KATIMO NATIONAL HIGH SCHOOL

Tagkawayan, Quezon I

PROJECT TITLE: FACULTY ROOM WIDENING/ REST AREA


TITLE PAGE OBJECTIVES CONTEXT PROJECT PROJECT IMPLEMETATION
STATEMENT (ACTIVITY PLAN)
ORGANIZATION: To provide a Katimo NHS is one One of the KEY Action Steps:
DEP ED KATIMO conducive and of the old public problem of the Formal Letter of request to Mayor Luis Oscar
NHS pleasant faculty school in Quezon KNHS was the lack Eleazar
office for the Province w/ solid of faculty office so it
PLACE: BRGY. teachers and to be and stable quality became a way to TIME LINE: 2 MONTHS ( JUNE- JULY 2021 )
KATIMO TAGK. able to work education. The convert the former
QUEZON properly. foundation of stock room. In this EXPECTED OUTCOME: Approval of the said
knowledge depends situation, space for project
DATE OF PROJECT on the teacher so a growing member
PREPARATION: they should have a of teachers is COST NEEDED: 50,000 Php.
JUNE-JULY 2021 good facility office limited. One of the
in their work. solutions is to END OF PROJECT:
DONOR: expand and make JULY 2021
HON.MAYOR LUIS the back of the said
OSCAR P. ELEAZAR office a resting
place as well.

Prepared by:
REGAL J. CAPINA
( Property Custodian ) APPROVED BY:
GILBERTO O. GRATUITO