Professional Documents
Culture Documents
Project Management
Lectures Prepared by
Dr. Amr A. Elsharkawy
1
Safety Moment
??
2
Project Performance
Measurement and
Evaluation
Lecture 6 , Cost Management
3
Learning Objectives
Cost Estimating
Cost Budgeting
Solved Examples
4
Objective !
5
Cost Management definitions
8
Cost Estimating
Sharing the resources Assuming work packages
are defined, detailed cost estimates can be made.
Here are typical kinds of costs found in a project:
10
Cost Budgeting
TOTAL BUDGETED
ACTIVITY ACTUAL COST ($) ACTIVITY DIFFERENCE ($)
COST ($)
C 26,000 26,000 0
D 48,000 50,000 -2,000
E 56,000 55,000 1,000
F 30,000 31,500 -1,500
G 80,000 76,000 4,000
H 16,000 18,000 -2,000
308,000 312,500 -4,500
14
Developments of Cost Control
TOTAL PERCENT OF
VALUE OF WORK ACTIVITY
ACTIVITY BUDGETED COMPLETION ACTUAL COST ($)
COMPLETED ($) DIFFERENCE ($)
COST ($) %
16
EVM Concept
The value of work performed expressed
in terms of approved budget (BCWP)
19
Metric Abbr. Description Formula/Value
Estimate at Completion
Estimate to The expected additional –Actual Cost
Completion ETC cost to complete. EAC–AC
Expected total cost based Budget at Completion/Cost
Estimate at on the current cost Performance Index
Completion EAC efficiency ratio. BAC/CPI
Budget at Completion–
Variance at Estimated cost overrun at Estimate at Completion
Completion VAC the end of project. BAC–EAC
Status
GREEN = On track >1.0 , 1.0 - 0.9
YELLOW = Slightly behind
schedule or budget 0.89 – 0.75
RED = Needs immediate
attention < 0.75
EVM Concept
21
EVM Concept
Three key earned value components.
Planned Value (PV) is determined by the cost
and schedule baseline
Actual Cost (AC) is determined by the actual
cost incurred on the project
Earned Value (EV) tells you, in physical terms,
what the project accomplished.
Cost and Schedule baseline
25
EVM example # 2
26
EVM example # 2
27
EVM example # 2
28
EVM example # 2
29
EVM example # 3
30
EVM example # 4
31
EVM example # 4
32
EVM example
For a small manufacturing project consider the following :
- Baseline cost for 100% of project = $80,000
- Planned progress as per schedule baseline = 40%
- Your calculation at 47.5% physical progress .
- Actual expenditure = $48,000
1- Calculate the required fund , assuming the same calculated projection of
cost performance, that must be obtained for the remaining work (ETC)
2- Interpret schedule and cost performance for this contractor, consider
KPIs = 0.90 is the target .
36