Professional Documents
Culture Documents
To cite this article: Assem Al-Hajj & Karima Hamani (2011) Material Waste in the UAE
Construction Industry: Main Causes and Minimization Practices, Architectural Engineering and
Design Management, 7:4, 221-235, DOI: 10.1080/17452007.2011.594576
Abstract
The United Arab Emirates (UAE) is facing the challenge of achieving sustainability on construction sites. One of
the main barriers lies in the increasing amounts of material waste generated from construction activities, dumped
in landfills. This research examined previous studies about the sources of waste and the recommended measures
to minimize it. The significance of these causes and frequency of implementation of adequate measures in the
UAE construction sites were examined. Four construction projects were visited before a survey of
contractors’ perceptions was conducted of the problem, causes of material waste, waste minimization
measures and their benefits. The research revealed that the main causes of material waste are lack of
awareness, excessive off-cuts resulting from poor design, and rework and variations. The most frequent
measures practised to minimize material waste are: staff training, adequate storage and just-in-time delivery
of materials. Waste measurement and waste segregation are areas that need more efficient implementation to
achieve material waste minimization targets. Moreover, contractors’ perceptions towards the benefits of
material waste minimization revealed that this waste is primarily considered a financial problem and its
minimization a cost-cutting activity. In contrast, the environmental dimension was neglected by surveyed
companies.
B Keywords – Construction; material waste; sustainability; UAE; waste management; waste minimization
construction waste (UAE Interact, 2007) and it is defining it as: ‘The by-products generated and
ranked second to USA in waste share per capita removed from construction, renovation and
among the world countries (Al-Qaydi, 2006). The demolition workplaces or sites of building and civil
amount of construction waste dumped in Dubai’s engineering structures’.
landfill for the year 2007 has reached 27.7 million Koskela (1992) and Alarcon (1993) studied other
tonnes, which is almost three times the volume types of waste in construction. Time- and
generated in 2006 (10.6 million tonnes). In 2008, it process-related waste is generated from activities
was reported that the construction waste from the that take time, resources or space without adding
first half of 2008 is already double that produced in value. Formoso et al. (1999) added that defined
2007 with 35,000 tonnes of sites’ debris discarded time- and process-related waste as: ‘any losses
daily (Alkhafaf, 2008). These figures show the produced by activities that generate direct or
urgent need for a revolution in the way the country indirect costs but do not add value to the product
is handling waste; adopting other waste from the point of view of the client’. Non-adding
management practices instead of disposal should value activities and how to minimize the waste they
be the way forward. generate are the basis of the lean construction
This research seeks to contribute to the philosophy. Although inefficiency-related waste has
implementation of this change by investigating the greater economic loss than material waste
causes of material waste in the UAE construction (Formoso et al., 1999), it is widely recognized that
sites and examining the current practices the latter is more important from an environmental
implemented by the contractors to minimize material perspective (Miyatake, 1996; Formoso et al., 1999;
waste. Du Plessis, 2002; Mora, 2005).
Similar to the definition of waste, waste
CONSTRUCTION WASTE: DEFINITION AND measurement has also been viewed and
MEASUREMENT implemented in different ways. Treloar et al. (2003)
Many categorization models have been applied to suggest the measurement of waste in terms of
classify the types of waste. Wastes can be classified embodied energy of materials. Bossink and
by their state (solid, liquid or gaseous), by their Brouwers (1996) reported three case studies where
characteristics (inert, combustible, bio-degradable, waste of each type of material was measured in
hazardous or nuclear) or by their origin (processing, different ways: (1) as a percentage of the total
household, emission treatment, C&D or energy amount of construction waste; (2) as a percentage
conversion). C&D waste can then be defined and of purchased materials; and (3) as a percentage of
studied separately. the total waste’s cost. These methods are all
Construction waste has been defined in various illustrative of the level of waste generated and they
ways. The Building Research Establishment (BRE) can be used simultaneously. However, in order to
(1978) defined waste as ‘the difference between calculate these percentages, the identification of
materials ordered and those placed for fixing on waste streams and volume/weight of waste
building projects’. In 1981, another definition generated for each one is necessary.
emerged from BRE stating that waste is ‘any In addition to the fact that recording and
material apart from earth materials, which needed to measuring waste is a prerequisite to its
be transported elsewhere from the construction site management (WRAP, 2007b), knowing how much
or used on the site itself other than the intended waste is generated can be used as a benchmarking
specific purpose of the project’. In the 1990s, the tool against other projects, other companies or
Environmental Act (1990) defined waste as: ‘scrap against good practice. The next step is then to
material or an effluent or other surplus substance explore the gap between what is achieved and good
arising from the application of any process’. In practice. Reducing the gap can be attained by
Hong Kong, the definition by HK Polytechnic looking at the sources of waste and analysing the
made it clear as to what construction waste is by causes behind its generation.
