltd. BAHRAIN / IRAQ / JORDAN / LYBIA Flender (Australia) Pty. Ltd.
Representative Office OMAN / QATAR / U.A.E. / YEMEN
Please refer to A. Friedr. Flender AG Suite 2 403 Great Eastern Highway
Perkantoran Puri Niaga II W.A. 6104, Redcliffe - Perth
Jalan Puri Kencana Blok J1 Middle East Sales Office
IMES Sanayi Sitesi Phone: +61 (0) 8 - 94 77 41 66
No. 2i, Kembangan Fax: +61 (0) 8 - 94 77 65 11
Jakarta Barat 11610 E Blok 502, Sokak No. 22
81260 Dudullu - Istanbul E-mail: sales@flender.com.au
Phone: +62 (0) 21 - 5 82 86 24
Fax: +62 (0) 21 - 5 82 86 23 Phone: +90 (0) 2 16 - 4 99 66 23
Fax: +90 (0) 2 16 - 3 64 59 13 NEW ZEALAND
E-mail: bobwall@cbn.net.id Please refer to Flender (Australia) Pty. Ltd.
E-mail: meso@flendertr.com
9 Nello Place, P.O. Box 6047
IRAN SAUDI ARABIA Wetherill Park
Cimaghand Co. Ltd. South Gulf Co. N.S.W. 2164, Sydney
P.O. Box 15745-493 Al-Khobar, Dahran Str. Phone: +61 (0) 2 - 97 56 23 22
No. 13, 16th East Street Middle East Trade Center Fax: +61 (0) 2 - 97 56 48 92
Beyhaghi Ave., Argentina Sq. 3rd floor, Flat # 23 E-mail: sales@flender.com.au
Tehran 15156 P.O. Box 20434 31952 Al-Khobar
Phone: +98 (0) 21 - 8 73 02 14 Phone: +966 (0) 3 - 8 87 53 32
Fax: +98 (0) 21 - 8 73 39 70 Fax: +966 (0) 3 - 8 87 53 31
E-mail: info@cimaghand.com E-mail: adelameen@hotmail.com
BA 5010 EN 06.03
12. Declaration by the manufacturer
described in these Operating Instructions are intended for incorporation in a machine, and that
it is prohibited to put them into service before verifying that the machine into which they are
incorporated complies with the EC Guidelines (original edition 98/37/EC including any subse-
quent amendments thereto).
This Manufacturer’s Declaration takes into account all the unified standards (inasmuch as
they apply to our products) published by the European Commission in the Official Journal of
the European Community.
Penig, 2003-06-20
Signature (Director ZGE Engineering) Sizes 3 to 16
Bocholt, 2003-06-20
Signature (Director IDE Engineering) Sizes 17 to 26
BA 5010 EN 06.03
Operating Instructions
BA 7300 EN 01.05
Recommended Lubricants
TEXACO
BA 7300 EN 01.05
1. Lubricants for gear units
According to manufacturer’s information the gear oils listed in these operating instructions are
manufactured and supplied world-wide in the above-mentioned quality as required by FLENDER
(Exceptions: Observe footnotes in the following tables).
For FLENDER gear units, only CLP-quality oils containing active agents to DIN 51 517-3 for increasing
corrosion protection and resistance to ageing and for reducing wear in mixed-friction areas are
approved. The scuffing resistance in the FZG test to DIN 51354-2 must comply with stage 12 or higher
under A/8,3/90 test conditions. In the FE-8 rolling bearing test to DIN 51 819-3 rolling element wear must
be under 30 mg and cage wear under 100 mg under test conditions D-7,5/80-80.
In addition, the gear oils must meet the following quality requirements demanded by FLENDER:
S Low degree of foaming with less than 15 % foam formation in the FLENDER foam test
S Compatibility with elastomer materials of the radial shaft-sealing rings applied in FLENDER gear units
S Compatibility with residues of corrosion-protection agent and run-in oils used by FLENDER
S Low wear, high pitting resistance and high efficiency (low temperature) in the cylindrical worm-gear
unit test
Note: The use of gear oils which do not comply with the above quality requirements
invalidate the FLENDER product guarantee obligation. Please note that every oil
manufacturer or supplier is responsible for the quality of his product.
Always select the gear oil in accordance with the oil group and viscosity class indicated on the rating
plate on the gear unit. If a different viscosity is selected, or oil of a type other than those recommended
in these instructions, the operator assumes the responsibility for its technical suitability. In order to
minimise the technical risk in such a case, the oil applied must be at least CLP oil quality to
DIN 51 517-3, which should be confirmed by the oil manufacturer.
The oil group and oil viscosity indicated on the rating plates as well as the
Caution! instructions in the gear-unit operating instructions must be adhered to.
BA 7300 EN 01.05
1.1.1 Oil groups
The synthetic oils have a wider temperature range and a higher viscosity index (i.e. a flatter
viscosity-temperature gradient) than the mineral oils. Guideline values for temperature range:
Note: The upper and lower operating temperatures of certain gear oils may deviate widely
from the values indicated. For operating conditions outside the above mentioned
temperature ranges, the flash point and pour point of the oils must be observed. For
these and other data and properties of the gear oils, refer to the oil manufacturers’
technical data sheets (to this purpose Flender must be consulted).
According to the manufacturers, the following are the minimum periods during which the oils can be
used without undergoing any significant change in quality. They are calculated on the basis of an
average oil temperature of 80 °C:
– mineral oils, bio-degradable oils and physiologically safe oils: 2 years or 10 000 hours of service
Note: The actual service lives may be higher or lower (for temperatures over 80 °C). The
general rule is that an increase in temperature of 10 K will halve the service life.
The degree of purity of the oil affects the operating reliability and life span of the oil and the gear unit.
It should therefore be ensured that the oil in the gear unit is clean. For the first oil change after start-up
and for subsequent oil changes, the specifications in the gear-unit operating instructions must be
observed. In the case of larger oil quantities, an analysis should be carried out before cleaning or
changing the oil.
When changing oil of the same type, the quantity of oil remaining in the gear unit should be kept as low
as possible. Generally speaking, a small remaining quantity will cause no particular problems. Gear oils
of different types and manufacturers must not be mixed. If necessary, the manufacturer should confirm
that the new oil is compatible with residues of the old oil. When changing to very different types of oil
or oils with very different additives, especially when changing from polyglycols to another gear oil or vice
versa, the gear unit must always be well flushed out with the new oil. Residues of old oil must be
completely removed from the gear unit.
Gear oils must never be mixed with other substances. Flushing with paraffin or
Caution! other solvents is not permitted, as traces of these substances always remain
inside the unit.
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
A11 VG 1000
4111 XEP
A31 VG 1000 5999 XEP
SYNTOGEAR PE 1000
A41 VG 1000
A42 VG 680
A46 VG 150
A47 VG 100
A51 VG 1000
A52 VG 680
A53 VG 460
Physiologically
safe oils A54 VG 320
(PHY oil)
A55 VG 220
A56 VG 150
A57 VG 100
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
A17 VG 100
BERUSYNTH
A22 VG 680 EP 680
Enersyn SG-XP 680 Beslux Sincart W 680
BERUSYNTH
A23 VG 460 EP 460
Enersyn SG-XP 460 Beslux Sincart W 460
Polyglycol BERUSYNTH
A24 VG 320 EP 320
Enersyn SG-XP 320 Beslux Sincart W 320
(PG oil)
BERUSYNTH
A25 VG 220 EP 220
Enersyn SG-XP 220 Beslux Sincart W 220
BERUSYNTH
A26 VG 150 EP 150
Enersyn SG-XP 150 Beslux Sincart W 150
BERUSYNTH
A27 VG 100 EP 100
Enersyn SG-XP 100
A41 VG 1000
A42 VG 680
A46 VG 150
A47 VG 100
A51 VG 1000
A52 VG 680
A53 VG 460
Physiologically
safe oils A54 VG 320
(PHY oil)
A55 VG 220
A56 VG 150
A57 VG 100
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s) classic performance
Optigear BM 1000 CEPSA
A11 VG 1000 Alpha SP 1000
Tribol 1100 / 1000 AEROGEAR 1000
Optigear BM 680 CEPSA
A12 VG 680 Alpha SP 680
Tribol 1100 / 680 AEROGEAR 680
Alpha SP 460 Optigear BM 460 CEPSA
A13 VG 460 Alpha MAX 460 Tribol 1100 / 460 AEROGEAR 460
Mineral oils Alpha SP 320 Optigear BM 320 CEPSA
A14 VG 320 Alpha MAX 320 Tribol 1100 / 320 AEROGEAR 320
(MIN oil)
Alpha SP 220 Optigear BM 220 CEPSA
A15 VG 220 Alpha MAX 220 Tribol 1100 / 220 AEROGEAR 220
Alpha SP 150 Optigear BM 150
A16 VG 150 Alpha MAX 150 Tribol 1100 / 150
Alpha SP 100 Optigear BM 100
A17 VG 100 Alpha MAX 100 Tribol 1100 / 100
A31 VG 1000
AEROGEAR
A32 VG 680 Alphasyn EP 680
SYNT 680
Optigear Synth. A 460 Optigear Synth. X 460 AEROGEAR
A33 VG 460 Alphasyn EP 460 Tribol 1710 / 460 SYNT 460
Poly-a-
olefin A34 VG 320
Optigear Synth. A 320 Optigear Synth. X 320 AEROGEAR
Alphasyn EP 320 Tribol 1710 / 320 SYNT 320
(PAO oil) Optigear Synth. A 220 Optigear Synth. X 220 AEROGEAR
A35 VG 220 Alphasyn EP 220 Tribol 1710 / 220 SYNT 220
A37 VG 100
A41 VG 1000
RIVOLTA
A42 VG 680 S.G.L. 680
Tribol BioTop
Biologically A43 VG 460 1418 / 460
degradable RIVOLTA Tribol BioTop
oils A44 VG 320 S.G.L. 320 1418 / 320
RIVOLTA Tribol BioTop
(BIO oil) A45 VG 220 S.G.L. 220 1418 / 220
Tribol BioTop
A46 VG 150 1418 / 150
RIVOLTA
A47 VG 100 S.G.L. 100
A51 VG 1000
(PHY oil)
A55 VG 220 Optileb GT 220
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
A31 VG 1000
(PHY oil)
A55 VG 220 Breox FGL 220 2)
A57 VG 100
2) PG oil
3) ESSO guarantees the qualities required by FLENDER only for products from Europe
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
GEARMASTER
A11 VG 1000 CLP 1000
GEARMASTER Klüberoil
A12 VG 680 CLP 680 GEM 1 - 680 N
GEARMASTER Klüberoil
A13 VG 460 CLP 460 GEM 1 - 460 N
Mineral oils GEARMASTER Klüberoil
A14 VG 320 CLP 320 GEM 1 - 320 N
(MIN oil)
GEARMASTER Klüberoil
A15 VG 220 CLP 220 GEM 1 - 220 N
GEARMASTER Klüberoil
A16 VG 150 CLP 150 GEM 1 - 150 N
GEARMASTER Klüberoil
A17 VG 100 CLP 100 GEM 1 - 100 N
GEARMASTER Klübersynth.
A21 VG 1000 PGP 1000
Ucolub BSL-IG 1000
GH 6 - 1000
GEARMASTER Klübersynth.
A22 VG 680 PGP 680
Ucolub BSL-IG 680
GH 6 - 680
GEARMASTER Klübersynth.
A23 VG 460 PGP 460
Ucolub BSL-IG 460
GH 6 - 460
Polyglycol GEARMASTER Klübersynth.
A24 VG 320 PGP 320
Ucolub BSL-IG 320
GH 6 - 320
(PG oil)
GEARMASTER Klübersynth.
A25 VG 220 PGP 220
Ucolub BSL-IG 220
GH 6 - 220
GEARMASTER Klübersynth.
A26 VG 150 PGP 150
Ucolub BSL-IG 150
GH 6 - 150
GEARMASTER
A27 VG 100 PGP 100
Ucolub BSL-IG 100
GEARMASTER
A31 VG 1000 SYN 1000
GEARMASTER Klübersynth.
A32 VG 680 SYN 680 GEM 4 - 680 N
GEARMASTER Galp Transgear Klübersynth.
A33 VG 460 SYN 460
Ucolub N-PA 460
SMP 460 GEM 4 - 460 N
Poly-a-
olefin A34 VG 320
GEARMASTER
Ucolub N-PA 320 Galp Transgear Klübersynth.
SYN 320 SMP 320 GEM 4 - 320 N
(PAO oil) GEARMASTER Galp Transgear Klübersynth.
A35 VG 220 SYN 220
Ucolub N-PA 220
SMP 220 GEM 4 - 220 N
GEARMASTER Galp Transgear Klübersynth.
A36 VG 150 SYN 150 SMP 150 GEM 4 - 150 N
GEARMASTER
A37 VG 100 SYN 100
GEARMASTER
A41 VG 1000 ECO 1000
GEARMASTER
A42 VG 680 ECO 680
GEARMASTER
Biologically A43 VG 460 ECO 460
degradable GEARMASTER Klübersynth.
oils A44 VG 320 ECO 320 GEM 2 - 320
GEARMASTER Klübersynth.
(BIO oil) A45 VG 220 ECO 220 GEM 2 - 220
GEARMASTER
A46 VG 150 ECO 150
GEARMASTER
A47 VG 100 ECO 100
(PHY oil)
A55 VG 220 Ucolub BSL 220 4)
A57 VG 100
4) PG oil
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
GEAR COMPOUND
A11 VG 1000 PLUS 1000
609 ALMASOL Vari- GEAR COMPOUND
A12 VG 680 Purpose Gear Lubricant
Mobilgear XMP 680
PLUS 680
608 ALMASOL Vari- GEAR COMPOUND
A13 VG 460 Purpose Gear Lubricant
Mobilgear XMP 460
PLUS 460
Mineral oils 605 ALMASOL Vari- GEAR COMPOUND
A14 VG 320 Purpose Gear Lubricant
Mobilgear XMP 320
PLUS 320
(MIN oil)
607 ALMASOL Vari- GEAR COMPOUND
A15 VG 220 Purpose Gear Lubricant
Mobilgear XMP 220
PLUS 220
604 ALMASOL Vari- GEAR COMPOUND
A16 VG 150 Purpose Gear Lubricant
Mobilgear XMP 150
PLUS 150
606 ALMASOL Vari- GEAR COMPOUND
A17 VG 100 Purpose Gear Lubricant
Mobilgear XMP 100
PLUS 100
A21 VG 1000
A22 VG 680
A23 VG 460
Polyglycol
A24 VG 320
(PG oil)
A25 VG 220
A26 VG 150
A27 VG 100
GEAR SINTEC
A31 VG 1000 Mobil SHC 639
CLP 1000
megol Gearoil Synth GEAR SINTEC
A32 VG 680 680
Mobilgear SHC XMP680
CLP 680
megol Gearoil Synth Mobil SHC 634 GEAR SINTEC
A33 VG 460 460 Mobilgear SHC XMP460 CLP 460
Poly-a-
olefin A34 VG 320
megol Gearoil Synth Mobil SHC 632 GEAR SINTEC
320 Mobilgear SHC XMP320 CLP 320
(PAO oil) megol Gearoil Synth Mobil SHC 630 GEAR SINTEC
A35 VG 220 220 Mobilgear SHC XMP220 CLP 220
Mobil SHC 629 GEAR SINTEC
A36 VG 150 Mobilgear SHC XMP150 CLP 150
GEAR SINTEC
A37 VG 100 CLP 100
A41 VG 1000
A42 VG 680
A46 VG 150
A47 VG 100
A51 VG 1000
A52 VG 680
A53 VG 460
Physiologically
safe oils A54 VG 320
(PHY oil)
A55 VG 220
A56 VG 150
A57 VG 100
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
TRANSOL
A12 VG 680 OMV gear HST 680
PREMIUM 680 PO Gravis MP 680
TRANSOL
A13 VG 460 OMV gear HST 460
PREMIUM 460 PO Gravis MP 460
Mineral oils TRANSOL
A14 VG 320 OMV gear HST 320
PREMIUM 320 PO Gravis MP 320 Q8 Goya NT 320
(MIN oil)
TRANSOL
A15 VG 220 OMV gear HST 220
PREMIUM 220 PO Gravis MP 220 Q8 Goya NT 220
A16 VG 150 OMV gear HST 150 PO Gravis MP 150 Q8 Goya NT 150
A21 VG 1000
A22 VG 680
A23 VG 460
Polyglycol
A24 VG 320
(PG oil)
A25 VG 220
A26 VG 150
A27 VG 100
TRANSGEAR
A31 VG 1000 PE 1000 PO Gravis SP 1000
TRANSGEAR
A32 VG 680 PE 680 PO Gravis SP 680
TRANSGEAR
A33 VG 460 PE 460 PO Gravis SP 460 Q8 El Greco 460
Poly-a-
olefin A34 VG 320
TRANSGEAR
PO Gravis SP 320 Q8 El Greco 320
PE 320
(PAO oil) TRANSGEAR
A35 VG 220 PE 220 PO Gravis SP 220 Q8 El Greco 220
A37 VG 100
A41 VG 1000
A42 VG 680
A46 VG 150
A47 VG 100
A51 VG 1000
A52 VG 680
A53 VG 460
Physiologically
safe oils A54 VG 320
(PHY oil)
A55 VG 220
A56 VG 150
A57 VG 100
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s) TEXACO
KASSILLA GMP 1000
A11 VG 1000 CARTER EP 1000
KASSILLA GMP 680
A12 VG 680 LoadWay EP 680
CARTER EP 680
Meropa WM 460 KASSILLA GMP 460
A13 VG 460 Shell Omala F 460 LoadWay EP 460
Auriga EP 460 CARTER EP 460
Mineral oils Meropa WM 320 KASSILLA GMP 320
A14 VG 320 Shell Omala F 320 LoadWay EP 320
Auriga EP 320 CARTER EP 320
(MIN oil)
Meropa WM 220 KASSILLA GMP 220
A15 VG 220 Shell Omala F 220 LoadWay EP 220
Auriga EP 220 CARTER EP 220
A27 VG 100
(PAO oil)
A35 VG 220 Shell Omala HD 220 MERETA 220 CARTER SH 220
A37 VG 100
A41 VG 1000
A42 VG 680
A56 VG 150
A57 VG 100
5) PG oil
BA 7300 EN 01.05
Table A Lubricating oils for FLENDER helical-gear, bevel helical-gear and planetary-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
VECO MATRANOL
A11 VG 1000 XP 1000
VECO MATRANOL
A12 VG 680 TUNGEAR 680 6) COMPOUND MP 680
XP 680
VECO MATRANOL
A13 VG 460 TUNGEAR 460 6) COMPOUND MP 460
XP 460
Mineral oils VECO MATRANOL
A14 VG 320 TUNGEAR 320 6) COMPOUND MP 320
XP 320
(MIN oil)
VECO MATRANOL
A15 VG 220 TUNGEAR 220 6) COMPOUND MP 220
XP 220
A17 VG 100
A21 VG 1000
A22 VG 680
A23 VG 460
Polyglycol
A24 VG 320
(PG oil)
A25 VG 220
A26 VG 150
A27 VG 100
A31 VG 1000
A32 VG 680
A33 VG 460
Poly-a-
olefin A34 VG 320
(PAO oil)
A35 VG 220
A36 VG 150
A37 VG 100
A41 VG 1000
A42 VG 680
A46 VG 150
A47 VG 100
A51 VG 1000
A52 VG 680
A53 VG 460
Physiologically
safe oils A54 VG 320
(PHY oil)
A55 VG 220
A56 VG 150
A57 VG 100
6) TUNGEAR is approved for Brazil under the name of GEAROIL in VG 220, 320, 460 and 680. Distributor: TRIBOTECHNICA Lubrificantes Sinteticos Sao Paulo.
TUNGEAR is approved for India under the name of Mox-Active Gear oil in VG 220, 320 and 460. Distributor: OKS Speciality Lubricants Bombay.
BA 7300 EN 01.05
Table B Lubricating oils for FLENDER worm-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
B22 VG 680 Degol GS 680 GEAR VSG 680 BERUSYNTH Enersyn SG-XP 680
EP 680
B23 VG 460 Degol GS 460 GEAR VSG 460 BERUSYNTH Enersyn SG-XP 460
EP 460
Polyglycol BERUSYNTH
B24 VG 320 Degol GS 320 GEAR VSG 320
EP 320
Enersyn SG-XP 320
(PG oil)
B25 VG 220 Degol GS 220 GEAR VSG 220 BERUSYNTH Enersyn SG-XP 220
EP 220
B26 VG 150 Degol GS 150 GEAR VSG 150 BERUSYNTH Enersyn SG-XP 150
EP 150
B31 VG 1000
B32 VG 680
B33 VG 460
Poly-a-
olefin B34 VG 320
(PAO oil)
B35 VG 220
B36 VG 150
B37 VG 100
B41 VG 1000
B42 VG 680
B46 VG 150
B47 VG 100
B51 VG 1000
B52 VG 680
B53 VG 460
Physiologically
safe oils B54 VG 320
(PHY oil)
B55 VG 220
B56 VG 150
B57 VG 100
BA 7300 EN 01.05
Table B Lubricating oils for FLENDER worm-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s) performance
Optigear BM 1000
B11 VG 1000 Tribol 1100 / 1000
Optigear BM 680
B12 VG 680 SPARTAN EP 680 1)
Tribol 1100 / 680
Optigear BM 460
B13 VG 460 SPARTAN EP 460 1)
Tribol 1100 / 460
Mineral oils Optigear BM 320
B14 VG 320 SPARTAN EP 320 1)
Tribol 1100 / 320
(MIN oil)
Optigear BM 220
B15 VG 220 SPARTAN EP 220 1)
Tribol 1100 / 220
Optigear BM 150
B16 VG 150 SPARTAN EP 150 1)
Tribol 1100 / 150
Optigear BM 100
B17 VG 100 SPARTAN EP 100 1)
Tribol 1100 / 100
Optiflex A 1000
B21 VG 1000 Tribol 800 / 1000
Breox SL 1000 RENOLIN PG 1000
Optiflex A 680
B22 VG 680 Tribol 800 / 680
Breox SL 680 RENOLIN PG 680
Optiflex A 460
B23 VG 460 Tribol 800 / 460
Breox SL 460 RENOLIN PG 460
Polyglycol Optiflex A 320
B24 VG 320 Tribol 800 / 320
Breox SL 320 RENOLIN PG 320
(PG oil)
Optiflex A 220
B25 VG 220 Tribol 800 / 220
Breox SL 220 RENOLIN PG 220
Optiflex A 150
B26 VG 150 Tribol 800 / 150
Breox SL 150 RENOLIN PG 150
Optiflex A 100
B27 VG 100 Tribol 800 / 100
RENOLIN PG 100
B31 VG 1000
B32 VG 680
B33 VG 460
Poly-a-
olefin B34 VG 320
(PAO oil)
B35 VG 220
B36 VG 150
B37 VG 100
B41 VG 1000
B42 VG 680
B46 VG 150
B47 VG 100
Tribol FoodProof
B52 VG 680 Breox FGL 680 2)
1800 / 680 2)
Tribol FoodProof
B53 VG 460 Breox FGL 460 2)
Physiologically 1800 / 460 2)
safe oils B54 VG 320
Tribol FoodProof
Breox FGL 320 2)
1800 / 320 2)
(PHY oil) Tribol FoodProof
B55 VG 220 Breox FGL 220 2)
1800 / 220 2)
B57 VG 100
1) ESSO guarantees the qualities required by FLENDER only for products from Europe
2) PG oil
BA 7300 EN 01.05
Table B Lubricating oils for FLENDER worm-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
B11 VG 1000
GEARMASTER SYNTHESO
B27 VG 100 PGP 100 D 100 EP
B31 VG 1000
B32 VG 680
B33 VG 460
Poly-a-
olefin B34 VG 320
(PAO oil)
B35 VG 220
B36 VG 150
B37 VG 100
B41 VG 1000
B42 VG 680
B46 VG 150
B47 VG 100
B56 VG 150
B57 VG 100
3) PG oil
BA 7300 EN 01.05
Table B Lubricating oils for FLENDER worm-gear units
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
B11 VG 1000
B21 VG 1000
B22 VG 680
B23 VG 460
Polyglycol
B24 VG 320
(PG oil)
B25 VG 220
B26 VG 150
B27 VG 100
B31 VG 1000
B32 VG 680
B33 VG 460
Poly-a-
olefin B34 VG 320
(PAO oil)
B35 VG 220
B36 VG 150
B37 VG 100
B41 VG 1000
B42 VG 680
B46 VG 150
B47 VG 100
B51 VG 1000
B52 VG 680
B53 VG 460
Physiologically
safe oils B54 VG 320
(PHY oil)
B55 VG 220
B56 VG 150
B57 VG 100
BA 7300 EN 01.05
Table C Lubricating oils for FLENDER gear motors
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
CLP 220 S Degol BG 220 Plus
C15 VG 220 ECO GEAR 220 M Degol BG 220 1) GEAR RSX 220
Mineral oils CLP 150 S Degol BG 150 Plus
C16 VG 150 ECO GEAR 150 M Degol BG 150 1) GEAR RSX 150
(MIN oil)
Degol BG 100 Plus
C17 VG 100 ECO GEAR 100 M Degol BG 100 1) GEAR RSX 100
C53 VG 460
Physiologically
safe oils C54 VG 320
(PHY oil)
C55 VG 220
BERUSYNTH
C23 VG 460 EP 460 Enersyn SG-XP 460 Beslux Sincart W 460
Polyglycol BERUSYNTH
C24 VG 320 EP 320 Enersyn SG-XP 320 Beslux Sincart W 320
(PG oil)
BERUSYNTH
C25 VG 220 EP 220 Enersyn SG-XP 220 Beslux Sincart W 220
C53 VG 460
Physiologically
safe oils C54 VG 320
(PHY oil)
C55 VG 220
BA 7300 EN 01.05
Table C Lubricating oils for FLENDER gear motors
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s) classic performance
Alpha SP 220 Optigear BM 220 CEPSA
C15 VG 220 Alpha MAX 220 Tribol 1100 / 220 AEROGEAR 220
Mineral oils Alpha SP 150 Optigear BM 150
C16 VG 150 Alpha MAX 150 Tribol 1100 / 150
(MIN oil)
Alpha SP 100 Optigear BM 100
C17 VG 100 Alpha MAX 100 Tribol 1100 / 100
Optiflex A 460
C23 VG 460 Tribol 800 / 460
Polyglycol Optiflex A 320
C24 VG 320 Tribol 800 / 320
(PG oil)
Optiflex A 220
C25 VG 220 Tribol 800 / 220
Optigear Synth. A 460 Optigear Synth. X 460 AEROGEAR
C33 VG 460 Alphasyn EP 460 Tribol 1710 / 460 SYNT 460
Poly-a-
olefin C34 VG 320
Optigear Synth. A 320 Optigear Synth. X 320 AEROGEAR
Alphasyn EP 320 Tribol 1710 / 320 SYNT 320
(PAO oil) Optigear Synth. A 220 Optigear Synth. X 220 AEROGEAR
C35 VG 220 Alphasyn EP 220 Tribol 1710 / 220 SYNT 220
RIVOLTA Tribol BioTop
Biologically C44 VG 320 S.G.L. 320 1418 / 320
degradable RIVOLTA Tribol BioTop
oils C45 VG 220 S.G.L. 220 1418 / 220
Tribol BioTop
(BIO oil) C46 VG 150 1418 / 150
Optileb GT 460
C53 VG 460 FoodProof 1800/460 2)
Physiologically
safe oils C54 VG 320
Optileb GT 320
FoodProof 1800/320 2)
(PHY oil) Optileb GT 220
C55 VG 220 FoodProof 1800/220 2)
2) PG oil
(PHY oil)
C55 VG 220 Breox FGL 220 4)
3) ESSO guarantees the qualities required by FLENDER only for products from Europe
4) PG oil
BA 7300 EN 01.05
Table C Lubricating oils for FLENDER gear motors
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
GEARMASTER Klüberoil
C15 VG 220 CLP 220 GEM 1 - 220 N
Mineral oils GEARMASTER Klüberoil
C16 VG 150 CLP 150 GEM 1 - 150 N
(MIN oil)
GEARMASTER Klüberoil
C17 VG 100 CLP 100 GEM 1 - 100 N
GEARMASTER SYNTHESO
C23 VG 460 PGP 460 Ucolub BSL-IG 460
D 460 EP
Polyglycol GEARMASTER SYNTHESO
C24 VG 320 PGP 320 Ucolub BSL-IG 320
D 320 EP
(PG oil)
GEARMASTER SYNTHESO
C25 VG 220 PGP 220 Ucolub BSL-IG 220
D 220 EP
GEARMASTER Galp Transgear Klübersynth.
