Professional Documents
Culture Documents
Prepared by
Netalisire Daniel
August 2021
LIST OF TABLES .................................................................................................................................................... ii
LIST OF ACRONYMS ............................................................................................................................................ ii
EXECUTIVE SUMMARY ..................................................................................................................................... iv
1 INTRODUCTION ............................................................................................................................................1
1.1 Background .................................................................................................................................................1
1.2 Building Overview.......................................................................................................................................1
1.3 Appraisal Methodology ..............................................................................................................................3
2 DESIGN REVIEW ............................................................................................................................................4
2.1 Design information .....................................................................................................................................4
2.2 Design Loading Data ...................................................................................................................................5
2.2.1 Roof ....................................................................................................................................................5
2.2.2 composite floor slab ............................................................................ Error! Bookmark not defined.
2.2.3 Beams .................................................................................................. Error! Bookmark not defined.
2.2.4 Input, Analysis and Design ..................................................................................................................5
2.3 Elemental Designs and Output Summary................................................................................................ 13
2.3.1 Helicopter shade (Ground floor and first floor) .............................................................................. 13
2.3.2 Recommended members to the structure ...................................................................................... 13
2.3.3 Input, analysis and design for recommended solution ................................................................... 15
3 INTEGRITY ASSESSMENT .........................................................................................................................21
3.1 Non-Destructive Field Testing ....................................................................................................................... 21
3.2 Compressive Strength Test ...................................................................................................................... 21
4 SUPERVISION ...............................................................................................................................................23
5 CONCLUSIONS AND RECOMMENDATION ........................................................................................23
5.1 Conclusions .............................................................................................................................................. 23
5.2 Recommendations................................................................................................................................... 23
6 REFERENCES ................................................................................................................................................24
7 List of Annexes:..............................................................................................................................................24
i|Page
LIST OF TABLES
Table 1 Building structure overview ............................................................................................................ 1
Table 4: Floor slab loading for first floor.................................................. Error! Bookmark not defined.
Table 5: Design Output Summary for Helicopter shade implemented on site .................................... 13
LIST OF ACRONYMS
L= Length
W= Width;
BL= Beam Length;
A= Area
DL=Dead load,
LL=Live load, SL=Serviceability load, UL=Ultimate Load, UW=Unit Weight
ii | P a g e
iii | P a g e
EXECUTIVE SUMMARY
Bar aviation contracted Mutoni contractors to contruct the airplane hanger
iv | P a g e
1 INTRODUCTION
1.1 Background
1.2 Building Overview
The existing frame is a steel structure. A general breakdown in typical components of the structure is as
follows: Floor system consisting of reinforced concrete composite slab, steel beams and columns
supported on isolated pad footings.
Item Description
Building Usage Helicopter shade
Structural system Steel beam structure supported on steel columns
No of levels 2 levels
Design drawings Available
Foundation type Isolated pad foundations
Table 1 Building structure overview
1|Page
Figure 1: Architectural Ground Floor Layout
2|Page
Figure 2: Architectural first floor layout
Document review: Structural drawings and corresponding design calculations were not reviewed
to ensure adequacy of the structural system to transmit loads safely to the ground as well as the
adequacy of the different structural elements. Quality control and quality assurance records were
also not reviewed.
3|Page
Non- destructive field testing: Schmidt rebound hammer were used to determine the in-situ
concrete compressive strength for the first floor. Section sizes of the different structural elements
were also measured using a tape measure.
2 DESIGN REVIEW
2.1 Design information
Job
4|Page
Table 2: Design information
2.2.1 Roof
EN1991-1-1 Roof (loads in kN/m2)
DL LL SL UL
Covering (Iron sheets) 0.15
Water proofing, batens, rafters 0.15
Purlins, Truss 0.15
Ceiling 0.25
Table 6.10 Imposed load 0.6
Totals 0.70 0.60 1.30 1.85
Table 3: Roof loading data
D B uW(kn/m2) DL LL SL UL Ref
Finishes(25mm) 0.025 1.000 20.00 0.50
Composite Slab 0.150 1.000 24.00 3.60
BS EN 1991-1-
Live load (Restaurant) 1.000 3.50 3.50 1:2002, Table 6
Totals 4.10 3.50 7.60 10.79
Table 4: Floor slab loading for first floor
2.2.3 Beams
The beam loading was obtained by multiplying the slab loads with the tributary widths of each beam.