1992. The world’s first standard BS7750 was waste minimization practices implemented by the
developed by the British Standard Institute in 1992 UAE contractors, two sets of information were
followed by the Eco-Management and Audit scheme gathered. First, four projects with different locations,
published by the EU in 1993 (Kein et al., 1999). The sizes, types and at different stages of construction
ISO 14001 for EMS first published in 1996 has been were visited to audit material waste management on
adopted by many countries including the UAE. ISO construction sites and to find out from project
14001 is considered as a vehicle for organizations managers about the processes used to minimize
to minimize the impact of their activities on the construction waste. The results obtained from this
environment. One of the main requirements of stage were analysed and combined with the
the ISO 14001 is waste minimization and the literature findings to design and to analyse the
development of a waste management plan as part of questionnaire survey. In the second stage, a
the EMS (Powell and Craighill, 2001; Poon et al., non-random sampling approach was adopted and
2004). only medium and large companies having
In addition, environmental assessment systems construction and general contracting as their primary
for sustainable buildings such as LEED (USA), business were targeted.
BREAM (UK), CASBEE (Japan) and GLOBE (Canada) The analysis of the questionnaire was mainly
are considering construction waste management as based on the calculation of weighted average values
one of the main criteria for granting credits (Shafii, and the standard deviation according to the
2006). Estidama, the bespoke rating system following formulas:
developed by Abu Dhabi, allocates five credits for
Snj¼1 Xj Nij
waste management in construction projects (A) ASi ¼
N
(ESTIDAMA, 2008). sffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
SN j¼1 ðXj ASi Þ
2
(B) di ¼
N
FINANCIAL BENEFITS
ASi
Envirowise (2007) have proved through case studies (C) IVi ¼ ASi þ
di
that the true cost of waste disposal is more than the
cost of paying a waste contractor to remove a skip where ASi is the average score of the attribute (i), Xj
from site and a number of researchers have the rank given to the attribute (i), Nij the number of
highlighted the financial benefits of waste respondents who gave the attribute (i) the rank Xj, n
minimization (e.g. Shen et al., 2005; Begum et al., the number of possible ranks given, di the standard
2006; Osmani et al., 2006; Tam et al., 2007). But, the deviation of the attribute (i) and IVi is the index value
true cost of waste is still underestimated by of the attribute (i).
contractors (WRAP, 2007b). The same method has been used by Begum et al.
Many surveys and studies have been carried out in (2006) in assessing the significance and levels of
different countries to identify the causes of waste and practice of waste minimization factors in Malaysia;
assess current practices. However, no such studies and by Shen and Tam (2002) in their study of the
have been found in the literature for the case of the benefits of and barriers to the implementation of
UAE. By building on the findings in other countries EMS in Hong Kong.
and taking into consideration the characteristics of
the UAE in terms of culture and legislation, this FINDINGS AND ANALYSIS
research aims to fill this gap by means of a carefully Table 1 shows general information on the four
selected research method. projects in the study including project type, location,
the stage it is at the time of the study and the
RESEARCH METHODOLOGY designation of the member of staff providing
In order to investigate the causes of material waste in the information. Also, Table 1 shows the type of
construction sites and to assess the current material waste found on-site, possible causes and the
measures taken to reduce material waste. during the site walks that there are some problems
Finally, general observations were provided on each of storage and handling that can eventually
project. The information about causes of waste engender material waste. In addition, the waste
and waste minimization practices implemented in minimization measure claimed to be implemented by
each project was obtained from observations during all the contractors particularly the segregation of
site walks and interviews with main contractors’ waste needs more attention. Only two types of
employees. material waste are separated: wood and steel. This
All the interviewees agreed that most of the waste was justified by interviewees by the fact that these
is due to off-cuts as the sizes of materials in the market two types of material are valuable and their wastage
are usually different from the sizes in the design cannot be allowed. The same idea is supported by
drawings. Two of them mentioned the poor quality of the statement of one interviewee that waste
products as one of the main sources of damages to minimization for them is part of their cost control
materials, especially the quality of wood. Two further and value engineering activities. Furthermore, the
causes are reported to be the lack of awareness and major benefit of waste minimization considered by
design errors and variations (see Table 2). all interviewees is related to cost savings.