C33 VG 460 SYN 460 Ucolub N-PA 460
SMP 460 GEM 4 - 460 N
Poly-a-
olefin C34 VG 320
GEARMASTER
Ucolub N-PA 320 Galp Transgear Klübersynth.
SYN 320 SMP 320 GEM 4 - 320 N
(PAO oil) GEARMASTER Galp Transgear Klübersynth.
C35 VG 220 SYN 220 Ucolub N-PA 220
SMP 220 GEM 4 - 220 N
GEARMASTER Klübersynth.
Biologically C44 VG 320 ECO 320 GEM 2 - 320
degradable GEARMASTER Klübersynth.
oils C45 VG 220 ECO 220 GEM 2 - 220
GEARMASTER
(BIO oil) C46 VG 150 ECO 150
(PHY oil)
C55 VG 220 Ucolub BSL 220 5)
5) PG oil
C23 VG 460
Polyglycol
C24 VG 320
(PG oil)
C25 VG 220
C53 VG 460
Physiologically
safe oils C54 VG 320
(PHY oil)
C55 VG 220
BA 7300 EN 01.05
Table C Lubricating oils for FLENDER gear motors
Viscosity
Code ISO-VG
no. DIN 51519
Lubricant at 40 °C
(mm2/s)
TRANSOL
C15 VG 220 OMV gear HST 220 PREMIUM 220 PO Gravis MP 220 Q8 Goya NT 220
Mineral oils
C16 VG 150 OMV gear HST 150 PO Gravis MP 150 Q8 Goya NT 150
(MIN oil)
C17 VG 100 OMV gear HST 100 PO Gravis MP 100
C23 VG 460
Polyglycol
C24 VG 320
(PG oil)
C25 VG 220
TRANSGEAR
C33 VG 460 PE 460 PO Gravis SP 460 Q8 El Greco 460
Poly-a-
olefin C34 VG 320
TRANSGEAR
PO Gravis SP 320 Q8 El Greco 320
PE 320
(PAO oil) TRANSGEAR
C35 VG 220 PE 220 PO Gravis SP 220 Q8 El Greco 220
C53 VG 460
Physiologically
safe oils C54 VG 320
(PHY oil)
C55 VG 220
Shell Cassida
C53 VG 460 WG 460 6)
Physiologically
safe oils C54 VG 320
Shell Cassida
WG 320 6)
(PHY oil) Shell Cassida
C55 VG 220 WG 220 6)
6) PG oil
BA 7300 EN 01.05
Table C Lubricating oils for FLENDER gear motors
Viscosity
Kenn- ISO-VG
ziffer DIN 51519
Lubricant at 40 °C
(mm2/s)
KASSILLA GMP 220 VECO MATRANOL
C15 VG 220 CARTER EP 220
TUNGEAR 220 7) XP 220
COMPOUND MP 220
Mineral oils
C16 VG 150 COMPOUND MP 150
(MIN oil)
C17 VG 100
C23 VG 460
Polyglycol
C24 VG 320
(PG oil)
C25 VG 220
(PAO oil)
C35 VG 220 CARTER SH 220
Kestone Nevastane
C53 VG 460 SY 460 8)
Physiologically
safe oils C54 VG 320
Kestone Nevastane
SY 320 8)
(PHY oil) Kestone Nevastane
C55 VG 220 SY 220 8)
7) TUNGEAR is approved for Brazil under the name of GEAROIL in VG 220. Distributor: TRIBOTECHNICA Lubrificantes Sinteticos Sao Paulo.
TUNGEAR is approved for India under the name of Mox-Active Gear oil in VG 220. Distributor: OKS Speciality Lubricants Bombay.
8) PG oil
BA 7300 EN 01.05
1.2 Lubricating greases for gear units and rolling bearings
For special gear unit applications, grease lubrication of the gears and/or bearings may be necessary.
Note: Greases may be used only if their use is specified in the operating instructions for the
gear unit. The relubrication periods must be adhered to.
Gear greases are suitable for the lubrication of gears and bearings with closed gear units (e.g. small
gear units) and open drives with low peripheral speeds (e.g. for girth gears, racks).
As well as lubrication, rolling bearing greases are used for the special sealing of bearing points, e.g.
with vertical gear-unit connection shafts or against environmental action such as dust or water spray.
Note: In closed gear units with internal oil lubrication the gear oils must not be allowed to
mix with bearing greases.
Table D Lubricating greases for FLENDER gear units and rolling bearings
Consistency
Code
Lubricant no. NLGI class
DIN 51818
classic performance
G13 3 Viscogen 1)
G14 2
Gear greases
G15 1
(MIN-GF)
G16 0
Mineral oil base
Tribol 5000
G17 00 Optitemp OG 0
Aralub FDP 00 CLS Grease Longtime PD 00
G18 000 MA Mehrzweckfett 00
Table D Lubricating greases for FLENDER gear units and rolling bearings
Consistency
Code
Lubricant no. NLGI class
DIN 51818
G13 3
G14 2
Gear greases
G15 1
(MIN-GF)
G16 0
Mineral oil base
MICROLUBE
G17 00 GB 00
G18 000
3) Li, Ca saponification
BA 7300 EN 01.05
Table D Lubricating greases for FLENDER gear units and rolling bearings
Consistency
Code
Lubricant no. NLGI class
DIN 51818
TEXACO
G13 3 Glissando FG 30 EP
G14 2
Gear greases
G15 1
(MIN-GF)
G16 0 Mobilux EP 004 Wiolub GFW
Mineral oil base
G17 00 Alvania GL 00 Marfak 00
G18 000
Table D Lubricating greases for FLENDER gear units and rolling bearings
Consistency
Code
Lubricant no. NLGI class
DIN 51818
G13 3
G14 2
Gear greases
G15 1
(MIN-GF)
G16 0 Multis EP 0
Mineral oil base
G17 00 Multis EP 00
G18 000
BA 7300 EN 01.05
2. Lubricants for ZAPEX couplings
According to manufacturer’s information the oils and greases listed in these operating instructions are
manufactured and supplied world-wide in the above-mentioned quality as required by FLENDER
(Exceptions: Observe footnotes in the tables).
For FLENDER ZAPEX couplings, only oils and greases containing active agents to DIN 51 517-3 for
increasing corrosion protection and resistance to ageing and for reducing wear in mixed-friction areas
are approved. The scuffing resistance of the oils in the FZG test to DIN 51 354-2 must comply with stage
12 or higher under A/8,3/90 test conditions.
In addition, the oils and greases must meet the following quality requirements specified by FLENDER:
Note: The use of lubricants which do not comply with the above quality requirements may
invalidate our product guarantee. Please note that every lubricant manufacturer or
supplier is responsible for the quality of his product.
Which lubricant to select always depends on the viscosity or NLGI class indicated in these operating
instructions. If a different viscosity or NLGI class or a lubricant of a type other than those recommended
in these instructions is used, the operator is responsible for its technical suitability. To minimise the
technical risk in such cases, we recommend using a lubricant of the above indicated quality, which
should be accompanied by a statement of suitability by the lubricant manufacturer.
The instructions given in the operating instructions for the couplings must be
Caution! observed!
Note: The upper and lower limits for the operating temperatures (flash point, pour point) of
individual oils and greases may vary considerably. For these and other data and
properties of oils and greases, refer to the lubricant manufacturers’ technical data
sheets.
According to the manufacturers, the following are the minimum periods during which the oils or greases
can be used without undergoing any significant change in quality:
The degree of purity of the lubricant affects the operating reliability and life span of the lubricant and
the coupling. Care must always be taken that the oil or grease in the coupling is clean. For the first
lubricant change after start-up of the coupling and for subsequent lubricant changes, the specifications
in the operating instructions for the coupling must be observed. With larger lubricant quantities, an
anlysis should be carried out to find out whether cleaning or changing is required.
When changing lubricant of the same type, the quantity of lubricant remaining in the coupling should
be kept as low as possible. Generally speaking, a small remaining quantity will cause no particular
problems. Lubricants of different types and manufacturers must not be mixed together. If necessary,
confirmation that the new lubricant is compatible with residues of the old lubricant should be obtained
from the manufacturer.
BA 7300 EN 01.05
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818
I11 VG 1000
class
s
CLP 680 S
Mineral oils I12 VG 680 ECO GEAR 680 M Degol BG 680 Plus GEAR RSX 680 Energol GR-XF 680
ISO cla
CLP 460 S
(MIN oil) I13 VG 460 ECO GEAR 460 M Degol BG 460 Plus GEAR RSX 460 Energol GR-XF 460
IS
I14 VG 320
Liquefied J15 1
greases
NLGII class
cl ss
Mineral oil
base J18 000
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818 classic performance
CEPSA
I11 VG 1000 AEROGEAR 1000
class
s
I14 VG 320
Liquefied J15 1
greases
ss
class
J16 0
NLGII cl
(MIN-FLF)
Tribol 3020/1000-00
J17 00 Longtime PD 00
NL
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818
I11 VG 1000
ISO class
cla s
I14 VG 320
Liquefied J15 1
greases
class
ss
J16 0
NLGII cl
(MIN-FLF) FLENDER
Hochleistungsfett RENOLIT
J17 00 SO-D 6024
NL
Mineral oil
base J18 000
1) ESSO guarantees the qualities required by FLENDER only for products from Europe
BA 7300 EN 01.05
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818
I11 VG 1000
class
s
GEARMASTER STRUCTOVIS 609 ALMASOL Vari- Mobilgear 636
Mineral oils I12 VG 680 CLP 680 BHD-MF Purpose Gear Lubricant Mobilgear XMP 680
ISO cla
GEARMASTER 608 ALMASOL Vari- Mobilgear 634
(MIN oil) I13 VG 460 CLP 460 Purpose Gear Lubricant Mobilgear XMP 460
IS
I14 VG 320
Liquefied J15 1
greases
NLGII class
cl ss
J16 0
GRAFLOSKON
(MIN-FLF) C-SG 500 Plus
J17 00 Mobilux EP 004
NL
Mineral oil
base J18 000
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818
I12 VG 680 GEAR COMPOUND OMV gear HST 680 PO Gravis MP 680 Shell Omala 680
Mineral oils PLUS 680
ISO cla
Liquefied J15 1
greases
ss
class
J16 0
NLGII cl
(MIN-FLF)
J17 00 Alvina GL 00
NL
Mineral oil
base J18 000
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818 TEXACO
VECO MATRANOL
I11 VG 1000 XP 1000
ISO class
cla s
VECO MATRANOL
Mineral oils I12 VG 680 TUNGEAR 680 2) XP 680
Meropa WM 460 VECO MATRANOL
(MIN oil) I13 VG 460 Auriga EP 460 TUNGEAR 460 2) XP 460
IS
Liquefied J15 1
greases
class
ss
J16 0
NLGII cl
(MIN-FLF)
J17 00
NL
Mineral oil
base J18 000
2) TUNGEAR is approved for Brazil under the name of GEAROIL in VG 460 and 680. Distributor: TRIBOTECHNICA Lubrificantes Sinteticos Sao Paulo.
TUNGEAR is approved for India under the name of Mox-Active Gear oil in VG 460. Distributor: OKS Speciality Lubricants Bombay.
BA 7300 EN 01.05
Table E Oil: Viscosity Lubricating oils and lubricating greases for FLENDER ZAPEX couplings
in cSt at 40 °C
Code DIN 51519
Lubricant no. Grease:
Consistency
DIN 51818
I11 VG 1000
class
s
Mineral oils I12 VG 680
ISO cla
(MIN oil) I13 VG 460
IS
COMPOUND
I14 VG 320 MP 320
Liquefied J15 1
greases
NLGII class
cl ss
J16 0
(MIN-FLF)
J17 00
NL
Mineral oil
base J18 000
BA 7300 EN 01.05
Edition: March 2002
Operating Instructions
Oil drain cock B 5100 EN
(ball valve with full straightway) Page 1 of 2
These operating instructions are binding for oil drain plugs (ball valves with full straightway) to Flender Works
Standard W 5100.
Double nipple N8
to DIN EN 10242
Plug T9
to DIN EN 10242
Double parallel nipple and plug with thread sealed with hemp and Fermit.
If oil drain plugs are combined with screw connections, a suitable ring must be provided. This ring bridges the
too short thread in the oil drain plug and brings the screw connection into contact on the end face (see Fig. 3).
Double nipple
Ring e.g Cast iron screw connection
Fig. 3: Oil drain plug with double nipple, ring and cast iron screw connection
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
These operating instructions are binding for breathers according to FLENDER works standard W 5122.
Mounting
The thread of the filter has to be coated with sealing compound LOCTITE 572 before screwing it into the female
thread.
∅F
H
SW
D
S
∅R
D SW L K H A F R S
R 1/4 22 8 23 35 19 28 8 16.5
R 1/2 22 12 26 38 19 28 10 17
R 3/4 27 14 32 46 25 32 18 23
!"
#
$
%
& '
& (
&
! %! &
!
!
'
) *+
(
&
,
-
!
./0$1
$
!
&
!
/%
2
! % ! 3
!
4
56#) !%
!
7)
%
%
$
$$
8 ) 8 ) 41
9K 9K
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
0
*& &
9 K
&
2
!
: &
# !
&" 2 + >6 ? 20 + 86 ?2 ϕ: 6
)6 2 + >6 ? 20 + >66 ϕ: )
6 2 + >6 ? @0 + A
!
&" !
&
± ) B
" 96 °0 C)66 °0
> % 8 B
#
" 96 °0 CA6 °0
'
986 °0 CA6 °0(
&
" $4
" 68
5767#7)" 4 & ' %
(
0
!" 0D
%
E
" 2.7%
/%
"
45 '?
(
F
%
! 5 8 #
∅)
G)+2
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
. !%
5 6 # ) 8
!
General
The electric resistance in the resistance thermometer sensor changes as the temperature fluctuates. This
change of resistance on the PT 100 or the converted output signal of the measuring transducer (4 to 20 mA)
can be used to measure temperature with an evaluating instrument or to define a switch point by means of limit
switches.
Operation
Pt 100 measuring thermometer sensor
The electrical conductivity of metal (here platinum) is based on the mobility of conduction electrons. As the
temperature rises, the movement of the atoms in the metal lattice about their rest position intensifies and so
obstructs the electrons flowing to the plus pole of a power source. This obstruction sets up a resistance in linear
proportion to the temperature.
To generate the output signal a constant test current (approx. 1 mA) is applied to the Pt 100. The resistance
in the Pt 100 causes a drop in voltage (U = R · l), which can be evaluated.
Measuring transducer
The two-wire measuring transducer is mounted in the J-head only if requested by the customer. It should be
noted that here only a single connection is possible.
The measuring transducer converts the temperature-dependent resistance to a standard uniform signal
of 4 to 20 mA. This signal can be transmitted over long distances without interference.
Environmental influences
– Operating temperature range: –40 to +85 °C
– Temperature influence: ≤ 0.01 % / K deviation of 22 °C
relative to measuring range final value of 20 mA
– Climate resistance: rel. humidity ≤ 95 % on annual average without dew contact
– Vibration strength: acc. to GL characteristic 2
– EMV: EN 61326
Housing
– Material: Polycarbonate (encapsulated)
– Screw connection: ≤ 1.5 mm2
– Assembly: in terminal head Form J
– Mounting position: any
– Weight: approx. 12 g
Connection
The customer can minimise measuring inaccuracies by using multiple wires. At Flender, as a rule, a 3- or 4-wire
arrangement from an additional terminal box is provided for (Fig. 1, 2). At the customer’s specific request, the
3/4-wire arrangement can be used from the J-head (Figure 4, 5). Through lack of space, however, the 4-wire
arrangement is possible only with a single connection (Fig. 5).
Customer Customer
Fig. 3: 2-wire circuit from Fig. 4: 3-wire circuit from Fig. 5: 4-wire circuit from
terminal head of Pt 100 terminal head of Pt 100 terminal head of Pt 100
Types
EL = Installation length ≈ 61
40 14 3
∅ 49
G 1/2A
∅8
25 SW 27
∅ 5.8
crimped in
O-rings
≈ 33
Guide tube
∅ 26.9-0.2
0
Measuring resistance Adapter
Pt 100 doubled SW 17
!et t" D#$ 3%&' M16 x 1.5
Terminal head IP 65
e(t)*e t+e,m"mete, - &1001
+5
EL-10 = Installation length ≈ 61
+5
25-10 50 14 3
Guide tube
∅ 5.8
Spring
crimped in
≈ 33
∅ 26.9-0.2
0
122
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
100 ≈ 61
14 3
G 1/2A
SW 27 SW 27 ∅ 49
∅ 9.5
Guide tube
Protective tube
≈ 33
26.9-0.2
0
SW 17
!et t" D#$ 3%&'
Terminal head IP 65 M16 x 1.5
e(t)*e t+e,m"mete, - &1003
NL = Nominal length
EL = Installation length 73 ≈ 74
25 3
crimped in
SW 27 SW 18 SW 27
∅ 49
∅ 5.8
∅8
O-rings
≈ 33
∅ 26.9-0.2
Guide tube Adapter
G 1/2A
0 28
sprung
Measuring resistance screw connection
Pt 100 doubled SW 17
Housing
Terminal head
≈5
Measuring tip
Anti-friction bearing
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
A B C D
a) Insert guide tube ”A” into hole in housing until the measuring tip of the resistance thermometer makes
contact.
b) Screw screw connection ”B” into the housing as far as it will go.
c) Pull out screw connection ”C” approx. 5 mm towards the terminal head. Then lock nut ”D” with screw
connection ”C”. This ensures that the pretensioned spring keeps the measuring tip permanently in contact
with the part to be measured.
FLUTEC
Fluid Level Gauge
Fluid Level Sensor
Temperature Switch
FSA / FSK / TSE
up to size 381
up to PN 1 bar
up to T = 80 °C
1. DESCRIPTION 1.2. FUNCTION OF THE FSA 1.3. APPLICATION
1.1. GENERAL By using a FLUTEC FSA, the fluid FLUTEC fluid level gauges FSA,
level can be easily seen on the fluid level sensors FSK and
FLUTEC fluid level gauges FSA, outside of the tank. The fluid temperature switches TSE are
fluid level sensors FSK and enters the unit via the lower used to monitor and control levels
temperature switches TSE are connection bore and is clearly of operating fluid.
units which serve to monitor and visible in the tube. Selection of
control the level of operating fluid. Areas of application are
the correct size allows the for example:
The flexible product range means respective level of the fluid to be
that many combinations are Machine tools, system
monitored.
possible: engineering, hydraulic oil,
FUNCTION OF THE FSK lubricating oil and cutting oil tanks
– FSA: five sizes. By using a FLUTEC FSK, the fluid as well as gearboxes.
Visual thermometer with level is monitored via an electrical 1.4. NOTES
°C and °F scale. switching signal. This switching
signal can be used as an warning The upper viscosity limit is
Temperature gauge which records 2,000 mm²/s.
the temperature of the operating message or to regulate the fluid
fluid in the tank; display in °C. level. The fluid enters the unit via It is not possible to combine a
Dual scale in °C and °F is the lower connection bore and temperature switch TSE with an
available on request. pushes up a float in the tube. The FT temperature gauge.
float now shows the level of the FSA/FSK
Simple, standardised mounting
fluid in the tank. If the level of Not suitable for use with glycol or
conditions (FSA/K).
fluid drops again, the float fluids containing glycol.
– FSK: four sizes. activates a switching contact. To ensure correct functioning,
Switching contact can be either On type C the circuit is then pressure, viscosity and
type O (opens when fluid is at low closed and on type O the circuit temperature specifications must
level) or type C (closes when is then open. be observed.
fluid is at low level) or type W
The special dual switching model FSK
(dual switching unit)
(type W) offers two possibilities. Depending on the fluid level of the
Temperature gauge which records It can either be used to close on tank the following switching logic
the temperature of the operating contact or to open on contact. applies.
fluid in the tank; display in °C.
FUNCTION OF THE TSE
Dual scale in °C and °F is
available on request. The FLUTEC TSE is a very useful
additional option to the FSA and
Simple, standardised mounting Tank fluid level
FSK products. However, it also
conditions (FSA/K).
has a useful application as a
– TSE: three nominal temperatures separate build-on unit on
possible: 60 °C, 70 °C and 80 °C. systems.
Can be easily fitted into the FSA The temperature sensor of the
and FSK. (opens on
TSE, when fitted, is surrounded
contact)
Simple, standardised mounting by operating fluid. When the
conditions (FSA/K). nominal temperature is reached,
Non-corroding surfaces. a contact opens and the circuit is
broken. Tank fluid level
2
2. TECHNICAL 2.1.2 Model code for FSA
SPECIFICATIONS (also order example)
2.1. GENERAL FSA - 076 - 2 . X / FT200 / 12
2.1.1 Designation and symbol
Fluid level gauge
Fluid level gauge FSA
Size
@ centre distance of bolts
076
127
176
254
381
Material of seals
2 = Viton (FKM)
1 = Perbunan (NBR)
Series
(determined by manufacturer)
Additional thermometer function
Fluid level sensor FSK
= no additional function
T = thermometer in display tube
FT 200 = temperature gauge 200 mm
FT 300 = temperature gauge 300 mm
TSE 60 = temperature switch nominal temperature 60 °C
TSE 70 = temperature switch nominal temperature 70 °C
TSE 80 = temperature switch nominal temperature 80 °C
Mounting
O - N/C contact
Banjo bolt thread
M 12 (standard)
M 10 (not on TSE)
3
2.1.4 Type of construction
Model code for TSE
The units are designed to be
(also order example)
mounted directly on to the
TSE - 70 / X / 12 operating fluid tank.
2.1.5 Type of connection
Temperature switch FSA / FSK
TSE (with earth connection) The unit is mounted using two
banjo bolts. The connection
Nominal temperature
bores can either be threaded
60 °C
holes or clearance holes
70 °C
(Ø 13, Ø 11).
80 °C
TSE
Series The temperature switch can be
(determined by manufacturer) fitted to the FSA / FSK in place
of the lower banjo bolt.
Banjo bolt thread
M 12 2.1.6 Mounting position
FSA vertically
on the tank wall
2.1.3 Standard models FSK vertically
Type Size Order no. = Weight on the tank wall
@ centre distance of bolts stock no. [kg] (connection plug at
the bottom of the tank)
FSA-076-1.X/-/12 076 700 000 0.17
TSE optional
FSA-076-2.X/-/12 076 700 002 0.17
2.1.7 Weight
FSA-127-1.X/-/12 127 700 036 0.19 (See table 2.1.3)
FSA-127-2.X/-/12 127 700 038 0.19
2.1.8 Flow direction
FSA-254-1.X/-/12 254 700 072 0.22 Optional
FSA-254-2.X/-/12 254 700 074 0.22 2.1.9 Ambient temperature
FSK-127-2.X/C/-/12 127 718 030 0.22 - 20 °C to + 80 °C
FSK-127-2.X/O/-/12 127 718 031 0.22 2.1.10 Materials
FSK-254-2.X/C/-/12 254 718 050 0.28 FSA / FSK
FSK-254-2.X/O/-/12 254 718 051 0.28 End caps and tube in high quality
TSE-60/X/12 703 724 0.11 synthetic material
TSE-70/X/12 703 714 0.11 Housing in aluminium
TSE-80/X/12 551 481 0.11 Soft seals in Viton (FKM) or
Perbunan (NBR)
FT 200 0 - 100 °C / M12 200 700 154 0.03
Bolts, nuts and washers in steel
FT 300 0 - 100 °C / M12 300 700 155 0.04 (plated)
Plug connections in high quality
synthetic material (FSK)
TSE
Housing with temperature sensor,
washer and nut in steel
(zinc-plated)
Plug connections in high quality
synthetic material
4
2.2. HYDRAULIC DETAILS
2.3. ELECTRICAL DETAILS 2.4. ELECTRICAL DETAILS
2.2.1 Nominal pressure OF FSK OF TSE
Max. 1 bar
2.3.1 Electrical functions 2.4.1 Electrical function
2.2.2 Operating fluids
Mineral oil to DIN 51524, Part 1 Type O opens on contact
and 2, water-oil emulsions and when fluid is at low level,
synthetic fluids, such as hydraulic contact opens
fluids based on phosphate ester when supplied, contact is open
(NOT water glycol).
For other fluids, please contact
our technical sales department.
2.2.3 Temperature of operating fluid
- 20 °C to + 80 °C
2.2.4 Scale range of thermometer
FSA / FSK
Thermometer T for FSA: when fluid is at working level,
+ 20 °C to + 80 °C contact is closed 2.4.2 Switching power
2.5 A/50 V -
Thermometer FT for FSA / FSK:
0 °C to + 100 °C 10,000 switching operations
0.5 A/50 V -
100,000 switching operations
2.4.3 Minimum switching current
50 mA
2.4.4 Switching tolerance
Terminal 3 is not connected
±5K
Type C
when fluid is at low level,
contact closes
when supplied, contact is closed
tank bore
SW18, 16
torque rating 10 +2 Nm
SW18, 16
torque rating 10 +2 Nm
SW 18
torque rating 10 +2 Nm
Size
≅ centre distance of bolts L0 L1 L2
076 108 34 76
127 159 76 127
176 208 125 176
254 286 203 254
381 413 330 381
6
3.2. FLUID LEVEL SENSOR FSK
tank bore
SW18, 16
torque rating 10 +2 Nm
Size
≅ centre distance of bolts L0 L2
127 201 127
176 250 176
254 328 254
381 455 381
7
3.3. SCALE RANGE FSA / FSK
sight glass
8
BA HEL.PAT.000 EN
Die technischen Daten entnehmen For the technical data, please refer Pou les données techniques,
Sie bitte der betreffenden to the list of equipment. veuillez consulter la list des
Geräteliste. appareils.
Heizkörper waagerecht montieren. Install heating element horizontally. Monter horizontalement l’élément de chauffage.
Flüssigkeit in den Behälter füllen und Pour liquid into the container until the level Remplir le réservoir de liquide et cela
zwar so weit, daß der Spiegel is at least 20 mm above the heating jusqu‘ à ce que le niveau soit au moins 20
wenigstens 20 mm oberhalb des element. Appropriate measures must be mm au-dessus de l’élément de chauffage.
Heizgerätes steht. Dieser Mindest- taken to assure that this minimum level is Ce niveau minimum de remplissage doit
flüssigkeitsstand ist durch geeignete maintained. être garanti par des mésures adéquates.
Maßnahmen sicherzustellen.
Für eine ausreichende Wärmeabgabe Please take care of a good heat emission. Il faut veiller à une transmission suffisante
muß gesorgt werden. de chaleur.
Der elektrische Anschluß erfolgt nach Connection according to wiring scheme. Le branchement èlectrique est effectué
Schaltbild. selon le schéma.
WS (AC) DS (3~)
Wechselstrom Drehstrom
single-phase three-phase
L1 L1 L2 L3
L2/N
Bei Verschmutzung empfiehlt es sich, The tube protection jacket has to be En cas de salissure, nous recommandons
den Heizkörper zu reinigen, damit eine cleaned from time to time in order to de nettoyer le radiateur pour garantir une
einwandfreie Wärmeabgabe warrant constant unrestraint heat emission. parfaite transmission de la chaleur.
gewährleistet ist.
Subject to change without notice • © Hans Turck GmbH & Co.KG 2002 • Edition:
Hans Turck GmbH & Co.KG • Postfach • D-45466 Mülheim an der Ruhr • Telefon 02 08/49 52-0 • Telefax 02 08/49 52-264
Inductive sensor
Bi5-G18-Y1
4
BN
+
BU
Function principles
Inductive proximity switches are designed
Type Bi5-G18-Y1 for wear-free non-contact detection of me-
Ident-No. 10060 tal objects. For this they use a high-fre-
quency electro-magnetic AC field that
Rated operating distance Sn 5 mm interacts with the target. With inductive
Mounting mode flush sensors, this field is generated by an LC re-
Hysteresis (switching distance) 1... 10 % sonant circuit with a ferrite core coil.
Min. repeat accuracy ≤2 %
Temperature drift ≤ ± 10 %
Operating temperature -25 ...+ 70 °C
Subject to change without notice • © Hans Turck GmbH & Co.KG 2002 • Edition: • 15.04.2004
Hans Turck GmbH & Co.KG • Postfach • D-45466 Mülheim an der Ruhr • Telefon 02 08/49 52-0 • Telefax 02 08/49 52-264
Bauart B3FH Seite
Ersatzteilliste (EL) Type Page
Spare parts list Größe 28,0 1/1
Size
Übersetzung 22,432
ratio
Bei Korrespondenz bitte angeben
Please quote in correspondence EL 4214492-040 DE/EN
Hierzu gehört Zeichnungs-Nr.
