Mode S S M T W T F S S M T W T F S S M T
1 Tank Civil Works 12 days Mon 05-07-21 Mon 19-07-21
2 Mobilization 1 day Mon 05-07-21 Mon 05-07-21
3 Infill of Tank Foundation 7 days Tue 06-07-21 Wed 14-07-21
and installation of liner and
Removal of Concrete
4 Installation of Leak 6 days Tue 06-07-21 Tue 13-07-21
Detection Sump w/ curing
5 Complete backfill top layer 3 days Tue 13-07-21 Fri 16-07-21
of soil in pit internal and
external.
6 Installation of 1 day Fri 16-07-21 Sat 17-07-21
Electrostation Grounding
7 Demobilization 1 day Sat 17-07-21 Mon 19-07-21
Page 1