ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022

Mode Jul Aug Sep Oct Nov Dec Jan Feb M


1 PROPOSED CONSTRRUCTION OF 168 Sun 01/08/21 Sat 08/01/22
RESIDENTIALBUILDING days
2 MOBILISATION WORKS 4 days Sun 01/08/21 Thu 05/08/21
3 PRELIMINARIES 4 days Sun 01/08/21 Thu 05/08/21
4 GRADING AND LEVELLING 1 day Sun 01/08/21 Mon 02/08/21
5 HOARDING 4 days Sun 01/08/21 Thu 05/08/21
6 TEMPORARY STRUCTURES SITE 4 days Sun 01/08/21 Thu 05/08/21
OFFICES STORES AND SANITARY
FACILITIES
7 SUB STRUCTURE WORKS 6 days Tue 03/08/21 Mon 09/08/21
8 SETTING OUT 1 day Tue 03/08/21 Wed 04/08/21
9 PAD FDN EXCAVATIONS 4 days Wed 04/08/21 Sun 08/08/21
10 BLINDING PAD FOUNDATIONS 2 days Tue 03/08/21 Thu 05/08/21
11 STEEL WORKS FOR BASES AND 3 days Wed 04/08/21 Sat 07/08/21
STARTERS
12 REINFORCED CONCRETE BASES 3 days Fri 06/08/21 Mon 09/08/21
13 STRIP FOUNDATION 10 days Mon 02/08/21 Thu 12/08/21
14 STRIP FOUNDATION EXCATION 6 days Mon 02/08/21 Sun 08/08/21
15 BLINDING STRIP FOUNDATIONS 8 days Wed 04/08/21 Thu 12/08/21
16 PLINTH WALLING 16 days Mon 09/08/21 Tue 24/08/21
17 PLINTHWALL CONSTRUCTIONS 16 days Mon 09/08/21 Tue 24/08/21
18 STUB COLUMNS 5 days Fri 13/08/21 Tue 17/08/21
19 PLINTHWALL RENDERING AND 5 days Sun 15/08/21 Fri 20/08/21
DAMP PROOFING
20 BACKFILLING AND COMPACTIONS 15 days Wed 18/08/21 Wed 01/09/21
21 BACKFILLING AND COMPACTION 10 days Wed 18/08/21 Sat 28/08/21
TRENCHES
22 MURRAM FILLING IN PARTITIONS 8 days Sun 22/08/21 Sun 29/08/21
23 HARDCORE PLACING 7 days Wed 25/08/21 Tue 31/08/21
24 SAND BLINDING 4 days Mon 23/08/21 Fri 27/08/21
25 ANTI TERMITE TREATMENT 2 days Tue 31/08/21 Wed 01/09/21
26 DPM AND BRC 2 days Tue 31/08/21 Wed 01/09/21
27 GROUND BEAM CONSTRUCTION 15 days Fri 20/08/21 Fri 03/09/21
28 STEEL WORKS FOR GROUND BEAMS 5 days Fri 20/08/21 Wed 25/08/21
29 SHUTTERING FOR SLAB AND BEAMS 4 days Tue 31/08/21 Fri 03/09/21
30 STAIRCASE FOUNDATIONS AND 3 days Sun 29/08/21 Tue 31/08/21
STARTERS
31 GROUND SLAB 8 days Tue 31/08/21 Tue 07/09/21
32 PLUMBING WORKS 2 days Wed 01/09/21 Thu 02/09/21
33 GROUND SLAB CONCRETE CASTING 4 days Tue 31/08/21 Fri 03/09/21
34 CURING SLAB 7 days Wed 01/09/21 Tue 07/09/21
35 SUBSTRUCTURE WORKS COMPLETION0 days Tue 07/09/21 Tue 07/09/21 07/09