Please refer to DWG No. 6107299
Teil-Nr. Menge Benennung Zeichnungs-Nr. Material-Nr. Gw(kg)
Part No. No. off Description Drawings No. Ident no. Weight
Order No. = 5
7
. 6
+
2
1 3
4
Rev. Description Sh.
A A
B-Seite
B-Side
150
B B
+TB01
C C
300
C-Seite D-Seite
C-Side D-Side
D D
Verschlußstopfen / Plugs
M12
A-Seite
M16 A-Side
2 M20
2 M25
1:2
M32
A A
B-Seite
B-Side
150
B B
+TB02
C C
300
C-Seite D-Seite
C-Side D-Side
D D
Verschlußstopfen / Plugs
M12
A-Seite
M16 A-Side
M20
1 M25
1:2
M32
A A
B B
C C
PE PE
D D
RD RD WH WH RD RD WH WH RD RD WH WH 2 4 1 2 4 1 PE 1 2 3 PE
-B801.1 -B801.2 -B802.1 -B802.2 -B804.1 -B804.2 -S803.1 -S803.2 -S821
Q
A A
B B
-X63 1 2 3 4 PE -X53 1 2
+EXT +EXT
C C
-X63 1 2 3 4 PE -X53 1 2
D D
1 2 3 4 PE 5 6 7 PE 8 9 10 11 12 13 14 +BN -BU
-B800 -B1
PMC / 440S
NAMUR
E E
Schwingungsmessung Näherungsschalter
Vibration measurement Proximity switch
F Date
30.06.06 120-CV-005-21 Order No. F
TBK
Drawn
Überwachung 6 123 673 +TB01
c revised 19.10.06 TBK Checked TBK 120-CV-006-21 Klemmenplan - Getriebe B3FH 2
Rev Description Date Name Norm DIN Made from In exchange for exchanged thru
Monitoring Terminal diagram - Gearbox B3FH STR 3 Sh.
1 2 3 4 5 6 7 8
3
CAD-DRAWING TO BE MODIFIED ON THE MONITOR ONLY THIS TECHNICAL DOCUMENT IS REGISTERED (DIN 34)
1 2 3 4 5 6 7 8
A A
B B
-X13 L1 L2 L3 PE
+EXT
C C
PE PE PE PE PE PE
D D
L1 N PE L1 N PE L1 N PE L1 N PE L1 N PE L1 N PE
-E883/1 -E883/2 -E883/3 -E883/4 -E883/5 -E883/6
E 230V / 50Hz 230V / 50Hz 230V / 50Hz 230V / 50Hz 230V / 50Hz 230V / 50Hz E
1215W 1215W 1215W 1215W 1215W 1215W
= + - : max. STR = + - :
+EXT -X53 1 UK5N 1 4.0 STR/2.3 +TB01 -B1 +BN
+EXT -X53 2 UK5N 2 4.0 STR/2.4 +TB01 -B1 -BU
USLKG 5 3 4.0 R
B B
C C
D D
E E
= + - : max. STR = + - :
+EXT -X63 1 UK5N 1 4.0 STR/2.1 +TB01 -B800 1
+EXT -X63 2 UK5N 2 4.0 STR/2.1 +TB01 -B800 2
+EXT -X63 3 UK5N 3 4.0 STR/2.1 +TB01 -B800 3
+EXT -X63 4 UK5N 4 4.0 STR/2.2 +TB01 -B800 4
B B
+EXT -X63 PE USLKG 5 PE 4.0 STR/2.2 +TB01 -B800 PE
C C
D D
E E
= + - : max. STR = + - :
+EXT -X73 1 UK5N 1 4.0 STR/1.1 +TB01 -B801.1 RD
+EXT -X73 2 UK5N 2 4.0 STR/1.1 +TB01 -B801.1 RD
UK5N 3 4.0 STR/1.2 +TB01 -B801.2 WH
UK5N 4 4.0 STR/1.2 +TB01 -B801.2 WH
B B
+EXT -X73 5 UK5N 5 4.0 STR/1.3 +TB01 -B802.1 RD
+EXT -X73 6 UK5N 6 4.0 STR/1.3 +TB01 -B802.1 RD
UK5N 7 4.0 STR/1.3 +TB01 -B802.2 WH
UK5N 8 4.0 STR/1.4 +TB01 -B802.2 WH
+EXT -X73 9 UK5N 9 4.0 STR/1.4 +TB01 -B804.1 RD
+EXT -X73 10 UK5N 10 4.0 STR/1.5 +TB01 -B804.1 RD
UK5N 11 4.0 STR/1.5 +TB01 -B804.2 WH
UK5N 12 4.0 STR/1.5 +TB01 -B804.2 WH
USLKG 5 13 4.0 R
C C
D D
E E
= + - : max. STR = + - :
+EXT -X93 1 UK5N 1 4.0 STR/1.6 +TB01 -S803.1 2
+EXT -X93 2 UK5N 2 4.0 STR/1.6 +TB01 -S803.1 4
+EXT -X93 3 UK5N 3 4.0 STR/1.6 +TB01 -S803.1 1
UK5N 4 4.0 STR/1.7 +TB01 -S803.2 2
B B
UK5N 5 4.0 STR/1.7 +TB01 -S803.2 4
UK5N 6 4.0 STR/1.7 +TB01 -S803.2 1
USLKG 5 7 4.0 STR/1.7 +TB01 -S803.2 PE
+EXT -X93 8 UK5N 8 4.0 STR/1.8 +TB01 -S821 1
+EXT -X93 9 UK5N 9 4.0 STR/1.8 +TB01 -S821 2
+EXT -X93 10 UK5N 10 4.0 STR/1.8 +TB01 -S821 3
+EXT -X93 11 USLKG 5 11 4.0 STR/1.8 +TB01 -S821 PE
C C
D D
E E
= + - : max. STR = + - :
+EXT -X13 L1 UK5N 1 4.0 STR/3.1 +TB02 -E883/1 L1
UK5N 1 4.0 STR/3.4 +TB02 -E883/4 L1
+EXT -X13 L2 UK5N 2 4.0 STR/3.2 +TB02 -E883/2 L1
UK5N 2 4.0 STR/3.5 +TB02 -E883/5 L1
B B
+EXT -X13 L3 UK5N 3 4.0 STR/3.3 +TB02 -E883/3 L1
UK5N 3 4.0 STR/3.5 +TB02 -E883/6 L1
UK5N 4 4.0 STR/3.1 +TB02 -E883/1 N
UK5N 4 4.0 STR/3.2 +TB02 -E883/2 N
UK5N 4 4.0 STR/3.3 +TB02 -E883/3 N
USLKG 5 5 4.0 STR/3.1 +TB02 -E883/1 PE
USLKG 5 5 4.0 STR/3.2 +TB02 -E883/2 PE
+EXT -X13 PE USLKG 5 5 4.0 STR/3.3 +TB02 -E883/3 PE
UK5N 6 4.0 STR/3.4 +TB02 -E883/4 N
C UK5N 6 4.0 STR/3.5 +TB02 -E883/5 N C
UK5N 6 4.0 STR/3.5 +TB02 -E883/6 N
USLKG 5 7 4.0 STR/3.4 +TB02 -E883/4 PE
USLKG 5 7 4.0 STR/3.5 +TB02 -E883/5 PE
USLKG 5 7 4.0 STR/3.6 +TB02 -E883/6 PE
D D
E E
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
Contents
Type : OLGS
Size : 11
Contents
1. Introduction 2
3. Use as specified 2
4. Copyright 2
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
1. Introduction
The Operating Instructions must be read, understood in all respects and observed by those persons
who are responsible for use of the FLENDER product.
Only familiarization with the Operating Instructions will prevent malfunction of the product and ensure
trouble-free operation. It is important therefore that the persons actually responsible should be familiar
with theses Operating Instructions.
Careful study of these Operating Instructions before handling our product and before startup is essen-
tial, as we accept no liability for damage and malfunctions resulting from non-compliance of these
Operating Instructions.
Note: We reserve the right to amend these these Operating Instructions where rendered
necessary by improvement of the products.
The product is intended for the scope of application as specified in the Technical Data.
3. Use as specified
The product is designed only for the scope of application specified in the Technical Data.
Before the product is used outside the scope of use as specified by the contract, this must be agreed
with FLENDER, as otherwise the warranty will be invalidated.
4. Copyright
FLENDER AG
D-46393 Bocholt
Germany
Phone: 02871/92-0
Fax: 02871/92-2596
Contents
S Every person engaged in installation, dismantling and reassembly, startup, operation and mainte-
nance (inspection, servicing, repair) of the oil supply system MUST have read and understood the
complete Operating Instructions, in particular the ”Safety” Operating Instructions.
S The oil supply system is intended for the scope of application specified in the Technical Data.
Any usage over and above this will be considered as improper use. The manufacturer accepts no
liability for damage resulting therefrom; the risk will be borne solely by the user.
S Proper usage will also be taken to include observance of the installation, dismantling and reassembly,
startup, operating and maintenance instructions specified by the manufacturer.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
S The oil supply system may only be operated, serviced and repaired by authorized, trained and
suitable instructed personnel.
S Responsibility during installation, dismantling and reassembly, startup, operation and maintenance
must be clearly defined and observed, so that there is no confusion as to responsibility from the aspect
of safety.
S Screwed pipe connections, flanged joint and monitoring devices may be undone as long as the
system is under pressure. First, pumps have to be switched off, and aggregates under pressure have
to be released.
S Any mode of operation which adversely affects the safety of the oil supply system is to be prohibited.
S The operator is obliged to inform the user of the system immediately of any changes occurring in
the oil supply system which adversely affect its safety.
S The user is obliged at all times to operate the oil supply system only when it is in satisfactory condition.
S The user MUST ensure cleanliness and unimpeded view at the place of installation of the oil supply
system by means of suitable instructions and inspections.
S Unauthorized conversion and modifications which adversely affect the safety of the oil supply system
are NOT permitted.
S All work on the oil supply system MUST be carried out only when it is stationary.
S Before commencing work on the oil supply system, its drives and ancillary equipment MUST be
secured to prevent accidental switch-on.
S Before restarting after repairs, it should be checked that all safety devices are fitted.
S Safety devices may only be removed when stationary, with the oil supply system secured.
S The loadability of the lifting gear to be installed must be at least that of the heaviest component weight
(see Operating Instructions, ”Technical Data”).
S In ALL cases, operation of the oil supply system will be subject to the local safety and accident
prevention rules.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Contents
1. Packing 2
2. Extent of disassembly 2
3. Handling 2
4. Storage 2
5. Scope of supply 2
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
1. Packing
The type of packing will also be determined by the means of shipment. Packing will, unless specially
agreed by contract, comply with the HPE Packing Guide lines as specified by the Federal Association
for Wooden Materials, Pallets and Export Packing e.V. and by the German Machine Building Institutes.
The symbols appearing on the packing in accordance with DIN 55 402 Part 1 should be observed.
This side up Fragile Keep dry Protect Centre of Use no Sling here
goods from heat gravity hooks
2. Extent of disassembly
The oil supply system is shipped in assembled state.
(Weight see section 1 ”Technical Data”)
3. Handling
Special care should be exercised when handling the oil supply system to
prevent damage due to the effect of force or careless loading and unloading.
Ropes or chains are to be used for handling the oil supply system. Attach only to the base frame or the
oil container. Ensure that the ropes do not damage fittings and oil lines. A lifting beam will therefore be
necessary for protection. The lengths of the ropes should be such that the base frame or the oil contai-
ner is suspended horizontally.
4. Storage
When the shipping packing is removed, the oil supply system must be stored on site in a clean, dry area.
The oil supply system is to be properly covered to prevent penetration of dust and moisture.
It must be ensured that temperature fluctuations in the place of storage do not lead to condensation
forming in the oil supply system.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
5. Scope of supply
The contents of the packages are listed in the package list. Check for completeness on receipt. Any
shipping damage and/or missing parts are to be reported immediately in writing. After consultation with
FLENDER AG, an expert should be called in.
Contents
1. General configuration 2
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
1. General configuration
The oil supply system described below is used for oil cooling and/or lubrication of a gear unit (see
Section 1 ”Technical Data”).
The oil supply system has been subjected to an exhaustive trial run in conjunction with the gear unit
and tested in accordance with the order data.
The pump draws the oil via a suction line from the pump sump of the gear unit.
A filter is provided in the oil circuit for filtration of the circulating oil.
The quantity of heat generated by losses, which is not dissipatable by convection, is dissipated by
means of a cooler.
Filtered and recooled oil is then passed back to the gear unit via a pressure line.
The modules described above are mounted on a base frame.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Contents
1. General Notes 2
2. Installation conditions 2
3. Installation 2
4. Final operations 3
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
1. General Notes
We earnestly recommend having installation of the oil supply system carried out by Flender personnel.
No liability is accepted for damage incurred as a result of improper execution by third parties.
2. Installation conditions
When planning space layout (e.g. planning carried out by customer), ensure that there is sufficient
space around the oil supply system to permit unimpeded assembly and repair work. Machines installed
upstream and downstream of the oil supply system should be located accordingly.
The load carrying capacity of hoists to be installed and used must at least be
adequate for the data of the oil supply system; see Section 1 ”Technical Data”.
Installation of the oil supply system must be carried out on a level, firm and rigid foundation. Ensure
that the oil can be drained off and that there is sufficient air supply for the motors. The valves and
wearing parts must be readily accessible and permit easy inspection.
The permissible deviation of the installation surface of the oil supply system from the horizontal is
2 mm/1 m (0.08”/40”); if necessary, shims should be used.
3. Installation
For handling of the oil supply system, see Section 4 ”Handling and Storage”.
Packing and shipping protection devices should be removed before installation. Carry out a visual
check for shipping damage and contamination. In the case of shipping damage, see Section 4 ”Handling
and Storage”.
All preserved flange surfaces should be cleaned with a solvent, e.g. benzine.
Customer supplied pipe fastenings (plastic clips) should be used for pipe connection. The distance
between 2 clips must be less than 2 m / 78.7”.
Electrical connections of motors and monitors should be carried out in accordance with terminal
drawings, equipment lists and specifications. Check voltage and circuits.
The sealing plugs and wooden flanges should be removed and the pipe fit tings supplied loose installed
in the system in accordance with lubrication diagram and drawings (see Section 1 ”Technical Data”).
Parts supplied loose with threaded connection should be sealed with Loctite 572 after thorough
cleaning.
To secure the system, use screws in accordance with the dimensioned drawing (see Section 1
”Technical Data”) and tighten with the torque specified by the screw manufacturer. Holding-down bolts
with metric thread in accordance with DIN 13 Sheet 20 in Strength Class 8.8 in accordance with DIN 267
should be used.
4. Final operations
After installing the oil supply system, all visible screw fastenings should be checked for tightness and
tightened if necessary.
Fit all safety devices necessary !
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Contents
2. Oil pump 2
3. Oil cooler 2
4. Startup 3
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
The following provisions are recommendations based on long years of experience. They are given
however without any responsibility on the part of the gear unit manufacturer. Responsibility for the oil
grade lies with the manufacturer of the oil and the operator of the system has to ensure satis factory
state of the oil grade (see Operating Instructions ”Gear unit”).
In all cases, before startup, the gear unit/oil supply system should be filled with oil (see Operating
Instructions ”Gear unit”). After filling, the filler openings should be properly reclosed and sealed.
Only oils in accordance with the specification should be used (see Operating Instructions ”Gear unit”).
Mixing oils of different manufacturers is NOT permissible.
To remove residues of preservatives which can lead to oil foaming, the oil supply system together with
the gear unit should be flushed before startup (see Operating Instructions ”Gear unit”).
The oil must then be drained carefully from the oil supply system, the monitors and the oil compartment
in the gear unit while it is hot. It may only be reused as flushing oil. If the flushing oil is to be used in
another system, it should first be carefully purified.
Fresh oil in accordance with the specification should be used for startup (see Operating Instructions
”Gear unit”).
Fill the oil supply system with oil in accordance with the Operating Instructions ”Gear unit” via the gear
unit resp. the oil container. Filling can be carried out with an auxiliary oil pump. Ensure that no dirt is
allowed to enter the oil circuit.
Fill until the specified oil level is reached on the oil level gauge with the pump stationary (see Operating
Instructions ”Gear unit”). The pump should then be started.
Before initial startup of the gear unit, the oil supply system must be run for at least 15 minutes to allow
all oil compartments to fill up (see Operating Instructions ”Gear unit”). Stop the oil supply system again
after wards and correct the oil level if necessary.
All pipes, screw unions and flanges should be tightened, this applying particularly to suction lines (to
prevent air being drawn into the system). Leaks should be resealed.
2. Oil pump
Oil pumps may only be run in one direction of rotation. The direction of
Caution!
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
rotation of motors must agree with the direction of rotation arrow on the pump.
3. Oil cooler
For the oil cooler, the customer / operator has to observe the space required for taking in the cooling
air in accordance with the assembly drawing (see Section 1 ”Technical Data”).
4. Startup
Before starting up the oil supply system, check that the requirements in accordance with these
Operating Instructions and the requirements in accordance with the gear unit Operating Instructions
have been fulfilled.
Before startup and after repairs and maintenance work, the oil supply system is to be cleaned
thoroughly to remove any impurities. This applies particularly to water (e.g. rain water and leakage of
the cooler) in order to prevent mixture of water and oil.
The works setting of the pressure relief valves/safety valves carried out by us
at our works may NOT be altered, as it is not used to regulate the pressure and
rate of flow. It is intended ONLY as overload protection!
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Contents
1. Operation 2
1.1 Lubrication diagram 2
1.2 Control information 2
1.3 Interlocking instructions 3
1.3.1 Fan motor 3
1.3.1 Pump enable 3
1.3.1 Gear unit enable 3
1.3.2 Warning 3
1.3.3 Gear unit stop 3
1.4 Response to malfunctions 4
1.5 Shut-down 4
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Section 8 BA 97 11 08 1004 EN
Operation Page 2 of 4
1. Operation
Filter (20)
The filter is monitored visually by means of a differential pressure indicator and electrically by means
of a differential pressure monitor.
Temperature control valve (32)
A temperature control valve is located in the by−pass of the cooler.
Pressure gauge (45)
The oil pressure is indicated visually by means of a pressure gauge.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Section 8 BA 97 11 08 1004 EN
Operation Page 3 of 4
General
A delay time of 10 s is to be provided for the pressure transducer and the flow monitor.
After switching off the main drive the oil supply system must continue to run until the drive has come
to a complete standstill.
FAN MOTOR OFF takes place when the following condition is fulfilled:
ENABLE GEAR UNIT takes place when all the following conditions are fulfilled:
1.3.4 Warning
GEAR UNIT STOP takes place when at least one of the following conditions is fulfilled:
If, when GEAR UNIT STOP occurs, the oil temperature is > switch point (65.4), the pump must be set
to remain on up to an oil temperature < switch point (65.3).
Section 8 BA 97 11 08 1004 EN
Operation Page 4 of 4
Monitoring during operation is essential to duly identify any malfunctions occurring (see Section 9,
”Disturbances, reasons and remedy”) and thus to implement preventive measures. The operating
pressures and oil temperatures should be recorded regularly.
If irregularities at variance with the normal condition are noticed during operation, or if the operating data
change, it is essential that the cause be identified immediately. If necessary, shut the system off. If the
causes cannot be identified, even with the aid of the Troubleshooting List, FLENDER should be
informed at once (see Section 11, ”Stocking spare parts, customer service addresses”).
For restart after malfunction, the information in Section 7, ”Start-up”, must be observed.
1.5 Shut-down
If the gear unit and oil supply system are shut down for longer periods, the following measures are
necessary:
a) Gear unit and oil supply system must remain filled with oil. Every 4 weeks gear unit and oil supply
system must be run for 1 hour. The necessary prelubrication and lubrication times should be
observed.
b) If the measures listed under a) are not possible, the gear unit and the oil supply system must be
preserved.
Recommended preservative agent:
For storage periods longer than 24 months the oil supply system must be re-preserved.
Preservation time up to 36 months: TRIBOL 1390 special anti-corrosion oil when using PAO-based
synthetic oil.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
If the oil supply system is shut down for a longer period or if there is a danger of freezing, the cooling
water must be drained off.
Contents
1. General 2
2. Possible malfunctions 2
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
1. General
The malfunctions listed below are only intended as points of reference for troubleshooting. With such
a complex system, all other modules must always be included in troubleshooting. If the cause of the
malfunction is not clear, we recommend therefore that the specialist personnel of FLENDER be
consulted in tracing possible causes.
2. Possible malfunctions
Lubricating oil pressure too Gear unit not yet warmed up to Wait
high operating temperature
Contents
1. Safety 2
2. Oils 2
3. Oil pump 2
4. Filter 2
5. Oil cooler 2
6. Preservation 2
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
1. Safety
During maintenance and inspection, Section 3 ”Safety” and Section 8 ”Operation” should be observed.
2. Oils
Oil grades and necessary oil change intervals will be found in the ”Gear unit” Operating Instructions
Section 10.
3. Oil pump
The special Operating Instructions of our supplier should be observed for the oil pump(s) (see
Section 12 ”Appendix”).
4. Filter
The special Operating Instructions of our supplier should be observed for the filters (see Section 12
”Appendix”).
5. Oil cooler
The special Operating Instructions of our supplier should be observed for the oil coolers (see Section 12
”Appendix).
6. Preservation
Contents
A stock of the most important replacement and wearing parts is essential for satisfactory operation and
serviceability of the gear unit at all times.
Please use the Spare Parts List for ordering spare parts.
For further information, see the Spare Parts Drawing contained in the Spare Parts List.
Please note that special production and supply specifications frequently exist for individual components
and that we always supply replacement parts in accordance with the state of the art and the latest legal
requirements.
The following data should be stated when ordering replacement parts:
Order No.
Part No.
Quantity
Please use the addresses listed below when ordering replacement parts or requesting a service fitter,
please refer to Section 12 ”Appendix”.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
We hereby declare that the products supplied by us are meant for being installed in
a machine and that their putting into operation is prohibited until it has been
ascertained that the machine, in which these components will be installed,
corresponds to the regulations of the EC guideline (original version 98/37/EC incl. the
further amendments).
Bocholt, 2004-04-06
Date Signature (Director HDE Engineering)
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
A. FRIEDR. FLENDER AG
Tel.: (0 81 31) 90 03 - 0 ksc.sued@flender.com
Kundenservice Center Süd Liebigstraße 14 85757 Karlsfeld
Fax: (0 81 31) 90 03 - 33 www.flender.com
(Außenstelle München)
A. FRIEDR. FLENDER AG
Tel.: (0 30) 91 42 50 58 ksc.ost@flender.com
Kundenservice Center Schlossallee 8 13156 Berlin
Fax: (0 30) 47 48 79 30 www.flender.com
Ost / Osteuropa
flender.guss@flender-
A. FRIEDR. FLENDER AG Obere Hauptstraße 09228 Chemnitz / Tel.: (0 37 22) 64 - 0
guss.com
FLENDER GUSS 228 - 230 Wittgensdorf Fax: (0 37 22) 94 - 1 38
www.flender-guss.de
sales-motox@flender-
Bahnhofstraße 40 - 44 Postfach 1709 Tel.: (0 70 71) 7 07 - 0
FLENDER TÜBINGEN GMBH motox.com
72072 Tübingen 72007 Tübingen Fax: (0 70 71) 7 07 - 4 00
www.flender.com
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
A. FRIEDR. FLENDER AG
Am Industriepark 2 Postfach 201160 Tel.: (0 28 71) 92 - 22 10 infos@flender-service.com
FLENDER SERVICE
46562 Voerde 46553 Voerde Fax: (0 28 71) 92 - 13 47 www.flender-service.com
INTERNATIONAL
Werk Herne
Postfach 101720 Tel.: (0 23 23) 9 40 - 0
Südstraße 111
44607 Herne Fax: (0 23 23) 9 40 - 3 33 infos@flender-service.com
44625 Herne
www.flender service.com
www.flender-service.com
Vertriebsbüro Penig
Postfach 44 / 45 Tel.: (03 73 81) 61 - 5 20 infos@flender-service.com
Thierbacher Straße 24
09320 Penig Fax: (03 73 81) 61 - 4 88 www.flender-service.com
09322 Penig
BA 73 00 12 0010 EN
Service facility addresses Page 2 of 5
EUROPE
Industriezentrum Nö-Süd
Phone: +43 (0) 22 36 - 6 45 70 office@flender.at
AUSTRIA Flender Ges.m.b.H. Strasse 4, Objekt 14 2355 Wiener Neudorf
Fax: +43 (0) 22 36 - 6 45 70 10 www.flender.at
Postfach 132
BELGIUM & Phone: +32 (0) 2 - 2 53 10 30
N.V. Flender Belge S.A. Cyriel Buyssestraat 130 1800 Vilvoorde sales@flender.be
LUXEMBOURG Fax: +32 (0) 2 - 2 53 09 66
Phone: +359 (0) 2 - 9 80 66 06
BULGARIA Auto-Profi N GmbH 52, Alabin Str. 1000 Sofia flender@auto-profi.com
Fax: +359 (0) 2 - 9 80 33 01
CROATIA / SLOVENIA Phone: +385 (0) 1 - 2 30 60 25
BOSNIA- HUM - Naklada d.o.o. Mandroviceva 3 a 10 000 Zagreb flender@hi.htnet.hr
Fax: +385 (0) 1 - 2 30 60 24
HERZEGOVINA
Branch Office Phone: +420 315 - 62 12 20
CZECH REPUBLIC A. Friedr. Flender AG 27 601 Melnik info-cz@flender.com
Fibichova 218 Fax: +420 315 - 62 12 22
kontakt@
Phone: +45 - 70 22 60 03
DENMARK Flender Scandinavia A/S Rugmarken 35 B 3520 Farum flenderscandinavia.com
Fax: +45 - 44 99 16 62
www.flenderscandinavia.com
ESTHONIA / LATVIA Addinol Mineralöl 11 415 Tallinn Phone: +372 (0) 6 - 27 99 99 flender@addinol.ee
Suur-Söjamäe 32
LITHUANIA Marketing OÜ (Esthonia) Fax: +372 (0) 6 - 27 99 90 www.addinol.ee
Phone: +358 (0) 9 - 4 77 84 10 webmaster@flender.fi
FINLAND Flender Oy Ruosilantie 2 B 00 390 Helsinki
Fax: +358 (0) 9 - 4 36 14 10 www.flender.fi
Head Office 78 996 Elancourt Phone: +33 (0) 1 - 30 66 39 00
FRANCE Flender S.a.r.l. sales@flender.fr
3, rue Jean Monnet - B.P. 5 Cedex Fax: +33 (0) 1 - 30 66 35 13
Sales Office
69 230 Saint Genis Phone: +33 (0) 4 - 72 83 95 20
Flender S.a.r.l Agence de Lyon sales@flender.fr
Laval Fax: +33 (0) 4 - 72 83 95 39
Parc Inopolis, Route de Vourles
1, rue du Vieux Moulin 67 400 Illkirch -
Graffenstaden Phone: +33 (0) 3 - 88 67 60 00
FRANCE Flender-Graffenstaden SA flencomm@flender-graff.com
B.P. 84 67 402 Illkirch - Fax: +33 (0) 3 - 88 67 06 17
Graffenstaden
Phone: +30 210 - 2 91 72 80
GREECE Flender Hellas Ltd. 2, Delfon str. 11 146 Athens flender@otenet.gr
Fax: +30 210 - 2 91 71 02
Phone: +36 (0) 1 - 3 45 07 90 flender@monornet.hu
HUNGARY Wentech Kft. Bécsi Út 3 - 5 1023 Budapest
Fax: +36 (0) 1 - 3 45 07 92 jambor.laszlo@axelero.hu
Parco Tecnologico Manzoni
Phone: +39 (0) 02 - 95 96 31
ITALY Flender Cigala S.p.A. Palazzina G 20 040 Caponago (MI) info@flendercigala.it
Fax: +39 (0) 02 - 95 74 39 30
Viale delle industrie, 17
Lage Brink 5 - 7 7317 BD Apeldoorn Phone: +31 (0) 55 - 5 27 50 00 sales@flender.nl
THE NETHERLANDS Flender Nederland B.V.