The above opinions show that material waste in All the facts cited above lead to the conclusion that
these projects is caused by parties other than those material waste minimization is not construed as a
directly involved in the construction stage. Similar means to achieve sustainable construction and to
findings were reported by Ofori (2000) when he save natural resources but as a financial solution to
stated that waste on-site is directly related to increase profit. Therefore, there is a large scope for
problems ‘on which the site personnel have very changing the attitude of construction companies
little or no influence’. However, it was observed towards the problem of material waste in
construction.
metal and timber. These two materials are indeed Factor (iii), unskilled labour and rework, was
highly considered by contractors because of their considered by Smith (2008) to be a cause of off-cuts,
high monetary value as it was concluded from the as a result of the construction boom in the UAE, and
projects in Table 1. This is why they are separated the increasing demand for workers regardless of
and measured to keep their wastage to a minimum. their level of experience and competence. Although
this description summarizes the ‘status quo’ in the
CAUSES OF MATERIAL WASTE UAE construction industry, it should not acquit the
The list of causes of material waste given in the contractors from their responsibilities towards waste
questionnaire was derived from the literature review production and management. It is the contractor’s
and the projects visited. Respondents were asked to obligation to raise awareness and provide a suitably
estimate the amount of waste generated in their trained workforce to reduce waste produced on-site.
projects between the ranges of no contribution (1) to Table 5 ranks an additional six factors related to
significant contribution (4). the procurement category of sources of waste
An analysis of the responses is presented in (ranking 8– 13 in Table 5 in order of significance).
Table 5. Three factors have been identified with a
mean greater than 3 (more than a moderate 1 Damages during delivery and transport
contribution). These factors are namely: (i) lack of 2 Poor quality of products
workers’ awareness, (ii) poor design, resulting in 3 Purchase of inadequate materials
excessive off-cuts, and (iii) unskilled labour and 4 Over-ordering of materials
rework. Poor design is clearly outside the 5 Poor advice from suppliers
contractors’ control. It may be the case that ‘lack of 6 Inadequate packaging.
awareness’ in the construction industry workforce
could be considered as a general issue, related to The six factors listed above have a weighting of less
the culture of the construction industry in the UAE, than 2.5 and therefore have been identified as
where sustainable practices and environmental making a minimal contribution to waste production.
impact are not a priority and hence, are out of the They are all part of the procurement process, which
contractors’ control. However, contractors have a is an area directly controlled by the contractor. This
responsibility and a role to play in raising analysis agrees with the findings of the study
environmental awareness, particularly in relation to undertaken by Ekanayake and Ofori (2000), who
minimizing construction material waste on-site. reported that contractors did not consider
significant relationship between the ranking of the considered as a high contributor to waste and (2)
preventive waste minimisation measures and the lack of awareness is still considered as a significant
correspondent causes involving these measures’. factor because the training and awareness activities
Table 8 shows the results found for the three firstly were not sufficiently efficient. Finally, the negative
ranked measures. correlations between the rankings of ‘adequate
The following conclusions can be drawn from the storage on-site’ and ‘inappropriate storage’, and
analysis in Table 8: all the coefficients in absolute between ‘ordering just what is needed of materials’
value exceeded the critical value of 0.4433 and it and ‘delivery schedules’ indicate that the two factors
was concluded that the null hypothesis should be are considered of minimal contribution to the
rejected. In addition, the positive correlation generation of material waste because of the
between the ranking of ‘Waste minimisation training frequent implementation of the appropriate
and awareness’ and ‘Lack of awareness’ can be measures.
interpreted in two ways: (1) this measure is It cannot be easily concluded that the other
frequently used because lack of awareness is preventive measures are used with less frequency
because their correspondent causes were
overlooked by respondents. This can be due to
TABLE 8 Correlation test between causes and preventive financial considerations such as in the case of
measures
‘ordering material to size’ or to the rules of the
PREVENTIVE MEASURE CAUSE OF WASTE r
market as it can be the case of ‘take back
Waste minimization training Lack of awareness +0.65
arrangements with suppliers’ as it was mentioned by
and awareness
the interviewees in the sites visited. For example, an
Adequate storage of material Inappropriate storage 20.56
investigation of a correlation between ‘using
Ordering just what is needed Delivery schedules 20.69
prefabricated components’ and ‘off-cuts’ gave a
of material
coefficient of 0.09, which indicates that there is
no significant correlation between the two relatively low and 30% of the respondents perceive
attributes. This can be interpreted by the fact that this benefit as being not important at all for them. It
this measure of using prefabricated components can can be concluded then that while economical and
be for other purposes such as time saving and health and safety benefits are strong drivers for
quality improvement and not necessarily to reduce waste minimization, the environmental benefits are
off-cuts. still overlooked by most of the contractors.
projects, to be the most important benefits and Environment Programme, International Environmental Technology Centre,
incentive for material waste minimization. South Africa, 1 –81.
