PROGRESS 92%
2. CONNECTION PIT DONE OBS
EXCAVATION m3 11
INSTALLATION U 13 14 CP NOT INSTALED
PROGRESS 47%
4. OTHERS DONE OBS
PLNOG COMMENTS
1- Inspection of grouting is done from 27/09/2021 & until today the Leak test of
UG sewage not started
2- the PVC connection DN160 to all manhol's is not finished until today
Page 1 of 1