Postbus 1073 7301 BH Apeldoorn Fax: +31 (0) 55 - 5 21 80 11 www.flender.nl
Boterdiep 37 3077 AW Rotterdam Phone: +31 (0) 10 - 4 97 08 08 info@bruinhof.nl
THE NETHERLANDS Bruinhof B.V.
Postbus 9607 3007 AP Rotterdam Fax: +31 (0) 10 - 4 82 43 50 www.bruinhof.nl
kontakt@
Phone: +45 - 70 22 60 03
NORWAY Flender Scandinavia A/S Rugmarken 35 B 3520 Farum flenderscandinavia.com
Fax: +45 - 44 99 16 62
www.flenderscandinavia.com
Branch Office
Phone: +48 (0) 32 - 2 26 45 61 flender@pro.onet.pl
POLAND A. Friedr. Flender AG Przedstawicielstwo w Polsce 43 - 190 Mikolów
Fax: +48 (0) 32 - 2 26 45 62 www.flender.pl
ul. Wyzwolenia 27
Phone: +351 (0) 21 - 7 54 24 10
PORTUGAL Rodamientos FEYC, S.A R. Jaime Lopes Dias, 1668 CV 1750 - 124 Lissabon info@rfportugal.com
Fax: +351 (0) 21 - 7 54 24 19
B-dul Garii Obor nr. 8 D Phone: +40 (0) 21 - 2 52 98 61
ROMANIA CN Industrial Group srl 021 747 Bucuresti office@flender.ro
Sector 2 Fax: +40 (0) 21 - 2 52 98 60
Phone: +7 (0) 8 12 - 3 20 90 34
RUSSIA Flender OOO Tjuschina 4 - 6 191 119 St. Petersburg flendergus@mail.spbnit.ru
Fax: +7 (0) 8 12 - 3 20 90 82
Branch Office Phone: +421 (0) 51 - 7 70 32 67
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
BA 73 00 12 0010 EN
Service facility addresses Page 3 of 5
AFRICA
NORTH AFRICAN 78 996 Elancourt Phone: +33 (0) 1 - 30 66 39 00
Flender S.a.r.l. 3, rue Jean Monnet - B.P. 5 sales@flender.fr
COUNTRIES Cedex Fax: +33 (0) 1 - 30 66 35 13
Phone: +20 (0) 2 - 5 75 15 44
EGYPT Sons of Farid Hassanen 81 Matbaa Ahlia Street Boulac 11 221, Cairo hussein@sonfarid.com
Fax: +20 (0) 2 - 5 75 17 02
Head Office
Flender Power Phone: +27 (0) 11 - 5 71 20 00 sales@flender.co.za
SOUTH AFRICA Cnr. Furnace St & Quality Rd. Isando - Johannesburg
Transmission (Pty.) Ltd. Fax: +27 (0) 11 - 3 92 24 34 www.flender.co.za
P.O. Box 131 Isando 1600
Sales Offices
Flender Power Unit 3 Marconi Park, 9 Marconi Phone: +27 (0) 21 - 5 51 50 03
sales@flender.co.za
Transmission (Pty.) Ltd. Crescent, Montague Gardens, Cape Town Fax: +27 (0) 21 - 5 52 38 24
P.O. Box 37 291 Chempet 7442
Unit 3 Goshawk Park
Flender Power Phone: +27 (0) 31 - 7 05 38 92
Falcon Industrial Estate New Germany - Durban sales@flender.co.za
Transmission (Pty.) Ltd. Fax: +27 (0) 31 - 7 05 38 72
P.O. Box 1608 New Germany 3620
Flender Power 9 Industrial Crescent, Ext. 25 Witbank Phone: +27 (0) 13 - 6 92 34 38
sales@flender.co.za
Transmission (Pty.) Ltd. P.O. Box 17 609 Witbank 1035 Fax: +27 (0) 13 - 6 92 34 52
Unit 14 King Fisher Park, Alton
Flender Power Phone: +27 (0) 35 - 7 51 15 63
Cnr. Ceramic Curve & Alumina Richards Bay sales@flender.co.za
Transmission (Pty.) Ltd. Fax: +27 (0) 35 - 7 51 15 64
Allee, P.O. Box 101 995 Meerensee 3901
AMERICA
C 1067 ABN Phone: +54 (0) 11 - 43 31 66 10
ARGENTINA Chilicote S.A. Avda. Julio A. Roca 546 chilicote@chilicote.com.ar
Buenos Aires Fax: +54 (0) 11 - 43 31 42 78
Head Office
32 210 - 660 Phone: +55 (0) 31 - 33 69 20 00
BRASIL Flender Brasil Ltda. Rua Quatorze, 60 vendas@flenderbrasil.com
Contagem - MG Fax: +55 (0) 31 - 33 31 18 93
Cidade Industrial
Sales Offices
04 576 - 050 Phone: +55 (0) 11 - 55 05 99 33
Flender Brasil Ltda. Rua James Watt, 152 flesao@uol.com.br
São Paulo - SP Fax: +55 (0) 11 - 55 05 30 10
conjunto 142 - Brooklin Novo
Rua Campos Sales, 1095 14 015 - 110 Phone: +55 (0) 16 - 6 35 15 90
Flender Brasil Ltda. flender.ribpreto@uol.com.br
sala 14 - centro Ribeirão Preto - SP Fax: +55 (0) 16 - 6 35 11 05
Rua da Mitra - quadra 30 - lote16
65 075 - 770 Phone: +55 (0) 98 - 32 25 84 92
Flender Brasil Ltda. Edifício Cristal - sala 207 flenderslz@uol.com.br
São Luis - MA Fax: +55 (0) 98 - 32 25 84 93
Bairro Renascença
Rua Padre Anchieta, 1691 80 730 - 000 Phone: +55 (0) 41 - 3 36 28 49
Flender Brasil Ltda. quality.engineer@bol.com.br
conjunto 1110 - Bairro Bigorrilho Curitiba - PR Fax: +55 (0) 41 - 3 36 28 49
Rua José Alexandre Buaiz,
29 050 - 545 Phone: +55 (0) 27 - 32 24 37 35
Flender Brasil Ltda. 160 sala 1017 - Enseada do flender.vitoria@uol.com.br
Vitória - ES Fax: +55 (0) 27 - 32 24 37 36
Suá
Flender Power Markham Phone: +1 (0) 9 05 - 3 05 10 21 info@flenderpti.com
CANADA 215 Shields Court, Units 4 - 6
Transmission Inc. Ontario L3R 8V2 Fax: +1 (0) 9 05 - 3 05 10 23 www.flender.ca
CHILE / ARGENTINA
BOLIVIA / ECUADOR Phone: +56 (0) 2 - 2 35 32 49 flender@flender.cl
Flender Cono Sur Ltda. Avda. Galvarino Gallardo 1534 Providencia, Santiago
PARAGUAY Fax: +56 (0) 2 - 2 64 20 25 www.flender.cl
URUGUAY
Flender Liaison Office Colombia
A.G.P. Representaciones Phone: +57 (0) 1 - 5 70 63 53 aguerrero@agp.com.co
COLOMBIA Av Boyaca No. 23 A Bogotá
Ltda. Fax: +57 (0) 1 - 5 70 73 35 www.agp.com.co
50 Bodega UA 7 - 1
Flender de Mexico Head Office Phone: +52 (0) 2 22 - 2 37 19 00 szugasti@flendermexico.com
MEXICO 72 000 Puebla
S.A. de C.V. 17, Pte, 713 Centro Fax: +52 (0) 2 22 - 2 37 11 33 www.flendermexico.com
Sales Offices
Flender de Mexico Phone: +52 (0) 55 - 52 54 30 37
Lago Nargis No. 38 11 520 Mexico, D.F. info@flendermexico.com
S.A. de C.V. Fax: +52 (0) 55 - 55 31 69 39
Col. Granada
Flender de Mexico Ave. San Pedro No. 231 - 5 Phone: +52 (0) 81 - 83 63 82 82
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
BA 73 00 12 0010 EN
Service facility addresses Page 4 of 5
ASIA
BANGLADESH No. 2 St. George’s Gate Road Phone: +91 (0) 33 - 2 23 05 45
Flender Limited Kolkata - 700 022 flender@flenderindia.com
SRI LANKA 5th Floor, Hastings Fax: +91 (0) 33 - 2 23 18 57
Head Office
PEOPLE’S REPUBLIC Flender Power Trans- Shuanghu-Shuangchen Rd. Phone: +86 (0) 22 - 26 97 20 63 flender@flendertj.com
Tianjin 300 400
OF CHINA mission (Tianjin) Co., Ltd. West, Beichen Economic Fax: +86 (0) 22 - 26 97 20 61 www.flendertj.com
Development Area (BEDA)
Sales Offices
Flender Power Trans- C - 414, Lufthansa Center Phone: +86 (0) 10 - 64 62 21 51
Beijing 100 016 beijing@flenderprc.com.cn
mission (Tianjin) Co., Ltd. 50 Liangmaqiao Rd. Fax: +86 (0) 10 - 64 62 21 43
Chaoyang District
Flender Power Trans- 1101 - 1102 Harbour Ring Plaza Phone: +86 (0) 21 - 53 85 31 48 shanghai@
Shanghai 200 001
mission (Tianjin) Co., Ltd. 18 Xizang Zhong Rd. Fax: +86 (0) 21 - 53 85 31 46 flenderprc.com.cn
Flender Power Trans- Rm. 1503, Jianyin Building Phone: +86 (0) 27 - 85 48 67 15
Wuhan 430 015 wuhan@flenderprc.com.cn
mission (Tianjin) Co., Ltd. 709 Jianshedadao, Hankou Fax: +86 (0) 27 - 85 48 68 36
Rm. 2802, Guangzhou
Flender Power Trans- Phone: +86 (0) 20 - 87 32 60 42 guangzhou@
International Electronics Tower Guangzhou 510 095
mission (Tianjin) Co., Ltd. Fax: +86 (0) 20 - 87 32 60 45 flenderprc.com.cn
403 Huanshi Rd. East
Flender Power Trans- G - 6 / F Guoxin Mansion Phone: +86 (0) 28 - 86 19 83 72
Chengdu 610 015 chengdu@flenderprc.com.cn
mission (Tianjin) Co., Ltd. 77 Xiyu Street Fax: +86 (0) 28 - 86 19 88 10
Rm. 3 - 705, Tower D
Flender Power Trans- City Plaza Shenyang Phone: +86 (0) 24 - 23 34 20 48
Shenyang 110 001 shenyang@flenderprc.com.cn
mission (Tianjin) Co., Ltd. 206 Nanjing Street (N) Fax: +86 (0) 24 - 23 34 20 46
Heping District
Rm. 302, Shanzi Zhong Da
Flender Power Trans- Phone: +86 (0) 29 - 87 20 32 68
International Mansion Xi’an 710 002 xian@flenderprc.com.cn
mission (Tianjin) Co., Ltd. Fax: +86 (0) 29 - 87 20 32 04
30 Southern Rd.
Flender Power Trans- Rm. 23E, Xinhua Plaza, No. 6 Phone: +86 (0) 871 - 3 12 43 68
Kunming 650 051 kunming@flenderprc.com.cn
mission (Tianjin) Co., Ltd. Renmin East Rd. Fax: +86 (0) 871 - 3 12 45 66
Rm. 1007, Building A, Golden
Flender Power Trans- Phone: +86 (0) 371 - 5 38 80 85 zhengzhou@
Center, Jincheng International Zhengzhou 450 008
mission (Tianjin) Co., Ltd. Fax: +86 (0) 371 - 5 38 80 89 flenderprc.com.cn
Plaza, No. 68 Jingsan Rd.
Flender Power Trans- Rm. 908 (east), No. 188 Phone: +86 (0) 25 - 83 24 25 50
Nanjing 210 024 nanjing@flenderprc.com.cn
mission (Tianjin) Co., Ltd. Guangzhou Rd. Fax: +86 (0) 25 - 83 24 48 20
Rm. 1408, Pearl River
Flender Power Trans- Phone: +86 (0) 411 - 83 77 93 55
International Building No. 99 Dalian 116 011 dalian@flenderprc.com.cn
mission (Tianjin) Co., Ltd. Fax: +86 (0) 411 - 83 77 92 19
Xinkai Rd. Xigang District
Rm. 1401, Tianlin Building
Flender Power Trans- Hunan Gold Source Hotel Phone: +86 (0) 731 - 5 16 73 09 changsha@
Changsha 410 007
mission (Tianjin) Co., Ltd. No. 279, Second Block Fax: +86 (0) 731 - 5 16 47 46 flenderprc.com.cn
Furong Rd.
Head Office
Hastings Phone: +91 (0) 33 - 22 23 05 45
INDIA Flender Limited No. 2 St. George’s Gate Road flender@flenderindia.com
Kolkata - 700 022 Fax: +91 (0) 33 - 22 23 18 57
5th Floor
Industrial Growth Centre Nimpura Phone: +91 (0) 3222 - 23 33 07
Flender Limited works@flenderindia.com
Rakhajungle Kharagpur - 721 302 Fax: +91 (0) 3222 - 23 33 64
Eastern Regional Sales Office
Hastings Phone: +91 (0) 33 - 22 23 05 45
Flender Limited No. 2 St. George’s Gate Road ero@flenderindia.com
Kolkata - 700 022 Fax: +91 (0) 33 - 22 23 08 30
5th Floor
Western Regional Sales Office Vashi Phone: +91 (0) 22 - 27 65 72 27
Flender Limited wro@flenderindia.com
Plot No. 23, Sector 19 - C Navi Mumbai - 400 705 Fax: +91 (0) 22 - 27 65 72 28
Southern Regional Sales Office Aminjikarai Phone: +91 (0) 44 - 23 74 39 21
Flender Limited sro@flenderindia.com
41 Nelson Manickam Road Chennai - 600 029 Fax: +91 (0) 44 - 23 74 39 19
Northern Regional Sales Office
Phone: +91 (0) 11 - 51 85 96 56
Flender Limited 302 Bhikaji Cama Bhawan New Delhi - 110 066 nro@flenderindia.com
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
BA 73 00 12 0010 EN
Service facility addresses Page 5 of 5
Representative Office
47301 Petaling Jaya Phone: +60 (0) 3 - 78 80 42 63
MALAYSIA Flender Singapore Pte. Ltd. 37 A - 2, Jalan PJU 1/39 flender@tm.net.my
Selangor Darul Ehsan Fax: +60 (0) 3 - 78 80 42 73
Dataran Prima
Phone: +49 (0) 28 71 - 92 22 59
PAKISTAN A. Friedr. Flender AG Postfach 1364 46 393 Bocholt ludger.wittag@flender.com
Fax: +49 (0) 28 71 - 92 15 16
Representative Office
28 / F, Unit 2814, The Enter- Phone: +63 (0) 2 - 8 49 39 93
PHILIPPINES Flender Singapore Pte. Ltd. Makati City junt@flender.com.ph
prise Centre, 6766 Ayala Ave- Fax: +63 (0) 2 - 8 49 39 17
nue corner, Paeso de Roxas
BAHRAIN / IRAQ Flender Güc Aktarma Middle East Sales Office
LYBIA / JORDAN 34776 Dudullu - Phone: +90 (0) 2 16 - 4 99 66 23
Sistemleri Sanayi ve IMES Sanayi Sitesi meso@flendertr.com
OMAN / QATAR Istanbul Fax: +90 (0) 2 16 - 3 64 59 13
U.A.E. / YEMEN
Ticaret Ltd. Sti. E Blok 502, Sokak No. 22
AUSTRALIA
Head Office
Phone: +61 (0) 2 - 97 56 23 22 sales@flender.com.au
Flender (Australia) Pty. Ltd. 9 Nello Place, P.O. Box 6047 N.S.W. 2164, Sydney
Fax: +61 (0) 2 - 97 56 48 92 www.flender.com.au
Wetherill Park
Sales Offices
Phone: +61 (0) 3 - 95 57 08 11
Flender (Australia) Pty. Ltd. Suite 3, 261 Centre Rd. VIC 3204, Melbourne sales@flender.com.au
Fax: +61 (0) 3 - 95 57 08 22
Bentleigh
Suite 5, 1407 Logan Rd. Phone: +61 (0) 7 - 34 22 23 89
Flender (Australia) Pty. Ltd. QLD 4122, Brisbane sales@flender.com.au
Mt. Gravatt Fax: +61 (0) 7 - 34 22 24 03
Suite 2 W.A. 6104 Phone: +61 (0) 8 - 94 77 41 66
Flender (Australia) Pty. Ltd. sales@flender.com.au
403 Great Eastern Highway Redcliffe - Perth Fax: +61 (0) 8 - 94 77 65 11
9 Nello Place, P.O. Box 6047 Phone: +61 (0) 2 - 97 56 23 22
NEW ZEALAND Flender (Australia) Pty. Ltd. N.S.W. 2164, Sydney sales@flender.com.au
Wetherill Park Fax: +61 (0) 2 - 97 56 48 92
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
OPERATING MANUAL
Series B, R, SF, T
Postfach 1565
D-53762 Hennef
4 Technical description
4.1 General description
4.2 Construction and mode of operation
4.3 Mechanical construction
4.3.1 Pump casing
4.3.2 Gear wheels
4.3.3 Shafts, bearings and lubrication
4.3.4 Shaft seal
4.3.5 Drive
4.4 Accessories
4.4.1 Pressure relief valve
4.4.2 Heating and cooling units
5 Mounting / installation
5.1 Installation position
5.2 Mounting for the first time
5.3 Drive elements
5.3.1 Aligning flexible couplings
5.3.2 Coupling guard
5.4 Electrical connection
5.5 Pipes
5.5.1 Purging
5.5.2 Connecting pipes
5.5.3 Additional connections
5.5.4 Suction line
5.5.5 Delivery line
5.5.6 Pressure test and leakage test
5.6 Protection against foreign bodies
and contamination
or where electrical safety is involved, with 2.4 Compliance with regulations pertaining
to safety at work
It is imperative that signs affixed to the machine, - If hot or cold machine components involve
e.g. hazards, they must be guarded against
accidental contact on site.
- arrow indicating the direction of rotation
- Guards for moving parts (e.g. coupling) must
- symbols indicating fluid connections not be removed from the machine while in
operation.
be observed and kept legible.
- Any leakage of hazardous (e.g. explosive,
2.2 Qualification and training of operating toxic, hot) fluids (e.g. from the shaft seal) must
personnel be drained away so as to prevent any risk to
persons or the environment. Statutory regulations
The personnel responsible for operation, are to be complied with.
maintenance, inspection and assembly must be
adequately qualified. Scope of responsibility and - Hazards resulting from electricity are to be
supervision of the personnel must be exactly prevented (see for example, the VDE Specifica-
defined by the plant operator. If the staff do not tions and the bye-laws of the local power supply
have the necessary knowledge, they must be utilities).
trained and instructed, which may be performed by
the machine manufacturer or supplier on behalf of 2.6 Safety instructions relevant for mainte-
the plant operator. Moreover, the plant operator is nance, inspection and assembly work
to make sure that the contents of the Operating
Manual are fully understood by the personnel. It shall be the plant operator's responsibility to
ensure that all maintenance, inspection and
2.3 Hazards in the event of non-compliance assembly work is performed by authorised and
with the safety instructions qualified personnel who have adequately
familiarised themselves with the subject matter by
Non-compliance with the safety instructions may studying this Manual in detail.
produce a risk to the personnel as well as to the
environment and the machine and results in a loss Any work on the machine shall only be performed
of any right to claim damages. when it is at a standstill, it being imperative that the
procedure for shutting down of the machine
For example, non-compliance may involve the described in this Manual be followed.
following hazards: Pumps and pump units which convey hazardous
media must be decontaminated.
- Failure of important functions of the
machine/plant On completion of work all safety and protective
facilities must be re-installed and made operative
- Failure of specified procedures of maintenance again.
and repair
Prior to restarting the machine, the instructions
- Exposure of people to electrical, mechanical and listed under "Initial commissioning" are to be
chemical hazards observed.
The pump / the pump unit is packaged differently, The gear pump, being the most popular type of
depending on the transport route and size. The rotary, positive-displacement pump, owes its great
packaging complies with our general packaging popularity primarily to the sophisticated involute
guidelines unless otherwise contractually agreed. gearing which permits low-cost series production
When transporting the complete unit, the cables with high precision, besides its simple construction.
must be attached, as shown, to pump and motor Most gear pumps have straight-toothed spur gears.
(not to the eyebolt of the motor and pump). Certain types are fitted with helical-tooth spur gears
or with double-helical (herring-bone) gears in an
effort to achieve greater running smoothness.
When the gear wheels, which are surrounded by a gear wheels are designed as pinions. Materials,
casing or adapter on all sides, rotate, the tooth surface hardnesses, wear-resistant coatings and
spaces fill with the medium to be pumped as the gearing quality will depend on the customer's sales
result of the partial vacuum produced and convey it order.
outwards and around to the delivery end. Combing
of the gear wheels which are turning in opposite 4.3.3 Shafts, bearings and lubrication
directions forces the medium into the delivery line.
The delivery pressure produced by a pump builds The pump shafts are mounted in plain bearing
up in the delivery line depending on the resistances bushes. The bearing points must be adequately
opposing the delivery flow. These resistances result lubricated by the medium!
from pipe friction and the various installed fittings,
fixtures and devices. CAUTION The pump must always receive fluid
The power demand increases with increasing and may never be allowed to run dry!
delivery pressure!
The running play on the sliding surfaces is rated so
The pump may never be operated as to constantly guarantee an adequate lubrication
CAUTION with the suction or delivery line film.
closed! The lower the viscosity of a medium to be pumped,
the closer the running play must be kept in order to
achieve a favourable volumetric efficiency of the
pump. However, this also necessitates a purer
medium to be pumped in order to achieve high
Suction Delivery operating reliability and as long a pump service life
as possible.
The pump casing encloses the gear wheels and is On versions with axial face seal (G), this seal has
generally equipped with a suction and delivery only slight or invisible (vapour) leakage losses
connection for the pipes. during operation. It requires no maintenance.
Depending on the particular type, it also contains a
pressure relief valve and one side of the drive and No maintenance is required either on versions with
counter-shaft bearing assembly. rotary shaft seal (R).
In the case of the disk or plate design, the gear
wheels are enclosed by a so-called adapter which In the case of twin seals, such as GG or GR
has the shape of a plate, the thickness of which versions, a quench fluid recipient serves to
corresponds to approximately the length of the gear lubricate and cool the downstream seal. These seal
wheel. combinations serve to exclude air in the case of
The drive and counter-cover serves to media which react in an undesirable manner when
accommodate the shaft bearing. coming into contact with atmospheric oxygen.
The shaft seal is accommodated in the drive cover
or in a casing. 4.3.5 Drive
5.6 Protection against foreign bodies and CAUTION Foreign bodies endanger the opera-
contamination tional safety and reliability of the
pump and may lead to blockage or total failure.
A distinction is made between two types of Larger quantities of ultra-fine contamination will
contamination: cause abrasion wear on the sliding surfaces and
will reduce the service life of the pump.
1. Primary contamination
6 Starting up / shutting down
- Filling and feed pumps are exposed to foreign
bodies, dirt particles or mineral pigments which 6.1 Preparations for starting up
are located in the medium to be pumped.
Before starting up, inspect the pump installation in
- Pipe elements, in particular upstream of the order to establish that it is in proper working order
pump, may be contaminated with fine dirt as specified in the technical documentation.
particles such as metal swarf, welding or
soldering beads or abrasives etc. originating In the case of electric motor-driven pumps, the
from production or installation. electrical connections may be made only by a
(see also 5.5.1 Purging) qualified electrician.
Facilities for personal safety (e.g.
CAUTION contact guard on clutches and belts)
must be fitted.
Ensure that there is adequate medium in the pump In principle, the same procedure as that described
before initial commissioning. in Point 6.2 Initial commissioning must be noted in
Gear pumps are always self-priming pumps. Under this case.
normal circumstances, they may induct the air If the pump has been placed out of operation for a
present in the suction line and convey it into the long period, please check that there is still
delivery line. It is advisable to also fill the suction adequate fluid in the pump in order to ensure
line with the medium to be pumped before starting, reliable re-induction.
particularly in the case of extremely unfavourable
suction conditions, in order to prevent the pump CAUTION Check the mobility of the internal
running dry. components of the pump in the case
Fill the pump and, wherever possible, of media which could set (e.g. by turning the drive
CAUTION also the suction line with the fluid to shaft).
be pumped and then bleed.
Always avoid the pump running dry! CAUTION On no account may a cold pump be
Should there be shut-off elements in the suction or started up suddenly with a hot
delivery line, these elements must be opened fully. medium. The temperature of the pump must be
Fully open all additional connections provided, e.g. increased slowly in order to avoid seizing of the
for sealing or purging fluid etc., and check flow. pump as the result of thermal shock.
It is advisable to regularly check the performance The rotary shaft seal requires no maintenance
data. Integration of corresponding monitoring either. Should it leak, it must be renewed.
devices, such as operating hours counters,
pressure gauges, pressure and temperature 7.2.3 Twin seals
monitors etc., will depend on the requirements and
the relevant regulations. On twin seals and combined seals, the quench fluid
level in the recipient must be checked constantly
Please note the following points when carrying out and topped up if necessary.
maintenance work on the overall system:
7.2.4 Pressure relief valve
- Check that all securing screws, bolts and
connections are tight and retighten if necessary. Please follow the steps below should it be
necessary to regulate / adjust the opening pressure
- Check alignment of the coupling. Examine of the pressure relieve valve:
elastomers for wear.
- Unscrew the pressure cap and undo the lock nut.
- Check the pump for leaks, in particular the
shaft seals. - The required opening pressure can be set by
turning the threaded bushing / regulating screw
7.2 Shaft seal which is then accessible.
Turning clockwise: increases the opening
7.2.1 Stuffing box packing pressure.
Turning counter-clockwise: reduces the opening
The stuffing box gland nut may be tightened only pressure.
lightly so that the packing allows slight leakage Recommended values for pressure setting:
during operation, thus dissipating the frictional heat. approx. 10 % above the operating pressure /
working pressure of the system.
If the leakage rate is too high after a long operating
period, tighten the nuts on the stuffing box gland - Screw the pressure cap back on
uniformly by 1/6 of a turn. Then observe the leak- (do not forget the sealant).
age. If it is no longer possible to tighten the stuffing
box gland nut, you must fit an extra packing ring. It 7.3 Dismantling and re-assembly
is generally not necessary to replace the entire
7.3.1 Basic instructions
packing assembly.
Should it be necessary to renew the packing The unit must be safeguarded so that it cannot be
assembly nevertheless, also assess the condition switched on before starting dismantling work.
of the shaft bearing assembly and the seal seat. The shut-off elements in the supply and delivery
If there are signs of major scoring on the shaft, the line must be closed. The pump must have reached
shaft must be exchanged since, otherwise, this will ambient temperature.
impair sealing with new packing rings.
7.3.2 Dismantling the unit
The joints of the packing rings or cut ring sections
must be mutually offset by approx. 90°. 1. Disconnect the electrical power supply
The joint should be at the top on the last ring at the 2. Remove any fitted additional connections
gland end. 3.: Unit on sub-plate:
The packing rings must be carefully bent open both 3.1. Remove the coupling guard
axially and radially only sufficiently to permit them to 3.2. Disconnect the motor terminals
just be slid over the shaft. Detach the motor from the sub-plate
3.3. Disengage the pump and motor
7.2.2 Axial face seal / rotary shaft seal 3.4. by moving the motor's position
3.5. Detach the suction and delivery connection
Maintenance of the axial face seal is restricted to 3.6. Detach the pump from the sub-plate
occasionally checking for leaks. 4.: Unit with pump support / intermediate
Very slight leakage of the axial face seal is bracket:
permitted. 4.1. Disconnect the motor terminals
Should the leakage be higher than this, the axial 4.2. Detach the motor
face seal must be renewed. When doing this, also 4.3. Detach the suction and delivery connection
inspect the pump bearing assembly. 4.4. Detach the pump from the pump support /
intermediate bracket
7.3.3 Dismantling the pump at the position of the sealing edge on the old
ring.