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 07/08/21
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
Mode Jul Aug Sep Oct Nov Dec Jan Feb M
36 SUPERSTRUCTURE GROUND FLOOR 11 days Thu 02/09/21 Sun 12/09/21
37 BLOCKWORK FOR GROUND FLOOR 11 days Thu 02/09/21 Sun 12/09/21
WALLS
38 GROUND FLOOR COLUMNS 6 days Mon 06/09/21 Sun 12/09/21
39 FIRST FLOOR SLAB 19 days Sun 12/09/21 Thu 30/09/21
40 FORMWORK AND SHUTTERING 8 days Sun 12/09/21 Sun 19/09/21
41 MAXPAN ALIGNMENT AND PLACING 4 days Sat 18/09/21 Tue 21/09/21
42 STEEL BENDING AND FIXING 5 days Thu 16/09/21 Mon 20/09/21
43 PLUMBING AND ELECTRICAL 3 days Sat 18/09/21 Mon 20/09/21
INSTALATIONS
44 STAIR CASE CONSTRUCTION 5 days Thu 16/09/21 Mon 20/09/21
45 CONCRETE CASTING 7 days Mon 20/09/21 Mon 27/09/21
46 CURING 9 days Tue 21/09/21 Thu 30/09/21
47 FIRST FLOOR BLOCK WALLING 9 days Mon 27/09/21 Wed 06/10/21
48 SETTING ON BLOCK WALLS 2 days Mon 27/09/21 Wed 29/09/21
49 BLOCKWORK FOR FIRST FLOOR WALLS 9 days Mon 27/09/21 Wed 06/10/21
50 FIRST FLOOR COLUMN CONSTRUCTION9 days Wed 29/09/21 Fri 08/10/21
51 STEEL FIXING AND BENDING 4 days Wed 29/09/21 Sun 03/10/21
52 FORMWORK AND SHUTTERING 6 days Fri 01/10/21 Thu 07/10/21
53 CONCRETE COLUMN CASTING AND 6 days Sat 02/10/21 Fri 08/10/21
CURING
54 RING BEAMS CONSTRUCTION 17 days Wed 06/10/21 Fri 22/10/21
55 FORMWORK AND SHUTTERING 9 days Wed 06/10/21 Thu 14/10/21
56 GUTTER FRAMING AND CONSTRUCTION 4 days Sun 10/10/21 Thu 14/10/21
57 STEEL BENDING AND FIXING 7 days Sun 10/10/21 Sun 17/10/21
58 CONCRETING GUTTERS AND RING BEAM6 days Thu 14/10/21 Wed 20/10/21
59 FIRST SLAB SHUTTERING DEMOLITION5 days Sun 17/10/21 Fri 22/10/21
60 ROOFING 21 days Mon 11/10/21 Sun 31/10/21
61 TRUSS ASSEMBLING 13 days Mon 11/10/21 Sun 24/10/21
62 ROOF TRUSS ERECTION 5 days Wed 20/10/21 Sun 24/10/21
63 PURLINS AND ANTI-SAG RODS 8 days Fri 22/10/21 Fri 29/10/21
64 ROOF COVERING 6 days Tue 26/10/21 Sun 31/10/21
65 PARAPET WALL CONSTRUCTION 8 days Sun 24/10/21 Sun 31/10/21
66 CEILING CONSTRUCTION 18 days Sat 30/10/21 Mon 15/11/21
67 CEILING FRAMING 7 days Sat 30/10/21 Fri 05/11/21
68 SUSPENDED SLAB COVERINGS 14 days Tue 02/11/21 Mon 15/11/21
69 FITTINGS 7 days Tue 26/10/21 Mon 01/11/21
70 WINDOWS FIXING 7 days Tue 26/10/21 Mon 01/11/21
71 DOORS FIXING 7 days Tue 26/10/21 Mon 01/11/21
72 FINISHING 39 days Sat 23/10/21 Mon 29/11/21
73 PLASTERING AND FINISHES 32 days Sat 23/10/21 Mon 22/11/21
74 CEILING FINISHES 7 days Mon 15/11/21 Mon 22/11/21
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 07/08/21
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
Mode Jul Aug Sep Oct Nov Dec Jan Feb M
75 WALL PLASTERING 21 days Wed 27/10/21 Mon 15/11/21
76 WALL RENDERING 15 days Wed 27/10/21 Wed 10/11/21
77 FLOOR SCREEDING 21 days Sat 23/10/21 Fri 12/11/21
78 TILING 18 days Fri 12/11/21 Mon 29/11/21
79 WALL TILING TOILETS 7 days Fri 12/11/21 Thu 18/11/21
80 FLOOR TILING 15 days Sun 14/11/21 Mon 29/11/21
81 PAINTING 36 days Fri 19/11/21 Thu 23/12/21
82 SANDING 21 days Fri 19/11/21 Thu 09/12/21
83 UNDERCOATING 14 days Tue 23/11/21 Mon 06/12/21
84 FINAL COATING 21 days Sat 04/12/21 Thu 23/12/21
85 EXTERNAL WORKS 58 days Sun 14/11/21 Sat 08/01/22
86 LAND SCAPING 30 days Sun 14/11/21 Sun 12/12/21
87 WALKWAYS 18 days Sun 19/12/21 Wed 05/01/22
88 PAVING AND FINAL TOUCHES 21 days Sun 19/12/21 Sat 08/01/22

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: msproj11 Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 07/08/21
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only