6 The environmental benefits are neglected, Ekanayake, L.L., Ofori, G., 2000, ‘Construction material waste source
overlooked and considered as less important by evaluation’, Proceedings of the 2nd Southern African Conference on
contractors in the UAE construction sites. Sustainable Development in the Built Environment: Strategies for a
Sustainable Built Environment, Pretoria.
The effectiveness of the waste minimization Ekanayake, L.L., Ofori, G., 2004, ‘Building waste assessment score: design
measures implemented could be further investigated based tool’, Building and Environment 39, 851 –861.
based on the content of this research. In addition, El-Sayegh, S.M., 2008, ‘Risk assessment and allocation in the UAE
construction waste, in order to be managed, should construction industry’, International Journal of Project Management 26,
be integrated and taken into consideration at the 431 –438.
planning and design stages of the project. Envirowise, 2007, Benefits of Resource Construction Efficiency [available
at www.envirowise.gov.uk/media/attachments/202895/BRE-
REFERENCES Construction-resource-efficiency.pdf] [accessed 14 July 2008].
Alarcon, L.F., 1993, ‘Modelling waste and performance in construction’, in: EPD, 2008, Monitoring of Solid waste in Hong Kong – Waste Statistics for
L. Alarcon (ed.), Lean Construction, A.A. Balkema, Rotterdam, 51– 66. 2007 [available at www.wastereduction.gov.hk/en/materials/info/
Al-Kaabi, N., Hadipriono, F., 2003, ‘Construction safety performance in the msw2007.pdf].
United Arab Emirates’, Civil Engineering and Environmental Systems ESTIDAMA, 2008, Assessment Method for New Residential and Commercial
20(3), 197 –212. Buildings, Department of Municipal Affairs, Abu Dhabi.
Alkhafaf, M., 2008, Waste Problems are Shared Responsibility Between Formoso, C.T., Isatto, E.L., Hirota, E.H., 1999, ‘Method for waste control in
Developer, Engineer and Lead Project Holders, Alsahara Press [available the building industry’, Proceedings IGLC-7, 7th Conference of the
at www.zawya.com] (accessed 21 July 2008). International Group for Lean Construction, Berkeley, CA, 26 –28 July.
Al-Qaydi, S., 2006, ‘Industrial solid waste disposal in Dubai, UAE: a study in Jacobsen, H., Kristoffersen, M., 2002, Case Studies on Waste Minimisation
economic geography’, Cities 23(2), 140– 148. Practices in Europe, European Environment Agency, Copenhagen.
Begum, R.A., Siwar, C., Pereira, J.J., Jaafar, A.H.A., 2006, ‘Benefit –cost Kein, A.T.T., Ofori, G., Briffett, C., 1999, ‘ISO 14000: its relevance to the
analysis on the economic feasibility of construction waste minimisation: construction industry of Singapore and its potential as the next
the case of Malaysia’, Resources, Conservation and Recycling 48, industry milestone’, Construction Management and Economics
86– 98. 17(4), 449 –461.
Bossink, B.A.G., Brouwers, H.J.H., 1996, ‘Construction waste: quantification Keys, A., Baldwin, A., Austin, S., 2000, ‘Designing to encourage waste
and source evolution’, Journal of Construction Engineering Management minimisation in the construction industry’, Proceedings of CIBSE National
122(1), 55 –60. Conference, Dublin.
CIOB, 2004, Sustainability and the Construction Industry, Chartered Institute Koskela, L., 1992, ‘Application of the new production philosophy to
of Building, Ascot. construction’, Technical Report No. 72, CIFE, Stanford University.
CIRIA, 1995, Waste Minimisation and Recycling in Construction – A Review, Lingard, H., Graham, P., Smithers, G., 2000, ‘Employee perceptions of the
Construction Industry Research and Information Association (CIRIA) solid waste management system operating in a large Australian
Special Publication, London. contracting organization: implications for company policy implementation’,
Dainty, A.R.J., Brooke, R.J., 2004, ‘Towards improved construction waste Construction Management and Economics 18(4), 383–393.
minimisation: a need for improved supply chain integration’, Structural Lingard, H., Gilbert, G., Graham, P., 2001, ‘Improving solid waste reduction
Survey 22(1), 20 –29. and recycling performance using goal setting and feedback’, Construction
DEFRA, 2007, Key Facts About: Waste and Recycling, London: Department Management and Economics 19(8), 809 –817.