Please refer to the various exploded views (if This can be achieved by:
available). - exchanging the shaft or shaft bushing
Identify the position of the pump components and - fitting with a spacer ring
number them consecutively! - pressing in to different depths in the location
1. Undo the casing bolts hole.
2. Release the counter-cover from the casing - Use a press-in tool and a suitable press-in die
using 2 forcing threads and hexagon when pressing in.
bolts - Make sure that you do not damage the sealing
3. Pull the counter-shaft with gear wheel out lip at sharp edges when sliding into the shaft!
of the pump casing - On smooth shafts, round off the keyways and
4. Release the safety catch on the coupling turned grooves. Fitted shafts should have a
half and detach it with an extractor tool conical bevel. If this is not possible, an
and then detach the feather key installation sleeve must be used to assist in
5. Version with packing: assembly.
5.1. Undo the gland stuffing box • Axial face seal
6. Direction of rotation-dependent axial face please refer to the special Installation Instructions
seal: and Operating Manual
6 1. Pull out the axial face seal • Pressure relief valve
7. Direction of rotation-independent axial please refer to Point 7.2.4
face seal:
(Please refer to the special Installation 7.4 Spare parts
Instructions and Operating Manual)
8. Version with single thrust bearing: Keeping a stock of the most important spare parts
8.1. Detach the bearing catch and parts subject to wear at the installation site is
9. Version with rotary shaft seal: an important precondition for ensuring that the
9.1. Detach the seal locating cover pump is always ready for operation.
10. Pull the drive shaft with gear wheel On the other hand, we recommend that you keep in
out of the pump casing stock a reserve pump and return the removed
11. On pumps with bearing components pump to our works for repair if necessary.
made of carbon / ceramic material,
always ensure that you take great care Please refer to our spare parts list with cutaway
when dismantling! view when ordering spare parts.
Use absolutely no force since these
components are fragile and could fracture. We are able to assume warranty only for original
spare parts supplied by us.
7.3.4 Assembling the pump / unit
It must be expressly pointed out that spare parts
Follow the generally valid rules applicable in the and accessories not supplied by us are not tested
field of mechanical engineering and machine cons- by us and are not approved by us. Installation
truction when re-assembling. and/or use of such products may thus impair design
O-rings must be inspected for damage and must be characteristics of the pump and thus endanger
replaced by new O-rings if necessary. active and/or passive safety. We are unable to ac-
cept liability and accept claims under warranty for
Flat gaskets must always be renewed. Ensure that damage and loss occurring as the result of using
the new gasket has precisely the same thickness non-original spare parts and accessories.
as the old gasket.
Hylomar SQ 32/M or Epple 33 for instance may be Please state the following information when sub-
used as permanently elastic universal seals. mitting orders for spare parts:
All seal and gasket residue must be removed
completely. When re-assembling, follow the re- - Contract No. / Serial No.
verse procedure to that followed when dismantling. - Part No.
• Stuffing box packing, see Point 7.2.1 - Quantity
• Rotary shaft seal
- Always use new rotary shaft seals. 8 Related documents
- Always ensure that they are fitted in the correct
position. Please refer to the technical data sheet or the sales
- The sealing edge of the new ring should not be order confirmation for the related documents.
2
09.02 DBA-DM01-E 1/1
Edition: May 1995
Operating Instructions
B 5921 EN
Double change-over filter Page 1 of 3
These operating instructions are binding for double change-over filters according to FLENDER works
standard W 5921.
Function
Double change-over filters are designed for continuous filtration. Normally, only one filter chamber is in
operation, the second filter chamber being held in reserve. As soon as the filter is clogged by increasing
contamination (see indicator contamination), changeover takes place to the second filter chamber.
Change-over of the liquid flow from one chamber to the other takes place without interrupting the actual liquid
flow.
Startup
Before startup, the entire system should be flushed through. This ensures that possible contamination occuring
during installation will not cause any malfunctions. Normally, the filter will be operated in single chamber mode.
In case of extremely high viscosity (cold start at low oil temperatures and/or high initial impurity content), parallel
operation of both filter chambers is advisable (switch-over lever in centre position). After completion of the
startup phase, change over to single chamber mode. The shut-off filter element intended as backup in
subsequent single chamber mode must be cleaned immediately after change-over to permit utilizing the full
impurity collection capacity.
Cleaning
Increasing contamination of the filter is apparent from the contamination indicator. The filter element held in
reserve should be filled (by slowly turning the switch-over lever, while at the same time opening the venting
screw until oil emerges). The pressure of the shut-off filter element should be released by opening the venting
screw and drained by unscrewing the drain plug. Afterwards, the filter chamber should be unscrewed and the
filter element withdrawn. The filter element should be washed with fresh cleaning liquid, such as benzine or
warmed diesel oil, and then blown through from the inside to the outside.
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
Cable connection b
PG 11 e
q f2
Outlet
Contamination P R Venting screw
X
indicator
f1
Type 2.F2
g2
c
X Name plate
Inlet
SW 27 P
g2 120 °
150
X Filter bowl
(flange connection) Switch-over lever
Drain plug
assembly S
R k
t
for a
Nom.
diam. d f1 f2 d1 d2 t
32 G 1 1/4 41 32 42.2 47.0 2.0
50 G2 45 36 61.0 74.0 3.0
80 - 50 41 81.0 89.0 -
Table 1: Flange connection dimensions
element a b c e h k D R S P q g1 g2 1)
l/min cm2 kg mm
32 150 1500 187 216 215 72 115 324 105 86 G 3/8 40 M 10 10 150 110 13 60 or 25
50 350 3500 267 260 247 88 134 435 130 110 G 1/2 40 M 12 9 160 130 20 60 or 25
80 900 9000 358 352 316 103 183 568 180 158 G 3/4 70 M 16 12 185 160 31 60 or 25
Table 2: Filter dimensions
1) The ”nominal” mesh width is determined by the smallest particle size of which 90 % is retained in the filter
mesh.
Technical Data
Operating pressure : max. 16 bar
Operating temperature : max. 120 °C
Oil flow velocity : max. 3 m/s
Materials
Housing and switch-over element : GG-25
Filter bowl : GK-AL
Filter (cage mesh) : CrNi/Al
Diaphragm : Perbunan
O-rings : Perbunan
O-ring dimensions : on filter chamber for DN 32: 85.09 x 5.33
50: 104.14 x 5.33
80: 148.59 x 5.33
on inlet flange for DN 32: 37.47 x 5.33
50: 59.69 x 5.33
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
2 P
THERMOSTATIC VALVES
(SELF ACTUATED TYPES)
MVA SERIES ``M...... ´´ GENERAL INFORMATION
MVA Thermostatic Valves are used to provide reliable, automatic control of fluid temperatures
in turbines, compressors and engine water jacket and lubricating oil cooling systems. They are
also suitable for process control and industrial applications where fluids must be mixed or
diverted depending on their temperatures. They may also be applied to co-generation systems
to control temperatures in the heat recovery loop assuring proper engine cooling and
maximising heat recovery.
All MVA Thermostatic Valves are equipped with positive 3-way valve action in which the water
or lubricating oil is positively made to flow in the direction required. On jacket water applications
when the engine is started up and is cold, the MVA Thermostatic Valve causes all of the water
to be positively by-passed back into the engine, thus providing the quickest warm-up period
possible. After warm up, the correct amount of water is by-passed and automatically mixed with
the cold water returning from the heat exchanger or other cooling device to produce the desired
jacket water outlet temperature. If ever required, the MVA Thermostatic Valve will shut off
positively on the by-pass line for maximum cooling. The 3-way action of the MVA Thermostatic
Valve allows a constant volume of water through the pump and engine at all times with no
pump restriction when the engine is cold.
No adjustments are ever required on MVA Thermostatic Valves. Once installed a MVA
Thermostatic Valve will provide years of trouble-free service.
TEMPERATURE SETTINGS
Because MVA Thermostatic Valves are set to a predetermined temperature at the factory,
costly errors due to mistakes of operating personnel are eliminated. After a MVA Thermostatic
Valve has been installed, it is impossible for the operator to arbitrarily change the operating
temperature and run the engine too cold or too hot unless the temperature element assemblies
themselves are changed.
MVA Thermostatic Valves are temperature rated for the expected nominal operating
temperature in jacket water service. On lubricating oil applications the system operating
temperature may be slightly above the nominal rating, depending on the type of oil flow rate, oil
cooler capacity and other conditions of the system.
For long life, MVA Thermostatic Valves should not be operated continuously at temperatures
more than about 75°F (24°C) above their nominal ratings. If higher continuous over-
temperatures are expected, contact the factory for recommendations.
OPERATION
The power creating medium utilises the expansion of a special thermostatic wax material which
remains in a semi-solid form and which is highly sensitive to temperature changes.
INSTRUCTIONS FOR MVA TEMPERATURE VALVE MODEL "M" WITH AND WITHOUT
MANUAL OVERRIDE
1) Maintenance
Properly applied and installed, MVA Thermostatic Valves require minimal maintenance. An
inspection at 2 or 3 year intervals is adequate to detect and make provision for manual wear.
Excessive temperatures, chemical, electrolytic attack or cavitation will shorten the life of the
element assemblies, seals and seats. These items are replaceable. Water additives may cause
swelling of the O-ring seals around the stem and the sliding valve to a point where they may
affect valve action and require replacement. Synthetic base lubricants will definitely attack the
O-ring seals which may be replaced by O-rings of alternate materials. Contact the MVA factory
for recommendations.
Carbonates, scale and other solids must not be permitted to build up on sliding valve or sensing
cup surfaces. The valve and element assemblies may be cleaned with mild acid or Oakite
solutions. Hard scale may require wire brush buffing.
2) Manual override
If for any reason "M"-Thermostatic valves with manual override should not work properly, each
element assembly is fitted with an infinitaly variable override which allows on accurate manual
temperature regulation.
Before the manual override is used we recommend, however, to check whether the cause of
trouble is not somewhere in the system, according to paragraph 3) "Trouble shooting". Manual
override should only be used in emergency case.
If a thermostatic valve with several element assemblies is installed (DN 65 - DN 125) it is
recommended to open one element assembly after the other against cooler by turning screw
until desired temperature is nearly reached. Final regulation is done with next element
assembly.
3) Trouble-Shooting
In the event that your cooling system does not operate close to the desired temperature, the
following check list may point to one or more causes for the problem.
Compen-
x This scheme shows the cooling water circuit
3
sation
1
of a fix installed or a ship engine with cooling
tank MVA by a heat exchanger. The MVA Thermostatic
Valve is in such a way installed, that the
engine temperature of the cooling water at the
outlet of the engine will be maintained
Cooling water constant. Should exist any problem cause by
enclosed air, a narrow ventilation pipe (x)
Fig. 7 Heat exchanger
leading from the highest point of the system
to the compensation tank will help.
M 20 ...M 40
K
E/ d/ n t 3 L
J K
DN
2 DN
2 3 DN D 2 3 M
M M
1 1 1 1 1
J K
BSP BSP
NPT NPT
J
A B C
CI CS Bz Al bar
0,7
BSP A B DI SS
0,6
NPT C kg kg kg kg
0,5
20 3/4" C 2,15 2,2 2,2 2,1
0,4
4 °E
20T B 7,7 7,7 9,1 4,8
0,3
25 1" C 2,15 2,2 2,2 2,1
0,2
25T B 7,7 7,7 9,1 4,8
0,1
32 11/4" C 3,0 3,2 3,4 2,1
40J 11/2" C 3,0 3,2 3,4 2,1
40T 11/2"
DN
A 4,1 4,1 4,9 4,2
20 2,0 2,3 3,8 5,2 5,6 7,0
40T B 7,7 7,7 9,1 4,8
25 2,2 2,5 4,2 5,7 6,2 7.8 m³/h
32 2,5 2,8 4,8 6,5 7,1 8,8
40 5,2 8,5 11,0 14,0 16,8 18,5
M 50 ...M 150
K
t
E/ d/ n
3 L
DN 2
D 2 3 M
M
t
1 N
1
J K J
D
A B C
CI CS Al
bar
0,7
DN A B DI SS
0,6
C kg kg kg
0,5
50 C 18 20 7 4 °E
50 AB 18 20 7
0,4
65 AB 24 31 10 0,3
80 AB 25 32 14 0,2
100 A B 60 60 24 0,1
125 A B 125 125 35
150 A B 136 136 48 DN
50 10 15 20 25 30 35
65 19 28 38 47 55 65
80 20 30 40 50 60 70 m³/h
100 40 60 80 100 120 140
125 60 90 120 150 180 210
150 90 135 180 225 270 315
M 25 C 1 A 120 C A
M 80T C 2 G 120 D A
075 °F = 24°C 21 °C - 29 °C
port connections flanges 090 = 32 27 - 35
1 = DIN 2501-1 PN 6 095 = 35 30 - 41
2 = DIN 2501-1 PN 10 100 = 38 35 - 43
3 = DIN 2501-1 PN 16 105 = 41 35 - 45
4 = ANSI B16.1 (Class 125) RF 110 = 43 38 - 47
5 = ANSI B16.5 (Class 150) RF 115 = 46 40 - 50
6 = DIN 2501-1 PN 25 120 = 49 44 - 54
7 = ANSI B16.5 (Class 300) RF 130 = 55 52 - 60
8 = DIN 2501-1 PN 40 135 = 57 54 - 63
B = BSP parallel 140 = 60 57 - 66
145 = 63 60 - 69
type of element 150 = 66 63 - 71
G = 2001A standard for water and oil 155 = 68 66 - 74
H = 2012A standard with manual over ride 160 = 71 68 - 77
J = 2030A standard for salt water 165 = 74 71 - 79
L = 2030P kanigen plated 170 = 77 74 - 82
M = 2035P kanigen plated 175 = 79 77 - 85
with manual override 180 = 82 79 - 88
185 = 85 82 - 91
195 = 91 87 - 98
205 = 96 93 - 102
215 = 102 99 - 107
Valve size DN 50 can bee in housing model T (Fig. A,B) and F 225 = 108 102 - 113
(Fig. C). Model T has in the coding the „T“ added. 230 = 110 104 - 115
240 = 116 108 - 122
for example: M50TC2G110DA
!
"#$
% &!
!
!
!
! ! !
! !
! !
' !
!
&!
!
! !
!
!
!
#
!
&!
)
(
* "% 0 ... 10 bar 0 ... 40 bar 0 ... 40 bar 0 ... 250 bar 0 ... 400 bar
(
"% 0 ... 140 psi 0 ... 580 psi 0 ... 580 psi 0 ... 3625 psi 0 ... 5800 psi
+
)
GL98
-34 ... +100 °C
+100 °C
3 bar 0.1 linear
3 bar 0.5 40 bar 2.0 linear 40 bar 2.0 linear 250 bar 10 linear 400 bar 20 linear
)
Class 1.6 ... 3 bar
Class 4 Class 1.6...40 bar Class 1.6...40 bar Class 1.6...40 bar Class 1.6...40 bar
3 ... 10 bar
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
)
- ./ 0 $
,
- 1/. 0 $
!
$ - $
(
"+%
&!
R 1/4 G 1/4
&
IP 65
2
! 0.21 kg
Electrical specifications
Nom. output signal (short-circuit protected)
4 − 20 mA d.c. 0-5, 1-5, 1-6 V d.c. 0-10 V d.c.
Supply voltage [UB], polarity protected 9 → 32 V d.c. 9 → 30 V d.c. 15 → 30 V d.c.
Supply - current consumption - ≤ 5 mA ≤ 8 mA
Supply voltage dependency ≤ ±0.05% FS/10 V
Current limitation
(linear output up to 1.5x nom. range) 34 mA (typ.) -
Output impedance - ≤ 25Ω
Load [RL] (load connected to 0V) RL ≤ (UB-9V)/0.02 RL ≥ 10 kΩ RL ≥ 15 kΩ
Environmental conditions
Medium temperature range −40 → +85°C
Ambient temperature range (depending on electrical connection) see page 3
Compensated temperature range 0 → +80°C
Transport temperature range −50 → +85°C
EMC - Emission EN 61000-6-3
Air mode 8 kV EN 61000-6-2
Electrostatic discharge
Contact mode 4 kV EN 61000-6-2
field 10 V/m, 26 MHz - 1 GHz EN 61000-6-2
EMC - Immunity RF
conducted 10 Vrms, 150 kHz - 30 MHz EN 61000-6-2
burst 4 kV (CM), Clamp EN 61000-6-2
Transient
surge 1 kV (CM,DM), Rg = 42Ω EN 61000-6-2
Insulation resistance > 100 MΩ at 100 V d.c.
Mains frequency test 500 V, 50 Hz SEN 361503
15.9 mm-pp, 5 Hz - 25 Hz
Vibration stability Sinusoidal IEC 60068-2-6
20 g, 25 Hz - 2 kHz
Random 7.5 g rms, 5 Hz - 1 kHz IEC 60068-2-34, IEC 60068-2-36
Shock 500 g / 1 ms IEC 60068-2-27
Shock resistance
Free fall IEC 60068-2-32
Enclosure (depending on electrical connection) see page 3
Mechanical characteristics
Wetted parts DIN 17440-1.4404 (AISI 316 L)
Materials
Enclosure DIN 17440-1.4404 (AISI 316 L)
Electrical connections See page 3
Weight (depending on pressure connection and electrical connection) 0.2-0.3 kg
Electrical connections
1 2 5 7 8 3
DIN 43650, Pg 9 AMP Econoseal IEC 947-5-2 ISO 15170-A1-3.2-Sn AMP Superseal 2 m screened cable
J series (male) M12×1 (Bayonet plug) 1.5 series (male)
Ambient temperature
-40 → + 85 °C -40 → + 85 °C -25 → +85 °C -40 → +85 °C -40 → +85 °C -30 → +85 °C
Enclosure
IP 65 IP 67 IP 67 IP 67 / IP 69K IP 67 IP67
Materials
Glass filled Glass filled Nickel plated Glass filled Glass filled Polyolifin cable
polyamid, PA 6.6 polyamid, PA 6.61) brass, CuZn/Ni polyester, PBT polyamid, PA 6.62) with PE shrinkage tubing
Ordering,
Special versions MBS 3050- −
Output signal
1 .......................................... 4-20 mA
2 .......................................... 0-5 V
3 .......................................... 1-5 V
4 .......................................... 1-6 V
5 .......................................... 0-10 V
Bimetallic dial thermometers according to FLENDER works standard W 5924 are precision instruments for
visual temperature monitoring of liquid and gaseous media.
Dimension drawing
Design
Installation
When installing the thermometer take care that the immersion tube is dipped into the medium to be monitored.
General
The electric resistance in the resistance thermometer sensor changes as the temperature fluctuates. This
change of resistance on the PT 100 or the converted output signal of the measuring transducer (4 to 20 mA)
can be used to measure temperature with an evaluating instrument or to define a switch point by means of limit
switches.
Operation
Pt 100 measuring thermometer sensor
The electrical conductivity of metal (here platinum) is based on the mobility of conduction electrons. As the
temperature rises, the movement of the atoms in the metal lattice about their rest position intensifies and so
obstructs the electrons flowing to the plus pole of a power source. This obstruction sets up a resistance in linear
proportion to the temperature.
To generate the output signal a constant test current (approx. 1 mA) is applied to the Pt 100. The resistance
in the Pt 100 causes a drop in voltage (U = R · l), which can be evaluated.
Measuring transducer
The two-wire measuring transducer is mounted in the J-head only if requested by the customer. It should be
noted that here only a single connection is possible.
The measuring transducer converts the temperature-dependent resistance to a standard uniform signal
of 4 to 20 mA. This signal can be transmitted over long distances without interference.
Environmental influences
– Operating temperature range: –40 to +85 °C
– Temperature influence: ≤ 0.01 % / K deviation of 22 °C
relative to measuring range final value of 20 mA
– Climate resistance: rel. humidity ≤ 95 % on annual average without dew contact
– Vibration strength: acc. to GL characteristic 2
– EMV: EN 61326
Housing
– Material: Polycarbonate (encapsulated)
– Screw connection: ≤ 1.5 mm2
– Assembly: in terminal head Form J
– Mounting position: any
– Weight: approx. 12 g
Connection
The customer can minimise measuring inaccuracies by using multiple wires. At Flender, as a rule, a 3- or 4-wire
arrangement from an additional terminal box is provided for (Fig. 1, 2). At the customer’s specific request, the
3/4-wire arrangement can be used from the J-head (Figure 4, 5). Through lack of space, however, the 4-wire
arrangement is possible only with a single connection (Fig. 5).
Customer Customer
Fig. 3: 2-wire circuit from Fig. 4: 3-wire circuit from Fig. 5: 4-wire circuit from
terminal head of Pt 100 terminal head of Pt 100 terminal head of Pt 100
Types
EL = Installation length ≈ 61
40 14 3
∅ 49
G 1/2A
∅8
25 SW 27
∅ 5.8
crimped in
O-rings
≈ 33
Guide tube
∅ 26.9-0.2
0
Measuring resistance Adapter
Pt 100 doubled SW 17
!et t" D#$ 3%&' M16 x 1.5
Terminal head IP 65
e(t)*e t+e,m"mete, - &1001
+5
EL-10 = Installation length ≈ 61
+5
25-10 50 14 3
Guide tube
∅ 5.8
Spring
crimped in
≈ 33
∅ 26.9-0.2
0
122
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
100 ≈ 61
14 3
G 1/2A
SW 27 SW 27 ∅ 49
∅ 9.5
Guide tube
Protective tube
≈ 33
26.9-0.2
0
SW 17
!et t" D#$ 3%&'
Terminal head IP 65 M16 x 1.5
e(t)*e t+e,m"mete, - &1003
NL = Nominal length
EL = Installation length 73 ≈ 74
25 3
crimped in
SW 27 SW 18 SW 27
∅ 49
∅ 5.8
∅8
O-rings
≈ 33
∅ 26.9-0.2
Guide tube Adapter
G 1/2A
0 28
sprung
Measuring resistance screw connection
Pt 100 doubled SW 17
Housing
Terminal head
≈5
Measuring tip
Anti-friction bearing
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
A B C D
a) Insert guide tube ”A” into hole in housing until the measuring tip of the resistance thermometer makes
contact.
b) Screw screw connection ”B” into the housing as far as it will go.
c) Pull out screw connection ”C” approx. 5 mm towards the terminal head. Then lock nut ”D” with screw
connection ”C”. This ensures that the pretensioned spring keeps the measuring tip permanently in contact
with the part to be measured.
These Operating Instructions are binding for volume flow meters to Flender Works Standard W 5927.
General
The volume flow meter described here works in accordance with the orifice plate measuring system, using the
Witte orifice plate, by which measurements from Reynold’s number Remin = 50 to Remax. 2320 can be carried
out virtually independently of viscosity. Measurement requires an even flow of 8 x pipe inner diameter upstream
and 5 x pipe inner diameter downstream of the orifice plate (undisturbed straight length of pipe). The meter can
be mounted in any position. Calibration for vertical mounting is done at the works.
Section 2. 3.
1. Pressure chamber
5. Measuring springs
6. Measuring diaphragm
6.
Type of protection: IP 65
Output: 2 changeover contacts (separately adjustable)
Connection diagram
Material
Membranes: Viton
Example: With a max. pump output of 112 l/min a volume flow meter with a volume flow range of up to
155 l/min can be used.
155 l/min % ⇒ 100 %
112 l/min % ⇒ 72 %
Design: A volume flow meter must be selected to the maximum value of the volume flow range of which
the max. pump output comes as near as possible.
Cable terminal
M 20 x 1,5
Zero adjustment
Switching adjustment
(internal)
In the case of use in an explosion hazard area the flow monitor can be made intrinsically safe by means of a
break relay (see example).
Explosion-hazard-free area
Intrinsically safe circuit Explosion-hazard area
(EEx ia) IIC
EN 50 014 ... 50 020
2 S1.1
1
28 l/min 3
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
6 S1.2
5
25 l/min 4
1 2 3 7 8 9
U1 12 15
10 13
11 14
16 17 18
PE L1 N
Type of protection: IP 54
Material
Membranes: Viton
Shield: St
Pressure chamber: Aluminium anodized (black)
Example: The 4 - 20 mA signal scaling ranges from 0 to 100 %. With a max. pump output of 112 l/min a
volume flow meter with a volume flow range of up to 155 l/min can be used.
Design: This means that, when the pump is at full output, the output signal is 12.35 mA. If this pump
is running at only 90 % of its max. output (=100.8 l/min), the output signal is 10.76 mA.
20
18
16
14
Output signal in mA
12
10
0
0 20 40 60 80 100
Volume flow in %
Cable terminal
M 20 x 1,5
A A
B B
PROYECTO REPOTENCIONAMIENTO
C
LOS PELAMBRES C
D D
E E
A A
0 3
= = =
+MCC +SLGS +EXT
B B
Ölversorgungsanlage Getriebe
Oil supply system Gearbox
Klemmenplan 6 123 673
C Terminal diagram 6 123 673 C
= =
+OLGS +B3FH
FLENDER FLENDER
D Klemmenleistenbezeichnung für -X . . D
Terminal strip marking for
Verdrahtungsfarben:
Hauptstromkreis schwarz Querschnitt nach Belastung
Neutralleiter blau Querschnitt nach Belastung
Schutzleiter grün/gelb Querschnitt nach Belastung
Leistung AC Power AC 1
Steuerstromkreis AC rot 1mm² oder größer nach Belastung
Leistung DC >24V Power DC >24V 2
Steuerstromkreis 24V DC (Pluspol) blau 1mm² oder größer nach Belastung
Steuerstromkreis 24V DC (Minuspol) weiß 1mm² oder größer nach Belastung Leistung DC =<24V Power DC =<24V 3
Sonstiges braun 1mm² oder größer nach Belastung Steuerspannung AC Controlvoltage AC 4
E Fremdspannung orange 1mm² oder größer nach Belastung Steuerspannung DC Controlvoltage DC 5 E
Datensignale Data signals 6
Wiring colours
Sonder Signale Special signals 7
Main circuit bk cross-section according to load
Neutral bu cross-section according to load
E Exi E Exi 8
Potective conductor gn/ye cross-section according to load Sonstige Others 9
Control circuit AC rd 1mm² or larger according to load
Control circuit 24V DC (plus) bu 1mm² or larger according to load
Control circuit 24V DC (minus) wh 1mm² or larger according to load
Specials bn 1mm² or larger according to load
External voltage or 1mm² or larger according to load
F Date
22.06.06 120-CV-005-01 Order No. = F
TBK
Drawn
Anlagenübersicht 6 113 281 4214492 +SLGS
Checked TBK 120-CV-006-01 Schaltplan Ölversorgungsanlage 2
Rev Description Date Name Norm DIN Made from In exchange for exchanged thru
General information Wiring diagram oil supply system ADB 2 Sh.
1 2 3 4 5 6 7 8
3
CAD-DRAWING TO BE MODIFIED ON THE MONITOR ONLY THIS TECHNICAL DOCUMENT IS REGISTERED (DIN 34)
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 1 2 3 4 5 6 7
A Zeile Änd. Benennung Blatt Planart Anlage Gruppe Ort Zeile Änd. Benennung Blatt Planart Anlage Gruppe Ort A
Line Rev. Description Sheet Plantyp Unit Group Place Line Rev. Description Sheet Plantyp Unit Group Place
1 Anlagendeckblatt ADB
1 ADB = +SLGS 21 Klemmenplan 1283
1 VKL = +SLGS-X72 +SLGS
Cover sheet Connection plan
2 Anlagenübersicht AUE
2 ADB = +SLGS 22 Geräteliste 3432
1 ZGL
General information List of equipment
3 Inhaltsverzeichnis INH
1 INH = 23 Geräteliste 3432
2 ZGL
Table of contents List of equipment
4 Aufbauplan SSL
1 SSL = +SLGS 24 *
Cabinet layout *
B 5 Aufbauplan SSL
2 SSL = +SLGS 25 * B
Cabinet layout *
6 Einspeisung ESP
1 STR = +SLGS 26 *
Power supply *
7 SPS - Aufbau SPSA
2 STR = +SLGS 27 *
PLC - Layout *
8 Leistungsteil LT
3 STR = +SLGS 28 *
Power unit *
9 Analogeingabe DSAE
4 STR = +SLGS 29 *
Analog input unit *
C 10 Digital Eingänge DE2
5 STR = +SLGS 30 * C
Digital inputs *
11 Digital Eingänge DE2
6 STR = +SLGS 31 *
Digital inputs *
12 Digital Ausgänge DA2
7 STR = +SLGS 32 *
Digital outputs *
13 Digital Ausgänge DA2
8 STR = +SLGS 33 *
Digital outputs *
14 Potentialfreie Kontakte PFK
9 STR = +SLGS 34 *
Potential free contacts *
D 15 Klemmenplan 1283
1 VKL = +SLGS-X10 +SLGS 35 * D
Connection plan *
16 Klemmenplan 1283
1 VKL = +SLGS-X12 +SLGS 36 *
Connection plan *
17 Klemmenplan 1283
1 VKL = +SLGS-X4 +SLGS 37 *
Connection plan *
18 Klemmenplan 1283
1 VKL = +SLGS-X51 +SLGS 38 *
Connection plan *
19 Klemmenplan 1283
1 VKL = +SLGS-X52 +SLGS 39 *
Connection plan *
E 20 Klemmenplan 1283
1 VKL = +SLGS-X62 +SLGS 40 * E
Connection plan *
Order No. = 5
7
. 6
+
2
1 3
4
Rev. Description Sh.