5|Page
Col Self 3.50
228.00 43.75 95.00 134.81
Ground level 3.50 0.00 3.50 4.73
Slab 0.00 0.00
Beams 0.00
Col Self 3.50
6|Page
a) Input
7|Page
Figure 4: Input Section properties, dead load and Live loads onto beams for analysis
8|Page
Figure 5: Summary of sections input
9|Page
b) Analysis
Figure 6: Bending Moments (critical load combination) in Beams for the shed
10 | P a g e
Figure 7: Shear forces (critical load combination) in the columns
11 | P a g e
c) Design
12 | P a g e
Utility ratio is the ratio of actual load on the member to the capacity of the member. If it exceeds more
than 1 then load imposed to the member is greater than its capacity and member fails under deflection.
Therefore, from the above design, member sections of 305x165x40 Kg/m that were used initially failed
under the utility check thus the causing a deflection in the slab as exhibited on site.
The summary of the output from the design of the structural elements is as follows:
Column
Column C1 (12 Nos) 300x165x10mm I section Adequate
Column C2 (13 Nos) IPE 200 I section Adequate
Column C3 (8 Nos) 406x178x85 I section Adequate
Footings
Footing F1 (12 Nos) 1500x1500x300 T12-200BEW Adequate
Footing F2 (8 Nos) 2000x2000x300 T16-200BEW Adequate
13 | P a g e
Stub column (12 Nos) 400x400 6T16 Adequate
Stub column (8 Nos) 450x450 12T16 Adequate
Table 6: Recommended Design output summary for Helicopter shade
14 | P a g e
2.3.3 Input, analysis and design for recommended solution
a) Input
15 | P a g e
Figure 10: Input Section properties, dead load and Live loads onto beams for analysis
16 | P a g e
Figure 11: Summary of sections input
17 | P a g e
b) Analysis
Figure 12: Bending Moments (critical load combination) in Beams for the shed
18 | P a g e
Figure 13: Shear forces (critical load combination) in the columns
19 | P a g e
c) Design
20 | P a g e
Therefore, from the above design, additional member designs of 406x178x85Kg/m to member sections
of 305x165x40 Kg/m that were used initially adequately support the structure and pass under the
utility check.
3 INTEGRITY ASSESSMENT
3.1 Non-Destructive Field Testing
During the course of the project, Solgeotechnics Ltd were contracted by the client to carry out an in-situ
compressive strength investigation from which the existing frame building was built. Field tests were
carried out on August 2021 and report was compiled (See Annex F).
Different concrete structural elements of the building after visual inspection were subjected to non-
destructive strength assessment. These included Composite floor slabs, Stub columns and staircase. The
test was conducted in accordance with BS EN 12504-2:2012 to estimate the in-situ strength of concrete
based on the correlation established between in situ strength at the particular location and rebound
numbers.
The slab average concrete compressive strength was found to be >10N/mm2 for the points tested. The
Ground Slab concrete compressive strength was found to be with an average of 23.0N/mm2.
21 | P a g e
The results from the field testing are indicative of competent materials and workmanship implemented with the requisite quality
observances. The detailed results of the field testing are herewith tabulated:
22 | P a g e
4 SUPERVISION
Therefore, from the above design, additional member designs of 406x178x85Kg/m to member
sections of 305x165x40 Kg/m that were used initially adequately support the structure and pass
under the utility check.
5.2 Recommendations
The construction works should proceed as per the drawings attached in Annex B and Annex C.
During the construction, the client has been advised to ensure that works are supervised by
competent professional personnel to ensure safety, structural soundness and compliance to
drawings and specification.
Client should as soon as possible undertake external works necessary to protect the foundations
from effects of storm water runoff that percolates into the ground.
23 | P a g e
6 REFERENCES
1) Appraisal of existing structures 3rd Edition.(2010), IstructE
2) Guide to surveys and inspections of buildings and Associated structures(2008), IstructE
7 List of Annexes:
ANNEX A: SITE PHOTOS
24 | P a g e
ANNEX A: SITE PHOTOS
25 | P a g e
Figure 15: Side view of the helicopter shade showing deflected Figure 16: Girder system attached to deflecting members to
beam minimize deflection
Figure 17: Corrugated sheet used as a steel deck for the slab
26 | P a g e
ANNEX B: ARCHITECTURAL DRAWINGS
27 | P a g e
ANNEX C: STRUCTURAL DRAWINGS
28 | P a g e
ANNEX D: FIELD TESTS REPORT
29 | P a g e