for the Environment, Food and Rural Affairs [available at www.defra.gov. Macozoma, D.S., 2002, ‘Secondary construction materials: an alternative
uk/evidence/statistics/environment/waste/kf/wrkf13.htm]. resource pool for future construction needs’, Proceedings of
DEFRA, 2008, Non-Statutory Guidance for Site Waste Management Plans, Concrete for the 21st Century Eskom Conference Centre, Midrand,
London: Department for the Environment, Food and Rural Affairs. Gauteng, March.
du Plessis, C., 2002, ‘Agenda 21 for sustainable construction in developing McDonald, B., 1998, ‘Implementing a waste management plan during the
countries’, in: WSSD (ed.), South Africa: International Council for construction phase of a project: a case study’, Journal of Construction
Research and Innovation in Building and Construction & United Nations Management and Economics 16(1), 71– 78.
McDonald, B., Smithers, M., 1998, ‘Implementing a waste management Shen, L.Y., Tam, V.W.Y., 2002, ‘Implementation of environmental
plan during the construction phase of a project: a case study’, management in the Hong Kong construction industry’, International
Construction Management and Economics 16, 71– 78. Journal of Project Management 20(7), 535 – 543.
Miyatake, Y., 1996, ‘Technology development and sustainable construction’, Shen, L., Lu, W., Yao, H., Wu, D., 2005, ‘A computer-based scoring method
Journal of Management in Engineering 12(4), 23– 27. for measuring environmental performance of construction activities’,
Mora, E., 2005, ‘Life cycle, sustainability and the transcendent quality of Automation in Construction 14, 297 –309.
building materials’, Building and Environment 42, 1329 –1334. Smith, M., 2008, ‘Construction sector battles to find skilled employees’,
Naoum, S., 2007, Dissertation Research and Writing for Construction Emirates Business, 22 June 2008 [available at www.zawya.com]
Students, 2nd edn, Butterworth-Heinemann, Oxford. [accessed 1 August 2008].
Ofori, G., 2000, ‘Greening the construction supply chain in Singapore’, Tam, V.W.Y., Shen, L.Y., Tam, C.M., 2007, ‘Assessing the levels of
European Journal of Purchasing & Supply Management 6(3 –4), material wastage affected by sub-contracting relationships and
195– 206. projects types with their correlations’, Building and Environment
Osmani, M., Glass, J., Price, A., 2006, ‘Architect and contractor attitudes 42, 1471 – 1477.
to waste minimisation’, Proceedings of the Institution of Civil Teo, M.M.M., Loosemore, M., Masosszeky, M., Karim, K., 2000, ‘Operatives
Engineers, Waste and Resource Management, 159, May 2006 Issue attitudes towards waste on a construction project’, Annual Conference –
WR2, 65 –72. ARCOM 2000 2, 509 – 517.
Poon, C.S., Yu, A.T.W., Wong, S.W., Cheung, E., 2004, ‘Management of Treloar, G.J., Guptar, H., Love, P.E.D., Nguyen, B., 2003, ‘An analysis of
construction waste in public housing projects in Hong Kong’, Construction factors influencing waste minimisation and use of recycled materials for
Management and Economics 22(7), 675 –689. the construction of residential buildings’, Management of Environmental
Powell, J., Craighill, A., 2001, ‘The key to sustainability in the building Quality: An International Journal 14(1), 134 – 45.
sector’, Report presented at the OECD Workshop on the Design of UAE Interact, 2007, UAE at a Glance [available at www.uaeinteraact.com,
Sustainable Building Policies, 28– 29 June 2001, Paris. the official website for the Ministry of Information and Culture in the UAE]
Rounce, G., 1998, ‘Quality, waste, and cost consideration in architectural [accessed 5 July 2008].
building design management’, International Journal of Project USEPA, 2003, Estimating 2003 Building-related Construction and Demolition
Management 16(2), 123–137. Materials Amounts [available at www.epa.gov/osw/conserve/rrr/imr/
Saunders, J., Wynn, P., 2004, ‘Attitudes towards waste minimisation cdm/pubs/cd-meas.pdf].
amongst labour only sub-contractors’, Structural Survey 22(3), WRAP, 2007a, Efficient Construction Logistics, Waste and Resources Action
148– 155. Programme, Banbury.
Shafii, F., 2006, ‘Achieving sustainable construction in the developing WRAP, 2007b, Reducing Material Wastage in Construction, Waste and
countries of south-east Asia’, Proceedings of the 6th Asia-Pacific Resources Action Programme, Banbury.
Structural Engineering and Construction Conference (APSEC 2006), Kuala WRAP, 2007c, Current Practices and Future Potential in Modern Methods of
Lumpur, Malaysia, 5 –6 September. Construction, Waste and Resources Action Programme, Banbury.