A A
+SGLS
B B
H1 H2 H6 H9 H11 H13 H8
S2 S3 S4 S5 S6
C 66 C
- AU
I OT
760
S
N
0
-S20
660
Q1
594
528
D D
E E
760
1:5
A A
75x50
B B
F1
F2
F3
T1 Q10 Q30 Q2 G1 D2 D4 W1
75x50
75x50
C C
U65
K10
K30
Q1 K10MK30M K20
75x50
730
610
75x50
470
385
X10,X12,X4,X51,X52,X62,X72
K1
K2
K3
K4
D D
250
185
75X100
30
704
E E
1:5
F Date 22.06.06 120-CV-005-01 Order No. = F
Drawn TBK
Aufbauplan 6 113 281 4214492 +SLGS
Checked TBK 120-CV-006-01 Schaltplan Ölversorgungsanlage 2
Rev Description Date Name Norm DIN Made from In exchange for exchanged thru
Cabinet layout Wiring diagram oil supply system SSL 2 Sh.
1 2 3 4 5 6 7 8
3
CAD-DRAWING TO BE MODIFIED ON THE MONITOR ONLY THIS TECHNICAL DOCUMENT IS REGISTERED (DIN 34)
1 2 3 4 5 6 7 8
A L1 /3.1 A
L2 /3.1
L3 /3.1
-Q2 1 3 5
0,5A
2 4 6
B L1
B
0V 400V
-G1
-T1
PE N M L+
PE
OV 230V fvp
L24 /2.1
-X4 1
PE -X4 2
-S20 11
PE
fvp fvp
12
-Q1 1 3 5
C -X51 1 C
-X51 1
45A +EXT
2 4 6
-F1 1 -F2 1 -F3 1
-S* 11
2 2 2
+EXT 12
-X51 2
-K20 1 -S1 3
+EXT
7 2 5 -X51 2
D D
-K20 A1
A2
SL1 /8.1 fvp
L0 /2.1
-X10 L1 L2 L3 PE -X4 3 4 5
+MCC NOT-AUS
E PE E
Emergency off
3x400V/50Hz L1 N PE
Netz -E1 3 1 2
Mains
/6.5 3 4
Rechtsdrehfeld 5 6
CW field of rotation
21 22
Schaltschrank Heizung
Switch cabinet heater
A A
PLC S7-300 CP 342-5
CPU 313 C
-D2 -D4 -W1
/5.1 2 E124.0 /6.1 12 E125.0 22 E126.0 /7.1 22 A124.0 /7.5 32 A125.0 16 PAWV752 2 PEWV752 /8.1 2 A0.0 /8.5 12 A1.0
/5.2 3 E124.1 /6.2 13 E125.1 23 E126.1 /7.2 23 A124.1 /7.5 33 A125.1 17 PAWI752 /4.3 3 PEWI752 /8.2 3 A0.1 /8.5 13 A1.1
/5.3 4 E124.2 /6.3 14 E125.2 24 E126.2 /7.2 24 A124.2 /7.6 34 A125.2 18 PAWV754 5 PEWV754 /8.2 4 A0.2 /8.6 14 A1.2
/5.4 5 E124.3 /6.4 15 E125.3 25 E126.3 /7.3 25 A124.3 /7.6 35 A125.3 19 PAWI754 /4.4 6 PEWI754 /8.3 5 A0.3 /8.6 15 A1.3
/5.5 6 E124.4 /6.5 16 E125.4 26 E126.4 /7.3 26 A124.4 /7.6 36 A125.4 14 PEWP760 8 PEWV756 /8.3 6 A0.4 /8.6 16 A1.4
/5.6 7 E124.5 /6.6 17 E125.5 27 E126.5 /7.3 27 A124.5 /7.7 37 A125.5 /4.2 9 PEWI756 /8.3 7 A0.5 /8.7 17 A1.5
B B
/5.7 8 E124.6 /6.7 18 E125.6 28 E126.6 /7.4 28 A124.6 /7.7 38 A125.6 11 PEWV758 /8.4 8 A0.6 /8.7 18 A1.6
/5.8 9 E124.7 /6.8 19 E125.7 29 E126.7 /7.4 29 A124.7 /7.8 39 A125.7 12 PEWI758 /8.4 9 A0.7 /8.8 19 A1.7
1L+ M 1L+ M
1L+ 1M 4M 2L+ 2M 3L+ 3M MPI PtP/DP DP
1 10 11 20 21 30 21 30 31 40 L+ M X1 X2 1 10 11 20 X1 + -
D D
E E
A /1.8 L1 A
/1.8 L2
/1.8 L3
/6.2
/6.4
-Q10 1 3 5 13 21 -Q30 1 3 5 13 21
14 22 14 22
36A 5,6A
2 4 6 2 4 6
B B
-K10M 1 3 5 -K30M 1 3 5
/8.1 2 4 6 /8.2 2 4 6
C C
D D
-X12 1 2 3 4 -X12 5 6 7 8
PE PE
W V U W V U
-M10 -M30
+OLGS +OLGS
M M
E 3 PE 3 PE E
18,5kW 2,2kW
120-CV-05-01A 120-CV-05-01B
120-CV-06-01A 120-CV-06-01B
Pumpe 10 Kühler
Pump 10 Cooler
B B
10 11 8 7
-U65
1 2
C C
-SHIELD -SHIELD
3 3
1 4
RD RD WH WH
-B65.1 -B65.2 -B50
I BN BK
+ - -B80
I 1(+) 2(-)
+OLGS +OLGS +OLGS
P
E E
A A
/2.2
2 3 4 5 6 7 8 9
B B
3
-S2 13 23 -S2 23 -S3 13 -S4 13 -S5 13 -S6 13
14 24 2 24 14 14 14 14
C C
D D
-X52 1 2 3 4
PE
3 2 1 PE
-S20
+OLGS
P
E E
Differenzdruckwächter Bedienung fern Bedienung vor Ort Start M10 Start M30 Lampentest Reset
Differ. pressure monitor Operating remote Operating local Start M10 Start M30 Lamptest Reset
A A
/2.3
12 13 14 15 16 17 18 19
-X51 3
B B
-X51 3
+EXT
-X51 4
+EXT
C C
-X51 4
D D
E E
A A
-D2 A124.0 A124.1 A124.2 A124.3 A124.4 A124.5 A124.6 A124.7 -D2 A125.0 A125.1 A125.2 A125.3 A125.4 A125.5 A125.6 A125.7
/2.4 /2.4
22 23 24 25 26 27 28 29 32 33 34 35 36 37 38 39
B B
31 31 31 31 31 31 31 31 31 31 31 31 31
-H1 -H2 -H3 -H6 -H7 -H8 -H9 -H10 -H11 -H12 -H13 -H14 -H16
32 32 32 32 32 32 32 32 32 32 32 32 32
C C
OLV:BB OLV:P1IB OLV:P1SG OLV:KIB OLV:KSG OLV:FSG OLV:D0,8 OLV:D0,5 OLV:T75 OLV:T80 OLV:V80 OLV:V70 NOT:AUS
D D
Betriebsbereit Pumpe 10 Störung Kühler Störung Öldruck <0,8bar Öltemperatur >75°C Volumenstrom <80% NOT-AUS
Ready for operation Pump 10 fault Cooler fault Oil pressure <0,8bar Oiltemperature >75°C Volume flow <80% Emergency off
Pumpe 10 in Betrieb Kühler in Betrieb Filter verschmutzt Öldruck <0,5bar Öltemperatur >80°C Volumenstrom <70%
Pump 10 in operation Cooler in operation Filter contaminated Oil pressure <0,5bar Oiltemperature >80°C Volume flow <70%
E E
A A
-D4 A0.0 A0.1 A0.2 A0.3 A0.4 A0.5 A0.6 A0.7 -D4 A1.0 A1.1 A1.2 A1.3 A1.4 A1.5 A1.6 A1.7
/2.5 /2.6
2 3 4 5 6 7 8 9 12 13 14 15 16 17 18 19
B B
A2 A2 A2 A2 A2 A2
/4.8 L0
1 14 11 2 14 11 /9.1 14 11 /9.2 14 11 /9.3 14 11 /9.4 14 11
/1.4 SL1
C C
-K10 11 -K30 11
1 14 2 14
D D
-K10M A1 -K30M A1
A2 A2
/1.8 SL2
1 2 /3.3 1 2
/3.1
3 4 /3.3 3 4
/3.1
5 6 /3.3 5 6
/3.1
13 14
E E
A A
B B
C C
Betriebsbereit Warnung
(Relais angezogen) (Relais abgefallen)
E E
Ready for operation Warning
(Relay picked up) (Relay dropped out)
In Betrieb Alarm
(Relais angezogen) (Relais abgefallen)
In operation Alarm
(Relay picked up) (Relay dropped out)
= + - : max. STR = + - :
= +MCC -X10 L1 UK10N 1 10.0 STR=/1.1 = +SLGS -Q1 2
= +MCC -X10 L2 UK10N 2 10.0 STR=/1.1 = +SLGS -Q1 4
= +MCC -X10 L3 UK10N 3 10.0 STR=/1.1 = +SLGS -Q1 6
= +MCC -X10 PE USLKG 10N 4 10.0 STR=/1.1
B B
C C
D D
E E
= + - : max. STR = + - :
= +OLGS -M10 W UK10N 1 10.0 STR=/3.1 = +SLGS -K10M 2
= +OLGS -M10 V UK10N 2 10.0 STR=/3.1 = +SLGS -K10M 4
= +OLGS -M10 U UK10N 3 10.0 STR=/3.1 = +SLGS -K10M 6
= +OLGS -M10 PE USLKG 10N 4 10.0 STR=/3.2
B B
= +OLGS -M30 W UK5N 5 4.0 STR=/3.3 = +SLGS -K30M 2
= +OLGS -M30 V UK5N 6 4.0 STR=/3.3 = +SLGS -K30M 4
= +OLGS -M30 U UK5N 7 4.0 STR=/3.3 = +SLGS -K30M 6
= +OLGS -M30 PE USLKG 5 8 4.0 STR=/3.3
C C
D D
E E
= + - : max. STR = + - :
USLKG 5 1 4.0 STR=/1.3 = +SLGS -T1 PE
USLKG 5 2 4.0 STR=/1.6 = +SLGS -G1 PE
= +SLGS -S1 5 UK5N 3 4.0 STR=/1.5 = +SLGS -E1 N
UK5N 4 4.0 STR=/1.5 = +SLGS -E1 N
B B
USLKG 5 5 4.0 STR=/1.5 = +SLGS -E1 PE
C C
D D
E E
= + - : max. STR = + - :
= +EXT -X51 1 UK5N 1 4.0 STR=/1.7 = +SLGS -S20 12
= +EXT -X51 2 UK5N 2 4.0 STR=/1.7 = +SLGS -K20 A1
= +EXT -X51 3 UK5N 3 4.0 STR=/6.8 = +SLGS -D2 19
= +EXT -X51 4 UK5N 4 4.0 STR=/6.8 = +SLGS -S6 14
B B
USLKG 5 5 4.0 R
C C
D D
E E
= + - : max. STR = + - :
= +OLGS -S20 3 UK5N 1 4.0 STR=/5.1 = +SLGS -D2 2
= +OLGS -S20 2 UK5N 2 4.0 STR=/5.1
= +OLGS -S20 1 UK5N 3 4.0 STR=/5.1
= +OLGS -S20 PE USLKG 5 4 4.0 STR=/5.2
B B
C C
D D
E E
= + - : max. STR = + - :
= +OLGS -B50 1 UK5N 1 4.0 STR=/4.3
= +OLGS -B50 4 UK5N 2 4.0 STR=/4.3 = +SLGS -D2 3
UK5N 3 4.0 STR=/4.3 = +SLGS -SHIELD 3
= +OLGS -B80 1(+) UK5N 4 4.0 STR=/4.4
B B
= +OLGS -B80 2(-) UK5N 5 4.0 STR=/4.4 = +SLGS -D2 6
UK5N 6 4.0 STR=/4.4 = +SLGS -SHIELD 3
USLKG 5 7 4.0 R
C C
D D
E E
= + - : max. STR = + - :
= +OLGS -B65.1 RD UK5N 1 4.0 STR=/4.1 = +SLGS -U65 1
= +OLGS -B65.1 RD UK5N 2 4.0 STR=/4.1 = +SLGS -U65 2
= +OLGS -B65.2 WH UK5N 3 4.0 STR=/4.2
= +OLGS -B65.2 WH UK5N 4 4.0 STR=/4.2
B B
USLKG 5 5 4.0 R
C C
D D
E E
B
Circuit breaker
6 -F3 STR=/1.5 000000361623 Sicherungsautomat FA
FAZ-B10 Moeller
Circuit breaker
7 -G1 STR=/1.6 000001212447 Netzteil GN
6ES7 307-1EA00-0AA0 Siemens
Power pack
8 -H1 STR=/7.1 000100363102 Leuchtmelder HL
M22-L-G 24V Moeller
Signal lamp
9 -H10 STR=/7.5 000100363101 Leuchtmelder HL
M22-L-R 24V Moeller
Signal lamp
C 10 -H11 STR=/7.6 000100363127 Leuchtmelder HL
M22-L-Y 24V Moeller C
Signal lamp
11 -H12 STR=/7.6 000100363101 Leuchtmelder HL
M22-L-R 24V Moeller
Signal lamp
12 -H13 STR=/7.6 000100363127 Leuchtmelder HL
M22-L-Y 24V Moeller
Signal lamp
13 -H14 STR=/7.7 000100363101 Leuchtmelder HL
M22-L-R 24V Moeller
Signal lamp
14 -H16 STR=/7.8 000100363101 Leuchtmelder HL
M22-L-R 24V Moeller
Signal lamp
D D
15 -H2 STR=/7.2 000100363100 Leuchtmelder HL
M22-L-W 24V Moeller
Signal lamp
16 -H3 STR=/7.2 000100363101 Leuchtmelder HL
M22-L-R 24V Moeller
Signal lamp
17 -H6 STR=/7.3 000100363100 Leuchtmelder HL
M22-L-W 24V Moeller
Signal lamp
18 -H7 STR=/7.4 000100363101 Leuchtmelder HL
M22-L-R 24V Moeller
Signal lamp
19 -H8 STR=/7.4 000100363127 Leuchtmelder HL
M22-L-Y 24V Moeller
E Signal lamp E
20 -H9 STR=/7.5 000100363127 Leuchtmelder HL
M22-L-Y 24V Moeller
Signal lamp
21 -K1 STR=/8.5 000001255143 Koppelrelais KK
3TX7 Siemens
Couplerelay
22 -K10 STR=/8.1 000001255143 Koppelrelais KK
3TX7 Siemens
Couplerelay
23 -K10M STR=/8.1 000001335202 Leistungsschütz KL
3RT10 Siemens
Power contactor
B
Power contactor
6 -K4 STR=/8.6 000001255143 Koppelrelais KK
3TX7 Siemens
Couplerelay
7 -Q1 STR=/1.1 000100363016 Leistungsschalter QL
3RV10 40-50A+3RV19 330 Siemens
Power switch
8 -Q10 STR=/3.1 000100363017 Motorschutzschalter QM
3RV10 +3RV19/28-40A Siemens
Motor protec. switch
9 -Q2 STR=/1.3 000001255172 Motorschutzschalter QM
3RV10 0,45-0,63A Siemens
Motor protec. switch
C 10 -Q30 STR=/3.3 000100363018 Motorschutzschalter QM
3RV10 +3RV19/4,5-6,3A Siemens C
Motor protec. switch
11 -S1 STR=/1.4 000000361122 Thermostat STW
SK 3110 Rittal
Thermostat
12 -S2 STR=/5.2 000100363141 Schlüsselschalter SS
M22-WRS3 20 R-0-R Moeller
Key operated switch
13 -S3 STR=/5.4 000100363113 Knebelschalter SK
M22-WRLK-W 10 0-R Moeller
Lever switch
14 -S4 STR=/5.6 000100363113 Knebelschalter SK
M22-WRLK-W 10 0-R Moeller
Lever switch
D D
15 -S5 STR=/5.7 000100363108 Drucktaster ST
M22-DL-W 10 Moeller
Push button
16 -S6 STR=/5.8 000100363111 Drucktaster ST
M22-DL-B 10 Moeller
Push button
17 -T1 STR=/1.3 000001304947 Steuertrafo TT
4AM48 4 - 500VA (400/230) Siemens
Control Transformer
18 -U65 STR=/4.1 000001217389 Meßumformer UM
MCR-PT 100-I Phoenix
Transducer
19 -W1 STR=/2.6 000001335148 PROFIBUS DP Schnittstelle WPBS
CP342-5 Siemens
E PROFIBUS DP interface E
20 *
*
21 *
*
22 *
*
23 *
*
Connection DN 80
Nominal pressure PN 16
Oil flow rate approx. 335 l/min
Housing material EN-GJL-250
Material filter dome GK-Al
Filter fineness 60 mm
Filter element of VA metal fabric
with optical differential pressure display
with electrical differential pressure monitor
Type/No.: 2.F2
Number of switching contacts: 1
Contact rating:
1 A / 250 V AC / 60 VA
1 A / 250 V DC / 30 W
Type of protection: IP 65
Switch point: 20 = 2 bar
45 1 Manometer FLENDER
Type to Flender works standard: W 5914 B 5914
Connection G 1/4
Nominal size NG 63
Housing material: VA
Diese technische Unterlage hat gesetzlichen Schutz ( DIN 34 )
60 1 Thermometer FLENDER
Type to Flender works standard W 5924 B 5924
Connection: G 1/2
Nominal size NG 63
Housing material: VA
Measurement range −20 ... +120 °C / -4 ... +249 °F
with proctective tube
Connection protective tube G 1/2
length of protective tube 50 mm
Sondermaschinenbau
Fördertechnik
Näscher-SNV GmbH Nordstr.7-9 58300 Wetter
CNC-Zerspanung
ThyssenKrupp Robins, Inc. Lohnfertigung
7730 E. Belleview Avenue, #404
Greenwood Village, Colorado 80111 Telefon: 02335-9799-233
Telefax: 02335-9799-29
E-mail: witt@naescher-snv.de
Internet: www.naescher-snv.de
13.04.2006
The low speed flange coupling with the internal locking devices will be mounted as follows:
1. After opening the cases make sure that the couplings and locking devices are in
good condition and remove any pieces of wood or other pieces from the bore
2. Place and fix a pin of approx. 38 mm in one of the bores that will be used for bolting
the brake disk later
3. Pin should be approx. 250 mm long and the longer end should be faced to the
bottom while coupling is still in horizontal position as delivered
4. DO NOT remove the bolts from the internal locking device that are painted with red
colour ! ! ! !
5. Now the coupling together could be lifted up by crane and by using an appropriate
rope (no steel rope)
6. Make sure that coupling bore is in horizontal position when coupling is lifted up
completely
7. Now the inner surface of the bore should be cleaned carefully with a SLIGHTLY
oiled cloth
8. Unscrew all bolts several turns (2 – 3)
9. Drive coupling together with locking device slowly and carefully on the completely
cleaned surface of the pulley shaft
10. Make sure that there are no particles of any obstacles on the surface of the shaft
11. While coupling is still in horizontal position drive the coupling by crane in the final
position
12. Measure continuously!
13. Now the crane can drop the coupling until the inner bore of the locking device
reaches the shaft
Näscher-SNV GmbH Nordstr. 7-9 58300 Wetter USt-IdNr. DE 811531571 HRB Hagen 5040
Geschäftsführer: Dipl.-Kfm. Ralph Näscher Dipl.-Kffr. Birgit Schwickerath-Näscher Bernd Vorpahl
2
14. The red marked bolts can be removed; they are longer used
15. Tighten bolts by hand
16. Control the vertical position of the surface where the brake disc is connected to
later
17. Drop coupling completely and rope of crane can be removed
18. The bolts are tightened in several steps until the final torque of 1800 Nm is
reached:
First take the smaller torque wrench and use the special adapter that
fits to the torque wrench output (□ 3/4”) and to the nut with □ 1” and
SW 19 (fits into the bolts of locking device).
Adjust the smaller torque wrench (applicable for 140 Nm to 760 Nm) at
360 Nm and tighten the bolts in the sequence as described in the
attached drawing.
Only when ALL BOLTS have reached the 360 Nm, several controls are
necessary, adjust the next torque at the wrench.
Next step is 540 Nm; proceed the same sequence as above and
continue to the next torque after checking several times that ALL
BOLTS have the same torque of 540 Nm.
Next step is 720 Nm; proceed the same sequence as above and
continue to the next torque after checking several times that ALL
BOLTS have the same torque of 720 Nm.
For the following torques of 1080 Nm, 1440 Nm and finally 1800 Nm the
big torque wrench (applicable for 750 Nm to 2000 Nm) should be used.
The special adapter □ 3/4” □ 1” is no longer used, since the nuts fit
directly into the output of the big torque wrench.
19. During mounting ALWAYS the perpendicular position of flange to pulley shaft
should be controlled
20. Torque and/or sequence should be varied to keep the perpendicular position
21. Only controlled torque wrenches should be used all time
22. After ALL bolts have reached the 1800 Nm the torque should be controlled at least
two times in order to make sure that REALLY ALL bolts have the 1800 Nm
23. Further details can be gathered from the attached information
24. In case of any questions or doubt DO NOT CONTINUE!!! Ask the supplier before
anything uncontrolled is done ! ! !
Näscher-SNV GmbH
Axel Witt
Phone ++49 2335 97 99 233
Fax ++49 2335 97 99 29
Mail witt@naescher-snv.de
Näscher-SNV GmbH Nordstr. 7-9 58300 Wetter USt-IdNr. DE 811531571 HRB Hagen 5040
Geschäftsführer: Dipl.-Kfm. Ralph Näscher Dipl.-Kffr. Birgit Schwickerath-Näscher Bernd Vorpahl
=!~_88- industries I el
.,
~c,
USER'S MANUAL
JOHNSON CALIPER BRAKE
~
...~
v ... ~Western Office
8500 River Road
RichmondBC
Canada V6X1Y4
Tel: 6042733737
industries
/ e/evanja
0 EasternOffice
108 SkywayAvenue
TorontoON
Canada M9W4Y9
Tel: 4162139991
DEuropeanOffice
Bath Road
BridgwaterSomerset
England TA64NU
Tel: 01278456411
Fax: 6042739654 Fax: 4162139992 Fax: 01278429949
INDEX
1.0 INSTALLATION
1.1 GENERAL 1
1.2 MOUNTING 1
1.3 PLUMBING 2
1.4 FLUSHING 2
F:\dbr\generic_DH_man
ual.wpd
"
V
,
c'
-,.,
.
_8~8888
.
v' 1.0 INST ALLA TION
1.1 GENERAL
The Johnson Industries 'DH' series caliper brake is a direct acting type of brake
utilizing hydraulically applied actuators acting directly onto the brake shoe. The calipers
are mounted in a frame via two bearing pins. Teflon slide bearings in the caliper allow
the brake to float laterally on the bearing pins to compensatefor axial movement of the
disc or lining wear. The 'DS' caliper brakes are available in a large range of clamping
forces and can be selectedwith various types of friction grades. The brakes are
available with actuators on either left or right hand side or both sides and three different
styles of basesfor horizontal, vertical or inclined mounting. Contact Johnson Industries
for assistancein selecting a brake most suitable for the user's application.
1.2 MOUNTING
Discs are normally installed prior to placement of the caliper. Discs are shipped with a
rust inhibitor coating applied to the exposed surfaces. This coating will permanently
damage the friction linings if allowed to come in contact with the disc. It is imperative to
thoroughly remove the rust inhibitor with a cleaning solvent prior to installation of the
\-;
calipers. Most calipers are shipped in the releasedmode for ease . of installation.
Before tightening caliper bolts, clamp the caliper onto the disc. This is done by applying
1000 psi of hydraulic pressureto the actuators. The hydraulic power pack used to
manually release the brakes must be limited to a maximum pressure of 2000 psi and the
oil must be filtered to a 10 micron absolute (ISO 18/15) cleanliness level. With the
caliper clamped on the disc verify that the shoes are parallel with the disc and that the
base sits flat. Correct with shims if necessary. Verify that t~.epads are fully seatedon
the disc and that the assembly is centered with the disc. Reposition the brakes or shim
the base if required.
Once the caliper is properly positioned release the brakes and verify that the caliper has
adequatefloat on both sides of the brake frame. After bolting the brake frame in place,
release the caliper and ensure that the caliper floats freely. It is critical that the brakes
have adequateradial clearancebetween the disc outer diameter and the caliper center
plate. This clearance must be checked and verified to be a minimum of 3/16 of an inch.
Once the positioning of the brakes is verified to be correct the brake mounting bolts
must be tightened. Preload the mounting bolts to the value specified on the certified
drawing or to a maximum of seventy-five percent of the bolt proof load. Use either
lock washers or jam nuts to ensure that the mounting bolts do not work loose. The
V Page 1
~
.
_8~8888
V
. brake pedestal mustbedesigned
to allowenoughwrenchclearance
to properlytighten
the mounting bolts.
When operating temperatures exceed 300°F (150°C), oversized bolt holes should be
used in both disc and hub. It is preferable to drill the disc/hub mounting holes together
using the same set up.
1.3 PLUMBING
The brake system must be plumbed with adequately sized piping or tubing, preferably
stainless, suitably rated for the operating pressures. Generally, 1/2 inch diameter JIC
tubing and 1/2 inch diameter pipe is sufficient for most applications. The piping must be
adequately supported with pipe clamps every 4 feet. The connection to the brake must
be done with 3/8 inch diameter flexible hose suitably rated for the operating pressure.
Before connecting to the brakes, the plumbing must be purged to remove all the coarse
contaminants. After connecting to the brakes and hydraulic unit, thoroughly flush all
hydraulic systemsto a 10 micron absolute (ISO 17/14) cleanliness level before
applying full operating pressure.
When all connections have been made, air must be bled from all hydraulic actuators
during initial pressurization. The brakes must be cycled several.times to get all the air
~ out.
1.4 FLUSHING
w
t
~ For hydraulically released brakes the system must be flushed prior to commissioning the
~ equipment to ensure proper and reliable operation of the equipment. This procedure
,
~ must be done periodically or whenever the circuit has been broken to replace a
,.-
t component. For newly commissioned systemsthe piping and/or hoses must also be
r pre-flushed prior to connecting to the equipment to remove any coarse contaminants.
After plumbing the complete system can be flushed by following the guidelines below.
The oil should ideally be flushed to an I.S.O. cleanliness level of 17/14. This cleanliness
level can be achieved by using a ten micron (or finer) filter element with a beta rating of
75 (or higher). The duration of flushing should be sufficient to allow all the oil in the
reservoir and system to be circulated a minimum of four times through the filter.
The set up for flushing should include a suitable filter, as specified above, in the return
line portion of the circuit to filter out contaminants before the oil reachesthe reservoir.
It is undesirable to flush the contaminants into the reservoir as they will be picked up by
\.) the pump and possibly cause damage. Many hydraulic control units have a return line
Page 2
.
_8~8888
V
. filter in which case it is only required that the element be suitably rated. For those cases
that do not have a return line filter a spin-on filter can be temporarily added to the
Many hydraulic brake systems have reciprocating flow type circuits whereas flushing
requires circulatory flow. For these cases a suitably rated hose must be plumbed
betweenthe flushing filter andthe secondactuatorport. For flow throughtype circuits
a return line will alreadybe present.
WARNING!
Do not add a shutoff valve betweenthe filter and
reservoirashigh pressurewill burstthe filter.
2.1 LININGS
\-.) When installing new linings ensurethat the linings arebondedaswell asriveted andthat
Page3
...
..~I~.a It!~~{~~1'',:,
,,1;(*,,~f~~~)C;
!iJ:::'~~~
"
.
_8~888-
'-
" all the rivets are snug. In critical applications it is advantageousto carry a spare set of
lined brakes shoes to avoid down time of operating machinery. Replacement linings
must be as originally specified.
