You are on page 1of 1

PROGRESS REPORT

SB Construction Corporation -Office


Checked Reviewed Approved
AIN TSILA DEVELOPMENT PROJECT
ATEK.I

1P RF-PR-PLNOG-0001 SUB-CON : DCC As of : Sep-21 CAMP EXTENSION

AREA 1. MANHOLE U DONE OBS


EXCAVATION m3 42
INSTALLATION U 13 R14 NOT INSTALED
GROUT U 24 R13 & R14 NOT DONE

PROGRESS 92%
2. CONNECTION PIT DONE OBS
EXCAVATION m3 11
INSTALLATION U 13 14 CP NOT INSTALED

JUNIOR C PROGRESS 74%


3. PVC DONE OBS
EXCAVATION PVC200 m3 135
EXCAVATION PVC160 m3 266
INSTALLATION PVC200 ml 169 47 ml NOT INSTALED
INSTALLATION PVC160 ml 358 303 ml NOT INSTALED

PROGRESS 47%
4. OTHERS DONE OBS

PLNOG COMMENTS

1- Inspection of grouting is done from 27/09/2021 & until today the Leak test of
UG sewage not started

2- the PVC connection DN160 to all manhol's is not finished until today

MANHOLE, CONNECTION PIT & PVC INATALLATION DONE

ONLY EXCAVATION DONE

Page 1 of 1

You might also like