Professional Documents
Culture Documents
Acknowledged: Dr. Suvash Chandra Paul (Faculty,IUBAT); Keerti Bhusan Pradhan (Faculty-LAICO);
Dr. Abu Naser Chowdhury (Faculty IUT); Mr. Soumik Nafis Sadeek (Faculty,IUBAT)
Content of lecture
2
Project Scheduling
Establishing objectives
Determining available resources
Sequencing activities
Identifying precedence relationships
3
Project Scheduling Techniques
Gantt chart
Critical Path Method (CPM)
4
Gantt Chart………
Time Period
Activity
J F M A M J J
Design
Build
Test
5
90
105
90 115
A 15 129
B 5 149 194
C 20
Immediate Estimated
D Activity Predecessor Completion Time 194
21
E A None 90
B A 15 25
F C B 5
14
D G 20
G E D 21 28
H F A 25
G C,F 14 30
I H D 28 45
I A 30
J J D,I 45
6
GANTT CHARTS-
MONITORING PROJECT PROGRESS
Gantt chart can be used as a visual aid for tracking the progress
of project activities.
7
MONITORING PROJECT PROGRESS
90
A 15
B 5 194
C 20
The shaded bars represent
D completed work BY DAY 135. 194
21
E 25
F
14
G 28
Do not conclude that the
H project is behind schedule. 30
I 45
Activity “I” has a slack and
J therefore can be delayed!!! 8
135
GANTT CHARTS –
ADVANTAGES AND DISADVANTAGES
Advantages.
Easy to construct
Gives earliest completion date.
Provides a schedule of earliest possible start and finish
times of activities.
Disadvantages
Gives only one possible schedule (earliest).
Does not show whether the project is behind schedule.
Does not demonstrate the effects of delays in any one
activity on the start of another activity, thus on the
project completion time.
9
CRITICAL PATH METHOD (CPM)
❑ The critical path method (CPM) is a step-by-step project
management technique for process planning that defines
critical and non-critical tasks with the goal of preventing
time-frame problems and process bottlenecks.
❑ The CPM is ideally suited to projects consisting of
numerous activities that interact in a complex manner.
10
CRITICAL PATH METHOD (CPM)
11
CRITICAL PATH METHOD (CPM)
12
CRITICAL PATH METHOD (CPM)
13
CRITICAL PATH METHOD (CPM)
• The fact that its name includes the word critical does not
mean that it includes all critical activities. It’s only
accounts for time.
• There can be more than one critical path if the lengths
of two or more paths are the same
• Project managers should closely monitor performance
of activities on the critical path to avoid late project
completion
• Critical path can change as the project progresses
14
CRITICAL PATH METHOD (CPM)
16
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
19
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
➢ Events and activities: In a PERT diagram, the main building
block is the event, with connections to its known predecessor
events and successor events.
➢ PERT event: a point that marks the start or completion of one
or more activities. It consumes no time and uses no
resources.
➢ predecessor event: an event that immediately precedes some
other event without any other events intervening. An event
can have multiple predecessor events and can be the
predecessor of multiple events.
➢ successor event: an event that immediately follows some
other event without any other intervening events. An event
can have multiple successor events and can be the successor 20
of multiple events.
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
PERT supplies a number of tools for management with
determination of concepts, such as:
22
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
23
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
24
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
25
Free Slack= Min. ES(suc.)-ES(Act.)-Dur(Act.)
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
26
27
Calculate free and total slack…….
Free Slack is the number of days that an activity can have before it starts delaying
the next (successor) activity.
28
Total Slack is the number of days that activity can have before it starts delaying
the whole project.
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
It determines the total calendar time required for the project; and,
therefore, any time delays along the critical path will delay the
reaching of the terminal event by at least the same amount.
29
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
Critical activity: An activity that has total float equal to zero. An activity
with zero float is not necessarily on the critical path since its path may not
be the longest.
Lag time: the earliest time by which a successor event can follow a specific
PERT event.
Example:
31
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
33
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
34
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
A network diagram from the example:
35
Immediate Estimated
Activity Predecessor Completion Time
A None 90
B A 15
C B 5
D G 20
E D 21
F A 25
G C,F 14
H D 28
I A 30
J D,I 45 36
PROGRAM (OR PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
duration.
Evaluate the ES of all the nodes for which EF of all the
immediate predecessor has been determined.
ES = Max EF of all its immediate predecessors.
EF = ES + Activity duration.
110,124
0,90 90,115 115,129 129,149 177
149,177
A
A FF G
G D
D HH 194
90 25 14 20 28
EARLIEST FINISH
120,165
90,120 194
149,194
II JJ 39
30 45
LATEST START TIME / LATEST FINISH TIME
Make a backward pass through the network as
follows:
Evaluate all the activities that immediately precede the
finish node.
The latest finish for such an activity is LF = minimal project
completion time.
The latest start for such an activity is LS = LF - activity duration.
Slack Time = LS - ES = LF - EF
42
Slack time in the Project
Activity LS - ES Slack
A 0 -0 0
B 95 - 90 5
C 110 - 105 5
D 119 - 119 0 Critical activities
E 173 - 149 24
must be rigidly
F 90 - 90 0
G 115 - 115 0 scheduled
H 166 - 149 17
I 119 - 90 29
J 149 - 149 0 43
PRACTICE (PERT)
44
PRACTICE (PERT)
45