2.2 BURNISHING
Burnishing of friction linings is done to provide good, clean contact between the linings
and disc. The procedure removes minor contamination on the disc or linings as well as
any minor high spots or misalignment of the linings. New linings require burnishing to
fully embed the linings on the disc and periodically over the life of the linings to remove
any light contamination or oxide film from the swept face of the disc.
Before burnishing, ensure that the disc and linings are free from contamination. If
cleaning is required, use a non oil based solvent. If the swept face of the disc has a
heavy oxide layer then initial burnishing is required to remove it. This stage should be
done at a lower temperature and clamping force. After the rust is removed inspect the
linings and verify that the lining grooves have not become packed with loose debris.
Clean out the grooves if necessary. Heavily contaminated or burnt linings must be
discarded.
In addition to preparing the linings and disc for burnishing, any safety interlocks of the
"-" drive mechanism from the brake system should be bridged to aliow the disc to be
driven through the brakes.
To burnish, apply 500 to 750 psi pressure to the actuators and drive through the brakes
at a disc speed of 100 to 150 fpm. The clamping force of the brake shoescan be
adjusted by controlling the pressurein the actuators. It is preferable to burnish at the
high end of the range to reduce the burnishing time but ulti~ately the brake torque while
burnishing will be limited by the torque capacity of the drive. Insufficient lining pressure
during burnishing can polish the lining material, resulting in a reduction of the friction
coefficient. If this has happenedthe linings must be removed and sandedmanually to
scuff the surface.
The temperature must be monitored through out the burnishing process. The
temperature of the disc should be maintained between 250°F (120°) and 450°F
(230°C) for the best results. When the upper temperature limit is reached pause
burnishing until the disc has cooled to the lower limit. It may be necessaryto turn off
the coolant flow for water cooled discs.
V ;;"
;;:c
Page 4 '"
",tic
, ,
t ,
.
_8~8888
. CAUTION
V Never allow the disc temperatureto exceed500°F
(260°C). Permanentdamageto the lining material
will result.
CAUTION
Do not put equipmentinto serviceif ratedbrake
torquecannotbe developed.ConsultJohnson
Industriesfor assistance.
","
~,;;O
.':~:~
, ",'" .
Page5
""
...
,~
~,..
:;";
"
.
_8~8888
U
. equivalent mustbespecifiedfor thediscmaterialandspecialattentionmustbepaidto
the thermalandbrakingstresseson the disc/hubassembly.ConsultJohnsonIndustries
for suchapplications.
WARNING
NEVER APPLY WATER TO A HOT DISC
Permanentdamagein the form of heatcheckingand
warpingwill result.
2.5 LUBRICATION
Page6
"",;, ~
-,
.
_8~8888
. caliper. Although lubricating the slide bearings will reduce the sliding friction, this
""---" practice should be avoided if possible. The lubricant will attract dust and therefore
require more frequent maintenance intervals and possible reduce the life of the bearings.
When replacing linings ensure that the threads of the shoe pins have sufficient anti galling
compound applied and that an EP greaseis also applied to the shank.
Brake release and lining wear proximity switches are available as an option. The
switches are supplied pre wired to DIN 43650 spadeterminals. If present, both
switches must be adjusted whenever the air gap is adjusted. Failure to adjust the
switches will result in improper indication of pad wear and brake release.
Switch actuation of the brake releaseproximity switch must occur within 1/16 of an
inch of full actuator retraction. Ensure that the switch resets before the pads contact
the disc. The position of the switch in the caliper must be adjusted whenever the air
gap has been adjusted. This procedure is done by releasing the brakes, removing the
connector, loosening the jam nut and turning the switch housing clockwise. Advance
the switch housing until it contacts the shoe plate then retract it one quarter turn.
Secure the setting by tightening the jam nut to 25 foot-pounds.
\-.-
The lining wear limit switch is set to trip at a maximum air gap value of 3/16 of an inch
(4.5 mm). Maintaining the air gap within specified limits is critical to the overall
performance of the brake. It is important that the wear switch is properly adjusted
whenever the air gap is adjusted. The wear switch set point is adjusted in the exact
same manner as the release switch.
Page 7
.
_8~_88-
,
\I
" hydraulicactuatorsealingsurfaces
arepermittedsolongastheresultantradial
clearanceafter honing doesnot exceed0.004inches.
3.2 PRESSURESUPPLY
V
Page8
'!I{~f,'~i;~;;iI~~ 111111. ;.,;.,
'
'1'!I;,,""'!.i,'~,""j, , ,;"~,,
,:~J~t~4i~ " ~., L
'-
.
_8~8888
.
v 4.4 a. Contaminated Verify linings and disc dry and Clean with non oil base<
Brakes slip linings or disc free from oil solventandburnish.
Checkfor oil leaks.
Cleangroovesif
b. Poor lining contact Verify 75% minimum contact. necessary.Burnish
Verify groovesnot plugged. linings.
Page9
. ,
.
_8~8888
v
. 1. Friction linings (c/w rivets)
2. Actuator seals
3. Release& wear switches
4. Slide bearings
For critical applicationswith high duty cycle it may be advantageous
to carry a setof
lined shoes,actuatorassembliesandcaliper pins to reducedown time.
5.2 SERVICE
Page10
:II,
.
_8~8888
.
, byinadequate
storageor handlingpriorto or aftersaleto theenduserarenot covered
\I by thiswarranty.We reservetherightto makechanges
andaddimprovements
at any
time without incurring any obligationto makesuchchangesandimprovementson
productsalreadyproduced. This warrantyandguaranteeis in lieu of all warranties,
conditions,or liabilities implied by law or expressedby statute.
\.,...;
~
Page 11
~ M30X3.5 X 55 DP
65.0O:t 0.25 FOR LIFTING EYE
1mm CHAMFER
BOTH SIDES
(36) ~42.0
l I
I
~~ 0
SPACED 10.
~
00 OOw I
NO ON-l I
~'1' ~'1'~
- 8 ~0 ~ - L[) I
~2438.0:f:0.5-- --
a r--.:~"-
0 ro
I
N N OJo I
..- ..- I
J i
A
TAG NO'S ORIGINALOTY EXPANSION
OTY
120-CY-OO5 5 1
120-CY-OO6 5 1
120-CY-OO7 3 0
NOTE:
SPECIFICATIONS DISCS SUPPLIED COMPLETE WITH
MATERIAL: QT100 STEEL! ASTM - A514 M39 X 10.9
CLASS 175 AND
BOLTS TO934,
DIN DIN CLASS
931, 10
.
..~
WEIGHT: 1790 KG [3940 LBS]
industries
/ elevanja
NUTS.
a,
F A! SZg
O~g
OtS .
U)
I')
n OU~
lVO L08~
I.
ffi O~g
'01"9
<
~w
z-'
W
Ik:
::I
VI
~
<
~
~
L()
Ix:)
I
.
,"
,r-°Ll-
"'-'
r-;;;;-
1 1 ~VI~ 1-,< 1')1
I')
tU-I-tU-I-tU-I-
I ' I I
U-j-tU-1
I
~ ~
~ ~
~oo:t
T I.r -
o I-,
Ik:
Ik:w
Oil.
fD:
Il.U
::I ..l-I
Ti
Ik: 1k:0 ~ ,
I..L.I
N
"i'~ ~ a;
~ > :2
1
~ 0 1'1
III Z -a.
,-
~ w
..
'<
'"
"'- .,
~
I.-
u
a.
'-
--- III w.. '0:
'01" ~ ~ ~ ~
~ ~ ~ ~ ;1:
0 'tJ 'f.'I'J:!'g1n
0 ~ 1'- '0
0 g:;-~g~i
.e ZQ.~F;
0 g ~a~~
0
ww Sg >- (I)
0 -.J Q)
(]) lOB
0 ~ OE
w 00
U") -
«
U")
>- ~Q)
Q.
O W"(I)
w-.J~o
~-.Jo-l
0 « ~ I 0
~il->1.-
0 (]) OQ)
il- I .S
0 ~~o~
0 ~ I~'
0 :J~U)a.
« .:3-~a.
«0:3
ul--~~
(]) >t:
0 zQ)
-..t o~
~ 0 0>-
N ~ .J::
I l-
II
-'-' ... . <
~
w
:I:
~~ I I-,
o
W
~~ 0'
UJ
~
- VI~ VI
W
W
~ rN...o.
~ ~~ I-, I3:. ~ VI .~ \2 ~
'-'
0 UVI N < a --'" 0. 0.
"..
-'z:X;:X;
~Flk:lk:ww
Ik: fD
~
I-,
i>
VI!:=
0
0
I
E -'
U
~
I
I
ro-.
rN
~...
N ~
N
Z zQ.
,,::1-;:--;:-O::ol~u
~
~x~ ,,~
~ ~
-'
~'"
'-.-
... N
~ 0
Ik:ZO~~zulk:-
w ~ ~
Il.
:;j1l.-"""'W'-'~fD
< VI<IlIu)r-.Il.<~
UOOO
Ik:-
~ ~
U~CXI
<
Ik:
-0
~ Ik: I
xll.
0 UN
U)
1k:~!:=I')"OJ
J, 0
~
00
0
.
cS
~
I-,
f;3
..,
-'
~!:; ~
-::Jw
- 0
0
~ z
~~
,.,
Qj
~
~ ~
I
I
"
I
I
U'FOOO~ I') ~U~ 1l.~i1;N ~OJOJa-a- 3:~ "'0 :;;-
"Ow»><wU)
1k:1111k:1k:U1~ IDU O~"<w- ~ VIa-a- ~~'" ~ Ik:'"
~ fDF < ~
Zw>UUUfDll.
gll.
I r-.OO~Z~lk:u~ffi~~OO- w ::Ju , ~
~ ~~
~:;j III ~X Oo)N::>~°::1 a a III I') Il.~ -0
~ 'OOOr o N~~~~~,<8R~~;;;:::t.~ 3:-'
~
~ '-'
... NNN~OO
Ik:~~~~no
- Ik:
Olk:wlk:'-'U
< x
~
UVI
- Ik:~
ww
(/) :'
~ N
0
z ~~Ik:Ik:Ik:~'E: .. ..~~~Il.~~~ 0:: >-:~ O~ Q.Z -~ ~ ~
~-'-'OOO I~~ ~~~ UJ3:~~ '01" 00::'-'0 ~O ~O ~
Q 'oI"~~~~~~Z~< ~~~~~"I-,>-O::~~,<w~~ ~I-, UI-, Z +J
-
~ ~
~
I-- Olk:
NOOZZZr-.
»> ~CXI~
~Ik:
-~-~WZ
~ '-'-
U XOlk:w::lQ.w~
0-'::10 -'VI~
O ~ A U ~
« I>-~OOO'ol"~'oI"O ~O~'oI"UJZ~Il.OOIt;<Vla: Z 'oI"~ (/) ~ ~
0 OI~UUUr-.NNZ ~Z~~Ik::;jOWU"'VI<U<~ ~Q ~O ~ ~ : ~
[;: ~~ [g~ v "'C -g §
U ~~ ~~ ~
.
-- C.3 ]'
..
W..
n VI
U~
-Z
Z >-
0 ,n U ~
"
L1-
~ .. w""
Ik: VI Z
'-'
::1-
<lk:cJlk:S
-
I-,Ik:
v,
I--,
~
m
-g
"
e
E
"
Z
::I
VI
w
~ ..
0
-
1k:0
o...~1l.1k:
01-, 0
~
00
E tn
~ - ww VI ::I Z I-, >- COw ~
wwo
o ~Z U::Iw
Ik:O Ik: ,-",0
0 ,<F ~
- Iwlk:l-,
VlWIl. ~
.c
.~~ ~
oc
~
0.' <:$ 0 Ik: ..Il. > 0 < ~ 'O~ ~ 0 -c 0-
..
ZIk:~ "'ou ,-,I-, U o<"z I o:E
~O...
~ Ik: "0 I-,\Q~
Z ~...Z
Z W UJ..
Il. > ,-,-,lk:zF.
< fD;::VlZ "
'-'
~ IS
1k:<1k:~ ~~ F F '-'~ VI!:=~ VI t::O>-V>X3: Z . ~-c
~~w<
~,-,Q.::I
Il.zUJ<
~-~Ik:
<
Ik:
<::I
~Ik: I-,
I-, I
Z
O
z
-
Qwlk:XWO
o:J<w I
< .~
oc oc
8
'-'1l.'-'1-, ..r~<w W ~t;; ~ <Q I-, Il.F ~VI Q O.c
<1l.<U -.J01k:1l. Il. <v, <::IUJ Il. wll.lk:WO < 0 ~
U<U< UZfDO 0 ~~ ~ ~~ ~ ~~i)?;~~E~ g . ~ IE
":N,.j~ IricO"':lXi
m~::: ~ ~~ ~ ~..: N ~~ ...
.,
115VAC
NE RAL
BRAKE #1
LS1
1 - '" - -/ ~
~ Brake Released
Dr al\o ~oroa~ou
L-
r--
TS1 TS2
- - - -i Lining Temperature O.Kr -
5 6 7 8
LSZ
0---0--- - - - -1 Linings worn I adjust air-gap r-
9 10
&
LS3
BRAKE #2
-1 Brake Released I-
11
14
TS3 TS4
- - - -i Lining TemperatureO.K.f- -
1 20
LS4
0---0- - - - -1 Liningsworn I adjust air-gap r-
21 22
&
SETTINGS LEGEND
TS1, TS2, TS3, TS4: 170'C FALLING LS1,LS3 - BRAKE RELEASE INDICATING PROXIMITY SWITCH
LS1, LS3: FULLY RETRACTED LS2,LS4 - AIR GAPILiNING WEAR INDICATINGPROXIMITYSWITCH
LS2, LS4: 4mm EXTENDING TS1",.4 - DISC TEMPERATUREINTER LOCK SWITCH
.
..~ industries/elevanja
ELECTRICAL SCHEMATIC
2DS2040A & 2DS2040B CALIPER BRAKES
CONVEYORS120-CV-005, -006, & -007
", .
8500 River .
Rood. Richmond
Tel 604 273 3737 --
BC Conodo V6X 1Y4
Fox 604 273 9654
BY:
SC:
di:I DATE: 98/06/02
REV.-4 Y.K, JanJ06
DWG. NO.
0 0
0 0
.". . . . . .
LEFT HAND SHOWN
(RIGHT HAND OPPOSITE)
...
~
INDUSTRIES LTD.
pjt/lpcnvrs/r14/lp385912
KRUPP
PELAMBRES
CANADA
CONVEYORS 120-CV-O5. & -06
8500 RIVERROAD.RICHMOND
BC FAX.(604) 273 9654 J/N 3859 SID JAN 99 DWG. NO.
CANADAV6X IY4 TLX.04-357554 S N's A3859- P2
-,
illM PART NO. .Qli DESCRIPTION
1 BHA1040 2 ACTUATOR ASSEMBLY
2 BBFL3859 1 ACTUATOR PLATE
3 BBFC3859 1 CENTER PLATE
4 BBFR3859 1 CALIPER PLATE
5 BS4978 2 SHOE PLATE
6 BFS3859 20 FRICTION LINING - 3 RIVET
. 7 BFSGBK3 20 FRICTION LINING - 2' RIVET
8 BILS3859 1 LINING INSULATER
9 F6R17 100 LINING RIVETS
10 BPSG3859 4 SHOE GUIDE PIN
11 BSRS2050 2 SHOE RETURN SPRING
12 BSB2040 4 SLIDE BEARING
13 F22C248H5 6 CALIPER ASSEMBLY BOLT
14 F22C5N 6 CALIPER ASSEMBLY NUT
15 F18C56S8 8 ACTUATOR MOUNTING BOLT
16 BMBLE16 2 CALIPER LIFTING EYE
17 BMBLE6 4 SHOE LIFTING EYE
18 BLTS3859 2 LINING TEPERATURE SWITCH
19 BRPS3040 1 BRAKE RELEASE SWITCH
20 BWPS3040 1 LINING WEAR SWITCH
21 BHH3859 1 FLOW-THRU LINE HOSE
22 F8DP32 4 DOWELL PIN
ASSEMBLY NOTES
1 APPLY RUST INHIBITOR TO SURFACES OF CENTER PLATE (ITEM 3) BEFORE ASSEMBLY
2 SANDBLAST AND APPLY PRIMER BEFORE MOUNTING ACTUATORS
3 FRICTION LININGS (ITEM 6 & 7) RIVETED TO SHOE PLATES (ITEM5)
4 APPLY NEVER SEIZE TO THREADS OF SHOE GUIDE PIN (ITEM 10)
5 TORQUE ACTUATOR BOLTS (ITEM 15) TO 580 FT-LBS
6 TORQUE CALIPER ASSEMBLY NUTS (ITEM 14) TO 650 FT-LBS
.
..~
7 ALLIGN FLATS OF NUTS AND BOLTS WITH CURVATUREOF FRAME
8 THERMAL INSULATOR APPLIED TO ACTUATOR SIDE ONLY
industries / elevanja
DH2040 CALIPER BRAKE
PARTS
LIST& ASSEMBLY
DETAIL
'" 8500 River Rood. Richmond BC Canada V6X 1Y4
Tel 604 273 3737 -- Fox 604 273 9654
BY: HE
SC:
DATE:NOV 05
REV.
DWG. NO.
~'i~
-;
PA RTS LI ST
'
. .~ dbrjoctjds_octrsj1040osm
industries / elevanja Itd BAH 11 40 ACTUATOR
"
Vancouver BC Canada -- Tel: 604 273 3737 Fax: 604 273 9654 GUST. MINERA LOS
ASSEMBLY
PELAMBRES
Toronto ON Canada -- Tel: 416 213 9991 Fax: 416 213 9992 JjN 4978 SID Mar .20/06 DWG. NO.
Bridgwater SaM England -- Tel:01278,456411
Fax:01278429949S N's BAH1040-418806-1,..-10 A1040-P2.1
-,
D.lE
1.
1 A1
The
shell
of
each
THE
the Con
catalo
numb
the con
curre
ratin
range
and
the the
tem
conta
arran
FEI"t\ftIAl.: THERMOSWITCH@
Contr
that
are
com
Undereco
or
Labo
or liste
by
certi
by
Can
Temperature Controller
Stand
Asso
(CSA
will
also
bea
the
sym
of
"'"\-.,I Installation Instructions
the
appro
agen
"4"
as In
addi
theUL
com
nized
units
awith
temp
firstrec
rang
up
to
500
will
hav
digit
of
Thethe
Cata
Num
fifth
digit
of
the
cata
num
des
whe
con
ATTENTION: To ensure safe and proper performance, read
tacts
open
or
close
on
temp
rise
If
con
ope
these instructions carefully before attempting to install or operate
on
temp
rise,
fifth
digit
of
the
num
is
an
eve
this Fenwal product. Please retain for future reference. Temperature
Adjusting
Sleeve
numb
(1700
If1700
theetc.)
If
cont
ature
rise,
close
on
temp
is
(-
73Low
to
+
204°
can
onebe
hour.clos
on
fourth
digit
is
"2"
or
"7"tem
fifth
digit
is
an
odd
(170
etc.).170
(e.g
170
170
~troffe
is
comp the
con
oper
Comc'
unit
rise
aretha
reco
if~~
ove
antici
temp =
units
[-10
to
+
400
over
to
500(
(26'"
.r~
,!,,
L.
r
iQ 1
~~
.
THER
Cont
headare
sup
in
five
config
- bas
Cartrec
Bloc
Hea
Hexthe
0.1
Heain
di
the
un lo
fro
ro
whp
th
asTp
is
t
C""c'.
Coup
Head
and
Circu
Flan
See
Figu
1.
Th
casty
mb
us
fo
cie
c~ cc' C c",'
To
avoid
restri
shell
expa
whe
tions
in mak
solid
meta inst
block
for
5/8a
0.62
in
0.81
In
13/16
heav
duty
is ser
diam
rea
stand int
a
hol
units
or 11Fe
Blo
reco
SeeHe
(S
the su
m
2)
fol-
the
ca -
M
typ
If
th w
(
in
a
un
is
to
bim
i
aN
n
rn
and high temperature units [-100 to +600°F (- 73 to 3 4 5
lowin
spec
contr
style
listin
for
add
inst
ho
mo
tw
sh
pi
on
ei
so
t
hTh
+316°C)] overrangedto 700°Ffor intervalsnot exceeding
tion
instru pin
sh
res
ag
vensi
rot
of o
t
b t
p
t
He
an
Co
He
(S
3
a
4-
In
l
INSTALLATION
pip
fitt
If
ins
in
a
pi
te
th
te
s b
Figure 1
lar
en
to
all
ad
cot
f
MOUNTING Cartridge (Style 1) - Hole should have a short spline to
1
~ aro the
tem
Se
Ta
1
for
m se
toch
va
INSTALLATION (Continued) 2. When removing controller from a heated system, never
I ~CAUTION I plu~ge it i.nto a colder medium or use an air blast for
I ~"'AU. .un I rapid cooling.
Excessivetorque applied to units may change temperatureset-
tings. Tension or Compression Operated Controllers
Table 1 1. Certain gases or liquids (including water at elevated J'
temperature) could be corrosive and/or cause electro-
THERMOSWITCH
Controller Max.Torque lytic action which could severely shorten life of control-
Standard(5/8in dia) 35 ft-lb* ler. Rate of corrosionor electrolysisis i~fluencedby
(47.5 N-m) many system parameters such as chemical makeup,
. . 70 ft-lb** temperature of solution, stray electrical currents, etc.
Heavy Duty (13/16 In dla) 94.9 Nom) Consult supplier of your chemicals or Fenwal for appli-
*4 ftolb(5.4 Nom)whenTeflontape lubricantis used. cation s~ggestions. Also, note th~t Fenwal offers ~ari-
**8 ftolb(10.8Nom)whenTeflontape lubricantis used. ous platings and Type 321 Stainless steel, hellarc
welded thermowells for added protection.
-
Circular Flange (Style 5) Three holes in flange allow . .. .
easy mounting on any flat surface. 2. Be sure that there IS sufficient but not excessive room
I h..~...~.ft..~1 for the installedcontrollerto expand in diameterand
I ~CAUTIONSI length.
Tens!on Operated Controllers . 3. Insulate head of controller when large ambient temper-
:~nslon op~rated THERMOSWITCH controllers are Id~n.- ature variations may occur. This precaution is not
tlfled by having a number other than 2 or 7 as the fourth digit necessary on junction box type controllers (Series
of their Catalog Number. Applying excess tension on the 17800).
element of a tension operated controller may permanently . . ..
warp the element, and in extreme cases, tear the anchor 4. DO ~OT Imme~s.econtrolle~ Into liquids or gases un-
pin loose. To avoid over-tension, pay close attention to the less It was specified for that job.
following cautions: 5. DO NOT seal controller head with silicone materials.
1. Do not expose controller to temperatures above its 6. DO NOT thermally shield controller from medium being
upper range limit. controlled. ~
1- ~
J
!
Table 2 TESTING TEMPERATURE SET POINT
S' Capacitance(fLF) The set point temperatureis the temperatureat which the
Voltage ervlce (nonpolarized) contacts on a THERMOSWITCH Controller just "make"
120VAC Resistance None Required (close). All controllers are set at room temperature [75
V 240 VAC Resistance 0.1 ::t 15°F (24 ::t8°C)] unless ordered with a specific factory
120 VAC Relays 0.001 to 0.01 setting (MOD 3).
240 VAC Relays 0.001 to 0.01 Testing the temperature set point in an application, under
15-25VAC Relays 0.02 conditionswhere the heat source is remotelylocatedfrom
120 VAC Motor Use Relay the controller, or when ambient temperature conditions are
240 VAC Motor Use Relay far below or above 75°F (24°C), may give misleading re-
sults. In some cases, this has led to rejection of controllers
that were within proper setting tolerance. If you require tem-
TESTING AND ADJUSTMENT perature set point testing, Fenwal recommends the Model
The arrow on the head of the controller indicates the direc- 80001-0 Test Kit. If you choose to build your own test
tion to turn the adjusting screw to increase the temperature equipment, .we reco~mend t.hat yo.u contact your Fenwal
setting. Each full turn of the adjusting sleeve will change the representative for guidance In setting up a good thermal
temperature the approximate amount shown in Table 3. test system.
V
~-
;i~~"":;j;$;;;...:j
~~-~-~~ --J
- "~1rc
,,"-, Tension Operated CompressionOperated
~ Approx. Fo Approx. Fo
""
Catalog Per Full Catalog Per Full
Number Turn of Number Turn of
Adj Sleeve Adj Sleeve
15050 to 16051 165 - -
17000 to 17352 80-115 17021 to 17323 70-100
17800 125 17821 75
17802 160 17823 90
18000 to 18002 80-100 18021 to 18023 75-90
~
...~ industries / elevanja
\J
.,
P
~Western Office
8500RiverRoad
RichmondBC
0 EasternOffice
108SkywayAvenue
TorontoON
DEuropeanOffice
BathRoad
BridgwaterSomerset
Canada V6X 1Y4 Canada M9W4Y9 England TA64NU
Tel: 6042733737 Tel: 4162139991 Tel: 01278456411
Fax:6042739654 Fax:4162139992 Fax: 01278429949
INDEX
1.0 INSTALLATION
1.1 GENERAL 1
1.2 MOUNTING 1
1.3 PLUMBING 2
1.4 FLUSHING 2
3.0 ACTUATORS
3.1 INSPECTIONAND MAINTENANCE 8
3.2 PRESSURE SUPPLY '..'..' '.' '.' ', 9
F :\dbr\generic_DS_manual" wpd
u
.~..~
1.0 INSTALLATION
1.1 GENERAL
The Johnson Industries 'DS' series caliper brake is a direct acting type of brake
utilizing spring set, hydraulically releasedactuators acting directly onto the brake shoe.
The calipers are mounted in a frame via two bearing pins. Teflon slide bearings in the
caliper allow the brake to float laterally on the bearing pins to compensatefor axial
movement of the disc or lining wear. The 'DS' caliper brakes are available in a large
range of clamping forces and can be selected with various types of friction grades. The
brakes are available in either left or right hand orientation and three different styles of
basesfor horizontal, vertical or inclined mounting. Contact Johnson Industries for
assistancein selecting a brake most suitable for the user's application.
1.2 MOUNTING
Discs are normally installed prior to placement of the caliper. Discs are shipped with a
rust inhibitor coating applied to the exposed surfaces. This coating will permanently
damage the friction linings if allowed to come in contact with the disc. It is imperative to
"'"-" thoroughly remove the rust inhibitor with a cleaning solvent prior to installation of the
calipers. Most calipers are shipped in the released mode for easeof installation.
Before tightening caliper bolts, set the caliper to clamp on the disc. This is done by
removing the caging ring from the actuators. To remove the caging ring, apply enough
pressureto the actuator to fully releasethe brakes (see the certified print at the back of
this manual). With the actuator pressurized, remove the cover and unscrew the caging
ring. Flip the caging ring around to mount the ring in the stowed position and re-install
the cover plate. Refer to the actuator instruction sheet at the back of this manual. The
hydraulic power pack used to manually release the brakes must be limited to a
maximum pressure of 3000 psi and the oil must be filtered to a 10 micron absolute
(ISO 18/15) cleanliness level. With the caliper clamped on the disc verify that the
shoes are parallel with the disc and that the base sits flat. Correct with shims if
necessary. Verify that the pads are fully seatedon the disc and that the assembly is
centered with the disc. Reposition the brakes or shim the base if required.
Once the caliper is properly positioned release the brakes and verify that the caliper has
adequatefloat on both sides of the brake frame. After bolting the brake frame in place,
releasethe caliper and ensure that the caliper floats freely. It is critical that the brakes
have adequateradial clearance between the disc outer diameter and the caliper center
, plate. This clearance must be checked and verified to be a minimum of 3/16 of an inch.
V Once the positioning of the brakes is verified to be correct the brake mounting bolts
Page 1
v
.~..~
must be tightened. Preloadthe mountingbolts to the value specifiedon the certified
drawingor to a maximum of seventy-fivepercentof the bolt proof load. Use either
lock washersor jam nuts to ensurethat the mountingbolts do not work loose. The
brakepedestalmust be designedto allow enoughwrenchclearanceto properlytighten
the mountingbolts.
1.3 PLUMBING
1.4 FLUSHING
~~~c
v
."..~
It is undesirableto flush the contaminantsinto the reservoirasthey will be picked up by
the pump andpossiblycausedamage.Many hydrauliccontrol units havea return line
filter in which caseit is only requiredthat the elementbe suitablyrated. For thosecases
that do not havea return line filter a spin-onfilter canbe temporarilyaddedto the
circuit for flushing.
WARNING!
".-I Do not adda shut off valve betweenthe filter and.
reservoirashigh pressurewill burst the filter.
2.1 LININGS
-""-""'~""'"""""
\-/
."..~
a non oil based solvent and burnished.
When the lining thickness wears down to 0.28 inches the shoesmust be removed and
new linings installed. Allowing the linings to wear further will eventually result in the
rivets contacting and scoring the disc. In dynamic applications, wearing of the linings
beyond the bottom of the lining grooves or allowing the grooves to become packed
with loose debris will have a detrimental effect on the stopping capacity of the brakes.
When installing new linings ensure that the linings are bonded as well as riveted and that
the rivets are all snug. In critical applications it is advantageousto carry a spare set of
lined brakes shoesto avoid down time of operating machinery. Replacement linings
must be as originally specified.
2.2 BURNISHING
Burnishing of friction linings is done to provide good, clean contact between the linings
and disc. The procedure removes minor contamination on the disc or linings as well as
any minor high spots or misalignment of the linings. New linings require burnishing to
fully embed the linings on the disc and periodically over the life of the linings to remove
v any light contamination or oxide film from the swept face of the disc.
Before burnishing, ensure that the disc and linings are free from contamination. If
cleaning is required, use a non oil based solvent. If the swept face of the disc has a
heavy oxide layer then initial burnishing is required to remove it. This stage should be
done at a lower temperature and clamping force. After the rust is removed inspect the
linings and verify that the lining grooves have not become packed with loose debris.
Clean out the grooves if necessary. Heavily contaminated or burnt linings must be
discarded.
In addition to preparing the linings and disc for burnishing, any safety interlocks of the
drive mechanism from the brake system should be bridged to allow the disc to be
driven through the brakes.
To burnish, the clamping force of the brake shoes and disc speed should selected so
that the frictional power generatedis in the range of 0.15 to 4.5 horsepower per square
inch of lining area. The clamping force of the brake shoescan be adjusted by
contr~lling the pressurein the actuators. It is preferable to burnish at the high end of the
range to reduce the burnishing time but ultimately the brake torque while burnishing will
be limited by the torque capacity of the drive. Insufficient lining pressure during
~ burnishing can polish the lining material, resulting in a reduction of the friction coefficient.
If this has happenedthe linings must be removed and sandedmanually to scuff the
Page 4
~
.~..~
surface.
The temperature must be monitored through out the burnishing process. The
temperature of the disc should be maintained between 2500P (120°) and 4500P
(230°C). When the upper temperature limit is reached pause burnishing until the disc
has cooled to the lower limit.
CAUTION
Never allow the disc temperature to exceed 5000P
(260°C). Permanent damageto the lining material
will result.
Burnish until a minimum of seventy-five percent lining contact and a bright disc surface
is achieved. To measure the degree of contact, set the brakes and use a .002" feeler
gauge to probe the perimeter of each brake shoe. If the amount the feeler gauge was
able to probe exceedstwenty-five percent of the lining area then further burnishing is
required. The adequacyof burnishing must also be verified with load tests or stopping
time measurements. If the actual brake torque does not meet the rated brake torque
""-" then further burnishing is required.
CAUTION
Do not put equipment into service if rated brake
torque cannot be developed. Consult Johnson
Industries for assistance.
For standard applications the disc should be manufactured from ASTM A588 or
equivalent material. The disc must be suitably dimensioned for the brake application.
The O.D. must be selected to provide the desired torque, the I.D. must allow enough
radial clearance to remove the shoesduring liner replacement and the thickness must be
chosen to safely absorb the brake energy input. Refer to the certified drawing at the
back of this manual for critical dimensions. For bolted connections the locating
diameter of the disc should be machined to a H8 tolerance class. The disc should be
balanced to ISO 1940/1 grade G40 for low speedapplications and G6.3 for high
speed applications. The swept path of the disc should have a surface finish within 32 to
64 rms micro inches. Surface finishes in excess of the maximum will result in rough
~ braking action and rapid lining wear. Scored or rough discs must be reconditioned,
Page 5
\;;
."..~
removingno morethan0.02 inchesper inch of thickness.Facesshouldbe flat and
parallel within 0.004inchesacrossthe sweptface. Lateral andradial run-out should
not exceed0.001inchesand0.002 inchesper 12 inchesof diameterrespectively.
WARNING
NEVER APPLY WATER TO A HOT DISC
Permanentdamagein the form of heatcheckingand
warpingwill result.
!g.!i~
"
\,
."..~
removingno more than0.02 inchesper inch of thickness.Facesshouldbe flat and
parallel within 0.004inchesacrossthe sweptface. Lateralandradial run-out should
not exceed0.001 inchesand0.002inchesper 12 inchesof diameterrespectively.
WARNING
NEVER APPLY WATER TO A HOT DISC
Permanentdamagein the form of heatcheckingand
warping will result.
I
v
."..~
air gap. After adjusting the air gap the release and wear switches must be adjusted also
(see section 3.5). The air gap is measuredby pushing one shoe against the disc while
measuring the distance between the lining and disc on the other shoe. Refer to the air
gap adjustment procedures (drawing DSPS-Ol) at the back of this manual.
WARNING
Adjusting the air gap without releasepressurein the
actuator will result in damage to the actuator spindle.
For applications that require a faster responsetime of the brakes, the air gap can be
reduced. In these casesclose attention must be paid to the axial run-out of the disc and
for possible dragging of the shoes. In applications with high axial run-out of the disc the
air gap can be increased to compensate. For these casesconsult Johnson Industries as
the lateral float capability of the brakes is critical.
"-- When adjusting the air gap, ensure that the caliper floats freely.' It will be necessary,on
a regular basis, to remove the bearing pins and clean both pins and slide bearings in the
caliper. Although lubricating the slide bearings will reduce the sliding friction, this
practice should be avoided if possible. The lubricant will attract dust and therefore
require more frequent maintenance intervals and possible reduce the life of the bearings.
When replacing linings ensure that the threads of the shoe pins have sufficient anti galling
compound applied and that pins on the actuator side also haS'an EP greaseapplied to
the shank.
Brake release and lining wear proximity switches are available as an option. The
switches are supplied pre wired to DIN 43650 spadeterminals. If present, both
switches must be adjusted whenever the air gap is adjusted. Failure to adjust the
switches will result in improper indication of pad wear and brake release.
Switch actuation of the brake release proximity switch must occur within 1/16 of an
inch of full actuator retraction. Ensure that the switch resetsbefore the pads contact
the disc. The position of the switch in the caliper must be adjusted whenever the air
V gap has been adjusted. This procedure is done by releasing the brakes, removing the
connector, loosening the jam nut and turning the switch housing clockwise. Advance
Page 7
II.
v
."..~
the switch housinguntil it contactsthe shoeplatethen retractit one quarterturn.
Securethe settingby tighteningthejam nut to 25 foot-pounds.
The lining wear limit switch is setto trip at a maximumair gapvalue of 3/16 of an inch
(4.5 mm). Maintaining the air gapwithin specifiedlimits is critical to the overall
performanceof the brake;an excessiveair gapresultsin insufficient braking torque. It
is importantthat the wear switch is properlyadjustedwheneverthe air gapis adjusted.
The wear switch setpoint is adjustedin the exactsamemannerasthe releaseswitch.
3.0 ACTUATORS
"
v'
."..~
this manual for the specified release and hold-off pressures. The measuredvalues must
be within plus or minus ten percent of the specified pressures.
A hydraulic control system should supply well filtered, high quality, petroleum based
fluid having good lubricity and oxidation resistance. An ISO VG32 hydraulic oil having
a viscosity index greater then 200 is recommended. The viscosity must not exceed
1000 cSt (4500 SUS) at the minimum ambient temperature. Bleed air from actuator
and lines after installation or servicing. Failure to bleed air from hydraulic lines and
actuator will result in slow and erratic actuation and can damage the seals.
\,-
V ;:;~
C'"',"'"
."'"
!j~'"
~.I
""c.:'ci'lJi:"'1"" Page 9
~~f~~f~
i""
f;\\-i
"'--'"
."..~
4.0 TROUBLE SHOOTING
v
Page10
-,~C,
-~..~
V
4.4 a. Contaminatedlining Verify linings and disc dry and Cleanwith solventand
Brakes slip or disc free from oil burnish. Checkfor oil
leaks.
R¥,conditionsweptface
c. Roughdisc surface Verify surfacefinish within of disc
finish specifications
Repositionand/orshim
. e. Linings not fully Verify brakesproperly brakesto fully seat
seatedon disc positionedand mounted. linings
Correctdisc run-out if
f. High axial run-out Measureaxial run-out. Verify possible. Adjust air gap
adequateair gap and lateral to accommodatedisc.
float.
Limit duty cycle of
brakes
g. Excessivedisc Verify maximumdisc
V temperature temperaturenot exceeded.
Page11
~""""'~,'x*c'"
-"..~
V
5.0 WARRANTY AND SERVICE
5.2 SERVICE
5.3 WARRANTY
Page12
I,
-"..~
V
goods or parts thereof which are shown to our satisfaction to have been proved, under
their intended use, defective in materials and workmanship within the ninety day
guaranteeperiod, provided that such defective parts are promptly returned as directed
by us, transportation chargesbeing paid by the purchaser, and provided further that no
burning or welding or any modifications of any sort has been done on any such defective
goods or parts. In every case,the customer shall be charged for replacement parts on a
pro rata basis for the elapsedportion of the warranty period. In the case of friction
linings, products and components manufactured by others, we extend to the Purchaser
the warranties of the manufacturer only. Deterioration, damage,or malfunction caused
by inadequate storage or handling prior to or after sale to the end user are not covered
by this warranty. We reserve the right to make changesand add improvements at any
time without incurring any obligation to make such changesand improvements on
products already produced. This warranty and guaranteeis in lieu of all warranties,
conditions, or liabilities implied by law or expressedby statute.
~
Page 13
-'-'"""-,"",,,y.~c
,
.
..~ industries
/ elevanja
AIR GAP ADJUSTMENT PROCEDURE
--, I
LI
I
I
I
I
I
I
I
I
I
I
I
I
rI
-_oJ
1. Ensure that the conveyor drive is locked out and that the conveyor is dogged or held
by another brake while the adjustments are being made;
2. Remove electrical connectors CD from rear of switches;
3. Loosen jam nuts (2) on switch body Q) ;
4. Rotate switch body Q) counter-clockwise until switch nose @) is recessed in brake base ~ ;
5. Apply full rel.ease pressure to braKe;
6. Screw the switch body ~
in until switch nose @ contacts rear of brake shoe @ ;
7. Back switch housing out 1/4 turn and tighten jam nuts (2) ;
8.. Replace electrical connectors G) ;
9. Return the brake to its set condition and remove any dog gin means employed to secure the hoist
while the switch adjustment was made.
WARNING: Before removing brake shoe @ for lining replacement recess switch nose @)fully.
Impact -to switch nose will damage switch.
WARNING: The position of the switch inside the housing (J) is factory set.
DO NOT ADJUST.
~-l'-('I7,"'
I
I
II
F"'---~_-L-_,--
:I I ==
,
I
I
I
I
t t
-=
-
,.-
~I
I
I
I
I I I
I
I
t-rf""'~?"'--'--
I
,.. --
--
I
JI
-L ~"" I 1
I L.-
I
I
I
I
I
I
I
I
I
I
I
J
I
I
J
1. Ensure that the conveyor drive is locked out and that the conveyor is dogged or held
by another brake while the adjustments are being made;
2. Fully release brake and cage actuators, remove temperature switches;
3. Retract actuator spindles per drawing DSPSS-01 and switches per drawing DSSA-01;
4. Secure brake shoes with hoist rings ; ~
5. Remove shoe guide pins Q) and return springs <2) on actuator side;
6. Remove brake shoes, reline and reinstall or replace with newly lined shoes;
7'. Replace shoe guide pins G) being sure to install return springs (?) on actuator side. Insure that
shoe pins are fully threaded into shoe;
8. Adjust actuator spindles per drawing DSPSS-01 and switches per drawing DSSA-01;
9. Return the brake to its set condition and remove any dogging means employed to secure the
conveyor while the shoe replacement was made.
.
..~ industries/ elevanja
'OS' SERIES BRAKE SHOE REPLACEMENT
PROCEDURE
" 8500 River Road, Richmond BC Conada V6X 1Y4
Tel 604 2.73 3737 -- Fax 604 273 9654
BY:
SC:
DCA DATE:
REV.
950622
950911
DWG. NO.
0 S P R - 0 1 2
Both Rood. Brldgwater Somerset England TA6 4NU
Tel 0278 456411 -- Fax 0278 429949 PAJH'. dbr /h Sp/R 14/3859d spr .
-
WARNING
Spring brake actuators store energy and can be dangerous.
Handle with caution. Follow proper procedure.
Always loosen assembly bolts uniformly.
A = 1.22:1:
0.01
1. Cage and remove actuator from the caliper brake (note assembly weight);
4. Compress springs in press with allowance to access spring guide at actuator base end.
Unscrew spring guide approximately 0.5" using actuator disassembly tool.
5. Slowly release the press, allowing the springs to safely release to their free height;
6. Upon assembly, reverse above procedures. Verify dimension" A" , hold off pressure,
release pressure ,and stroke per specification.
J:JQJf;. SPECIFICATIONS:
To check integrity of spring 1. HOLD-OFF PRESSURE: 2000 psi
pack, verify release and hold-off 2. RELEASEPRESSURE: 1850 psi
pressures are as per 3. SPRINGPRELOAD: 950 psi
specification. 4. ACTUAJORSTROKE: 0.438 in
5. ASSEMBLYWEIGHT: 175 Ibs
. BAH1040 ACTUATOR
"..~ industries
/elevanja
8500 River Rood. Richmond BC Canodo V6X 1Y4
Tel 604 273 3737 -- Fax 604 273 9654
BY:
SC:
H.EPKENS
SERVICE
INSTRUCTIONS
DATE:MAR 1/01
REV.
DWG. NO.
1 u-
-;::-
W
~
.~
~...,,., ~
~:J° z I ~o I""" ~ , ::;.,
w=>~o
0- < I-
x~~II{)0- 10 W . De:
f--
~\I.::;
'-.- ~ 0
:J
<°<
~ -J
uo r--
..
"""w~
~
2
-
~
~ U
0
~O-I')
ZS:N
~ N Z
0 ..Q)
00
0 ~
-'
UJ
~
Q) ~~
...
.
u~FO wQ: De:< uu O-FU) ~ Q)Q)~~", ~ "
0 ffi ~ Q: ~ ~ ~~ ID U 0 0"( W ~ 01 01 :f ,.., I ,
z'>u ~u ID r-- oo~~~~u~~~~oo- '\U 1:;-
Con
~o,
o~
-J -J
u- 0- W
~
~
I
"£'.
u~x
~ 0-
W
W...: ~
0 ~..
.. u- ..
~o
:;;~N
OIN=>':;(~=>OgWI{)O~~1')
X -
~~~u-':;(Or--Q:,.j-a)~NR.
< ~ ~ ~W ~ - ~ 0-
-J
-J <.1,
..
X
'"
,ft
"".,.,
1:;:
::;
~S
.
~
Z 0- 0-
< - ~ e:.-
E ~ W< U
O-~ ~,.,
~ N VI
-
0
ID
,.j-
0 0
zu
-J
<
~
0
~
>
z I
~
-
~ ~
W
0 => < => ~ U) ~
u- ~ :J ~ W
.. ~ .'1-, ~ ID UJ
x ~o """~"(~~~
s:
~
0..:-J 0
.-
Q) .. ..
L-
~
o
-
~z~
~~
~~~~~o:rO
~- ~- WZ U
)-,
-J z U) O-JW
=> w~ w
01-:JU) - Z +J
... '"
>- z
U N ~ 0 Z
°U) U)
0- F'-
~ U
0
10 ~ I')
10
I') a) N
N ,.j-
-J-JX
wo<I ~
~
~-x
Z ~ ~ ~:J
0<
W °- W
0-0 U Z0 U) < U < Q.
Iu<U)
~ De: ~ VI
,ft ~..
- ,.j- :] > ~
~ ~ -c~g
...
u
W ..
0
I-'" .-C 8-g.
~
0- ~ ~ ~ ~
Con
0
.. ~
::>
U)
woo
Z :oJ 'C
§o
~
Z U) ~ .. - mE"'
:J
W W °
- WW
U =>
U)
W
=>
-J..
Z
0 ~
I-,
- ~
""
~ ~
~ °
0
Z~
.. <~Z <I ~o
0 ~
u-OU
.. ~
0-
0
>
':;(F
0"(
-JI-
~
U
0
I
U
.; ~
g."
~
...
~Ou-- ~ 0 I-U) - Z
0 Z
0 I..Z W 0
W <"
Z . """ .;
~':;(~O z-JO - - -J~ U) ~U) U) ~o
WUW':;( a:~w':;( ':;( ~=> FI- Z o ;.~
~2~=>
< 0- < t ~~~
~ 0 ~
ffi
0-
ffi W~
0- ~ z U)
~ ~5
'< => W
~
0- ~ ~I
-J
8£
~.g
Uo:ru< uzmo O.J- 0- oS: 0
..~
W
... .. o~ NI'),.j- I{)
De:
Q.
~NI'),.j- 1{)1Or--a) 01 ~~ ~ ~~ ~
~"~~"..
ITEM PART NO, QTY DESCRIPTION
~ 1 BAH1140 2 ACTUATOR ASSEMBLY
2 BBFL3859 1 ACTUATOR PLATE
3 BBFC3859 1 CENTER PLATE
4 BBFR3859 1 CALIPER PLATE
~ 5 BS4978 2 SHOE PLATE
~ 6 BFS3859 20 FRICTION LINING - 3 RIVET
7 BPSG3859 4 SHOE GUIDE PIN
8 BSRS2030 2 SHOE RETURN SPRING
9 BSB2040 4 SLIDE BEARING
10 F22C248H5 6 CALIPER ASSEMBLY BOLT
11 F22C5N 6 CALIPER ASSEMBLY NUT
12 F18C56S8 8 ACTUATOR MOUNTING BOLT
13 BMBLE3859 2 CALIPER LIFTING EYE
14 BPS3040 4 SHOE LIFTING EYE
15 BLTS3859 2 LINING TEPERATURE SWITCH
16 BRPS3040 1 BRAKE RELEASE SWITCH
17 BWPS3040 1 LINING WEAR"SWITCH
18 BHH3859 1 FLOW-THRU LINE HOSE
19 F16F2J 2 PROX SWITCH LOCK NUT
20 F8DP32 4 DOWELL PIN
21 BILS3859 1 LINING INSULATOR
~ 22 F6R17 100 LINING RIVETS
6 BFSGBK3 20 FRICTION LINING - 2 RIVET
.
..~ industries
/ elevanja KRUPP CANADA /
OS2040 CALIPER BRAKE ASSEMBLY
" 8500
. .
River Road, Richmond BC Canada V6X 1Y4
Tel 604 273 3737 -- Fax 604 273 9654
BY: HE
SC:
LOS PELAMBRES
DATE:JULY 30/98
REV,
DWG. NO.
Tel 0278
Bath Road, Fax 0278
456411 Somerset
Bridgwater --, 429949
Englond TA6 4NU PATH: pj' t/l pcnvrs / r 14/1p 385923 A3 8 5 9 - P5 .
,.,
~
z n
~ E N
I-
W
~(/)(/)(/)
0) a::: a::: a:::
E I
Ck:: .--~~~ CX)
u (f)
ON " m m m (/). . 0 r
-; W
,/
~
=5
-
I- -
:z:
I-
I'dr-..o
a
1.(")'--'--
'
:z:
0
zrn
. ~
- ~ ~~
'"' "'.J
NZ I- .--
<x:
Ck:: ~ => W "..
u w w
..
..
,?:VJ
-
(j
...
~
~'"'
O-~
(j
00 --
<0
0
Z
<0
0
z
~
N
~
-.-;:;1 ~o -.-;:;1 co~ « « I
"::J "'1- "::J ,.,"- ~ ~ ~
,
I
-, I
0
w
;;o~
.- N z v,
'~ ~ '\. N ~,~, ci ~
I ~ '" I <:38 ~ ~!m
I I ~ ::i
I 0 1 I N
m
Z
W
2:
I I ~ > I<{ ~
Z U) W 0 ~IV
I I - o~ > 0)
U) ~ ~ 0 ~
I I ~ W::) z ~
'-'U) U) .- m LL ~ ~
I I ~~~ ~ aU) ~ >
I I <{<{<{
mmm U)
.U) I-W
~ ~5
I I 0 '" I") w)-
> m 0
w ~<{ W
.. .~
c;
I I 0 ~ wm ~ ~,;: ~
~o Z ~ i?; ~ ~
I
1 m II 0
w
3:
'"
VI
II ~ \.,
U \"""',,,
~ (5 0 ~ I ~~S~~q
I I .. z:J ~
< I ~+!2~~~
I
I
I
I
g
~
W
~
0
e >
oI
~
g
Z"~F;
~a~~
D- U)I") -0 u
I I )-m 01- -
W ~> z3:: l-
I I >
J
D-U)
D-
WU)
~
«
~
I I <{<{ <{w Ow wtn<o
I I a>
U) w <:3
N
. U)~ :J:WO
U ~o
I D-~..
z<{
~/n/~~~
.:x-U-w-.JU) (/)-,,~
---
I I-a <{wl-<{U) U o
00 ~ZLL w O .r)
I I ~~<{ mw<{U)~ :J20
I I 3::8~ ,J,U)U)~D- ~ ~
I I U)~O mWO<{w ~>-()
I--, >~z~z C~I
-: I I WW4: U)<{om:J >-0-0
\ U)~~-3 ~o N
"-" I ~::)~~ ~mWWw :J:O-~
L -~
S
-ZU)U)~
U)U)::) N~::iW<{
)-U)~~ ~«<n
-J a::
-' :) WWOOmD-~~~ «~o
~~
~Q
(j°l-
t;j
It:
(j:)
~
U) D- D- <{
~ 0 Z
W
~
>
U)
D-
<{
~ W
~
m
I -
U
~
U
-
:)
CJ
>
Z
0 0
,~5
o~
,0-
N:I:
W
-.J.-
m
0 0
-..
a
~
u
I-- 0 0
()
COIt:-
,.",-(j
~o
"'1- > I- .- I- U) W
--
U) I I D- Lrl
~
I- CO)'" .. C -
'" ..
..
:J
.~
""...m
UJ
Z . ~~~ on ...
"C
.-
., .,
~e ~ " "
Nm
~ m I - ~s
~
m
~
e
m
m ~
m
'"
moo'"
""
It:
-
~
e
In
~
~
Qj ~
I I
I
~.
~
. ~
., -
<EJ "';~
<EJ <EJ +~ +N cn ~~
~ ~ ~
~
~
UJ
~
~ ll-
\jj
UJ
~ l:E cn
:~ -~
x ..
~ ::J:~
- '" II) C ~ -
0
~
In
~
ID ID -C
.-c:
g~
8.5
u t
.
0- m e
<EJ~
.
In
.~
~
.,
<EJ~ In
~
-
.",
<EJ~
In
~
'"
"'
:! .]§
.
~~p.
~
~ .- 16'
0
\ c c UJ
c g "
~ UJ UJ . '::
.~ g
I I I .. ~~
I I I . ~~
~ ~ ~ ..~
I
~
---
0-
I
N W co
o::~
W ~ ~
« W ~m
.r
=> rn rn > rv .. .. c.6~
(/) O::(/) LI- ~ ~~
a » 0- t.? => De: De: om
0
~ (/)(/)
'--"'-"
~W
::5<.<2
Z
Iuwg (/)
~ ~
i3 ~»~
ww urn ~=>t.?o
-O=>z
OJ
w
~
r o~~owo::o::o::w~w«w ~ ~t')
z~ O»o>OOO>(/)O::t.? ~
00- ~ ~I--I--I--~ ~ ~
~~~rnggg~::5::5::5~~~~~
Q:: 0-1--000 =>=>=> =>=>=>(r:
~
~
? ~
o::~ -ZZZ~~~~~(/)(/)(/)1-- ~
oo~3wwwo=>=>=>O(/)(/)(/)o w '
(/)-oo::~~~Wooowwwww
w =>« - a a a I 0 0 0 I 0::0::0::~ ~ w ~..
oarno(/)(/)(/)o«««oo-o-o-w >-=
In
~ s ~
V) De: 0.
~
I-- tJ ,_8~
~~!D1n
~~~N~f"")~~~~~~~N~ ~~ ;q
§+~~~~
I- ZQ.~F
r . DOOrn
orororo~~~wrnNo«wIrnro rnorn~ g ~'B~~
z~~~oO~
mmmf"")f"")~
O
XO~N~I~O~
f"")~~X~Ll-Om W
1--~~~»oINOrnlf"")If"")~ ~
o::oO-rn(/)(/»>ooo>O->t.?a ~ G
«zrnO»(/)o«««O(/)O::O-w ~
O-WWIIIIIIIIIIIIW 0 ~
~
w
I
O~Nf"")~~
a ~«
C~Nf"")~~w~rom~~~~~~ ~ ~
>-°
~>-
~~
~m
«:2:
w
0 0 ~ U)
uU)
-«
:::>
a
.~ ~ ~
c:"';~
~ ~~ .. ~
0 ~Q) ~~ I
I
'-. E;~
",:g
... ...
cn ~~
.~
..- ~ ~
~
"':0
>-z
cn ::;...
:] ~~
-r-.
""
.g-o
06
c: u6-0.c
...
.
0 0 .- u..,
m ~
. -0"
C E
0 0
E In
~~
. ~
"C '"
8 ~
..
. ~:
.~
'" '"g
. ~c8
8 ,s
..~
I'
N
0-
I
N
(Q
~LO
L--; ~~0 m
~ OC
OC
N
.q- ...
a J
"
t) .d
:) N
« ~
-!!?.
w
.. "
u
0
~ ~
-:;:;.
u
0
W :E.
:I: .. ~
..
>-
~
U
~
W
~
<
aJ II) ~ Q.
~ 1 ,_8-
~ ~~1o",
9 "::t:"~ ~ ~;
~ Za.~F
g ~a~~
ococ
ww
-,-,Q,Q, -' ~ 0:::
5~~~~Q,~
r= II) II) oc oc ~ VI OC
g 0
a. wWII) w OCwI- I-
-zzoo uF:w~ <:r
5~~~~ocj::;~Q,u -.J
VI~~>,,>,,~~oc::;!~
~a.a.uu~VlaJum -..It)
.U)
~
~m
22
~-
~~~oU)~U)..;-x~
Ln";-LnLnN..;-OCX)N U 3:~
<:( ~
I-";-Ln..;-~NNI"'1I) U rvlr)
<C O N
ocQ.Q."'Ln~Omm~ LL-
a.
<IIQ.a.IIII)W<
VI II) II) II) II) II)L..L.. I (/)
Q::
~'-'-'-'-'-N'-NN 0.->-«
~ ~
t:m~.-~~~~~~
O~N"'..;-LnU)r--
2~:J:
<C~:z
0:::"":,
WO-
-<.n
cn<.n
0.-<:(
a
a
a
OC
.--
W
OZ
.~~ ~ong:
zoo
:J1n
>- - ~ 9,. . .0.
U Q. I U ~
W ,... ~.
--'
'"'
ZOCOCOCOCI~
o~~OO!nz~~ ~ '"'~
r=«'d'd~ir~~ a.OCOC
a.-"-"-"-"
~\I.~
"-'::-!S°
ir=>=>=>=>~Vla.a.
" ~
~=>=>=>=>-u
~ ~ ~ z VI VI Q)
~
~ ~
...
"
o~~~~g,,555
~UUUUOCVlWW ~Q) ~
I I
I
ma.IU~OCNcx)
O.NN~~~Ln~O
5;~ oa
Z U)U)..;-..;-..;-r--LnO "",on
LnLnLnLnLnLnr--Ln
NNNNNNO~
~. ~
!;;II)II)II)VlII)~II
««<
~~~OCOC ~ ~WW
II)VIVI
(/)
;is'"' °
X'""
a.IIIIOOO CD
~
O'-'-'-'-N~'-'- --
-=...'"
"OJ "OJ
~ (/) ~~
w x oa
t:'-N"'..;-LnU)r--OO ~ ~~
-C -g]
c: u6"5-
~
-- g ~
. -0"
C E
E V)
0 0
. :§~
"' 0
.- .
~ . g"f
. ': OJ.
.. "'
.~"8 "'
° .c
. ~~
~ ..~